Hindustan Construction Co. Ltd. vs National Hydro Electric Power Corporation Ltd.

Court
Delhi High Court

* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
Date of decision: 28 JULY, 2026
IN THE MATTER OF:
EX.APPL.(OS) 1025/2024
IN
+ OMP (ENF.) (COMM.) 87/2018
HINDUSTAN CONSTRUCTION CO. LTD. .....Decree Holder
Through: Mr. Dayan Krishnan, Senior
Advocate with Mr. Rishi Agrawala,
Ms. Shruti Arora, Mr. Rajat Sinha,
Ms Tarini Khurana, Mr. Shreedhar
Kale, Advocates

versus

NATIONAL HYDRO ELECTRIC POWER CORPORATION LTD.
.....Judgement Debtor
Through: Ms. Shikha Tandon, Mr. Shubham
Mittal, Mr. Piyush Sharma, Mr. Anuj
Kumar Sharma, Advocates
CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT
EX.APPL.(OS) 1025/2024 in OMP (ENF.) (COMM.) 87/2018
1. The present application under Section 151 of the CPC has been filed
by the Decree Holder seeking direction of this Court directing the Judgment
Debtor to make the balance payment of the awarded amount passed in
favour of the Decree Holder vide Award dated 31.12.2015 which was upheld
by this Court in OMP (COMM) 224 of 2018 vide Judgment dated
02.04.2024.
2. The facts of the case leading to the filing of the present application are
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 1 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

that the Decree Holder awarded a contract dated 10.05.2006 to the Judgment
Debtor for execution of civil works package (Lot-1): Construction of
Diversion Arrangement, Concrete Gravity Dam along with Spillway, Roller
Compacted Concrete Dam, Intake Structure Powerhouse, Tail Race
Channel, Switchyard and other associated civil works of Teesta Low Dam
H.E. Project – Stage – IV on a certain agreed contract price by the Judgment
Debtor.
3. Disputes arose between the parties. The Arbitral Tribunal was
constituted to adjudicate the disputes. An Award was passed on 31.12.2015
and the Petitioner was awarded a sum of Rs.53,73,94,463/-. The operative
portion of the Award reads as under: -
“219. RELIEF:
In view of our findings above, we hereby summarize
our award as follows:

Sr.
No.
Particulars Amount (Rs.)
1. Claim 1(a) 8,21, 72,489/-
2. Claim 1(b) 7,05,14,386/-
3. Claim 2 28,68,81,832/-
4. Interest 9, 78,25,755/-
5. Total 53,73,94,463/-



220. With regard to interest from date of award
onwards, the Arbitral Tribunal, exercising its powers
under Section 31(7)(b) of the Act allows interest on the
aforementioned amounts @ 18% p.a.”

4. A sum of Rs.53,73,94,463/- along with pendent lite interest @ 14%
was to be paid from 29.08.2013 till the date of the award. The learned
Arbitrator also awarded future interest @ 18% from 31.12.2015 till the date
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 2 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

of payment.
5. The Award has now been confirmed. Amounts have also been paid
under the Award. The details of the amounts which have been paid in the
interregnum, the manner it has been paid will be discussed in the later part
of the judgment.
6. A number of awards arising of the disputes in the construction sector
were pending challenge before various judicial forums wherein one of the
parties was the government or a public sector undertaking. Contractors who
were successful in the proceedings were not able to get the fruits of the
Awards due to these challenges in Court. These contractors were therefore
in severe liquidity crunch. Representations were given by these contractors
to the Government of India highlighting the difficulties faced by them. In
order to assuage the difficulties faced by the contractors, the Government
brought out two Office Memorandums both dated 05.09.2016 for releasing
interim payments in cases where awards were under challenge. Needless to
state that these interim payments were subject to the final outcome of the
proceedings under Section 34 of the Arbitration & Conciliation Act.
7. Both the Office Memorandums (OMs) are being reproduced as
under:-
“First Office Memorandum dated 05.09.2016”

“No.N-14070/14/2016-PPPAU
Government of India
National Institution for Transforming India (NITI
Aayog)
NITI Bhavan, New Delhi
September 05, 2016

Office Memorandum
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 3 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07


Subject: Measures to revive the Construction Section
– reg.

