Shailendra Teji vs Ujjain Municipal Corporation

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
1 WP-17430-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT INDORE

BEFORE
HON'BLE SHRI JUSTICE SANDEEP N. BHATT
st
ON THE 31 OF AUGUST, 2026
WRIT PETITION No. 17430 of 2026
CHANDA BAI SARVAN
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WITH
WRIT PETITION No. 17432 of 2026
SHAILENDRA TEJI
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17434 of 2026
SURAJ TEJI
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17552 of 2026
RAKESH KHOKAR
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17554 of 2026
NATHI BAI
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17556 of 2026
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
2 WP-17430-2026
SAVITRI BAI
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS


WRIT PETITION No. 17560 of 2026
SURESH
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17563 of 2026
DILIP
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17568 of 2026
CHETRAM
Versus
UJJAIN MUNICIPAL CORPORATION

WRIT PETITION No. 17569 of 2026
RAM KANYA BAI
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17572 of 2026
SEEMA TANWAR
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS

WRIT PETITION No. 17573 of 2026
KAMLA SARVAN
Versus
UJJAIN MUNICIPAL CORPORATION AND OTHERS
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
3 WP-17430-2026
Shri Tehjeeb Khan - Advocate for the petitioner

Shri Rishi Tiwari – Advocate along with Shri Nilesh Yadav – Advocate for the
respondent nos. 1 and 2 / Ujjain Municipal Corporation.
Shri Prashant Singh – Advocate General along with Shri Rahul Gupta, learned counsel
for the respondent no. 3/ MPRDC.
-------------------------------------------------------------------------------------------------
Reserved on : 18/08/2026.
Delivered on : 31/08/2026
-------------------------------------------------------------------------------------------------
ORDER
1/ This order will govern the disposal of WP/17430/2026 WP/17432/2026,
WP/17434/2026, WP/17552/2026 , WP/17554/2026. WP/17556/2026 ,
WP/17560/2026, WP/17563/2026 , WP/17568/2026 , WP/17569/2026 ,
WP/17572/2026 and WP/17573/2026 as it is jointly submitted by counsel for the
parties that all these writ petitions involve the same issue on the identical facts
situation. For the sake of convenience, the facts are noted from WP No. 17430 of
2026
2/ Present petition i.e. WP No. 17430 of 2026 has been filed under Article 226
of the Constitution of India seeking following reliefs :
1. Call for the entire records pertaining to the case of the petitioner..
2. Quash the impugned order dt. 04.05.2026 (Filed as
ANNEXURE-P/1) passed by the respondents no. 2.
3. Issue an appropriate writ, order, or direction, including a writ in the nature of
mandamus, restraining the Respondents, their agents, servants, or any person
acting on their behalf, from dispossessing the Petitioner from the subject
property without paying compensation as per Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013;
4. Grant any other relief(s) which this Hon’ble Court may deem fit, proper and
just-in the facts and circumstances of the case, in the interest of justice.
3/ The facts of the case in brief are that the petitioner is the lawful owner and
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
4 WP-17430-2026
occupier of the subject property, having purchased the same from respondent Nos.

2 and 3 by way of a registered sale deed dated 10.03.2021. The said property was
originally allotted by respondent Nos. 1 and 2 in favour of the petitioner’s
husband, namely Late Mangilal Sarwan. It is further submitted that the petitioner
has been residing in the said property along with her family members. Thereafter,
due to construction Hari Fatak railway over bridge project, notice of
dispossession was issued against the petitioner. Thereafter, the petitioner had
preferred Writ Petition b 12369/2026 and vide order dated 06.04.2026, this Court
directed the respondents to issue a proper show-cause notice to the petitioner and
further granted 15 days’ time to the petitioner to submit a reply thereto and
thereafter, the respondents shall be at liberty to pass an appropriate speaking order
strictly in accordance with law. In compliance with the said order, respondent No.
2 had issued a show cause notice dated on 10.04.2026 to the petitioner by
directing to vacate the subject property within a period of 7 days, failing which
coercive action was proposed to be taken against him. The petitioner submitted a
detailed reply before respondent Nos. 1 and 2 within the stipulated period on
24.04.2026. Thereafter, respondent No. 2 passed the impugned order dated
04.05.2026 (Annexure-P/1), and directed to vacate his residential house within a
period of 10 days. Being aggrieved by the same, the petitioner has preferred
present petition before this Court. This Court, vide order dated 14/05/2026, by
granting interim relief, directed to maintain status quo with respect of the subject
property.
4/ Learned counsel for the petitioners has submitted that there is misuse of
Section 305 of the Madhya Pradesh Municipal Corporation Act, 1956 [ in short “
the Act, 1956”] to avoid statutory acquisition. Section 305 applies strictly to
regularizing existing street building lines managed directly by the Municipal
Corporation for municipal roads. The proposed 4-lane Railway Over Bridge
(ROB) at Hari Fatak is a fresh, central state engineering project independently
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
5 WP-17430-2026
funded, designed, and executed by the M.P. Road Development Corporation Ltd.

