Public Works Department, Govt. Of Nct Of Delhi vs M/S. Sps Infrabuild Pvt. Ltd
- Court
- Delhi High Court
$~43
* IN THE HIGH COURT OF DELHI AT NEW DELHI
# CNR No. DLHC010795472025
+ O.M.P. (COMM) 427/2025, I.A. 25870/2025
PUBLIC WORKS DEPARTMENT, GOVT. OF NCT OF
DELHI .....Petitioner
Through: Mr. Anubhav Gupta, Panel
Counsel (Civil), GNCTD.
versus
M/S. SPS INFRABUILD PVT. LTD .....Respondent
Through: Mr. Avinash Trivedi, Mr. Rahul
Aggarwal, Mr. Anurag
Kaushik, Mr. Jatin Arora, Mr.
Rishank Gola, Mr. Aryan
Sangwan and Mr. Rahul
Kumar, Advs.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT(ORAL)
% 19.11.2026
I.A. 25871/2025 (for delay in filing) and I.A. 25873/2025 (for delay
in re-filing)
1. The present applications have been filed on behalf of the
Petitioner seeking condonation of delay of 29 days in filing and a
further delay of 264 days in re-filing the present petition.
2. Learned Counsel appearing on behalf of the Petitioner submits
that the delay is neither intentional nor deliberate but due to the initial
processes, such as upon receipt of the arbitral award, legal opinion
was sought from the Counsel who had represented it in the arbitration
proceedings, which was received on 25.09.2024. Thereafter, the
matter was processed through various Departmental Authorities,
including the Superintending Engineer, Finance Officer, Chief
Engineer, Principal Chief Engineer, Engineer-in-Chief and the Law
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:00:35
O.M.P. (COMM) 427/2025 Page 1 of 6
Department, for obtaining the requisite approvals to challenge the
award and, thereafter, draft petition was prepared and sent to the
Department for approval on 23.01.2025, and the signed petition was
filed on 24.01.2025.
3. Learned Counsel for the Petitioner further submits that the
petition was initially filed on 24.01.2025, within the outer limit of 120
days expiring on 25.01.2025.
4. He further submits that the delay of 264 days in re-filing is
attributable to the voluminous nature of the record, comprising
approximately 1907 pages and the personal difficulties faced by the
Counsel, including a bereavement in the family and serious illness of
his mother.
5. Learned Counsel for the Petitioner further contends that the
initial filing was complete in all material respects, as all relevant
documents, Court fees, affidavits and vakalatnama had been filed and
no new pleadings or documents were introduced in the subsequent
filing.
6. Per contra, learned Counsel appearing on behalf of the
Respondent has opposed these applications, contending that the
petition itself was filed beyond the maximum period of 120 days
prescribed under Section 34(3) of the Arbitration and Conciliation
1
Act, 1996 and that such delay is incapable of being condoned. It is
further contended that the Petitioner has failed to provide any
1
“Act” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:00:35
O.M.P. (COMM) 427/2025 Page 2 of 6
satisfactory explanation for the delay in re-filing.
7. I have considered the rival submissions.
8. In the present case, the impugned award was corrected on
27.09.2024 and as per the filing log, the petition was initially filed on
24.01.2025. The initial filing, therefore, falls within the outer limit
prescribed under Section 34(3) of the Act. However, the fact that the
petition was filed within the maximum permissible period does not, by
itself, entitle the Petitioner to condonation of the delay beyond the
prescribed period of three months. The Petitioner is still required to
demonstrate sufficient cause for the delay of 29 days.
9. The explanation furnished by the Petitioner for the said delay is
primarily that upon receipt of the award, the matter was processed
through various Departmental Authorities for obtaining approvals to
challenge the award. The Petitioner has referred to the movement of
the file between the Superintending Engineer, Finance Officer, Chief
Engineer, Principal Chief Engineer, Engineer-in-Chief and the Law
Department, before the decision to challenge the award was finally
taken and the petition was prepared and filed.
