NARAYAN KUMAR INFRASTRUCTURE PRIVATE LIMITED vs BONGAON MUNICIPALITY

Court
Calcutta High Court

IN THE HIGH COURT AT CALCUTTA
(ORIGINAL SIDE)
COMMERCIAL DIVISION


Present:
The Hon’ble Justice Krishna Rao

C.S. (COM) No. 8 of 2023

Narayan Kumar Infrastructure Private Limited
Versus
Bongaon Municipality


Mr. Shiv Ratan Kakrania
Mr. Tanish Ganeriwala
Mr. Tanuj Kakrania
Mr. Sagnik Mukherjee
Ms. Jiya Bose
Ms. Shreya Goenka
Ms. Surabhi Mehta
… For the plaintiff.

Hearing Concluded On : 25.03.2026
Judgment On : 30.04.2026




2

Krishna Rao, J.:
1. The plaintiff has filed the suit praying for a decree for a sum of Rs.
4,92,36,921.80 along with interim interest and interest upon judgment
at the rate of 18% per annum.

2. The defendant floated a tender being tender No. WBMAD/51/2017-
st
2018/B-M/PWD dated 21 November, 2017 inviting offers from
prospective tenderers for the work of “Construction of Bus Terminions
along with Commercial (Market Complex) and Residential Complex” at
Gandhipally in Ward No.14 under Bongaon Municipality.

3. The plaintiff, who was known as M/s. Narayan Kumar, participated in
the said tender and submitted an offer to execute the work at the rate
of 0.20% below the rate put to tender.

4. The defendant found the offer of the plaintiff to be the lowest and
accordingly the defendant issued a work order in favour of the plaintiff
th
on 9 February, 2018.

5. Simultaneously, the parties executed various documents, i.e. the
conditions of contract, the additional conditions, the detailed notice
inviting tenders, the special terms and conditions, etc. which together
comprised a final, binding and concluded contract between the parties.

th
6. The work order was issued by the defendant on 9 February, 2018,
wherein the stipulated time given for the work to be completed by the
plaintiff was within a period of 365 days to be reckoned with effect from

3

the commencement date which was to begin within seven days from the
date of the issuance of the work order.

7. The work order as well as the various other contractual documents
forming part and entirety of the contract also contains detailed
provisions regarding the rights, obligations, liabilities and
responsibilities of either parties with respect to execution of the
contract. The contract documents further contained, a work schedule
in the nature of a bill of quantities which stipulated the various items of
work which were required to be undertaken by the plaintiff, as the
tenderer, apropos which item wise rates were prescribed.

th
8. Immediately after the issuance of the work order dated 9 February,
2018, the plaintiff, in right earnest, mobilised itself by engaging
sufficient men, materials, equipment and infrastructural capabilities so
as to be able to execute the work within the period prescribed in the
contract.

9. Right from the beginning, the plaintiff has faced numerous obstacles
and hindrances which added a severe and substantial impact on the
progress of the work. The plaintiff at various points of time faced with
the following problems:

(i) It was always agreed and understood between the parties
and, in fact, made explicit in the contract, by Clause 11 of
the Conditions of Contract that the plaintiff would be
obliged to execute the whole and every part of the work in
accordance with the specifications and in conformity to the

4

designs, drawings and instructions issued in writing by
engineer-in-charge. Unfortunately however, the engineer-
in-charge of the defendant, despite repeated requests and
reminders having been issued by the plaintiff from time to
time, failed to provide the plaintiff with the requisite
drawings or to even approve of the drawings which were
prepared and made over to the engineer-in-charge by the
plaintiff. The plaintiff has sent various emails and letters
to the defendant in this regard.

(ii)
The plaintiff was under an obligation to have the site
surveyed through a competent third party, which it had
duly engaged. However, in order to effectively carry out
the survey, the plaintiff needed necessary reference points
to be furnished by the defendant, but the defendant had
failed to furnish such reference points and the points
which were submitted by the defendant were completely
otiose since they did not pertain to the work site in
question.