(MPRDC- Respondent No. 3). Learned counsel has further submitted that there is
abuse of power. The Ujjain Municipal Corporation [ in short “ UMC”] cannot
invoke Section 305 as a legal shield to summarily evict citizens and bypass
statutory land acquisition proceedings on behalf of an independent enterprise like
Madhya Pradesh Road Development Corporation [ in short “MPRDC] . There is
also violation of Article 300-A of the Constitution of India & Non-Compliance
with the provisions of the Right to Fair Compensation and Transparency in Land
Acquisition, Rehabilitation and Resettlement Act, 2013 [ in short “ the Act of
2013”]. Deprivation of property without prior determination and payment of fair
compensation is unconstitutional. Learned counsel has further submitted that
MPRDC (Respondent No. 3) has already sanctioned and transferred Rs.
4,81,66,544/- to the Collector, Ujjain specifically for land acquisition and
compensation. Despite receiving these funds, the Collector has failed to issue
formal acquisition notifications or pass an award under the Act of 2013. It is
further submitted that dispossession prior to the publication of an award and full
payment/tender of compensation directly violates Section 38 of the Act of 2013.
The futuristic FAR/TDR adjustments under Rule 61 of M.P. Bhumi Vikas
Niyam, 2012, or temporary rental handouts (Rs. 5,000/month) cannot substitute
the mandatory, pre-eviction monetary compensation and rehabilitation required
by law. The case of Ravindra Ramchandra Waghmare , which has been relied by
the respondents to justify FAR/TDR adjustments, is completely. distinguishable
from the facts of the present case. He has further relief upon the case i.e. Kalyani
(Dead) through L.Rs. v. The Sulthan Bathery Municipality (AIR 2022 SC 2073),
wherein Hon'ble Apex Court held that while road construction is a public
purpose, depriving a person of property without paying compensation is arbitrary
and violative of Article 300-A of the Constitution of India. Compensation is an
inbuilt requirement of Article 300-A of the Constitution of India. The public
urgency does not override law: The impending Simhastha 2028 event or general
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
6 WP-17430-2026
public interest cannot justify summary expropriation of private property without

authority of law. Learned counsel has further submitted that the public interest
allows acquisition, but does not grant authority to dispossess citizens without
prior statutory acquisition and compensation payment. Section 305 cannot
overwrite central land acquisition laws for a separate state highway project
executed by MPRDC. Meager temporary rent is an administrative handout, not a
lawful substitute for an expert structural valuation and fair acquisition award.
Without a formal notification and award under the Act of 2013, the Collector
cannot disburse funds. Dispossession prior to an award violates Section 38. Under
such circumstances, learned counsel prays that present petitions be allowed by
setting aside the impugned order.
5 / Per-contra, learned counsel for the respondent nos. 1 and 2 / Ujjain
Municipal Corporation has submitted that the section 305 of the Act casts a duty
upon the respondent / Corporation to regulate regular line of building as
delineated in the Ujjain Development Plan, 2035. There is a provision of the Hari
Phatak Bridge in the development Plan, 2035 (Annexure-R/1). Learned counsel
has further submitted that the Development Plan is binding on the Corporation.
The regular line of building has already been delineated at the time of finalization
of the Ujjain Development Plan, 2035 and the aforementioned development plan
is binding on the respondent Corporation. The Hon'ble Apex Court in the matter
of Ravindra Ramchandra Waghmare Vs. IMC: (2017) 1 SCC 667 has held that a
development plan is binding upon the Corporation and local authorities and all
concerned including the owners. The impugned order has been passed after
granting due opportunity of hearing vide notice dated 17.04.2026 (Annexure-R/7)
and subsequently, after considering the objections raised by the petitioner, a
detailed order has been passed by respondent no. 2.. Learned counsel has further
submitted that from a bare perusal of the impugned order it is evident that, the
petitioner will be compensated and the calculation of the compensation will be
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
7 WP-17430-2026
done as per the Collector Guidelines of the year 2026-27. Since, the payment of

compensation might take sometime, an amount of Rs. 5,000/- per month for a
period of 03 months will be paid to the petitioner as an interim measure. If the
petitioner are not satisfied by the compensation offered, then they may take
recourse to section 387 of the 1956, Act which provides for arbitration. It is
further submitted that the subject Railway Over Bridge (ROB) is being
constructed from the Hari Phatak Junction which is situated on the Indore road to
Mahankal Lok, Neelkanth Dwar via Begum Bagh Colony. Another limb of the
bridge connects Gopal Mandir and Kshipra river Ram Ghat. Thus, the
aforementioned bridge is crucial for connectivity to the Mahakal Temple, Gopal
Mandir, Ram Ghat, etc. Hence, in view of the upcoming Simhastha event in
which crores of devotees are expected to visit the aforementioned holy places, an
additional 04 lane bridge is being constructed. Even, the DPR, design and
planning of the proposed 04 lane bridge has been vetted by the technical experts
of IIT Indore (Annexure-R/2) and the aforementioned railway over bridge has
also been approved by the Chief Bridge Engineer (C.B.E of the Railways along
with other authorities of railways (Annexure-R/3). Under such circumstances,
looking to the larger public interest, present petition be dismissed.
6/ Learned Advocate General on behalf of respondent no. 3/ MPRDC has
submitted that there is availability of an efficacious statutory remedy under
Section 64 of the Act of 2013 and by virtue of the judgment delivered in the case
of Saira Bee & Ors. v. Urban Administration & Development Dept. (Writ Appeal
No. 117/2025, the Division Bench of this Court held that once a final land
acquisition award is passed, the High Court under Article 226 will not interfere
with the acquisition, and the remedy for remaining occupants is strictly to
approach the authority under Section 64 of the Act of 2013. In the case of Anil
Verma v. State of M.P. (W.P. No. 13246/2026, MP High Court Bench at Indore
has reiterated that after passing of an compensation, and maintaining a writ
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
8 WP-17430-2026
petition to stall execution of a public project is impermissible. Learned counsel

