M/S B.P.Vishwakarma vs Chairman Cum Managing Director

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-JBP:45536
1 WP-13697-2018
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR

BEFORE
HON'BLE SHRI JUSTICE MANINDER S. BHATTI
th
ON THE 29 OF JUNE, 2026
WRIT PETITION No. 13697 of 2018
M/S B.P.VISHWAKARMA
Versus
CHAIRMAN CUM MANAGING DIRECTOR AND OTHERS
Appearance:
Shri Jagdamba Bux Singh - Advocate for the petitioner.
Shri Sapan Usrethe - Advocate for the respondents No.1 to 5.
ORDER
This petition has been filed by the petitioner under Article 226 of the
Constitution of India while praying for the following reliefs:
"(i) This Hon'ble Court may be pleased to order the payment of
outstanding bills amount worth Rs. 10,46,048.00 for which the
bills have already been passed by the Respondent no.5;
(ii) This Hon'ble Court may be further pleased to direct the
Respondents to make payment of interest @ 18% P.A. over the
amount payable to the petitioner beyond the due date;
( ⅲ ) This Hon'ble Court may be pleased to order the payment of
compensation worth Rs. 10 lakh for mental harassment and breach
of contract by the Respondents;
(iv) This Hon'ble Court may be pleased to pass any other
writ/order/direction in the present facts and circumstances of the
case as deemed just and proper in the interest of justice."
2. Learned counsel for the petitioner contends that the petitioner herein
was awarded the work of "Operation & Comprehensive Maintenance of
Signature Not Verified
Signed by: SAVITRI PATEL
Signing time: 01-07-2026
11:55:24

NEUTRAL CITATION NO. 2026:MPHC-JBP:45536
2 WP-13697-2018
Electro-Mechanical Service for Usof Sites in Panna SSA" by the

respondents, as enumerated in Annexure P/1. The aforesaid work so allotted
to the petitioner was executed by him in due time and completion certificates
to that effect were also issued. In spite of repeated applications from the
petitioner, the payment for the work duly completed remains outstanding
(Annexure P/3 to Annexure P/13). It is contended by the counsel for
petitioner that it is a case where there exists no dispute regarding execution
of work by the petitioner to the satisfaction of the respondents and once, the
certificates were issued certifying completion thereof and the claim of the
petitioner was also forwarded for payment vide Annexure P/14, there was no
occasion for the respondents to keep the amount outstanding. In support of
his contention, the counsel has also referred to a letter dated 22.09.2017
written by the Telecom District Engineer, BSNL to Chief General Manager,
BSNL seeking approval for payment of outstanding bills (Annexure P/19).
3. Per contra, learned counsel for the respondents contends that the
present petition is liable to be dismissed, inasmuch as there exists disputed
questions of fact which cannot be gone into by this Court in exercise of its
writ jurisdiction. It is contended by the counsel that a detailed return in the
matter has been filed and the contents incorporated therein makes it clear that
there was no completion of work in terms of the terms and conditions of the
agreement. The deficiencies are also detailed alongside. Moreover, it is
contended by the counsel that in view of the disputed question of fact
involved in the lis before this Court, it was for the petitioner to invoke the
arbitration clause in the matter since, no writ petition could directly have
Signature Not Verified
Signed by: SAVITRI PATEL
Signing time: 01-07-2026
11:55:24

NEUTRAL CITATION NO. 2026:MPHC-JBP:45536
3 WP-13697-2018
been filed in order to espouse his cause. It is also contended by the counsel

that there are specific averments in the return to the effect that the bills which
are being sought to be relied upon by the petitioner containing the
endorsement regarding the completion of work, are also fabricated. It is
further contended by the counsel that the details of each bill have been
enumerated in paragraph 6 of the return, a perusal of which clearly reflects
that there was no satisfactory completion of work by the petitioner.
4. No other point is argued or pressed by both parties.
5. Heard the rival submissions of both parties and perused the record.
6. A perusal of the record reflects that in the case in hand, the
petitioner is mainly pressing reliance on the certificate which is available
along with the bill submitted by the present petitioner. The said certificate
according to counsel, has been issued in terms of the clause titled "Payment
Terms" which is at page no.34 of the petition. The same is reproduced herein
as under:
"PAYMENT TERMS: The bill for the work will be processed and
paid by Panna SSA.
Procedure for Preparation and settlement of bills:
Procedure for preparation, processing and payment of bills: The
contractor shall prepare the bills in triplicate ensuring execution of
work in its completeness as envisaged above correctness of rates
and quantum of work and submit the bills to S.D.E. in-charge of
work of Panna SSA. The bills shall be prepared accurately on the
basis of approved rates. The contractor should submit the bill
within 30 days from the date of completion of work. The SD.E In-
charge shall record the certificate on the bill. This would enable
the S.D.E. to ensure whether the defects pointed during execution
have been rectified or not. The SDE in-charge of the work shall
Signature Not Verified
Signed by: SAVITRI PATEL
Signing time: 01-07-2026
11:55:24

NEUTRAL CITATION NO. 2026:MPHC-JBP:45536
4 WP-13697-2018
scrutinize bills and accord necessary certificates and submit the
bills with the documents as mentioned below to the Divisional
Engineer, in-charge of work..............."

7. A perusal of the aforesaid reflects that once the work is done, the
contractor is required to prepare the bills in triplicate, ensuring execution of
work in completeness as envisaged above, correctness of rates as well as the
quantum of work. The bills so submitted by the petitioner to the S.D.E. In-
charge of work, are required to be certified by him. After the issuance of
certificate, the bill are again put to scrutiny. Thereafter, there is another stage
of issuance of necessary certificates and submission of bills alongwith the
documents as mentioned herein-above to the Divisional Engineer, In-charge
of the work.
8. There is no document on record to demonstrate that the second
certificate was there, as is necessitated by the aforesaid clause on "Payment
Terms". Apparently, the respondents have disputed the execution of work in
paragraph 6 of the return and therefore this court is of the view that since
such a question, being a disputed question of fact, cannot be adjudicated
upon by this Court in the exercise of its writ jurisdiction, it is for the
petitioner to invoke the arbitration clause incorporated in the agreement.
9. Accordingly, this petition stands disposed of while reserving the
aforesaid liberty with the present petitioner to invoke the arbitration clause. It
is made clear that, if the petitioner approaches the respondent seeking
invocation of the arbitration clause, the same shall be dealt with by the
respondent within a period of 30 days from the date of the request so made
by the petitioner.
Signature Not Verified
Signed by: SAVITRI PATEL
Signing time: 01-07-2026
11:55:24

NEUTRAL CITATION NO. 2026:MPHC-JBP:45536
5 WP-13697-2018
10. With the aforesaid, the present Writ Petition stands disposed of

with liberty to the extent indicated hereinabove.
(MANINDER S. BHATTI)
JUDGE