M/S Nk Toll Road Ltd vs National Highways Authority Of India
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Reserved on: 17 April, 2026
th
Pronounced on: 27 April, 2026
+ ARB. A. (COMM.) 12/2026 & I.A. 1379/2026
M/S NK TOLL ROAD LTD. .....Petitioner
Through: Mr. Ankur Kashyap, Mr. Hasan
Murtaza, Mr. Aman Bajaj, Mr.
Sameer Sharma, Mr. Aman Bajaj, Mr.
Purushartha Singh, Mr. Ankit Kr.
Singh and Mr. Siddharth Dua, Mr.
Jaideep Khot, Advs.
M: 9289037441
versus
NATIONAL HIGHWAYS AUTHORITY OF INDIA .....Respondent
Through: Mr. Nishant Awana, Ms. Rini Badoni
and Ms. Nitya Sharma, Advs.
M: 7838760760
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
JUDGMENT
MINI PUSHKARNA, J.
Background
1. The present appeal has been filed under Section 37(2)(b) of the
Arbitration and Conciliation Act, 1996 (“Arbitration Act”) against the
rd
interim order dated 03 January, 2026 (“impugned order”) , passed in the
on-going arbitration proceedings, titled as “N.K. Toll Road Limited Versus
National Highway Authority of India” . The Arbitral Tribunal, vide the
impugned order, disposed of the application of the
appellant/claimant/concessionaire, i.e., N.K. Toll Road Limited, filed under
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 1 of 19
Section 17 of the Arbitration Act, seeking stay on the operation and effect of
th
the Cure Period Notice dated 07 October, 2025, issued by the respondent,
namely, National Highway Authority of India (“NHAI”) under Articles
th
32.1.1 and 32.1.3 of the Concession Agreement dated 30 January, 2006
(“Concession Agreement”) , executed between the parties.
2. More particularly, the Arbitral Tribunal restrained the respondent from
taking any action with respect to the breaches/defaults alleged by it in Para
9(a)(i) to (iii) of the Cure Period Notice, since the said allegations were
subject matter of adjudication by the Arbitral Tribunal in the on-going
arbitration proceedings. However, the Arbitral Tribunal held that the
respondent would be well within its right to proceed with the Cure Period
Notice in respect of the alleged default of non-compliance of divestment
requirements under the Concession Agreement, as mentioned in Para
9(a)(iv) of the Cure Period Notice.
3. By way of the present appeal, the appellant has confined its challenge
to the limited extent that while the Arbitral Tribunal has granted interim
protection to the appellant against the alleged defaults relating to periodic
overlay obligations, consequential damages, and FASTag remittance forming
part of the Cure Period Notice [Para 9(a)(i) to (iii)] , it nevertheless
permitted the respondent to proceed further with the said Cure Period
Notice, insofar as it concerns the alleged non-compliance of Article 34.11 of
the Concession Agreement [Para 9(a)(iv)] , thus, rendering the Concession
Agreement exposed to forthwith termination.
Factual Matrix
4. The facts, in brief, leading to the filing of the present appeal are as
follows:
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 2 of 19
th
4.1. The parties entered into the Concession Agreement dated 30 January,
2006 for design, construction, development, finance, operation and
maintenance of a project highway from Km 258.645 (end of Namakkal
Bypass) to Km 292.600 (start of Karur Bypass), on NH-7 from a two-lane to
a four-lane highway, covering 33.48 Kms to be executed on a Build-
Operate-Transfer (“BOT”) Toll basis. Additionally, the project involved the
improvement, operation and maintenance of the Sections from Km 248.625
(start of the proposed flyover on Namakkal Bypass) to Km 258.645 (end of
Namakkal Bypass) on NH-7 on a BOT basis.
th
4.2. The aforesaid Concession Agreement commenced from 29 July,
th
2006, and is scheduled to expire on 28 July, 2026, i.e., for a period of
twenty (20) years, which is further extendable by three (3) months.
4.3. In furtherance of the Concession Agreement, the appellant completed
the construction of the project highway, and thereby, commenced the toll
operations. However, during the operation and maintenance of the project
highway, various disputes arose between the parties, in relation to the
interpretation and enforcement of specific provisions of the Concession
Agreement.
4.4. Upon failure of resolution of the disputes amicably, the appellant
herein invoked the arbitration clause, i.e., Article 39.2 of the Concession
th
Agreement, by issuing a letter dated 24 May, 2024, wherein, the appellant
claimed damages against the respondent under two broad heads, namely,
Force Majeure (Covid-19) and Change in Law.