has further submitted that out of nearly 1,500 affected landowners, more than
1,300 have accepted the Award and compensation and the land owned by the
petitioner constitutes only a negligible portion of the total acquisition for the
19.815 km project corridor and handful of objectors cannot be permitted to
frustrate or delay a mega public infrastructure project undertaken in larger public
interest. In support of his contention, learned counsel has placed reliance upon the
judgment delivered by Hon'ble Supreme Court in the case of A.J. George v. State
of Kerala (2017 SCC OnLine Ker 23421) wherein it has been held that a land
acquisition award is indivisible, and once passed and accepted by the majority of
beneficiaries, an individual landowner cannot break the integrity of the award or
seek quashing of proceedings on the basis of minor procedural objections.
(Relevant Para 7 & 11). In the case of Bhimavarapu Giridhar Kumar Reddy v.
Union of India (2023 SCC OnLine AP 4484) the Andhra Pradesh High Court held
that where a highway is being constructed on either side, a small patch of land
forming a negligible portion of the corridor cannot be permitted to hold the public
infrastructure project hostage.
7/ Learned counsel has further submitted that the respondents have
substantially complied with all mandatory requirements unde Act of 2013,
including Sections 4, 5, 7, 11, 15, 19 and 21, read with the applicable Madhya
Pradesh Rules, He has placed reliance upon the judgment delivered in the case of
Binding Legal Precedent: Yudhvir Singh v. Govt. of NCT of Delhi (2024 SCC
Onine Del 471), relying upon the judgment of the Hon'ble Supreme Court in CCE
v. Hari Chand Shri Gopal, (2011) I SCC 236, the Division Bench of the Delhi
High Court applied the Doctrine of Substantial Compliance to hold that where the
mandatory requirements and public interest objectives of the 2013 Act stand
fulfilled, procedural shortfalls or technical rule deviations do not render the
acquisition void. Learned counsel has further submitted that the road alignment,
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
9 WP-17430-2026
right of way and one-sided expansion are purely technical matters beyond the

scope of judicial review [See : Girias Investment (P) Ltd. v. State of Karnataka
((2008) 7 SCC 53) and Union of India v Dr. Kushala Shetty, (2011) 12 SCC 69].
He has further submitted that the acquisition serves an overriding public purpose
and any interference would seriously jeopardize Simhasth Mahakumbh, 2028.
The project in question is a time-bound, mega frontier infrastructure corridor and
the MPRDC has already issued the Work Order to the concessionaire/contractor
and failure to hand over vacant Right of Way exposes MPRDC will result heavy
per-day financial penalties, causing grave and continuing loss to the public
exchequer, apart from jeopardizing preparedness for Simhasth 2028. It is further
submitted that there is no irreparable prejudice survives; balance of convenience
and public interest decisively favours the respondents He has further submitted
that the present petition is founded upon an erroneous interpretation of the
applicable statutory rules; the Madhya Pradesh Rules, 2015 alone govern the
present Acquisition Proceedings. The entire challenge raised by the petitioner
proceeds on an incorrect legal premise. The acquisition proceedings in the present
case are governed by the Madhya Pradesh Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2015,
framed by the State Government in exercise of powers conferred under Section
109 of the Act of 2013. The State Rules constitute the applicable statutory
framework regulating acquisitions within the State of Madhya Pradesh. In view of
the aforesaid, present petition deserves to be dismissed and no relief is required to
be considered.
8/ I have considered the rival submissions of the parties and also considered the
judgments cited by respective parties and also perused the records.
9/ It transpires that it is the case of the petitioners that they are lawful title
holders/occupiers in long-standing, settled possession of residential properties
situated in 12 Kholi/Barahkholi locality, Hari Fatak, Ujjain. It also transpires
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
10 WP-17430-2026
from the record that some of the petitioners are allotted the properties by way of