The construction sector has been facing a
number of problems, mainly arising from the liquidity
constraints caused on account of their payments not
being released by the Government Departments/ Public
Sector Undertakings (PSUs) pursuant to the arbitral
awards. To discuss the problems of the construction
sector, detailed deliberations/ consultations were held
with the representatives of the construction industry,
banks, major government PSUs and concerned
Ministries/ Departments. Based on the above
deliberations/ consultations, the NITI Aayog placed a
proposal before the Cabinet Committee on Economic
Affairs (CCEA) for its consideration suggesting
various short-term and long-term measures required
for addressing the issues ailing the construction sector.
The CCEA, chaired by the Prime Minister, has
considered the proposals of NITI Aayog in its meeting
held on 31st August 2016 and approved the same for
the revival of construction sector.

2. Accordingly, following instructions are hereby
issued for compliance and necessary action by all
concerned i.e. the Government Departments/
Ministries/ Public Sector Undertakings awarding the
public contracts/ implementing various projects
involving construction activities.

2.1 In case of contracts/ concessions where the process
of arbitration was initiated under the pre-amended
Arbitration Act, the PSUs/ Departments may seek the
consent of the contractors/ concessionaires to transfer
the pending cases under the amended Arbitration Act,
wherever possible. The shift to amended Arbitration
Act is expected to make the arbitration process more
cost effective and help in settlement of the disputes in a
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 4 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

timely manner;

2.2 In case of claims where the PSU/ Department has
challenged the Arbitral Award already announced,
75% of the award may be paid by the PSU/
Department to the contractor/ concessionaire against
Bank Guarantee without prejudice to the final order
of the Court in the matter under challenge. The
payment may be made into a designated Escrow
Account with the stipulation that the amount so
released will be used, first, for payment of lenders'
dues, second, for completion of the project and then
for completion of other projects of the same
PSU/Department, as mutually agreed/ decided. Any
balance remaining in the escrow account subsequent
to settlement of lenders' dues and completion of
projects of the PSU/ Department may be allowed to be
used by the contractor/concessionaire with the prior
approval of the lead banker and the Department/PSU.

2.3 In case the subsequent court order requires
refund of the money paid by a PSU/ Department
against a Bank Guarantee, the amount shall be
refunded by the contractor/ concessionaire along with
appropriate interest. The rate of interest on such
refund amount may be decided by the PSU/
Department keeping in view the cost of capital to the
PSU/ Department or the rate of interest provided for
in the Contract Agreement or the rate of interest
awarded under the Arbitral Award under challenge.

Notes:

(i) For Departments, cost of capital shall be taken as
Weighted Average Coupon rate of outstanding stock of
Central Government securities for the period ending in
the preceding quarter, or Weighted Average Coupon
rate of Central Government securities issued during
the preceding quarter (whichever is higher);
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 5 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07


(ii) PSUs shall either calculate their own cost of
capital or take State Bank of India's One Year
Marginal Cost of fund-based Lending Rate plus 2%;

(iii) The appropriate interest rate on such refund shall
be decided at the time of releasing funds to the Escrow
Account;

(iv) If otherwise eligible and subject to contractual
provisions, retention money and other amounts
withheld may also be released against bank guarantee
as per the laid down criteria.

3. All the concerned Ministries/ Departments shall also
issue instructions to their respective PSUs for taking
necessary action accordingly.

(A. Muthuvezhappan)
Director (PPPAU)”

“Second Office Memorandum dated 05.09.2016”

“No.N-14070/14/2016-PPPAU
Government of India
National Institution for Transforming India (NITI
Aayog)

NITI Bhavan, New Delhi
September 05, 2016

Office Memorandum

Subject: Initiatives on the measures for revival of the
Construction Sector -regarding.

The construction sector has been facing a
number of problems, mainly arising from the liquidity
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 6 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

constraints caused on account of their payments not
being released by the Government Departments/ Public
Sector Undertakings (PSUs) pursuant to the arbitral
awards. To discuss the problems of the construction
sector, detailed deliberations/ consultations were held
with the representatives of the construction industry,
banks, major government PSUs and concerned
Ministries/ Departments. Based on the above
deliberations/ consultations, the NITI Aayog placed a
proposal before the Cabinet Committee on Economic
Affairs (CCEA) for its consideration suggesting
various immediate and long-term measures required
for addressing the issues ailing the construction sector.
The CCEA, chaired by the Prime Minister, has
considered the proposals of NITI Aayog in its meeting
on 31st August 2016 and approved the same for the
revival of construction sector.

