M/S Samdariya Builders Private Limited vs Madhya Pradesh Housing And Infrastructure Development Board

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
1 WP-40472-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR

BEFORE
HON'BLE SHRI JUSTICE ALPESH Y. KOGJE,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VIVEK JAIN
th
ON THE 29 OF SEPTEMBER, 2026
WRIT PETITION No. 40472 of 2026
CNR No.: MPHC010717772026
M/S SAMDARIYA BUILDERS PRIVATE LIMITED
Versus
MADHYA PRADESH HOUSING AND INFRASTRUCTURE
DEVELOPMENT BOARD AND OTHERS
Appearance:
Shri Manoj Sharma - Senior Advocate with Ms. Lavanya Verma -
Advocate for the petitioner.
ORDER
Per: Hon'ble Shri Justice Alpesh Y. Kogje, Chief Justice
This petition under Article 226 of the Constitution of India is filed
challenging the communication dated 21.09.2026 (Annexure P/1) and
Request For Proposal (RFP) dated 30.07.2026 (Annexure P/2) issued by the
Deputy Housing Commissioner, Madhya Pradesh Housing & Infrastructure
Development Board, Circle Bhopal with a further direction to treat that the
petitioner is not disqualified under the Special Eligibility Criterion at Serial
No.19 of the Bid Summary and consequentially evaluate the technical bid of
the petitioner on the basis of the remaining criteria and if found qualified, to
open and consider the price bid along with the technically qualified bidders
Signature Not Verified
Signed by: CHRISTOPHER
PHILIP
Signing time: 06-10-2026
17:40:09

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
2 WP-40472-2026
as if, the petitioner is found qualified in each criteria.

2. The impugned communication is of the Deputy Housing
Commissioner, MPHIDB, Circle Bhopal refusing to consider the petitioner's
bid for Bhopal Collectorate re-densification project on account of the reason
that a letter from Executive Engineer, MPHIDB, Division Rewa supplied
under the Sr.No.19 of the Bid Summary (special eligibility criteria) mentions
the delay of 2 years in constructing the government printing press at Rewa
by the petitioner and in this regard a penalty of Rs.7.30 lakhs was imposed
upon the petitioner.
3. According to the learned advocate, the decision of not considering
the technical bid of the petitioner though had preceded with calling for a
reply on the very same day which the petitioner did file, but the decision was
predetermined and only a post-decisional hearing was provided which is an
empty formality. It is also argued that the effect of the impugned
communication also amounts to debarring the petitioner from participating
in future project, for which there is no specific notice for such a
consequence, and before taking such a decision, principles of natural justice
are required to be followed. It is further submitted that the special eligibility
criteria will not be attracted in view of the fact that delay, if any, in the Rewa
project was not fully attributable to the petitioner.
4. Learned advocate has gone on to rely upon the pleadings to argue
that there were reasons attributable to the employer itself which resulted in
the delay in the project and therefore, the petitioner cannot be penalized.
5. Having considered the aforesaid submissions on behalf of the
Signature Not Verified
Signed by: CHRISTOPHER
PHILIP
Signing time: 06-10-2026
17:40:09

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
3 WP-40472-2026
petitioner and on perusing the documents, the facts are that the petitioner was

one of the bidders for the project "Construction of Collectorate, Divisional
Commissioner Office, IG Office and Multilevel Parking at existing
Collectorate Campus Bhopal under the re-densification Policy of GoMP"
(Annexure P/2). As per the RFP document, Annexure P/2, the particulars of
the project are as follows:-
S.No Title Particulars
"Construction of Collectorate, Divisional Commissioner
Office, I.G Office & Multilevel Parking at Existing
Collectorate Campus, Bhopal under Re-densification
Policy of GoMP"
Name of the
a)
Project
Land Area for
Government
Construction Site
b)
3.75 Hectare (Approximate) at Old Secretariat, Bhopal
3.36 Hectare at Old Secretariat, Bhopal
CLP part Area Land Use
CLP 1 2.15 Hectare Commercial
Compensatory
c)
Land Parcel
Mixed Land
CLP 2 0.63 Hectare
Use
Mixed Land
CLP 3 0.58 Hectare
Use
Estimated Cost of
Government
Facilities
d)
Rs.217.96 Crore (Excluding GST)
Reserve Price /
Upset Value for
Premium
e)
Rs.256.92 Crore
Construction
f) 36 Months, including rainy season
Period
6. The clause 19 of the Bid Summary (at page 46 of the petition)
prescribes the qualification requirement for the bidder. Clause 19 specifies
eligibility of bidder, financial capacity, technical capability, and also
prescribes special eligibility criteria which requires information to be
furnished that whether the bidder has completed any project of MPHIDB
Signature Not Verified
Signed by: CHRISTOPHER
PHILIP
Signing time: 06-10-2026
17:40:09

