SRI. SANJEEV. A. KURUP vs CHIEF COMMISSIONER
- Court
- Karnataka High Court
- 1 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 17 DAY OF NOVEMBER, 2026
BEFORE
THE HON'BLE MR. JUSTICE B M SHYAM PRASAD
WRIT PETITION NO. 35210 OF 2026 (LB-BMP)
C/W
WRIT PETITION NO. 35234 OF 2026 (LB-BMP)
IN WP No. 35210/2026
BETWEEN:
SRI. VINITH KUMAR. G. K.
S/O SRI. GOVINDARAJAN
AGED ABOUT 29 YEARS
R/AT NO.11, SHAKTHINAGAR,
DOORWANINAGAR,
BEHIND ROYAL HERITAGE
APARTMENT,
BENGALURU-560 016
Digitally
signed by
VANAMALA
N
Location:
HIGH
COURT OF
KARNATAKA
…PETITIONER
(BY SRI. MALLIKARJUN N K., ADVOCATE)
AND:
1. CHIEF COMMISSIONER
GREATER BENGALURU AUTHORITY (GBA)
N R SQUARE, HUDSUN CIRCLE
- 2 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
BENGALURU 560 001
2.
COMMISSIONER
BENGALURU EAST CITY CORPORATION /
GREATER BENGALURU AUTHORITY,
COMMISSIONER OFFICE,
OPP. PHOENIX MALL,
RHB COLONY, MAHADEVAPURA,
BENGALURU, KARNATAKA 560 048
3. THE JOINT COMMISSIONER
BENGALURU EAST CITY CORPORATION /
K.R. PURA ZONE-2,
GREATER BENGALURU AUTHORITY (GBA),
K.R. PURA,
BENGALURU - 560 036
4. THE ASSISTANT EXECUTIVE ENGINEER
MAHADEVAPURA SUB-DIVISION,
M.I.G. LAYOUT,
BENGALURU EAST CITY CORPORATION,
GREATER BENGALURU AUTHORITY (GBA),
BENGALURU - 560 016
…RESPONDENTS
(BY SRI. PAWAN KUMAR, ADVOCATE)
THIS WP IS FILED UNDER ARTICLE 226 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT
THE RESPONDENTS NO TO TAKE ANY COERCIVE
STEPS AGAINST THE PETITIONERS ON THE
SCHEDULE PROPERTY TILL CONCLUSION OF
- 3 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
APPEAL NO. 154/2026 BEFORE THE R1 CHIEF
COMMISSIONER GBA VIDE ANNX-J.
IN WP NO. 35234/2026
BETWEEN:
1.
SRI. SANJEEV. A. KURUP
S/O LATE ATCHUTHA KURUP
AGED ABOUT 71 YEARS
2. SMT. LATA PILLAI @
LATA R. PILLAI
W/O SANJEEV A KURUP
AGED ABOUT 67 YEARS
BOTH ARE RESIDING PROPERTY
NO. 08, NEAR VINAYAKA TEMPLE,
UDAYANAGAR,
DOORAVANI NAGAR
BENGALURU-560 016
...PETITIONERS
(BY SRI. MALLIKARJUN N K., ADVOCATE)
AND:
1. CHIEF COMMISSIONER
CHIEF COMMISSIONER,
GREATER BENGALURU AUTHORITY (GBA)
N R SQUARE, HUDSUN CIRCLE
BENGALURU 560 001
2.
COMMISSIONER,
BENGALURU EAST CITY CORPORATION,
COMMISSIONER OFFICE, OPP PHOENIX MALL
- 4 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
RHB COLONY, MAHADEVAPURA,
BENGALURU, KARNATAKA 560 048
3.
THE JOINT COMMISSIONER
BENGALURU EAST CITY CORPORATION /
K.R. PURA ZONE-2,
GREATER BENGALURU AUTHORITY (GBA),
K.R. PURA, BENGALURU - 560 036.