4.5. Pursuant thereto, an Arbitral Tribunal was constituted for adjudication
of the disputes between the parties. Before the said Arbitral Tribunal, the
appellant filed its Statement of Claims (“SoC”) , seeking declaration that the
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 3 of 19
appellant is not liable to pay damages qua the claims of the respondent
pertaining to non-performance of periodic Bituminous Concrete (“BC”)
overlay obligations, non-payment of damages, non-remittance of FASTag
additional fee/double toll fee, etc. Additionally, the appellant raised various
monetary claims in the form of compensation from the respondent, majorly
on account of Force Majeure and Change in Law.
4.6. In response, the NHAI filed its Statement of Defence (“SoD”) , along
with a Statement of Counter-Claims.
4.7. During the pendency of the arbitration proceedings, the respondent
th
issued the Cure Period Notice on 07 October, 2025, thereby, invoking
Articles 32.1.1 and 32.1.3 of the Concession Agreement, alleging certain
defaults on the part of the appellant. The alleged defaults, summarized in
Para 9 of the Cure Period Notice, included failure to undertake the periodic
overlay works, failure to pay damages imposed by the respondent on
account of the alleged delay in such overlay works, non-remittance of
additional FASTag fee and non-compliance of Article 34.11 relating to
retention of funds in the Escrow Account or, alternatively, furnishing of a
Bank Guarantee. Further, the Cure Period Notice also envisaged termination
of the Concession Agreement in the event of failure of appellant to cure the
alleged defects within a period of 30 days.
4.8. The aforesaid Cure Period Notice had been issued by the respondent
th
on the basis of a letter dated 28 September, 2024 of the Independent
Consultant/Engineer (“IE”) , i.e., L N Malviya Infra Projects Pvt. Ltd, which
had, in terms of Article 34.11 of the Concession Agreement prepared
calculations in compliance of divestment requirements under the said
Article. As per the said letter, in terms of Article 34.11, the amount to be
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 4 of 19
retained corresponding to calculations based upon traffic volume taken at
10,000 Passenger Car Units (“PCUs”) came to a total of Rs. 46,54,70,305/-,
whereas, the calculation qua the renewal works was to the tune of Rs.
39,01,98,330/-. Accordingly, the appellant was directed to retain a sum of
Rs. 46,54,70,305/- in the Escrow Account, or furnish a Bank Guarantee of
an equivalent sum, on account of the said calculation based on traffic
volume being higher than the calculation in respect of renewal works.
4.9. Pursuant to the said letter of the IE, the respondent sought compliance
th
of Article 34.11 from the appellant vide its letter dated 05 October, 2024,
whereby, the appellant was requested to retain the amount of Rs.
46,54,70,305/- as a Bank Guarantee.
4.10. The aforesaid requirement, as pointed out by the respondent, was
th
disputed by the appellant vide its response dated 11 November, 2024, by
stating that the very basis for seeking compliance with divestment
requirements was pending adjudication before the Arbitral Tribunal.
4.11. It is in this background that during pendency of the arbitral
proceedings, which were at the stage of final hearing, the Cure Period
th
Notice came to be issued by the respondent on 07 October, 2025. The
rd
appellant, in response to the Cure Period Notice, vide letter dated 23
October, 2025, denied the defaults alleged by the respondent.
4.12. Further, aggrieved thereof, the appellant filed an application under
Section 17 of the Arbitration Act before the Arbitral Tribunal, seeking stay
of the Cure Period Notice issued by the respondent and interim protection
against coercive and consequential actions arising therefrom.
4.13. Consequently, the impugned order came to be passed, whereby the
Arbitral Tribunal partly allowed the application filed by the appellant under
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 5 of 19
Section 17 of the Arbitration Act. The appellant/claimant has, thus, filed the
present appeal seeking to set aside the impugned order.
Rival Submissions of the Parties:
5. Before recording the submissions of the parties, it is reiterated that the
challenge before this Court is only confined to the finding of the Arbitral
Tribunal in respect of Para 9(a)(iv) of the Cure Period Notice. Though the
respondent in its reply has also sought to dispute the finding of the Arbitral
Tribunal pertaining to determinable nature of the Concession Agreement
between the parties, no separate appeal has been preferred by the respondent
against the impugned order, in any respect. Therefore, this Court deems it
appropriate to restrict the submissions of the parties qua the sole issue raised
before this Court, as noted hereinabove.
