M/S Sisl Infotech Private Limited vs M/S I Sourcing Technologies Private Limited,

Court
Delhi High Court

$~44
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010369622026
+ O.M.P.(I) (COMM.) 332/2026 & I.A. 21696/2026
M/S SISL INFOTECH PRIVATE LIMITED .....Petitioner
Through: Mr. Saurabh Kirpal, Senior
Advocate, Mr. Harshit Sethi,
Mr. Prabhas Bajaj, Mr. Rajat
Choudhary, Mr. Harsh
Chauhan, Ms. Mansi Tripathi,
Mr. Arya Yadav, Advs.

versus

M/S I SOURCING TECHNOLOGIES PRIVATE LIMITED,
.....Respondent
Through: Mr. Ritin Rai, Sr. Advocate
with Mr. Jay Kansara, Mr.
Aman Raj Gandhi, Mr.
Parthasarthy Bose and Ms.
Lavina Bhargava, Advocates.

CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT(ORAL)
% 13.08.2026

1. The present petition has been filed seeking following relief:-

A. “Direct the Respondent to forthwith return to the Petitioner
all data, records, documents, confidential information, proprietary
information, intellectual property, databases, credentials, access
details and all other material received, generated or retained by the
Respondent during the subsistence of the Service Agreement dated
30.04.2024, together with all copies thereof in whatsoever form,
and further direct the Respondent to certify on affidavit that no
copies thereof have been retained by it;

B. Direct the Respondent to forthwith disclose, hand over and
transfer to the Petitioner all End User Data / databases maintained
pursuant to the Service Agreement dated 30.04.2024, and further
direct the Respondent to forthwith refrain from using any such
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 1 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

data:

C. Grant an order of injunction restraining the Respondent, its
directors, officers, employees, representatives, agents or anyone
acting through or under it from directly or indirectly tampering
with, altering, deleting, disabling, interfering with or otherwise
dealing in any manner whatsoever with the End User Data,
databases or any other infrastructure relating to the subject
Baanknet project pending the arbitral proceedings.


D. Direct the Respondent to cease and desist from advertising,
utilizing. accessing, reproducing, copying, transferring, disclosing,
publishing, exploiting or otherwise dealing with any proprietary
information, confidential information, trade secrets, data or
intellectual property belonging to the Petitioner or to PSBA or
related to the Baanknet project in any manner whatsoever, either
directly or indirectly, whether for itself or for the benefit of any
third party, pending the conclusion of the arbitral proceedings.

E. Direct the Respondent to immediately remove, delete and
take down from all websites, social media platforms, marketing
material, brochures, presentations, advertisements, portfolios, case
studies and any other public or private platform, every reference
whatsoever to the Service Agreement dated 30.04.2024, the
Baanknet project executed for PSB Alliance Private Limited, the
Petitioner's name, the End Customer's name, and/or the
Respondent's alleged role, participation or involvement in the said
project, and restrain the Respondent from making any further
publication or representation in relation thereto during the
pendency of the arbitral proceedings;

F. Grant an order of injunction restraining the Respondent, its
directors, officers, employees, representatives, agents or anyone
acting through or under it, from directly or indirectly
communicating, corresponding, negotiating, soliciting, dealing or
otherwise interacting or contacting with the End-Customer Bank
users or PSB Alliance Private Limited (PSBA) or any of its
representatives in relation to the subject Baanknet project;

G. Direct the Respondent to furnish security, or in the
alternative deposit before this Hon'ble Court, a sum of
Rs.3,75,00,000/- (Rupees Three Crores Seventy Five Lakhs Only)
along with 12% interest, being the amount pain by the Petitioner
under Annexure-B ("Software Development and Support") towards
development of an independent customized application & allied
deliverables, which remain incomplete, deficient and/or were never
performed in accordance with the Service Agreement dated
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 2 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

30.04.2024;

H. Direct the Respondent to furnish security, or in the
alternative deposit before this Hon'ble Court, a sum of
Rs.45,43,571/- (Rupees Forty Five Lakhs Forty Three Thousand
Five Hundred Seventy One Only) along with 12% interest, being
the amount wrongly taken by the Respondent from the Petitioner
towards application support resources/manpower under Clause J of
Annexure-A of the Service Agreement dated 30.04.2024 despite
the Respondent being contractually bound to provide the said
services as part of its original contractual obligations)

I. Direct the Respondent to furnish security, or in the
alternative deposit before this Hon'ble Court, a sum of
Rs.15,00,000/- (Rupees Fifteen lakhs Only) along with 12%
interest, paid by the Petitioner to the Respondent towards STQC
Certification which the Respondent failed to secure;

J. Direct the Respondent to furnish security, or in the
alternative deposit before this Hon'ble Court, a sum of
Rs.15,00,000/- (Rupees Fifteen lakhs Only) along with 12%
interest, being the amount wrongly taken by the Respondent from
the Petitioner towards enhancements despite the Respondent being
contractually bound to provide the said services as part of its
original contractual obligations;

K Direct the Respondent to furnish security, or in the
alternative deposit before this Hon'ble Court, a sum of
Rs.3,00,00,000/-(Rupees Three Crores Only) along with 12%
interest, being the amount wrongly taken by the Respondent from
the Petitioner towards resource costs incurred by the Petitioner on
account of the illegalities committed by the Respondent.

