Apurvakriti Infrastructure Private Limited vs Tata Projects Limited
- Court
- Bombay High Court
2026:BHC-OS:13298
Sonali Mane CARAP-23-2026.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMM. ARBITRATION APPLICATION NO. 23 OF 2026
Apurvakriti Infrastructure Private Limited
A Company registered under Companies Act, 2013
Having registered address at 2" Floor, 24/5,
100 Foot Road, Ghitorni, New Delhi, India 110030 … Applicant
Versus
1. Tata Projects Limited and Anr.
Near Navi Mumbai Metro Depot Yard
Taloja, Panchanand Phase-1,
Navi Mumbai 410208
2. The City and Industrial Development Corporation )
of Maharashtra Limited (CIDCO) CIDCO Bhavan,
CBD Belapur, Navi Mumbai, Maharashtra. … Respondents
Adv. Paromita Majumdar , Adv. Gaurangi Patil a/w Adv. Mayureshwari
Rajan Kordaay, Adv. Meenakshi Vimal Adv. Vibhor Jain i/b GP and
Associates for Applicant.
Adv. Aaushi Doshi a/w Adv. Surbhi Ahuja, Adv. Ruchita Chavan i/b India
Law LLP for Respondent No.1
MANE
SONALI
DILIP
Digitally signed by
MANE SONALI DILIP
Date: 2026.06.17
18:10:47 +0530
1 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
CORAM : ARUN R. PEDNEKER , J.
RESERVED ON : 12 JUNE, 2026
PRONOUNCED ON : 17 JUNE, 2026
JUDGEMENT :
1. By the present Commercial Arbitration Application under Section
11 of the Arbitration and Conciliation Act, 1996 the Applicant seeks
appointment of an Arbitrator with respect to the disputes that have arisen
between the parties under an Agreement-cum-Work Order dated 2 March,
2015.
2. The learned counsel for the Applicant submits that the Respondent
No. 1 issued a Work Order on 2 March, 2015 for the construction of
Ballastless track work for Belapur-Pendhar corridor of Navi Mumbai Metro
Rail Project Line 1 (NMML1). It is further submitted that the Consortium
AnTaCs of which the Respondent No.1 is a partner was entrusted with the
work by CIDCO. The Applicant is a sub-contractor of the Respondent No.1
and has undertaken the work for Rs.58,27,00,000/-.
3. Subsequently, certain disputes arose as regards the payment of the
outstanding amount by the Respondent No.1 to the Applicant. Work
Completion Certificate dated 4 December 2023 was issued by the
Respondent No.1 to the Applicant. Thereafter, Demand Letter dated
8 May, 2025 was sent by the Applicant to the Respondent No.1. Since the
2 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
outstanding amounts were not paid, notice was issued invoking the
arbitration clause under Section 21 of the Arbitration and Conciliation Act,
1996 under clause 31.3 of the Special Conditions of Contract executed
between the Respondent No.1 and CIDCO by contending that the said
Clause is applicable to the agreement between the parties. The said notice
was replied by letter dated 6 August, 2025 by the Respondent No.1 wherein
it stated that the amicable settlement talks are going on, and they have not
failed. Thereafter, another Notice dated 26 September 2025 was issued
invoking the arbitration Clause under Section 21 of the Arbitration and
Conciliation Act, 1996. The same was not responded to, as such the present
application for appointment of arbitrator is filed.
4. Ms. Paromita Majumdar the learned counsel appearing for the
Applicant submits that the G.C.C. signed between Respondent No.1 with
CIDCO particularly Clause 31.1 thereof, provides for arbitration of disputes
between the parties. The said contract is between the Respondent No.1 and
CIDCO. However, the same has been incorporated by reference into the
Tender-cum-Work Order dated 2 March 2015. By virtue of such
incorporation, the arbitration clause as provided in the General Conditions
of Contract signed between CIDCO and Respondent No.1 would also apply
to the contract between the Applicant and the Respondent No.1. Dispute has
arisen between the parties and thus she seeks invocation of the arbitration
clause and appointment of an Arbitrator. She relies upon the following
judgements:
3 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
i) M. R. Engineers And Contractors Private Limited Vs. Som Datt Builders
1
Limited
2
ii) Hirani Developers Vs. Nehru Nagar Samruddhi CHS Ltd. and Anr .