(iii) That due to the lackadaisical attitude displayed by the
defendant, the work was delayed at every stage where
drawings were supplied since the layouts thereof were not
in conformity with the survey conducted or proposed to be
conducted at the work site. The plaintiff time and again
wrote to the defendant regarding this issue and several
letters and emails were exchanged between the plaintiff to
the defendant.

(iv) In addition to the above, sometimes around August, 2018,
the plaintiff was faced with the predicament wherein one
of the drawings supplied to the plaintiff by the defendant
authorities indicating the requirement for Pile Cap Casting

5

or (TECC of 75mm) to be executed. Considering the same
fact, such item was not mentioned in the bill of quantities
and was thus outside the scope and ambit of the work
entrusted to the plaintiff, therefore, the plaintiff called upon
the defendant for appropriate instructions and to advise
the plaintiff on what was required to be done regarding the
Pile Cap Casting since execution of such additional work
would entail the plaintiff to get extra item appropriate to
the work to be done. Even after repeated requests by the
plaintiff, the defendant maintained stoic silence and
having no alternative the plaintiff was constrained to
execute the work.

(v) The conditions of contract further stipulated that the
plaintiff would have to raise periodical or monthly running
account bills upon the defendant. Therefore, it was a
reciprocal obligation for the defendant to disburse
payments against such running account bills in periodical
fashion and within a reasonable time. However, the
defendant failed to discharge its liabilities, the plaintiff,
thus, was required to repeatedly issue letters to remind
the defendant of its obligation to make payment,
th
particularly with regard to the 9 Running Account Bill.

(vi) Numerous letters have been issued regards to the non-
payment of running account bill and for payment regarding
the additional works of land filling, etc., by the plaintiff to
the defendant. Not only did the defendant failed miserably
in discharging its obligation under clauses 8 and 9 of the
conditions of contract but there were also instances where
the defendant made over cheques to the plaintiff against
the running account bills raised by the plaintiff, only for
the same to be dishonoured upon presentation. On or

6

around July, 2019, while the plaintiff was contending with
the various issues, obstacles and hindrances, the
defendant issued formal instructions upon the plaintiff to
slow down the rate of work at the worksite on the pretext
that the defendant did not have adequate funds to make
payment to the plaintiff. Thereafter, the plaintiff made
several representations to the defendant requesting it to
issue instructions to resume the work given that the
plaintiff was suffering from several losses on account of
idle men, machinery and infrastructure.

(vii) On or around May 2020, the plaintiff got to know that the
defendant had already sanctioned the establishment of a
fish market at the exact same premises where the bus
terminions were to be constructed and as a result, most of
the material and establishment left behind at the worksite
had been removed and/or pilfered. Roadside vendors, etc.,
had also set up shop at the worksite which makes it
impossible for the plaintiff to once again resume the work.

(viii) Notwithstanding the apparent exigencies involved, the
defendant in an attempt to avoid liability, by a letter dated
th
29 August, 2020 purported to shift the entire blame upon
the plaintiff and instructed the plaintiff to resume
execution of the work, knowing fully well that the same
was impossible given the prevailing the situation.


10. There has been material breach on the part of the defendant in
discharging its obligations under the contract, and such breach has
resulted in direct and consequential losses to the plaintiff. Not only has
the plaintiff suffered monetary losses and injury owing to such breach,

7

th
but it also entitled to claim the unpaid value of the 9 Running
Account Bill.

11. The plaintiff states that the plaintiff is entitled to unbilled amount of
work done as well as the earnest money which had been deposited at
the outset and also the security deposit that has been deposited at the
outset and also the security deposit that has been deducted periodically
st th
from the 1 to the 8 Running Account Bills, wherein the Running
Account Bills will itself reflect that an aggregated sum of
Rs.45,59,116/- has been deducted on account of security deposit and
additionally a sum of Rs.41,13,041/- was furnished at the
commencement of the contract in terms of the work order.