2. The NITI Aayog has separately issued instructions
on the subject with regard to the immediate measures
to be taken by all concerned. In addition to the said
instructions, the CCEA has also directed that the
following gmeasures may be expeditiously examined by
all the concerned Departments/ Ministries /PSUs:

2.1 Item-rate contracts, may be substituted by EPC
(turnkey) contracts, wherever appropriate. Such
contracts have been in vogue for over two decades in
the developed world and Federation Internationale
Des Ingenieurs-Conseils (FIDIC - an International
Federation of Consulting Engineers, known by its
French acronym) has also published such contractual
frameworks;

2.2 Model bidding documents and Model EPC
contracts, suitably revisited or modified wherever
required to suit the requirements of particular sectors,
may be adopted by PSUs/ Government Departments
for construction works;
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 7 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07


2.3 Ministry of Finance has issued model bidding
documents for RFQ, RFP etc. which may be adopted
(with appropriate changes wherever required) in all
sectors. Model EPC contracts have been developed for
Highways and Railways and published by the erstwhile
Planning Commission also. NHAI has already adopted
this document and all construction contracts are
currently being structured on this model. NITI Aayog
shall assist the concerned departments, wherever
required, in this regard.

2.4 The method of conciliation has proved more
effective in settling disputes as per experience of some
of the PSUs. All PSUs/ Departments issuing public
contracts may consider setting up Conciliation
Committees/Councils comprising of independent
subject experts in order to ensure speedy disposal of
pending or new cases. Recourse to such conciliation
may be open before, during or after the Arbitration
proceedings. A provision to this effect would also need
to be made in the Contract Agreements in future as a
mechanism for resolution of disputes.

3. All the concerned Ministries/ Departments shall also
communicate the above to their respective PSUs for
taking necessary action on the aforesaid measures.

(A. Muthuvezhappan)
Director (PPPAU)”

(emphasis supplied)
8. In terms of the Office Memorandums, interim payments were
received by the Petitioner. On 18.08.2017, a sum of Rs.47,55,94,100/- was
released to the Decree Holder against the amount that was due and payable.
Another sum of Rs.37,10,29,058/- was received by the Decree Holder on
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 8 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

29.06.2024. Both the amounts represented 75% of the amounts due and
payable on the date when the partial amounts were received.
9. The present application has been filed by the Decree Holder seeking
payment of balance amount.
10. The short question which arises for consideration in this case is how
to apportion an amount paid in execution of an award between principal and
interest and whether in the facts and circumstances of this case, the
calculation given by the Decree Holder should be accepted or not even after
paying the amounts of Rs.47,55,94,100/- on 18.08.2017 and a sum of
Rs.37,10,29,058/- on 29.06.2024, was there anything else due and payable.
Disputes have arisen between the parties regarding the adjustments of the
amounts towards the principal and interest.
11. The Apex Court in Leela Hotels Ltd. v. Housing & Urban
Development Corpn. Ltd., (2012) 1 SCC 302 has laid down as to how the
amounts in terms of the Award is to be appropriated. The Apex Court has
held that first the interest component has to be appropriated and then the
balance amount has to be appropriated to the principal amount unless there
is any agreement to the contrary. The relevant portion of the said Judgment
reads as under:-
“36. Consequently, the only issue which remains for
decision is whether the amounts deposited and/or paid
by H UDCO to M/s Leela Hotels in terms of the award of
the learned arbitrator, was first to be appropriated
towards payment of the interest due on the principal
sum or whether the same was to be appropriated
against the principal sum itself.

xxx

Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 9 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

39. As indicated hereinbefore, the submissions
made by the learned ASG on behalf of H UDCO was
based on the proposition as contained in Sections 59
and 60 of the Contract Act, 1872, on account of the
stipulation recorded on behalf of H UDCO that the
amount of Rs 89.78 crores was being tendered towards
the principal sum, to which there was no objection
from the appellant and, accordingly, it must be held
that since the amount had been received without
demur, such payment fell within the provisions of
Section 59 of the aforesaid Act. In fact, the Division
Bench of the High Court proceeded to consider such
payment and acceptance to be a voluntary acceptance
by the appellant of the aforesaid amount as
appropriation towards the principal as it made good
business sense to accept the same and to utilise the
same in spite of waiting for something indefinite in the
future. Such a submission, though legal and correct, is
not supported by the materials on record.