3
iii) Ajay Madhusudan Patel & Ors. Vs. Jyotindra S. Patel & Ors.
iv) ASF Buildtech Private Limited Vs. Shapoorji Pallonji And Company
4
Private Limited
5. Per contra, Ms. Aaushi Doshi the learned counsel appearing for
the Respondent No.1 submits that the General Conditions of Contract which
the Applicant relied upon are signed by the Respondent No.1 with CIDCO
and the Applicant is not a party to said General Conditions of Contract. The
arbitration clause invoked would not apply to the Work Order between the
Applicant and the Respondent No.1 She further submits that there is no
incorporation of the arbitration clause from the General Conditions of
Contract executed between the Respondent No.1 and CIDCO into the tender
document executed between the Applicant and Respondent No.1. She
submits that there is no arbitration clause in the agreement between the
parties and that the matter may not be referred to arbitration. She relies upon
the following judgements:
1
(2009) 7 SCC 696.
2
2026 SCC Online SC 854
3
(2024) 9 S.C.R. 894 : 2024 INSC 710.
4
2025 INSC 616
4 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
5
i) Dascon Sourav Commercial Private Limited Vs. CLE Private Limited
6
ii) NBCC (India) Limited Vs. Zillion Infra Projects Private Limited
7
iii) Inox Wind Limited Vs. Thermocables Limited
iv) Maharashtra State Electricity Distribution Company Limited
8
(MSEDCL) and Ors. Vs. R. Z. Malpani
v) Hindustan Petroleum Corporation Limited Vs. BCL Secure Premises
9
Private Limited
iv) Elite Engineering And Construction (Hyderabad) Private Limited
Represented by Its Managing Director Vs. Techtrans Construction India
10
Private Limited Represented by its Managing Director
6. Having heard the learned counsel for the parties the relevant
clauses of the Work Order dated 2 March, 2015 is noted below:
5
2024 SCC OnLine Cal 3590.
6
(2024) SCC 174.
7
(2018) 2 SCC 519.
8
2026 SCC OnLine SC 553.
9
(2026) 3 SCC 711
10
(2018) 4 SCC 281.
5 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
Details of Annexure attached to this WO
Annexure-1 : Schedule of item, Price and Qty
Annexure-2 : Scope Matrix
Annexure-3 : CIDCO Tender No.C.A. No.
02/CIDCO/RP/SE (TP-III)/2012-13 including all
amendments/corrigendum thereof
Annexture-4 : CIDCO's SCC (VOI II of V)
Annexture-5 : CIDCO's GCC (VOI II of V)
Annexture-6 : CIDCO's requirement (Technical specifications, drawings,
General specifications and Maintenance specifications etc.)
........
.......
Subject : Work Order of construction of Ballastless track work for 'Belapur-
Pendhar' corridor of Navi Mumbai Metro Linde 1 (NMML1),
CIDCO which includes Design. Supply incl. spares (as per scope
matrix), Erection. Testing and Commissioning as per CIDCO
Specification in Navi Mumbai, Maharashtra State.
Ref : 1) CIDCO Tender C.A. No. 02/CIDCO/RP/SE (TP-III)/2012-13
2) CIDCO LOA No. CIDCO/SP/CE(SP)/2014/160 dt. 04.07.14
3) CIDCO WO Ref. No. CIDCO/SP/SE (To-III)/2014/183 dt.
01.08.2014.
4) Your offer vide email dt. 03.01.2015
5) MOM dt. 22.01.2015
6) Your email dt 29.01.2015 regarding RMC prices
7) Your confirmations dt 09.02.2015 for MOM clarifications,
taxation and final landed price.
With reference of the above, we are pleased to issue this Work
Order for the subject work along with the documents enclosed herewith as
Annexures and the Terms and Conditions as detailed below. The technical
6 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
specification, drawings of CIDCO, addendums & Corrigendums thereof and
all terms and conditions (except otherwise specifically agreed to in writing)
as specified hereunder read along with all annexures and reference
documents listed above shall form an integral part of this Work Order.
