M/S Skyline Air Conditioning Engineers Pvt Ltd vs Union Of India & Anr.

Court
Delhi High Court

$~20
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: 27 November, 2026
# CNR No. DLHC010524372026
+ ARB.P. 1950/2026
M/S SKYLINE AIR CONDITIONING ENGINEERS PVT LTD
.....Petitioner

Through: Ms. Neeru Nagpal with Mr. Arvind
Kumar Nagpal, Advocates.

versus

UNION OF INDIA & ANR. .....Respondents

Through: Ms. Radhika Bishwajit Dubey, CGSC
for UOI with Ms. Rakshita Goel, GP,
Ms. Gurleen Kaur Waraich,
Mr.Kritarth Upadhyay, Mr. Amulya
Dev Mishra and Mr. Saksham Sharma,
Advocates.
CORAM:
HON'BLE MR. JUSTICE MANOJ JAIN
J U D G M E N T (oral)

1. The present petition has been filed under Section 11(6)(a) of
Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘ the Act ’) ,
seeking appointment of a Sole Arbitrator for resolution of disputes which
have arisen between the parties.
2. Respondents had issued Notice Inviting Tender (NIT) for
comprehensive maintenance and work at GTB Hospital. The bid of the
petitioner was accepted, being the lowest one.
3. According to petitioner, though the work was completed successfully,
there were fundamental breaches of several terms and conditions of the
Signature Not Verified
Digitally Signed
By:SONIA THAPLIYAL
Signing Date:28.11.2026
14:43:34
ARB.P. 1950/2026 1


agreement and despite consistent persuasion by the petitioner, the respondent
failed to release due payments to the petitioner.
4. The outstanding amount is stated to be more than Rs.8 crores.
5. According to petitioner, the agreement between the parties contains
arbitration clause and that the parties are bound by General Conditions of
Contract (GCC), 2019, which contains arbitration clause. Reference is made
to clause No. 25.
6. Learned counsel for the petitioner submits that before invoking
arbitration, they had sent a communication to respondent on 15.05.2025,
requesting them to refer the disputes to the Disputes Redressal Committee
(DRC) for due adjudication in terms of the agreement between the parties but
despite such communication, for the reasons best known to the respondents,
no such Committee was ever constituted by the respondents and it is in the
abovesaid backdrop that there is a prayer for appointment of Arbitrator.
7. On the last date of hearing, Ms. Radhika Bishwajit Dubey, learned
CGSC had appeared for Union of India and was requested to take instructions
from the respondents about the status of constitution of any DRC, and if so,
the status of abovesaid communication sent by the petitioner.
8. Ms. Dubey, learned CGSC, in all fairness, submits that she has not
received any instructions in this regard.
9. Fact, however, remains that the abovesaid communication sent by the
petitioner is clear enough and invocation of the arbitration is only after no
such Committee was constituted by the respondents. There is no dispute
with respect to the fact that there is an agreement between the parties which
contains arbitration clause.
10. Both the sides do agree that Arbitrator has to be a person having
Signature Not Verified
Digitally Signed
By:SONIA THAPLIYAL
Signing Date:28.11.2026
14:43:34
ARB.P. 1950/2026 2


requisite Engineering background with experience in execution of public
works engineering contracts, and he should have worked earlier at a level not
lower than the Chief Engineer (equivalent to level of Joint Secretary to the
Government of India), in terms of the stipulated agreement.
11. Keeping in mind the abovesaid submissions, the petition stands
disposed of with the following directions:-
i) The disputes between parties concerning said agreement are
referred to Arbitration.

ii) The Arbitration will be held under the aegis of DIAC and
would be governed by the Rules of DIAC. The fee of the
Arbitrator shall be fixed as per fee schedule under DIAC
(Administrative Cost and Arbitrator’s fees) Rules 2018.
iii) DIAC shall appoint a Sole Arbitrator to adjudicate the disputes
between the parties. Such Sole Arbitrator would be a person
having requisite Engineering background, as indicated above.
iv) The learned Arbitrator, so appointed, is requested to furnish
declaration in terms of Section 12 of the Act prior to entering
into the reference.
v) It is made clear that all the rights and contentions of the
parties, including as to the arbitrability of the claim and any
other preliminary objections regarding limitation, misjoinder
etc. as well as merits of claim or counter claim, if any, are left
open for adjudication by the learned Arbitrator.
vi) The parties shall approach DIAC within one week from today.
12. The petition stands disposed of in aforesaid terms.
13. A copy of this order be communicated by the Registry to the learned
Signature Not Verified
Digitally Signed
By:SONIA THAPLIYAL
Signing Date:28.11.2026
14:43:34
ARB.P. 1950/2026 3


coordinator of the DIAC.

(MANOJ JAIN)
JUDGE
NOVEMBER 27, 2026/st/sa