L Direct the Respondent to furnish security, by way of an
unconditional and irrevocable Bank Guarantee and/or Fixed
Deposit Receipt, to the satisfaction of this Hon'ble Court, for the
aggregate amounts claimed by the Petitioner in the present
proceedings, or in the alternative, attach/freeze the Respondent's
bank accounts, receivables, movable and immovable properties to
the extent of the Petitioner's claim and restrain the Respondent
from withdrawing, transferring, alienating, encumbering or
otherwise creating any third-party rights therein pending
adjudication of the disputes through arbitration;

M. During the pendency of the present petition, this Hon'ble
Court may be pleased to issue interim orders/directions with regard
to the Prayers (supra);
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 3 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

N. Pass such other and further order(s) or direction(s) in favour
of the Petitioner as this Hon'ble Court may deem fit and proper in
the facts and circumstances of the present case in and in the interest
of justice”.

2. The Petitioner was awarded a project by PSB Alliance Pvt. Ltd.
for supply, installation and maintenance of an E-Auction Solution.

3. According to the Petitioner, for execution of part of the said
project, the Petitioner engaged the Respondent under a Service
Agreement dated 30.04.2024.

4. Under the agreement the Respondent was required to develop
and support the E-Auction Solution. Further, he was required to
develop certain customised applications and provide the relevant
source code with other works.

5. The dispute subsequently arose between the parties with the
Petitioner alleging that the Respondent failed to fulfil several of these
obligations and directly communicated with PSB Alliance without the
Petitioner authorisation.


6. Following an email sent by the Respondent to PSB Alliance i.e
Principal contractor on 07.08.2026, the Petitioner terminated the
Service Agreement on the same date and invoked arbitration under
1
Section 21 of the Arbitration and Conciliation Act, 1996 on
08.08.2026.

1
“the Act” hereinafter
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 4 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

7. The Petitioner has thereafter, filed the present petition under
Section 9 of the Act, seeking interim protection, including the
preservation and return of data, source code credential and documents
restrained against misuse or disclosure of confidential information and
unauthorised dealings with PSB Alliance or other End Users and
security in respect of its monetary claims pending constitution of the
Arbitral Tribunal.

8. Issue notice.


9. Mr. Jay Kansara, learned Counsel has accepted notice on behalf
of the Respondents.

10. At this stage, Mr. Nitin Rai, learned Senior Counsel appearing
for the Respondent has made a statement at Bar that Respondent shall
maintain all confidentiality related to data and other information in
terms of the agreement.

11. Learned Senior Counsel appearing for the Respondent submits
that the Respondent has no objection to the disputes being referred to
arbitration by appointment of the Learned Sole Arbitrator.

12. Learned Counsel appearing for the parties jointly submit that
the present petition under Section 9 of the Act may be treated as an
application under Section 17 of the Act to be decided by the learned
Sole Arbitrator.
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 5 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

13. In view of the consent of the parties, Mr. Justice Ashok
Bhushan (Retd.), Judge, Supreme Court [Mobile No. 9910428111] is
appointed as a learned Sole Arbitrator to adjudicate the disputes arisen
between the parties.

14. The arbitration shall be carried under the rules and aegis of
Delhi International Arbitration Centre (“DIAC”). The learned
Arbitrator shall be entitled to fees as per the Schedule of Fees
maintained by the DIAC.


15. It shall be open to the parties to raise all pleas, including
objection as to arbitrability and jurisdiction, before the learned Sole
Arbitrator who shall decide the same in accordance with law.

16. It is clarified that the observations made herein are only for the
purpose of deciding the present petition. The learned Sole Arbitrator
shall adjudicate the disputes with claims and counter claims
independently and on their own merits, uninfluenced by any
observations contained in the present order.

17. The Registry is directed to send a receipt of this order to Mr.
Justice Ashok Bhushan (Retd.), Judge, Supreme Court, learned
Arbitrator through all permissible modes including email.

18. At this stage, learned Senior Counsel appearing for both the
parties submit that they are willing to subscribe to the mediation
Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 6 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16

process for amicable settlement.

19. Acceding to the same, the matter is referred to Delhi High Court
Mediation and Conciliation ( SAMADHAN ) with the aspiration that
mediation process will be concluded within four weeks and the parties
are directed to appear in person or through their authorized
representative along with their respective Counsel before the
Mediation Centre on 18.08.2026.

20. The learned sole arbitrator shall enter reference within a period
of three weeks from 18.08.2026, in case settlement or mediation talks
are failed.

21. In case, if there is no settlement arrived at between the parties,
they will go before the learned Arbitrator.

22. Both parties are at liberty to file application under Section 17 of
the Act before the learned Arbitrator.

23. Accordingly, the present petition is disposed of in the above
terms.


OM PRAKASH SHUKLA, J
AUGUST 13, 2026/at

Signature Not Verified
O.M.P.(I) (COMM.) 332/2026 Page 7 of 7


Signed By:ANUBHAV
TRIPATHI
Signing Date:19.08.2026
14:35:16