40. Admittedly, there was no agreement between the
parties as to how the amounts to be paid in terms of the
award were to be appropriated by the appellant.
Accordingly, in terms of the well-settled principle that
in such cases it was for the creditor to appropriate
such payment firstly against the interest payable,
would, in our view, be squarely attracted to the facts of
this case. As was laid down by the Privy Council
in Venkatadri Appa Row v. Parthasarathy Appa
Row [(1920-21) 48 IA 150 : AIR 1922 PC 233] (IA p.
153) and later reiterated in Rai Bahadur Seth
Nemichand case [AIR 1922 PC 26] , when monies are
received without a definite appropriation on the one
side or the other,

“the rule which is well established in ordinary cases
is that in those circumstances the money is first
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 10 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

applied in payment of interest and then when that is
satisfied in payment of the capital”.

41. In the latter case, the said principle was
restated and it was indicated that a creditor to whom
principal and interest are owed is entitled to
appropriate any indefinite payment which he gets from
a debtor to the payment of interest. It was also
indicated that a debtor might in making a payment
stipulate that it was to be applied only towards the
principal. If he did so, the creditor was at liberty to
refuse payment on such terms, but then he would have
to give back the money or the cheque by which the
money is proffered and if the same is accepted, the
creditor would then be bound by the appropriation as
proposed by the debtor.”


12. According to the Decree Holder, as on 12.03.2026, an amount of
Rs.14,14,83,063/- was still due and payable and as on 02.07.2026, an
amount of Rs.16,39,87,708/- is still due and payable by the Judgment
Debtor. This is being disputed by the Judgment Debtor stating that the
amount stands fully paid and no further amounts are due and payable.
13. Learned Counsel for the Decree Holder has claimed the amounts
which are due and payable as on 02.07.2026, in the following manner:-







Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 11 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

























Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 12 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

14. It is the case of the Decree Holder that amounts have been calculated
strictly in terms of the Judgment passed by the Apex Court in Leela Hotels
Ltd. (supra) as per which the interest component has to be adjusted first and
then the principal amount.
15. Per contra , learned Counsel for the Judgment Debtor places reliance
only upon the two OMs dated 05.09.2016 issued by NITI Aayog. According
to the Judgment Debtor, the Decree Holder was required to furnish a Bank
Guarantee for an amount equivalent to 75% of the payout amount together
with interest thereon as a condition precedent for release of the amount.
16. It is stated by the learned Counsel for the Judgment Debtor that the
Decree Holder vide Letter dated 09.12.2016 submitted documents for the
Judgment Debtor’s verification and confirmation of the 75% payout and
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 13 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

annexed its own calculation which is Annexure-III to the Letter dated
09.12.2016. The Decree Holder has included future interest at the rate of
18% and Annexure-III expressly records that as per the Decree Holder, the
apportionment of 75% of the post-award amount as on 31.12.2016 was
Rs.40,30,45,847/- and apportionment of 75% post-award interest as on
31.12.2016 was 7,27,47,015/- and thus, as per the Decree Holder, the total of
75% payout amount is Rs.47.56 crores.
17. It is stated by the learned Counsel for the Judgment Debtor that the
Judgment Debtor vide Letter dated 28.12.2016 confirmed the amounts as
admitted by the Decree Holder vide its Letter dated 09.12.2016. It is stated
that the Decree Holder further vide Letter dated 08.02.2017 had
unconditionally accepted the release of payments. It is stated that there was a
delay on the part of the Decree Holder to give various documents. It is,
therefore, stated that after receiving the amounts, it is not open for the
Decree Holder to go back from their stand and claim the amount in terms of
the Judgment passed by the Apex Court in Leela Hotels Ltd. (supra) which
is barred by time.
18. It is further the case of the Judgment Debtor that Decree Holder once
having apportioned the amount of Rs.40.30 crores towards principal out of
the receipt of Rs.47.56 crores cannot now in 2024 reapportion it to Rs.31.76
crores, that too after 07 years of receipt of the 75% of the payout amount.
The Decree Holder is estopped from reopening the calculation as having
once accepted the payments as per its own calculation without demur cannot
now seek to prejudice the Judgment Debtor who acted upon the Decree
Holder’s calculation.
19. Learned Counsel for the Judgment Debtor has drawn the attention of
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 14 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