AnTaCs consortium has been entrusted by CIDCO the subject work, where
in Tata Projects Ltd. is the consortium partner.
1.0 Scope of Work: Construction of Ballastless Track Work
for 'Belapur-Pendhar' corridor of Navi Mumbai Metro Rail
Project Line1 (NMML1). CIDCO which includes Design, Supply
incl. spares (as per scope matrix), Erection, Testing and
commissioning as per CIDCO Specification. All the works shall
be executed on 'back to back' in accordance with the
Specifications and Standards stipulated in CIDCO bid.
5.0 Completion Schedule: AIPL shall submit the preliminary
designs within 3 weeks from the dt. of WO.
In terms 0° Clause 43.1 of the GCC and as mentioned in Schedule
14, Annexure-A of SCC of CIDCO contract, all works to be
executed under this contract shall be completed by 30th Jan 2017
fi.e. 30 Months (including monsoon) from the date of issue of
Work Order by CIDCO}. The Key Dates mentioned in Annexure-8
attached as per CIDCO contract concluded by AnTaCs
Consortium, the commencement to be reckoned as 01.08.2014.
6.0 Recoveries for delay in work completion: (i) Delay In
Completion:
If CONTRACTOR is not able to achieve the Key Date, then you
shail be fiable to pay liquidated damages at 0.25% per week
(partial week would not be counted for this calculation) of
contract value. The Liquidated Damage for delay in completion
shail be limited to 5% of the contract value. Delay in providing
the stage wise access to the CONTRACTOR by the CIDCO/TPL if
any, shall be exempt! from levy of Liquidated Damage on pro rata
basis.
ii) Failure to achieve Availability Targets:
7 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
If CONTRACTOR fails to achieve the availability targets set out
in System Assurance Document within 24 months. then
CONTRACTOR is liable to pay liquidated damages at the rate of
0.25% per month up to 2.5% of the contract value.
(iii). Any other damages imposed by the Client (CIDCO) as
specified in Genera! Specification of CIDCO Contract.
(iv) Non compliance of instructions given by Client (CIDCQ) as
per Clause 43.0 of SCC of the CIDCO contract.
The overall liquidated damages under S No. (i to iii) of this
Clause shall be restricted to 7.5% of the contract value.
7. The entire Work Order dated 2 March, 2015 does not have an
independent arbitration clause. As such the Applicant has relied on the
arbitration clause No.31.3 of the General Conditions of Contract, executed
between the Respondent No.1 and CIDCO and is noted below:
31.3 In the event the dispute or difference or claim, as the
case may be, is not resolved, as evidenced by the signing of the
written terms of settlement by the Parties, within 30 (thirty) days
of reference for amicable settlement, the same shall be- finally
settled by binding arbitration under the Arbitration and
Conciliation Act, 1996. as amended and revised from time to time
and for the time being in force (the Arbitration Act).
8. The law as regards incorporation of arbitration clause by reference
is discussed by the Supreme Court in the case of M. R. Engineers And
Contractors Private Limited Vs. Som Datt Builders Limited reported in
(2009) 7 SCC 696, wherein the Supreme Court dealt with the scope of
Section 7(5) of the Arbitration and Conciliation Act, 1996. The issue
8 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
involved was whether the arbitration clause contained in the main contract
would stand incorporated by reference in the subcontract, where the
subcontract provided that it shall be carried out in accordance with the terms
and conditions applicable to the main contract. The Supreme Court
summarized the law as under:
24. The scope and intent of Section 7(5) of the Act may
therefore be summarized thus:
(i) An arbitration clause in another document, would get
incorporated into a contract by reference, if the following
conditions are fulfilled :
(1) The contract should contain a clear reference to the
documents containing arbitration clause,
(2) the reference to the other document should clearly
indicate an intention to incorporate the arbitration clause
into the contract,
(3) The arbitration clause should be appropriate, that is
capable of application in respect of disputes under the
contract and should not be repugnant to any term of the
contract.
(ii) When the parties enter into a contract, making a general
reference to another contract, such general reference would
not have the effect of incorporating the arbitration clause
from the referred document into the contract between the
parties. The arbitration clause from another contract can be
incorporated into the contract (where such reference is
made), only by a specific reference to arbitration clause.