4. THE ASSISTANT EXECUTIVE ENGINEER
MAHADEVAPURA SUB-DIVISION,
M.I.G LAYOUT
BENGALURU EAST CITY CORPORATION,
GREATER BENGALURU AUTHORITY (GBA),
BENGALURU 560 016
...RESPONDENTS
(BY SRI. PAWAN KUMAR, ADVOCATE)
THIS WP IS FILED UNDER ARTICLE 226 OF
THE CONSTITUTION OF INDIA PRAYING TO DIRECT
THE RESPONDENTS NO TO TAKE ANY COERCIVE
STEPS AGAINST THE PETITIONERS ON THE
SCHEDULE PROPERTY TILL CONCLUSION OF
APPEAL NO. 153/2026 BEFORE THE R1 CHIEF
COMMISSIONER GBA VIDE ANNX-L.
THESE PETITIONS, COMING ON FOR
PRELIMINARY HEARING, THIS DAY, ORDER WAS
MADE THEREIN AS UNDER:
CORAM: HON'BLE MR. JUSTICE B M SHYAM PRASAD
- 5 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
ORAL ORDER
The petitioners are owners of different
properties, but their cause to invoke this Court’s
jurisdiction under Article 226 of the Constitution of
India is identical. The petitioners are served with the
respective Confirmation Order under Section
243[3][e] and 244 of the Greater Bengaluru
Governance Act, 2024 [for short, ‘ the GBG Act’ ], and
they filed their appeals under Section 250 of the GBG
Act against these Confirmation Orders. The Appellate
Authority has not considered the petitioners’ request
for interim order staying precipitative action during
the pendency of the appeal/s.
2. The proceedings under Section 243[3] of
the GBG Act are initiated against the petitioners on
the ground that they have begun/completed
construction without a sanctioned plan. The
petitioners do not assert that they have a sanctioned
plan, but they contend that after the proceedings
- 6 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
are initiated under Section 243[3] of the GBG Act,
the Authorities have issued them with revenue
entries for the respective properties in Form No. A;
initially they had revenue entries in Form No. B; and
that they being admitted to revenue entries in Form
No. A, are entitled to apply for the sanction plan and
they have accordingly applied.
3. Mr. Mallikarjun N K, the learned counsel
for the petitioners, relying upon these
circumstances, submits that the petitioners are
constrained to file these petitions for direction to the
Appellate Authority who is seized of the
corresponding appeals to direct the respondents not
to take coercive measures because the Appellate
Authority has called for records without considering
the request for interim order and there would be
precipitation if there is no interim order by this
Court notwithstanding the circumstances as stated
above.
- 7 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
4. Mr. Pawan Kumar, the learned Standing
counsel for the common respondents, is heard on
the terms for the disposal of the petitions, especially
with Mr. Mallikarjun N K stating, when queried by
this Court, that the petitioner in
W.P.No.35210/2026 has stopped construction over
the last one year because of the proceedings and
that the petitioners in W.P.No.35234/2026 have
bonafide completed residential accommodation
comprising of ground and first floors and that
neither of these petitioners propose to change the
nature of the construction until there is a final
outcome in the pending appeals.
5. This Court is of the view that in the
circumstances, the petitions must be preferred
directing the respondents not to take coercive
measures to dismantle/demolish the standing
structures in the petitioners’ respective properties
during the pendency of the respective appeals
- 8 -
HC-KAR
NC: 2026:KHC:63623
WP No. 35210 of 2026
C/W WP No. 35234 of 2026
CNR: KAHC010782282026
observing that any coercive measure shall be subject
to the final outcome in the pending appeals while
stipulating specifically that the petitioners shall not
change the nature of the properties by
recommencing the construction or otherwise.
It is ordered accordingly and the petitions stand
disposed of .
Sd/-
(B M SHYAM PRASAD)
JUDGE
RB
List No.: 3 Sl No.: 1