this Court to the table as submitted by the Decree Holder to them claiming
the amounts stating that the amounts as claimed by them have been paid and
therefore no amounts are due and payable by the Judgment Debtor.
20. Learned Counsel for the Judgment Debtor states that the payments
have been made strictly in accordance with the two OMs and therefore
nothing is due and payable.
21. Reliance has been placed by the learned Counsel for the Judgment
Debtor upon a judgment passed by the Apex Court in Kerala SEB v. Kurien
E. Kalathil, (2018) 4 SCC 793 wherein the Apex Court did not permit the
Decree Holder from changing his stand. Attention of this Court has been
drawn on paragraph Nos.12, 13, 14, 21 and 22 which read as under:
“12. Even as per the respondent's own Letter No.
D.W/94/090 dated 25-11-1994, the respondent contractor
has deducted the advances paid only towards the
principal and claimed interest. The said letter reads as
under:

“I am herewith submitting a comprehensive statement
(claim bill), giving the details of labour escalation
payable against each CC Bill, deducting the advances
paid to me which are adjustable against the dues. The
net labour escalation amount payable as on 31-10-
1994 works out to Rs 6,32,84,050, after thus deducting
the advances received. The interest amount payable
has also been worked out and included in the enclosed
bill, separately, which comes to Rs 7,66,35,927. The
total amount due as on 31-10-1994 is Rs
13,99,19,1977. This amount may be paid to me without
further delay.”

Thus by his own calculation and as per his own letter
dated 25-11-1994, the respondent contractor has
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 15 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

adjusted all payments received from the Board firstly
towards the principal.

13. But when the respondent filed IA No. 6 of 2006, the
entire method of calculation was changed by showing
adjustment of payments firstly towards interest and then
towards principal, only to claim that in spite of payment
of Rs 12,82,96,320 by the Board, amounts are still due
and payable to him. In the calculation sheet filed along
with IA No. 6 of 2006 while making adjustments of
payment of rupees four crores (payment made to the
respondent contractor during the pendency of the earlier
round of writ petition), the same was adjusted firstly
against the interest and then against the principal
amount. The calculation sheet filed by the respondent
contractor in IA No. 6 of 2006 is as under:

Principal (in Rupees) Interest @ 9% (in Rupees) Remarks
Balance DR CR Date Particulars DR CR Balance
6,32,84,050
Amount
received from
Kerala State
Electricity
Board is firstly
adjusted
against interest
and then
principal
amount
Interest up to CC.
Principal amount
of labour
escalation up to
CC. 78 as per
Ext. P-20
4,02,18,107
78 for the period

up to 20-6-1995
20-6-
1995
Amount received
1,00,00,000 3,02,18,107
Rs 1 crore

Interest from 21-
37,13,820 3,39,31,927
6-1995 to 13-2-

1996
13-2-
1996
Amount received
1,00,00,000 2,39,31,927
Rs 1 crore

Interest from 14-
1,56,043 2,40,87,970
2-1996 to 23-2-

1996
23-2-
1996
Amount received
2,00,00,000 40,87,970
Rs 2 crores

Interest 24-2-
1996 to 20-3-
2,88,67,930 3,29,55,900

2001
5,62,39,95
0
70,44,100 20-3-
2001
3,29,55,900 0 Out of Rs 4
crores received
the interest as
on this date Rs
3,29,55,900 is
wiped off and
balance Rs
70,44,100
Amount received
(4 crores)
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 16 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

adjusted
against
principal
amount
Interest 21-3-
2001 to 5-9-2001
23,43,588

4,85,83,53
8
76,56,412 5-9-
2001
23,43,588 0 Out of Rs 1
crore received,
the interest as
on this date Rs
23,43,588 is
wiped off and
balance Rs
76,56,412
adjusted
against
principal
amount
Interest from 6-9-
Amount received
(1 crore)
4,43,242
2001 to 12-10-