allotment letters and also sale deeds. The details of which are as under :
CL.
No.
Case no. Name Type of Document.
47 WP-17430/2026 CHANDABAI SARVAN Registered Sale Deed
47.1 WP-17432/2026 SHAILENDRA TEJI Registered Sale Deed
47.2 WP-17434/202 SURAJ TEJI Allotment
47.3 WP-17552/2026 RAKESH KHOKAR Allotment
47.4 WP-17554/2026 NATHI BAI Allotment
47.5 WP-17556/2026 SAVITRI BAI Registered Sale Deed
47.6 WP-17560/2026 SURESH Registered Sale Deed
47.7 WP-17563/2026 DILIP Allotment
47.8 WP-17568/2026 CHETRAM Allotment
47.9 WP-17569/2026 RAM KANYA BAI Allotment
47.i0 WP-17572/2026 SEEMA TANWAR Registered Sale Deed
47.11 WP-17573/2026 KAMLA SARVAN Allotment
10/ Therefore, considering this aspect, it transpires that necessary procedure is
followed by issuing show-cause notice and by inviting objections and the
objections are also decided by the concerned Authority and also directed to vacate
the premises within ten days. It also transpires that in view of the order passed by
the Authority, the Authority has also granted Rs,5000/- per month towards
interim rental assistance for temporary period of three months. It also transpires
that the petitioners have raised several questions like Whether the Madhya
Pradesh Road Development Corporation (MPRDC) can resort to the provisions of
Section 305 of the M.P. Municipal Corporation Act, 1956 to dispossess/demolish
the houses of petitioner, when the infrastructure project (Hariphatak ROB) is
executed and owned by an independent state entity (MPRDC) rather than being a
municipal project of the Ujjain Municipal Corporation ? and Whether the Master
Plan prepared under the M.P. Town and Country Planning Act applies to projects
executed by the Madhya Pradesh Road Development Corporation (MPRDC) ? . It
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
11 WP-17430-2026
is one of the contention of the petitioner that whether the respondents can force

the physical eviction of lawful titleholders when funds to the tune of ₹ 4.81 Crores
have been transferred by MPRDC to the Collector, Ujjain, but neither statutory
acquisition proceeding have been initiated, nor any order is passed under the
RFCTLARR Act, 2013 [ new Land Acquisition Act, 2013]?. Therefore, he has
submitted that there is violation of Article 300-A of the Constitution of India and
also non-compliance of the Act, 2013, therefore, prayed to allow the petition,
which was contested by the respondent / MPRDC and respondents no. 1 and 2
have also contested the same by giving various dates and events from May, 2023
till 14/05/2026, i.e. till this Court has granted the interim relief by way of status-
quo and has submitted that Section 305 of the M.P. Municipal Corporation Act is
applicable as there is provision of Hari Fatak Bridge in the Development Plan,
2035 and in view of Section 305 of the M.P. Municipal Corporation Act, 1956,
the exercise of power is in accordance with law. It is also further contended by
counsel for the Corporation that in view of the judgment delivered in the case of
Ravindra Ramchandra Waghmare Vs. IMC reported in (2017) 1 SCC 667, the
regular line of building has already been delineated at the time of finalization of
the Ujjain Development Plan, 2035, which is binding to the Corporation and he
has referred paragraph no. 66 of the said judgment. He has further contended that
the opportunity of hearing is also granted vide notice dated 17/04/2026 and
subsequently, after considering the objections raised by the petitioner, a detailed
order has been passed by respondent no. 2.. Learned counsel has further
submitted that the petitioners will be compensated and the calculation of the
compensation will be done as per the Collector Guidelines of the year 2026-27
and an amount of Rs. 5,000/- per month for a period of 03 months will also be
paid to the petitioners as an interim measure. If the petitioners are not satisfied
with the compensation offered, then they may take recourse to section 387 of the
1956, Act which provides for arbitration. It is further submitted that the subject
Railway Over Bridge (ROB) is being constructed from the Hari Fatak Junction
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
12 WP-17430-2026
which is in larger public interest. Looking to the coming Sinhastha Kumbh at

Ujjain, lacs of devotees will be coming to the Ujjain and he has submitted that all
the present petitions are found meritless and require to be dismissed accordingly.
11/ As already submitted by learned Advocate General for the respondent /
MPRDC, the challenge is primarily on the ground of no compensation is given
and meager amount is being paid, no document of titled is filed by the petitioners.
He has also contested the petition on the ground that the compensation is already
deposited by the Corporation to the tune of Rs. 4.81 Crores with the Collector,
Ujjain and the petitioner may approach for getting such compensation amount and
the relief prayed in the petition/s is only to the extent of getting compensation and
when the compensation is already deposited, then there is no question of
considering anything further. He has further submitted that in view of the fact that
when the amount of compensation is determined, the statutory remedy under
section 64 of the Act of 2013 is available to the present petitioner, whereby it is
provided that any person aggrieved by the measurement of land, determination of
compensation, apportionment thereof, or Rehabilitation and Resettlement
entitlements is required to seek a statutory reference before the competent
Authority instead of invoking the extraordinary jurisdiction and he has relied
upon the judgment delivered in the case of Saira Bee & Ors. v. Urban
Administration & Development Dept. (Writ Appeal No. 117/2025, Paragraph
nos. 9 and 11 are relevant for the sake of reference, which is reproduced as under
:
“9. It is clear from the language of the aforesaid section that any person
interested who has not accepted the award may seek a reference in respect of the
measurement of the land, amount of compensation, right of rehabilitation and
resettlement under Chapter V and VI or the apportionment of the compensation,
therefore, if the petitioner were dissatisfied with the non-providing of
rehabilitation and resettlement the remedy was under Section 64 of Act, 2013.
The authority under Section 64 of Act, 2013 is competent to decide the issue of
settlement and rehabilitation also
11. In the case of U.P. Avas Vikas Parishad V/s Chandra Shekhar reported in
2024 INSC 210 the Apex Court has granted exemption from submission of
Social Impact Assessment in a given facts and ircumstances, relevant para is as
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
13 WP-17430-2026
follows:-