(iii) Where a contract between the parties provides that the
execution or performance of that contract shall be in terms of
another contract (which contains the terms and conditions
relating to performance and a provision for settlement of
disputes by arbitration), then, the terms of the referred
9 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
contract in regard to execution/performance alone will apply,
and not the arbitration agreement in the referred contract,
unless there is special reference to the arbitration clause
also.
(iv) Where the contract provides that the standard form of
terms and conditions of an independent Trade or
Professional Institution (as for example the Standard Terms
& Conditions of a Trade Association or Architects
Association) will bind them or apply to the contract, such
standard form of terms and conditions including any
provision for arbitration in such standard terms and
conditions, shall be deemed to be incorporated by reference.
Sometimes the contract may also say that the parties are
familiar with those terms and conditions or that the parties
have read and understood the said terms and conditions.
(v) Where the contract between the parties stipulates that the
Conditions of Contract of one of the parties to the contract
shall form a part of their contract (as for example the
General Conditions of Contract of the Government where
Government is a party), the arbitration clause forming part
of such General Conditions of contract will apply to the
contract between the parties.
9. The judgement of M. R. Engineers And Contractors Private
Limited (supra) has been followed in various cases. In the case of Hirani
Developers Vs. Nehru Nagar Samruddhi CHS Ltd. and Anr . 2026 SCC
Online SC 854, the Hon'ble Supreme Court has held that, an arbitration
clause in another document would get incorporated into the contract by
reference, if the contract contains clear reference to the document containing
the arbitration clause and such reference to the other document clearly
indicates the intention to incorporate the arbitration clause into the contract.
The Supreme Court clarified that a general reference to another contract
would not have the effect of incorporating the arbitration clause from the
10 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
referred document into the contract between the parties. In the case of
NBCC (India) Limited Vs. Zillion Infra Projects Private Limited (2024) 7
SCC 174, The Supreme Court has observed that perusal of Section 7(5) of
the Arbitration Act itself would reveal that it provides for a conscious
acceptance of the arbitration clause from another document by the parties.
9A. The Supreme Court in the case of Inox Wind Limited (supra) has
held that though general reference to an earlier contract is not sufficient for
incorporation of an arbitration clause in the later contract, a general
reference to a standard form would be enough for incorporation of the
arbitration clause. A general reference to a consensual standard form is
sufficient for incorporation of an arbitration clause.
The Supreme Court in Inox Wind Limited (supra) referring to the
judgement of Queen's Bench (U.K.) in the case of Habas Sinai Ve Tibbi
Gazlar Insthisal Endustri AS V. Sometal Sal 2010 Bus LR 880 has noted
following board categories in which the parties attempt to incorporate an
arbitration clause :
(1) A and B make a contract in which they incorporate standard
terms.
These may be the standard terms of one party set out on the back
of an offer letter or an order, or contained in another document to
which reference is made; or terms embodied in the rules of an
organisaiton of which A or B or both are members; or they may be
terms standard in a particular trade or industry.
(2) A and B make a contract incorporating terms previously
agreed between A and B in another contract or contracts to which
they were both parties.
11 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
(3) A and B make a contract incorporating terms agreed between
A (or B) and C. Common examples are a bill of lading
incorporating the terms of a charter to which A is a party;
reinsurance contracts incorporating the terms of an underlying
insurance; excess insurance contracts incorporating the terms of
the primary layer of insurance; and building or engineering sub-
contracts incorporating the terms of a main contract or sub-
contracts incorporating the terms of a sub-contract.
(4) A and B make a contract incorporating terms agreed between
C and D. Bills of lading, reinsurance and insurance contracts and
building contracts may fall into this category.
In Categories 1 and 2, a general reference would be sufficient for
incorporation of an arbitration clause from a standard form of
contract. In cases falling under Categories 3 and 4 mentioned
above which are two-contract cases, it was held that a stricter
rule has to be followed by insisting on a specific reference to the
arbitration clause from an earlier contract.