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
4 WP-40472-2026
with a delay of more than 1 year attributable to bidder, then such bidder

would stand disqualified. In this connection, letter dated 09.2.2024 issued by
Executive Engineer, Madhya Pradesh Housing & Infrastructure
Development, Division Rewa addressed to the petitioner mentions the delay
by the petitioner of 2 years and therefore has communicated that in the
context of the above, a hearing was held by the Additional Commissioner-2,
Headquarters Bhopal, on 02.02.2024, to approve the deadline for the
construction of the Government Printing Press, Jai Stambh Chowk, Rewa.
The Deputy Commissioner, Circle Rewa, and Mr. Ajit Samdariya, on behalf
of petitioner, were present at the hearing. The Additional Commissioner-2,
Headquarters Bhopal, while giving his decision regarding the delay in
construction, attributed the two-year delay to the contractor and resolved the
deadline issue. According to the contract, a penalty of Rs.1000 per day was
imposed for the delay. Accordingly, the 2-year delay was estimated to
Rs.730000/-. Therefore, the petitioner was informed to deposit the penalty of
Rs.730000/- so that the final assessment can be done at the earliest.
7. Pursuant to such communication of 09.02.2024, the petitioner had
also addressed a letter dated 12.03.2024 to the Executive Engineer of
MPHIDB for the Rewa work for transferring of the amount in connection
with the aforementioned communication of 09.02.2024, etc. It is on this
factual matrix that the impugned communication dated 21.09.2026 was
addressed to the petitioner wherein it was mentioned that under the re-
densification policy, the petitioner participated in the work of construction of
Collector's Office, Commissioner's Office, IG's Office, Multilevel Parking in
Signature Not Verified
Signed by: CHRISTOPHER
PHILIP
Signing time: 06-10-2026
17:40:09

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
5 WP-40472-2026
the Collectorate Complex Bhopal under the Re-densification Scheme. The

documents submitted by the petitioner were examined and on reviewing the
note sheet and letter provided by the Executive Engineer Rewa, it was found
that there has been a delay of two years by the petitioner in completing the
construction work of Government Printing Press Jai Stambh Chowk Rewa
and on account of this the Board has imposed a penalty of Rs 07.30 lakh.
8. In view of the aforesaid factual matrix, there is no doubt that the
petitioner is falling short of the required criteria under Clause 19 of the Bid
Summary.
9. In so far as the attempt on the part of the petitioner to argue that the
delay as mentioned in connection with the Rewa project was attributable to
the employer itself, is concerned, the same cannot be the subject matter of
decision in the present petition as there does not appear to be any challenge
to such communication for the Rewa project, nor there is any adjudication by
an appropriate forum so as to conclude that the delay in the Rewa project
could not be attributed to the petitioner.
10. With regard to the contention of the petitioner that the impugned
communication will have an effect of petitioner being blacklisted, the perusal
of the impugned communication does not indicate or justify such
apprehension. Therefore, the Court does not deem it fit to address such
contention which is not substantiated by any document. The Court has
perused the tender document wherein Clause 21 of Section 1- Draft
Concession-cum-Development Agreement provides for a dispute
resolution including arbitration. It may be argued that the clause relating to
Signature Not Verified
Signed by: CHRISTOPHER
PHILIP
Signing time: 06-10-2026
17:40:09

NEUTRAL CITATION NO. 2026:MPHC-JBP:79092
6 WP-40472-2026
the resolution of dispute provided in Section 1 may not come into operation

prior to reaching the stage of execution of the agreement, then in that case,
the petitioner has no established right which can be examined under Article
226 Constitution of India in the matter as in the present case, where the
relation between the parties is of contractual nature. Filling up of a bid has
not created any right in favour of the petitioner so as to clear the stage of the
bidding process, particularly when as per the provision of bid summary on
record, the petitioner has earned a disqualification. In such a situation, the
Court does not deem it fit to arrest an ongoing tender process. Any
interference by the Court to undertake a judicial review of a commercial
decision will affect the ongoing process of bidding which already is having a
time limit for completion of work apparently of a public importance.
11. In view of above, we do not find any merit warranting
interference in this petition. The petition is accordingly dismissed.
(ALPESH Y. KOGJE)
(VIVEK JAIN)
CHIEF JUSTICE
JUDGE