20. We may hasten to add that the procedure prescribed under Chapter II
of the 2013 Act, mandates to carry out the Social Impact Assessment
Study in certain situations. The adherence to such a cumbersome
procedure in the instant case will be an exercise in futility for two
reasons. Firstly, a major part of the acquired land has already been
utilized for the notified public purpose. Secondly, the study referred to
above, will delay the assessment and payment of compensation to the true
tenure holders/owners of Khara No.673. Consequently, we direct the
appropriate Government to dispense with the procedure contemplated
under Chapter II of the 2013 Act”
12/ In the case of Anil Verma v. State of M.P. (W.P. No. 13246/2026, this
Court has reiterated that after passing of Award, taking possession strictly follows
Section 38 of the 2013 Act upon payment/tender of compensation, and
maintaining a writ petition to stall execution of a public project is impermissible.
The petitioner' land constitutes an small fraction of the acquisition and the entire
project cannot be stalled at the instance of a few landowners and out of nearly
1,500 affected landowners, more than 1,300 landowners have accepted the Award
and compensation. He has also referred the judgment delivered in the case of
George v. State of Kerala (supra), where the Kerala High Court held that a land
acquisition award is indivisible, and once passed and accepted by the majority of
beneficiaries, an individual landowner cannot break the integrity of the award or
seek quashing of proceedings on the basis of minor procedural objections. He has
also placed reliance upon the judgment delivered in the case of Bhimavarapu
Giridhar Kumar Reddy v. Union of India (supra), where the Andhra Pradesh High
Court held that where a highway is being constructed on either side, a small patch
of land forming a negligible portion of the corridor cannot be permitted to hold
the public infrastructure project hostage. He has further submitted that there is
substantial compliance with the mandatory provisions of the Act of 2013 and the
M.P. Rules, 2015. By referring to the judgment delivered in the case of Yudhvir
Singh v. Govt. of NCT of Delhi (supra), relying upon the judgment of the Hon'ble
Supreme Court in CCE v. Hari Chand Shri Gopal, (supra), the Division Bench of
the Delhi High Court applied the Doctrine of Substantial Compliance to hold that
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
14 WP-17430-2026
where the mandatory requirements and public interest objectives of the 2013 Act

stand fulfilled, procedural shortfalls or technical rule deviations do not render the
acquisition void. He has further submitted that the road alignment, right of way
and one-sided expansion are purely technical matters beyond the scope of judicial
review. Relying upon the judgment delivered in the case of Union of India v Dr.
Kushala Shetty, (supra) he has submitted that the Court should not exercise the
jurisdiction under Article 226 with such alignment decisions. He has lastly
submitted that erroneous interpretation of applicable statutory rules by the
petitioner that in fact the M.P. Rules, 2015 alone govern the present acquisition
proceedings. He has also submitted that balance of convenience and public
interest decisively favours the respondents and no irreparable prejudice survives
in the present case. Therefore, he has submitted that in view of the material
suppression of facts in view of the judgment delivered in the case of K.D. Sharma
v. Steel Authority of India Ltd. ((2008) 12 SCC 481, para 36) the present petition
deserve dismissal on that count also.
13. The judgment cited by learned counsel for the petitioners is also required to
be reproduced, which are as under with relevant paragraphs thereof :
a) Dinesh v. State of Madhya Pradesh [2024 SCC Online SC 937]
"17. n the case of Union of India and Others v. Mukesh Hans2 , it was observed:
“35. At this stage, it is relevant to notice that the limited right given to an
owner/person interested under Section 5-A of the Act to object to the
acquisition proceedings is not an empty formality and is a substantive
right, which can be taken away for good and valid reason and within the
limitations prescribed under Section 17(4) of the Act. The object and
importance of Section 5-A inquiry was noticed by this Court in the case
of Munshi Singh v. Union of India [(1973) 2 SCC 337] wherein this Court
held thus :
‘7. Section 5-A embodies a very just and wholesome principle that a
person whose property is being or is intended to be acquired should
have a proper and reasonable opportunity of persuading the
authorities concerned that acquisition of the property belonging to
that person should not be made. … The legislature has, therefore,
made complete provisions for the persons interested to file
objections against the proposed acquisition and for the disposal of
their objections. It is only in cases of urgency that special powers
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
15 WP-17430-2026
have been conferred on the appropriate Government to dispense with
the provisions of Section 5-A:’