Perusal of tender document dated 2 March, 2015 and the GCC
executed between the Respondent No.1 and CIDCO would indicate that the
present matter falls in the category (3) above, as such strict rule has to be
followed for incorporation of arbitration agreement into the tender document
dated 2 March, 2015 by special reference to the arbitration clause of GCC.
10. Thus, from the above noted judgments, it is clear that there has to
be a specific incorporation of the arbitration clause, where the parties refer
to another document and seek to apply the same to a later contract. In the
instant case, upon a perusal of the clauses of the Work Order dated 2 March,
2015 it is to be noted that, there is no specific reference to arbitration clause
31.3 noted above. The technical specifications issued by the CIDCO and
12 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
corrigendum thereof are binding on the Applicant. From the tender
document dated 2 March, 2015, it is apparent that all the technical
specifications, annextures and other terms and conditions of the General
Conditions of Contract executed between CIDCO and Respondent No.1 are
Order
incorporated into the Tender-cum-Work dated 2 March, 2015.
However, there is no specific clause in the Tender-cum-Work Order
incorporating the arbitration clause i.e. clause 31 of the Special Conditions
of Contract executed between CIDCO and Respondent No.1.
11. The learned counsel for the Applicant has submitted that the issue
as regards the applicability of clause 31 General Conditions of Contract be
left to the Arbitrator to be decided under Section 16 and reliance is placed
on the judgement of Ajay Madhusudan Patel & Ors. (supra) at para 64,
where the Supreme Court has taken a view that the referral court is required
to prima facie rule on the existence of the arbitration agreement, however,
recognizing the complexity of determining whether the non-signatory party
is veritable party of the arbitral agreement such a determination, the arbitral
tribunal was considered the proper forum, since it can decide whether the
non-signatory is a party to the arbitration agreement on the basis of factual
evidence and application of legal doctrine. In this process, the non-signatory
must also be given an opportunity to raise objections regarding the
jurisdiction of the arbitral tribunal in accordance with the principles of
natural justice.
13 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
12. The learned counsel for the Applicant has also relied upon the
judgement of ASF Buildtech Private Limited Vs. Shapoorji Pallonji And
Company Private Limited 2025 INSC 616, Particularly, at Para no. 96
whereas the Supreme Court has held, that the referral court only has to
determine the prima facie existence of an Arbitration Agreement, whereas,
the issue of determining parties to an arbitration agreement is quite distinct
from "existence" of the arbitration agreement, as such issue relates the
jurisdiction of competence of the arbitral tribunal, and thus, empowered to
decide the same under Section 16.
13. It is further submitted that the approach of referral court in relation
to the question of whether the non-signatory party is a veritable party to the
arbitration agreement, in the case of Cox and Kings Ltd. v. SAP India Pvt.
Ltd. (2024) 4 SCC 1, the Supreme Court has observed that once an arbitral
tribunal stands constituted it becomes automatically open to all the parties to
raise preliminary objections touching upon the jurisdiction of the tribunal
and seek an adjudication thereof.
14. Referring to the above judgements learned counsel for the
Applicant has stated that the matter be referred to the arbitral tribunal and
the arbitral tribunal be called upon to decide the interpret issues as regards
whether clause 31 of the General Conditions of Contract signed between the
Respondent No.1 and CIDCO would also apply to the parties. However, this
Court is unable to accept the submissions of the Applicant. Considering the
judgements as noted above in M. R. Engineers And Contractors Private
Limited (supra), NBCC (India) Limited (supra) and Hirani Developers
14 / 15
::: Uploaded on - 17/06/2026 ::: Downloaded on - 17/06/2026 18:36:44 :::
Sonali Mane CARAP-23-2026.docx
(supra) and Inox Wind Limited (supra) and also considering the tender
document, this Court holds that Clause 31 of the General Conditions of
Contract signed between the Respondent No.1 and CIDCO is not
incorporated in the Tender-cum-Work Order dated 2 March, 2015 executed
between the Respondent No.1 and the Applicant. In absence of arbitration
agreement between the parties, it would not be possible for this Court to
refer the disputes to arbitration. Accordingly, the Commercial Arbitration
Application is dismissed .
[ ]
ARUN R. PEDNEKER , J.
15 / 15