2001

2,90,26,780 1,95,56,758 12-
10-
2001
Amount
received (2
crores)
4,43,242 0 Out of Rs 2 crores
received the
interest as on this
date Rs 4,43,242 is
wiped off and
balance Rs
1,95,56,758
adjusted against
principal amount
Interest 13-
2-2001 to 1-
6-2002
16,60,491
2,39,55,276 50,71,504 1-6-
2002
Amount
received
(67,31,995)
16,60,491 0 Out of Rs
67,31,995 received
the interest as on
this date Rs
16,60,491 is wiped
off and balance Rs
50,71,504 adjusted
against principal
amount
Interest 2-6-
2002 to 17-
8-2002
4,54,822
2,27,34,120 12,21,156 17-
8-
2002
Amount
received
(16,75,978)
4,54,822 0 Out of Rs
16,75,978 received
the interest as on
this date Rs
4,54,822 is wiped
off and balance Rs
12,21,156 adjusted
against principal
amount
Interest 18-
8-2002 to
10-2-2003
9,92,204
1,38,37,977 88,96,143 10-
2-
2003
Amount
received
(98,88,347)
9,92,204 0 Out of Rs
98,88,347 received,
the interest as on
this date Rs
9,92,204 is wiped
off and balance Rs
88,96,143 adjusted
against principal
amount
Interest from 28,66,168 28,66,168
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 17 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

11-2-2003 to
31-5-2005
8,17,16,415

14. Pursuant to the directions [Kurien E. Kalathil v. State
of Kerala, OP No. 283 of 1995, decided on 2-4-1998
(Ker)] of the High Court and after disposal of Kerala
SEB v. Kurien E. Kalathil [Kerala SEB v. Kurien E.
Kalathil, (2000) 6 SCC 293] , the appellant Board made
a total payment of Rs 12,82,96,320. Since the respondent
contractor changed the method of adjustment i.e. by
adjusting the payment firstly towards interest and then
towards principal, even after payment of Rs 12,82,96,320,
according to him Rs 3,38,57,618 was still due to him. The
said calculation shown in IA No. 6 of 2006, reads as
under:

Ext. P-20 (Labour escalation)
Labour escalation claimed in CC Bill 14 to 78 ( Ref. Ext. P-
6,32,84,050
20 )
Labour escalation claimed in CC Bill 79 to 85 ( Schedule 3 ) 90,96,582
Total 7,23,80,632
Total interest up to 31-5-2005 @ 9% p.a. ( Schedules 2

& 3 )
(8,17,16,415 + 80,56,891) 8,97,73,306
Total amount due as on 31-5-2005 16,21,53,938
Less : Amounts received from K.S.E. Board on various
dates (adjusted firstly against interest and then principal
amount)
( Schedule 6 ) 12,82,96,320
Balance amount due as on 31-5-2005 ( Schedule 5 ) 3,38,57,618
Principal amount 2,29,34,559
Interest 1,09,23,059
3,38,57,618

This manner of appropriation, firstly towards the interest
is in clear violation of the directions [Kerala
SEB v. Kurien E. Kalathil, (2000) 6 SCC 293] given by
this Court to make payment under Ext. P-20 and the
method of adjustment which the respondent contractor
himself adopted in Ext. P-20. In the original Ext. P-20,
when the respondent contractor himself has expressly
adjusted all payments made by the appellant towards
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 18 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

principal and not towards interest, the respondent
contractor cannot turn round and change the method of
calculation by showing the adjustment of payments made
first against the interest and then towards the principal.
This important aspect of change in the method of
adjustment/appropriation was lost sight of by the High
Court and the direction of the High Court to make further
payment of Rs 4,12,58,224 under Ext. P-20 is not
sustainable.

xxx

21. An “appropriation of money” is the indication of an
intention that money should be applied in a particular
way. In the present case, the statement of the respondent
contractor himself and other circumstances clearly
indicate that payment ought to be adjusted only towards
the principal amount. As discussed earlier, in Ext. P-20
the respondent contractor himself has shown the labour
escalation due as principal amount and interest thereon
separately and has given the credit of the advances made
by the Board firstly towards the principal and claimed
the balanced amount of the principal. At this juncture, we
may usefully recapitulate the respondent's own letter to
the appellant Board dated 25-11-1994 extracted in para
12 above where the respondent contractor himself has
stated that he has deducted the advances from the
principal amount claimed under “labour escalation
charges” and “interest” are shown separately.

22. By his own statement, the respondent contractor has
firstly appropriated the advances towards the labour
escalation due i.e. the principal amount. The respondent
contractor is not justified in changing the method of
calculation and claim appropriation of the payments
firstly towards the interest and then towards the principal
amount. The claim of the respondent contractor for a
further sum of Rs 2,29,34,559 with interest under Ext. P-
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 19 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

20 cannot be sustained and the direction of the High
Court to pay the same is liable to be set aside.”