18. In the case of Hindustan Petroleum Corpn. Ltd. v. Darius Shapur Chenai
and Others3 , this Court has held the right to make objections under Section 5-A
to be akin to a fundamental right. The relevant paras are extracted hereinbelow:
-
“6. It is not in dispute that Section 5-A of the Act confers a valuable right
in favour of a person whose lands are sought to be acquired…….
9. ……..It is also not in dispute that Section 5-A of the Act confers a
valuable important right and having regard to the provisions contained
i n Article 300-A of the Constitution it has been held to be akin to a
fundamental right.
15. Section 5-A of the Act is in two parts. Upon receipt of objections, the
Collector is required to make such further enquiry as he may think
necessary whereupon he must submit a report to the appropriate
Government in respect of the land which is the subject-matter of
notification under Section 4(1) of the Act. The said report would also
contain recommendations on the objections filed by the owner of the land.
He is required to forward the records of the proceedings held by him
together with the report. On receipt of such a report together with the
records of the case, the Government is to render a decision thereupon. It is
now well settled in view of a catena of decisions that the declaration made
under Section 6 of the Act need not contain any reason. (See Kalumiya
Karimmiya v. State of Gujarat [(1977) 1 SCC 715] and Delhi Admn. v.
Gurdip Singh Uban [(2000) 7 SCC 296]).
29. The Act is an expropriatory legislation. This Court in State of M.P.
v. Vishnu Prasad Sharma [(1966) 3 SCR 557] observed that in such a case
the provisions of the statute should be strictly construed as it deprives a
person of his land without consent. [See also Khub Chand v. State of
Rajasthan [(1967) 1 SCR 120] and CCE v. Orient Fabrics (P) Ltd. [(2004)
1 SCC 597]]” (2005) 7 SCC 627
19. This Court has interpreted Section 15(2) of the Act of 2013 in the case
of Shiv Singh and Others v. State of Himachal Pradesh and Others4 , wherein it
was held as under:-
“6. Under the scheme of the Act, once the objections are filed by the
affected landowners, the same are required to be decided by the Collector
under Section 15(2) of the Act after affording an opportunity of being
heard to the landowners, who submitted their objections and after making
further inquiry, as the Collector may think necessary, he is required to
submit his report to the appropriate Government for appropriate action in
the acquisition in question.
7. In this case, we find that the Collector neither gave any opportunity to
the appellants as contemplated under Section 15(2) of the Act and nor
submitted any report as provided under Section 15(2) of the Act to the
Government so as to enable the Government to take appropriate decision.
In other words, we find that there is non-compliance of Section 15(2) of
the Act by the Collector. In our view, it is mandatory on the part of the
Collector to comply with the procedure prescribed under Section 15(2) of
the Act so as to make the acquisition proceedings legal and in conformity
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
16 WP-17430-2026
with the provisions of the Act.” (emphasis supplied).

6. Para 6 of the order dated 3rd March, 2023 clearly indicates that the
SDO(Revenue) had forwarded the matter to the Collector while disposing of the
objections raised therein and seeking injunction under Section 19 of the Act.
27. Furthermore, on discussion made above, the land acquisition notification
dated 27th May, 2022 was issued by the State Government. Hence, neither the
District Collector could act as the appropriate Government in regard to the
acquisition in question nor was he authorised to delegate the powers to the SDO.
As a matter of fact, considering the scheme of the Act of 2013 and the law
a s laid down by this Court in the case of Shiv Singh (supra), the District
Collector was simply required to hold inquiry on the objections filed
under Section 15(2) of the Act and thereafter, to forward the record of
proceedings along with his opinion to the State Government for its decision.
The State Government is mandated to take a decision on the objections as
per Section 15(3) of the Act. However, these mandatory requirements of the
statute were not followed in the case, and hence, the proceedings are hit by non-
compliance of Sections 15(2) and 15(3) of the Act of 2013.
28. Even if, for the sake of arguments, the SDO is treated to be an officer
authorised to hear the objections made under Section 15(2) of the Act,
apparently, the final decision on such objections would have to be taken by the
appropriate Government as per Section 15(3) of the Act which is lacking in this
case.
29. The High Court while dismissing the batch of writ petitions filed by
the land owners including the appellant treated the same as having rendered
infructuous observing that the final award had already been passed on 3rd
October, 2023. It is not in dispute that the writ petitions came to be filed on 11th
September, 2023 and thus the mere fact that the final award had been issued
during pendency of the petitions would not save the acquisition proceedings
because the hearing of the objections is a sacrosanct act treated akin to a
fundamental right as held in the case of Hindustan Petroleum Corpn.
Ltd. (supra). Thus, the non- compliance of this mandatory requirement would
vitiate the acquisition.
30. Consequently, the impugned judgment dated 13th October, 2023 is hereby
quashed and set aside ‘qua the appellants herein’. As a result, the final award
dated 3rd October, 2023 is declared to be illegal and quashed ‘qua the
appellants lands’.
31. The respondents-authorities are directed to consider and decide the
objections filed by the appellants under Section 15 of the Act of 2013 as per law
whereafter, further proceedings may follow.
b) Kesar Singh v. State of Madhya Pradesh [2025 SCC Online MP 3827]
26. The second contention raised by learned counsel for the petitioner is that the
objections submitted to the notification under Section 4 have not been decided
by the Collector as required under subsection 2 of Section 5A of the L.A. Act. It
is correct that after issuance of the notification under Section 4 all the
landowners/ petitioner submitted objections in writing before the Collector, but
the Additional Collector heard all the objections, prepared a report and placed
before the Collector Indore. The learned Collector after going through the eport
has rejected all the objections and granted approval to the notification under
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
17 WP-17430-2026
Section 4 of the LA Act. Thereafter, the matter was placed before the
Commissioner who has also granted approval. Section 5-A is reproduced below
for ready reference : -