10. In the considered opinion of this Court, the explanation does not
disclose any circumstances beyond the control of the Petitioner, which
prevented it from taking timely steps to institute the proceedings. The
movement of file between different Departments and the time
consumed in obtaining internal approvals are matters of administrative
procedure and cannot, by themselves, constitute sufficient cause for
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:00:35
O.M.P. (COMM) 427/2025 Page 3 of 6
condonation of delay.
11. In this regard, the observation of this Court in Government of
2
NCT of Delhi v. Shyam Sunder Tyagi assumes significance. The
Division Bench reiterated that in commercial matters, delay in re-
filing must also be treated with nearly the same seriousness as delay in
filing. It was further emphasised that where personal exigencies of
counsel are relied upon to explain the delay, the absence of any
satisfactory explanation for the period subsequent to the cessation of
such exigencies would disentitle the litigant from seeking condonation
of the delay.
12. Coming to the delay of 264 days in re-filing, it is well settled
that although the consideration governing re-filing are distinct from
those applicable to the original filing, the delay cannot be condoned
mechanically. This Court is required to examine whether the entire
period of delay has been satisfactorily explained.
13. In the present case, the Petitioner seeks to explain the delay in
re-filing, primarily on the ground that the petition was voluminous,
comprising approximately 1907 pages at the time of its initial filing,
and that the Counsel was facing personal difficulties. In this regard,
reliance has been placed upon the demise of the grandfather of
Counsel’s wife and the deteriorating health of his mother, whose heart
functioning was stated to have reduced to 25%.
14. While this Court is conscious of the personal circumstances
2
2026 SCC OnLine Del 5360
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:00:35
O.M.P. (COMM) 427/2025 Page 4 of 6
referred to by learned Counsel, the explanation furnished does not
account for the entire period of 264 days. The personal difficulties
relied upon relate substantially to the period around April 2025,
whereas the delay in re-filing extends over a much longer period, from
January to October 2025.
15. No satisfactory explanation has been furnished as to what steps
were taken during the remaining period to cure the defects and re-file
the petition. The mere assertion that the record was voluminous also
does not explain why the defects could not be removed within the
reasonable period.
16. In this regard, the judgment of the Division Bench of this Court
3
in Public Works Department v. Shyam Sunder Tyagi assumes
significance, wherein it was held that the entire period of delay in re-
filing must be satisfactorily explained and that an unexplained period
of delay would disentitle the party from seeking condonation.
17. Applying the aforesaid principles to the facts of the present
case, this Court finds that the Petitioner has failed to furnish a
satisfactory explanation for substantial portions of the period of 264
days. Neither the voluminous nature of the record nor the personal
difficulties pleaded on behalf of the Counsel sufficiently account for
the prolonged inaction. The explanation furnished is, therefore, neither
comprehensive nor adequate to establish sufficient cause for
condonation of the delay in re-filing.
3
2026 SCC OnLine Del 4214
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:00:35
O.M.P. (COMM) 427/2025 Page 5 of 6
18. The observations in Chief Engineer, Employees State
4
Insurance Corporation v. Enarch Consultants Pvt. Ltd , also
reinforce the requirement that limitation cannot be permitted to be
circumvented by reference to internal administrative processes or
subsequent procedural steps which do not furnish a legally sustainable
explanation for the delay.
19. In view of the above discussion, this Court is not satisfied that
sufficient cause has been made out either for condonation of the delay
of 29 days in filing or for a further delay of 264 days in re-filing the
petition. Accordingly, both the applications seeking condonation of
delay are dismissed.
20. Consequently, I.A. 25871/2025 and I.A. 25873/2025 seeking
condonation of delay in filing and re-filing is dismissed.
O.M.P. (COMM) 427/2025
21. Accordingly, the petition under Section 34 of the Act is also
dismissed. Pending application(s), if any, also stand disposed of.
OM PRAKASH SHUKLA, J
NOVEMBER 19, 2026/ gunn