22. It is stated by the learned Counsel for the Judgment Debtor that even
in Leela Hotels Ltd. (supra), the Apex Court has held that if the Parties have
agreed to the contrary then principle of apportion of the interest first is not
applicable. It is the case of the Judgment Debtor that by this method, the
Decree Holder is actually compounding the interest which is not
permissible.

23. Heard learned Counsel for the parties and perused the material on
record along with the two OMs and the tabulated charts.
24. In the opinion of this Court, the communication given by the Decree
Holder does not amount to an agreement to the contrary because the
communications were given in lieu of the two OMs regarding the amounts
which were payable during the pendency of the challenge to the Award. The
communications do not have any effect once the Award has been upheld.
The amounts which are due and payable under the Award is payable in
accordance with the law laid down by the Apex Court in Leela Hotels Ltd.
(supra).
25. Learned Counsel for the Judgment Debtor has placed emphasis on the
Judgment passed by the Apex Court in Kerala SEB v. Kurien E. Kalathil,
(2018) 4 SCC 793. In the opinion of this Court, the said Judgment is
distinguishable on facts. In fact, Kerala SEB (supra) follows the Judgment
passed by the Apex Court in Leela Hotels Ltd. (supra) and does not give any
other view and in the opinion of this Court, the view taken by the Apex
Court in Kerala SEB (supra) is completely distinguishable.
26. A perusal of the aforementioned OMs dated 05.09.2016 which are the
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 20 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

basis of the entire argument, shows that they have been brought out by the
NITI Aayog only to assuage the problems faced by the contractors in
construction sector. It was felt that contractors, who put money in the
contracts had obtained Awards in their favour, were not getting the amounts
in view of the prolonged litigation and were facing several litigations. In
order to solve this problem, it was decided to release some money to the
contractor’s subject to submission of Bank Guarantee so that in case the
Award is set aside then the Government would be in a position to take the
money back with interest from the contractors. These OMs are, therefore, an
aid to the execution. In the present case, the Award has attained finality. The
amounts, therefore, have to be strictly paid in accordance with the law laid
down by the Apex Court in Leela Hotels Ltd. (supra). The correspondence
relied upon by the learned Counsel for the Judgment Debtor regarding
admission as how the amount has to be paid under the OMs issued by the
NITI Aayog is of no significance. Once the Award has attained finality then
the amount under the Award has to be paid in accordance with the law laid
down by the Apex Court in Leela Hotels Ltd. (supra) in execution
proceedings after adjusting the amounts already received under the OMs. It
cannot be said that any correspondence made regarding OMs issued by NITI
Aayog would result in any agreement to the contrary as alleged by the
Judgment Debtor. The Decree Holder vide Letter dated 08.02.2017 has
accepted the amounts paid under the OMs issued by the NITI Aayog which
is being reproduced as under:
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 21 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

27. It is to be mentioned that the Decree Holder had accepted the amounts
without prejudice to the entitlement to receive the balance payment in terms
of the Award. Once the Award has attained finality, the OMs pale into
insignificance and the amount is to be paid in accordance with law which is
in accordance with the judgment passed by the Apex Court in Leela Hotels
Ltd. (supra). The correspondence entered into between the parties for the
Signature Not Verified
OMP (ENF.) (COMM.) 87/2018 Page 22 of 23

Signed By:HARIOM
SINGH KIRMOLIYA
Signing Date:03.08.2026
17:21:07

implementation of the OMs reproduced above is not part of the execution
proceedings but only an interim measure taken by the Government to
assuage the problems faced by the contractors which cannot be said to be a
contract to the contrary. Further, this Court is of the opinion that the table
given by the Decree Holder is in accordance with the law laid down by the
Apex Court in Leela Hotels (supra).
28. In view of the above, the application is allowed.
29. The Judgment Debtor is directed to pay a sum of Rs.16,39,87,708/- as
on 02.07.2026 which according to the Judgment Debtor is due and payable
in accordance with the judgment passed by the Apex Court in Leela Hotels
Ltd. (supra) within six weeks from the date of uploading of the Judgment.
OMP (ENF.) (COMM.) 87/2018 & EX.APPL.(OS) 463/2019,
EX.APPL.(OS) 1848/2024
30. In view of the Orders passed in EX.APPL.(OS) 1025/2024, the
petition is disposed of, along with pending application(s), if any.



SUBRAMONIUM PRASAD, J
JULY 28, 2026