“5A. Hearing of objections. - (1) Any person interested in any land which
has been notified under section 4, sub-section (1), as being needed or
likely to be needed for a public purpose or for a Company may, [within
thirty days from the date of the publication of the notification], object to
the acquisition of the land or of any land in the locality, as the case may
be.
(2) Every objection under sub-section (1) shall be made to the Collector in
writing, and the Collector shall give the objector an opportunity of being
heard [in person or by any person authorized by him in this behalf] or by
pleader and shall, after hearing all such objections and after making such
further inquiry, if any, as he thinks necessary, either make a report in
respect of the land which has been notified under section 4, sub-section
(1), or make different reports in respect of different parcels of such land,
to the appropriate Government, containing his recommendations on the
objections, together with the record of the proceedings held by him, for
the decision of that Government. The decision of the [appropriate
Government] on the objections shall be final.
(3) For the purpose of this section, a person shall be deemed to be
interested in land who would be entitled to claim an interest in
compensation if the land were acquired under this Act.]”.
27. As per sub-section (2) of Section 5A “every objection under ub-section (1)
shall be made to the Collector in writing, and the Collector shall give the
objector an opportunity of being heard in person or by any person authorized by
him or by pleaders”. It further provides that after hearing all such objections and
after making enquiry, the collector shall prepare its report containing his
recommendations on the objections and shall place before the government for
decision and the decision taken by the appropriate Government on the
objections shall be final. As per Section 5-A the competent authority is the
Collector, therefore, it is for the Collector to hear the objections and submit a
report with its recommendations to the appropriate Government.
28. It is settled law that where a statute requires a particular act to be done in a
particular manner that the Act has to be done in that manner alone. No such
notification has been brought on report by the respondents whereby the State
Government has delegated power to the Additional Collector to invite the
objections and hear the person concerned. It is also settled law that in exercise
of quasi judicial power as well as judicial power it is for an authority or a Judge
who has to decide the matter should give hearing to the parties concerned. The
arguments cannot be heard by one the competent authority and decided by
other. It is mandatory and statutory requirement for the Collector to give a
personal hearing to the person concerned, make enquiry and submit a report
with its recommendation. There cannot be a delegation of authority or
entrustment to the subordinate officers like Additional Collector/ Dy. Collector
to hear the objections, prepare a report and submit for approval. Therefore, the
objections under Section 5-A were not heard and decided by the competent
authority. After grant of approval by the Commissioner, the notification under
Section 6 has been issued which is also liable to be quashed
35. Therefore, now the respondents/the Housing Board cannot be permitted to
further proceed in this matter. If they desire, they may come up with the new
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
18 WP-17430-2026
housing scheme under the provisions of the Adhiniyam, 197

c) Shiv Singh v. State of Himachal Pradesh [(2018) 16 SCC 270]
6) Under the scheme of the Act, once the objections are filed by the affected
landowners, the same are required to be decided by the Collector under Section
15(2) of the Act after affording an opportunity of being heard to the
landowners, who submitted their objections and after making further inquiry, as
the Collector may think necessary, he is required to submit his report to the
appropriate Government for appropriate action in the acquisition in question.
7) In this case, we find that the Collector neither gave any opportunity to the
appellants as contemplated under Section 15(2) of the Act and nor submitted
any report as provided under Section 15(2) of the Act to the Government so as
to enable the Government to take appropriate decision. In other words, we find
that there is non-compliance of Section 15(2) of the Act by the Collector. In our
view, it is mandatory on the part of the Collector to comply with the procedure
prescribed under Section 15(2) of the Act so as to make the acquisition
proceedings legal and in conformity with the provisions of the Act.
d) Hindustan Petroleum Corpn. Ltd. Darius Shapur Chenai [(2005) 7 SCC 627]
6. It is not in dispute that Section 5-A of the Act confers a valuable right in
favour of a person whose lands are sought to be acquired. Having regard to the
provisions contained in Article 300A of the Constitution of India, the State in
exercise of its power of 'eminent domain' may interfere with the right of
property of a person by acquiring the same but the same must be for a public
purpose and reasonable compensation therefor must be paid.
9. It is trite that hearing given to a person must be an effective one and not a
mere formality. Formation of opinion as regard the public purpose as also
suitability thereof must be preceded by application of mind as regard
consideration of relevant factors and rejection of irrelevant ones. The State in its
decision making process must not commit any misdirection in law. It is also not
in dispute that Section 5-A of the Act confers a valuable important right and
having regard to the provisions contained in Article 300A of the Constitution of
India has been held to be akin to a fundamental right.
15. S of the Act is in two parts. Upon receipt of objections, the
ection 5-A
Collector is required to make such further enquiry as he may think necessary
whereupon he must submit a report to the appropriate Government in respect of
the land which is the subject matter of notification under Section 4(1) of the
Act. The said Report would also contain recommendations on the objections
filed by the owner of the land. He is required to forward the records of the
proceedings held by him together with the report. On receipt of such a Report
together with the records of the case, the Government is to render a decision
thereupon. It is now well-settled in view of a catena of decisions that the
declaration made under Section 6 of the Act need not contain any reason.
[See Kalumiya Karimmiya Vs. The State of Gujarat and Others , ( 1977) 1 SCC
715 and Delhi Administration Vs. Gurdip Singh Uban and Others , (2000) 7
SCC 296
29. The Act is an expropriatory legislation. This Court in State of Madhya
Pradesh and Ors. Vs. Vishnu Prasad Sharma and Ors. [1966 (3) SCR 557]
observed that in such a case the provisions of the statute should be strictly
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
19 WP-17430-2026
construed as it deprives a person of his land without consent. [See also Khub
Chand and Ors. Vs. State of Rajasthan and Ors. , 1967 ( 1) SCR 120 and
Collector of Central Excise, Ahmedabad vs. Orient Fabrics (P) Ltd. , (2004) 1
SCC 597].