6. Accordingly, on behalf of the appellant, the following submissions
have been advanced:
6.1. The Arbitral Tribunal permitted enforcement of Article 34.11 of the
Concession Agreement on the basis of an unreasoned order, in absence of
any finding of a breach/default and permitted subsequent coercive action,
which violates the Principles of Natural Justice and constitutes a failure to
exercise its jurisdiction in accordance with Section 17 of the Arbitration Act.
6.2. Article 34.11 of the Concession Agreement is not an independent
obligation. The said Article forms part of the Chapter VIII, i.e., “Defects
Liability”, which is applicable only post-identification of an undisputed
defect that requires rectification. Further, Articles 34.1 to 34.10 establish a
structured mechanism commencing with joint inspections of the project
highway, followed by the respondent’s assessment of the road condition,
proposals for renewal works, the IE’s technical scrutiny and objections, and
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 6 of 19
if necessary, resolution of disputes through the dispute resolution
mechanism enshrined in the Concession Agreement. Thus, Article 34.11
operates within and not outside the inspection centric framework.
6.3. Article 34.11 has been invoked by the respondent based upon the
th
letter dated 28 September, 2024 of the IE, as per which, the IE had
assumed that the appellant failed to undertake the third periodic overlay,
whereas, the disputed overlay obligation is sub-judice before the Arbitral
Tribunal. Further, the respondent by placing reliance on the IE’s letter and
Article 34.11, in its SOD and Counter-Claims has itself brought the issue of
third overlay within the scope of adjudication before the Arbitral Tribunal.
6.4. Once the principal issue regarding the alleged third BC overlay is
before the Arbitral Tribunal, all contractual obligations flowing therefrom
shall necessarily fall within the Arbitral Tribunal’s adjudicatory domain.
Therefore, allowing the respondent to invoke Article 34.11 amounts to pre-
judging the issues that are yet to be finally decided by the Arbitral Tribunal.
6.5. The pavement condition of the project highway continues to remain
compliant with the contractual parameters. The same is apparent from the
technical assessments carried out by the IE, as recorded in its various letters,
which contain the results pertaining to Bump Integrator Test and Benkelman
Beam Deflection, as prescribed under Articles 4.3.1(ii) and 4.3.2 of
Schedule-L attached along with the Concession Agreement.
6.6. The contentions of the respondent regarding public safety are
misplaced as public interest lies in preserving the operational stability rather
than precipitating a change of operator in the final months of the concession
period. Furthermore, termination at this stage would frustrate and render the
pending arbitration proceedings substantially infructuous.
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 7 of 19
6.7. The impugned finding of the Arbitral Tribunal also suffers from
infirmity on account of failure to interpret and construct Article 34.11 of the
Concession Agreement, and further, by omitting to balance the interest of
the parties, while rendering the impugned finding.
7. Per contra , on behalf of the respondent, the following submissions
have been put forth:
7.1. The appellate interference under Section 37 of the Arbitration Act is
extremely circumscribed and the appellant has failed to demonstrate any
perversity, patent illegality or jurisdictional error in the impugned order. The
Arbitral Tribunal, on the basis of the record before it, has taken a plausible
view, which does not warrant any interference.
7.2. The Concession Agreement expressly confers upon the respondent an
independent and substantive non-derogable right to issue a Cure Period
Notice, and upon failure of the appellant to cure defaults specified in the
Cure Period Notice within the stipulated cure period, to further terminate the
Concession Agreement. The same is not contingent upon or subordinate to
the arbitral proceedings.
7.3. The pendency of the arbitral proceedings does not create any embargo
on exercise of contractual rights by either party, and moreover, the
appellant’s monetary claims, being fully compensable in damages, can be
efficaciously adjudicated irrespective of whether the Concession Agreement
continues or stands terminated.
7.4. The Arbitral Tribunal itself recognised the separability and
enforceability of Article 34.11 and expressly permitted the respondent to
proceed in respect thereof.
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 8 of 19
7.5. The admitted failure of the appellant to retain Rs. 46,54,70,305/- or to
furnish a Bank Guarantee, constitutes a clear and continuing default, which
justifies invocation of the cure mechanism under the Concession Agreement.