12. The plaintiff has received payments against Running Account Bill Nos.
1 to 7 in its Bank Account from the defendant.

13. The plaintiff further submits that additionally it has suffered losses to
the tune of approximately Rs. 2,77,73,825.24, on account of damages
suffered on the following heads:

(i) The plaintiff has from time to time submitted bills to the
defendant but the defendant has failed and neglected to
make payments amounting to Rs. 39,09,330.24 for the
th
pending 9 Running Account Bill of the plaintiff.

(ii) Damages for abruptly stopping work at the worksite upon
intimation by the defendant to the plaintiff.


8

(iii) Claim for release of Earnest Money Deposit (EMD) and
security deposit deducted from various Running Account
Bills amounting to a total sum of Rs. 41,13,041/- and Rs.
45,59,116/- which have become due and payable.

(iv) Claim for compensation on account of losses suffered due
to extended stay on the site, which after reasonable
quantification by the plaintiff leads to an amount of
Rs.73,86,535/-.


14.
The plaintiff states that it has suffered losses with respect to its profit
earnings since all the resources, facilities, infrastructure were deployed
during the contractual period on the project site and due to that the
plaintiff has not been able to obtain any pecuniary benefit from
anywhere else since everything remained arrested in the worksite and
this amounted to a loss of Rs.78,05,803/-.

15. Before filling of the suit, the plaintiff had instituted pre-institution
mediation process but the defendant failed to appear before the
th
Mediation and accordingly a non-starter report dated 11 September,
2023, was issued by the Member Secretary, Mediation and Conciliation
Committee, High Court.

th
16. According to the report of the Deputy Sheriff of Calcutta dated 20
nd
February, 2024, on 2 February, 2024, the original writ of summons
along with a copy of the plaint were served upon the defendant, which
th
was duly received by the defendant on 10 February, 2024, and a copy
of the writ of summons along with a copy of the plaint was sent to the

9

th
defendant by post which was duly delivered to the defendant on 7
February, 2024.

17. According to the report issued by the Deputy Registrar (Legal) dated
th
14 May, 2024, the defendant has not entered appearance, therefore by
th
an order dated 25 June, 2024, this Court had placed the matter in
the list of “Undefended Suit”

18. The plaintiff in order to prove its case has examined one witness,
namely, Mr. Manik Bhunia, as P.W.1 and had exhibited altogether total
number of 17 (Seventeen) documents and are marked as “Exhibit A to
Exhibit Q” which are as follows:
st
Exhibit A: Copy of the Tender Notice dated 21
November, 2017 released by the defendant.

th
Exhibit B: Copy of the work order dated 9
February, 2018 issued by the defendant to the
plaintiff.

Exhibit C (Collectively) : Set of documents which are
copies of all the contracts entered between the parties
are marked and exhibited collectively.

Exhibit D (Collectively) : Original Copies of Work
Schedule marked and exhibited collectively.

Exhibit E (Collectively) : Original Copies of Letters
nd th
and/or Emails dated 2 April, 2018, 19 May, 2018,
th rd th
5 September, 2018, 23 November, 2018, 24
th th
November, 2018, 11 December, 2018, 5 February,
th th th
2019, 7 February, 2019, 8 February, 2019, 13
th th
February, 2019, 14 February, 2019, 11 March,
th
2019 and 27 April, 2019, marked and exhibited
collectively.

Exhibit F (Collectively) : Another set of original
th
copies of Letters and/or E-mails dated 6 October,
th th th
2020, 11 October, 2018, 12 October, 2018, 26
th th
October, 2018, 27 October, 2018, 27 December,

10

th th
2018, 12 January, 2019 and 15 January, 2019
marked and exhibited collectively.