There cannot, therefore, be any doubt that in a case of this nature due
application of mind on the part of the statutory authority was imperative.
e) Raghbir Singh Sehrawat v. State of Haryana, [(2012) 1 SCC 792]
42. It if difficult, if not impossible, to appreciate as to why the State and its
instrumentalities resort to massive acquisition of land and that too without
complying with the mandate of the statute. As noted by the National
Commission on Farmers, the acquisition of agricultural land in the name of
planned development or industrial growth would seriously affect the availability
of food in future. After independence, the administrative apparatus of the State
has not spent enough investment in the rural areas and those who have been
doing agriculture have not been educated and empowered to adopt alternative
sources of livelihood. If land of such persons is acquired, not only the current
but the future generations are ruined and this is one of the reasons why the
farmers who are deprived of their holdings commit suicide.
43. It also appears that the concerned authorities are totally unmindful of the
plight of those sections of the society, who are deprived of their only asset like
small house, small industrial unit etc. They do not realise that having one's own
house is a lifetime dream of majority of population of this country.
Economically affluent class of society can easily afford to have one or more
houses at any place or locality in the country but other sections of the society
find it extremely difficult to purchase land and construct house. Majority of
people spend their lifetime savings for building a small house so that their
families may be able to live with a semblance of dignity. Therefore, it is wholly
unjust, arbitrary and unreasonable to deprive such persons of their houses by
way of the acquisition of land in the name of development of infrastructure or
industrialisation. Similarly, some people set up small industrial unit after
seeking permission from the competent authority. They do so with the hope of
generating additional income for their family. If the land on which small units
are established is acquired, their hopes are shattered. Therefore, before
acquiring private land the State and/or its agencies/instrumentalities should, as
far as possible, use land belonging to the State for the specified public purposes.
If the acquisition of private land becomes absolutely necessary, then too, the
concerned authorities must strictly comply with the relevant statutory provisions
and the rules of natural justice.
14/ I have considered the rival submissions made at the bar and also considered
the relevant facts of the matter as discussed earlier.
15/ I am of the view that there is substantial compliance of the required
procedure, which is found from the record. Moreover, the petitioners, who are
allotted the land at the relevant point of time, and now the compensation is
assessed to the rune of Rs. 4.81 Crores and deposited the same with the Collector,
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
20 WP-17430-2026
Ujjain, which can be availed by the petitioners and if they are aggrieved, there is

remedy by challenging that assessment or Award by way of initiating proceeding
under section 64 of the Act, 2013. The judgments which are cited by counsel for
the respondents are squarely applicable to the facts and circumstances of the
present case. I found no perversity, illegality and arbitrariness in any of the
proceeding except minor lapses. The entire procedure is required to be expedited
in larger public interest. Therefore, I found no reason to exercise my jurisdiction
under Article 226 of the Constitution of India in the present cases.
16/ In view of the above discussions, though the contentions raised by the
petitioners are sound attractive, but not in consonance with the merits of the case,
therefore, the said contention is required to be rejected. Considering the larger
interest of the public involved and looking to the Simhasth 2028. is also coming,
in that context also, the acquisition of the lands is necessary and considering the
fact that out of 1500 affected persons, 1300 affected persons have already
accepted the Award, on that count also, no case is made out in favour of the
petitioners and present petitions require to be dismissed. Accordingly, present
petitions are dismissed.
17/ The signed order be kept in the file of WP/17430/2026 and a copy thereof
be kept in the file of connected WP/17432/2026, WP/17434/2026,
WP/17552/2026 , WP/17554/2026. WP/17556/2026 , WP/17560/2026,
WP/17563/2026 , WP/17568/2026 , WP/17569/2026 , WP/17572/2026 and
WP/17573/2026
18. Interim relief / stay, if any, shall stand vacated.
C.C as per rules.
(SANDEEP N. BHATT)
JUDGE
Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27

NEUTRAL CITATION NO. 2026:MPHC-IND:24216
21 WP-17430-2026
amol


Signature Not Verified
Signed by: AMOL
NIVRUTTIRAO MAHANAG
Signing time: 31-08-2026
18:23:27