7.6. Article 34 of the Concession Agreement provides a comprehensive
framework for defects liability and the divestment requirements therein are
linked to renewal works, which are not merely restricted to BC overlay, as
expressly provided in the Clause 33.2 of the Concession Agreement. Thus,
the compliance under Article 34.11 is not dependent on the completion of a
particular overlay cycle, but rather, is a mechanism to ensure a reserve of
adequate funds so that renewal works can be executed prior to handing over
of the project highway to the respondent upon expiry of the concession
period. Moreover, the said Article operates “from the date which is 2 years
prior to the expiry of the Concession Period” , and is not made contingent
upon adjudication of any prior dispute.
7.7. Any injunctive relief that disables the respondent from implementing
an express divestment-stage safeguard (Article 34.11) and from exercising
termination rights (Article 32), despite admitted non-compliance, would
interfere with the respondent’s statutory duty and frustrate the public interest
in relation to safe and efficient operation of the national highways.
Analysis and Findings:
8. I have heard learned counsels appearing for both the parties and
perused the pleadings and documents on record before this Court.
9. At the outset, this Court notes that the respondent vide the letter dated
th
07 October, 2025, i.e., the Cure Period Notice, issued to the appellant,
highlighted various defaults of the appellant under the Concession
Agreement, in Para 9(a) of the same, as follows:
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 9 of 19
“xxx xxx xxx
xxx xxx xxx”
10. On the basis of the aforesaid defaults, the appellant was called upon
by the respondent to deposit various amounts, as notified in Para 9(b) of the
Cure Period Notice, in the following manner:
“xxx xxx xxx
xxx xxx xxx”
11. As regards the defaults highlighted by the respondent in the Cure
Period Notice in Paras 9(a)(i), (ii) and (iii) , and recovery of damages
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 10 of 19
thereto are concerned, the Arbitral Tribunal categorically held that the said
issues were pending before it, and therefore, such notice for recovery of
damages in respect of the aforesaid alleged defaults would tantamount to
pre-judging the issues already pending adjudication before the Arbitral
Tribunal.
12. However, in relation to the defect pointed out in Para 9(a)(iv) of the
Cure Period Notice, with regard to non-compliance of the divestment
requirement of retaining certain amounts in the Escrow Account, and deposit
of Rs. 46.54 Crores on account thereof, the Arbitral Tribunal categorically
held that retention of such amount in the Escrow Account is an independent
obligation of the appellant under the Concession Agreement, and therefore,
the same is required to be retained by the appellant herein. The finding of
the Arbitral Tribunal in this regard, which is subject matter of challenge in
the present appeal, is reproduced as under:
“xxx xxx xxx
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 11 of 19
xxx xxx xxx
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 12 of 19
xxx xxx xxx”
13. In respect of the issues raised before this Court, it is to be noted that
the Concession Agreement between the parties imposes continuous
obligations upon the appellant, being the concessionaire, regarding various
compliances, which are required to be made under the Concession
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 13 of 19
Agreement. The issue regarding the obligation of the appellant to retain the
sums in Escrow Account emanates from Article 34.11 of the Concession
Agreement, which reads as under:
“34.11. From the date which is 2 years prior to the expiry of the
Concession Period a sum equal to the Fees realisable during the last
two years of the Concession Period for a traffic volume calculated at
the rate of 10,000 (ten thousand) PCUs per day per year or a higher
sum estimated by the Independent Consultant for Renewal Works,
shall notwithstanding anything to the contrary contained in this
Agreement, be retained in the Escrow Account provided that if a
Bank Guarantee of an equivalent sum in the form and content
acceptable to NHAI has been furnished by the Concessionaire to
NHAI, no such retention shall be made.”
(Emphasis Supplied)
14. Hence, Article 34.11 of the Concession Agreement provides that from
two years prior to expiry of the concession period, a sum equal to the fees
realizable during the last two years of the concession period or a higher sum
estimated by the IE for renewal works, shall be retained in the Escrow
Account, or be secured by furnishing a Bank Guarantee of an equivalent
sum. The said covenant, as mandated under Article 34.11, is
notwithstanding anything to the contrary contained in the Concession
Agreement, meaning thereby, the mandate of Article 34.11 is an
independent obligation, irrespective of other stipulations under the
Concession Agreement. The mandate under Article 34.11 cannot be linked
to other stipulations provided under the Concession Agreement with regard
to requirement of BC overlay, as sought to be done by the appellant.
th
15. In terms of the aforesaid Article, the IE by way of his letter dated 28
September, 2024, calculated the amount of toll revenue as Rs.
46,54,70,305/-, whereas, the amount for renewal works was estimated as Rs.
th
39,01,98,330/-. The letter dated 28 September, 2024 issued by the IE is
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 14 of 19
reproduced as under:
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 15 of 19
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 16 of 19
16. Thus, in terms of Article 34.11, the appellant was required to retain
the higher sum towards the toll revenue as calculated by the IE, which in the
present case is an amount of Rs. 46,54,70,305/-.
17. The appellant has never challenged the calculations made by the IE
th
vide the letter dated 28 September, 2024. Accordingly, since the calculation
in respect of traffic volume was higher, the appellant was required to retain
Rs. 46.54 Crores in the Escrow Account or furnish a Bank Guarantee of an
equivalent sum, in terms of Article 34.11 of the Concession Agreement. The
retention of the sum under Article 34.11 is a separate and independent
obligation under the Concession Agreement, which the appellant is enjoined
upon to comply.
18. Further, it is to be noted that the fifteen issues, which are subject
matter of adjudication before the Arbitral Tribunal, have been framed vide
th
the Procedural Order dated 10 March, 2025. It is manifest from the reading
of the said issues that none of them can be said to overlap, in any manner
whatsoever, with the obligation under Article 34.11. Furthermore, the
appellant’s attempt to confine Article 34.11 solely to a disputed BC overlay
obligation is contrary to the plain language of the contractual terms. Article
34.11 relates to renewal works across all project assets, including pavement,
structures and ancillary facilities. The obligation under Article 34.11 is not
dependent upon completion of a particular BC overlay cycle, but on
ensuring that adequate funds are reserved so that all renewal works can be
executed prior to handing back. The fact that the appellant has been
continuing to perform the various renewal works is no justification for not
complying with the obligation under Article 34.11, which stipulates in
categorical terms regarding retaining an amount in Escrow Account or
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 17 of 19
providing Bank Guarantee of equivalent sum in terms of the calculations
made by the IE.
19. Accordingly, in view of the aforesaid discussion, this Court finds no
infirmity with the impugned finding of the Arbitral Tribunal.
20. It is well settled that the scope of adjudication under Section 37 of the
Arbitration Act is extremely narrow and the consideration under Section
37(2)(b) of the Arbitration Act is not fundamentally different from that
under Section 34 of the Arbitration Act. It is only when the interim order
suffers from patent illegality or perversity that the Court shall exercise its
jurisdiction under Section 37(2)(b) of the Arbitration Act. However, as long
as the view adopted by the Arbitral Tribunal is a plausible one, the Court
should refrain from interfering with the order passed by the Arbitral
Tribunal. Thus, this Court in the case of Dinesh Gupta and Others Versus
Anand Gupta and Others, 2020 SCC OnLine Del 2099 , held as follows:
“xxx xxx xxx
114. This Court, while exercising appellate jurisdiction, under
Section 37(2) of the 1996 Act, over the interim order of the learned
Sole Arbitrator, is not expected, or even required, to delve deep into
the facts of the case. Nor is it expected to substitute its own
discretion, for the discretion of the learned Sole Arbitrator. If the
exercise of discretion, by the learned Sole Arbitrator, suffers from
patent illegality, or is otherwise unconscionable in law or on facts,
interference may be justified; never otherwise .
xxx xxx xxx”
(Emphasis Supplied)
21. Viewing the present case in the light of the settled proposition of law
regarding minimal interference by Courts under Section 37 of the
Arbitration Act, the view expressed by the learned Arbitral Tribunal is
plausible and well-reasoned.
22. Furthermore, the issue with respect to balance of convenience, prima
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:27.04.2026
17:49:51
ARB. A. (COMM.) 12/2026 Page 18 of 19
facie case and irreparable prejudice cannot be raised by a party with regard
to questions involving compliance of mandatory obligations under the
contract. Thus, the appellant cannot seek to raise such pleas qua the
compliances required to be made by the appellant under the terms of the
Concession Agreement.
23. For the aforesaid reasons, no interference is warranted in the
impugned order passed by the Arbitral Tribunal. The present appeal is
accordingly dismissed.
MINI PUSHKARNA
(JUDGE)
APRIL 27, 2026/ SK
Signature Not Verified