Exhibit G (Collectively) : original copies of Letters
th th
and/or E-mails dated 7 March, 2019, 14 June,
th th th
2019, 15 June, 2019, 17 June, 2019, 18 June,
th th th
2019, 11 July, 2019, 12 July, 2019, 19 July,
th th th
2019, 26 July, 2019, 11 August, 2019, 12
th th
August, 2019, 9 September, 2019, 10 September,
rd th th
2019, 3 December, 2019, 16 December, 2019, 17
th th
December, 2019, 8 February, 2020, 24 February,
th th th
2020, 24 March, 2020, 25 March, 2020, 26
rd th th
March, 2020, 3 April, 2020, 5 April, 2020, 28
st th th
July, 2020, 21 August, 2020, 6 October, 2020, 7
th th
October, 2020, 5 November, 2020, 8 February,
th nd th
2021, 9 February, 2021, 22 June, 2021 and 26
July, 2021, marked and exhibited collectively.

th
Exhibit H: Copy of a Letter dated 11 July, 2019,
sent by the plaintiff to the Chairman of the Defendant
th
regarding payment of the 7 RA Bill and regarding
restraining of stopped civil work.

th
Exhibit I: Copies of a Letter dated 4 August, 2018
th
and 11 October, 2018 along with an e-mail dated
th
12 October, 2018 sent by the plaintiff addressing
the Chairman of the Defendant.

Exhibit J (Collectively): Copies of Original
Correspondences exchanged between the parties
th nd rd
dated 11 June, 2018; 2 January, 2019; 3
th
January, 2019 and 6 March, 2019.

Exhibit K (Collectively) : Original Copies of Running
th th
Account Bills dated from 13 July, 2018 to 15 July,
2019.

Exhibit L (Collectively) : Copies of Bank Statements
of the Plaintiff maintained with Karnatak Bank and
ICICI Bank.

th
Exhibit M: Original Copy of an e-mail dated 7 May,
2020 sent by the plaintiff to the defendant.

th
Exhibit N: Original Copy of the 9 Running Account
Bill with measurement sheets.

Exhibit O: Original Copy of the extract of the cost
th
(cost sheet) dated 29 May, 2019.

11

Exhibit P (Collectively) : Original Copies of the
th
challans and receipts and money receipts from 8
February, 2019 upto 2021 marked and exhibited
collectively.

Exhibit Q: Copy of Tabular Computation.


st
19. The defendant floated a tender dated 21 November, 2017 for
construction of Bus Terminions along with Commercial Market
Complex and Residential Complex at Gandhipally in ward No. 14 under
Bongaon Municipality. The plaintiff has proved the said tender notice
being “Exhibit-A”. The plaintiff had participated in the tender process
and the plaintiff has declared as a successful tenderer. After acceptance
th
of the tender, on 9 February, 2018, a work order was issued by the
defendant to the plaintiff which has been proved being “Exhibit-B”. As
th
per the work order, the date of commencement of the work is dated 16
th
February, 2018 and completion of the work is dated 15 February,
2019.

20. As per the case of the plaintiff, the defendant failed to discharge its
th
reciprocal obligation. As per the work order dated 9 February, 2018,
the plaintiff has to undertake survey of the site and to prepare lay out
within 10 days from the date of issuance of work order. By a letter
nd
dated 2 April, 2018, the plaintiff requested the defendant to confirm
the reference points so that the same could be used for preparing the
th
lay out in terms of the work order. On 5 September, 2018, the plaintiff
had again requested the defendant to confirm the reference points so as
rd
to enable the plaintiff to prepare the layout plan. By a letter dated 23

12

th
November, 2018 and e-mail dated 24 November, 2018, the plaintiff
had informed the defendant that though the plaintiff has received the
st
drawing for Block-A on 1 November, 2018 but the work for the same
could not be started as there were difficulties on layout of the same. By
th
a letter dated 11 December, 2018, the plaintiff had informed the
defendant that the plaintiff has received revised version of drawing of
Block-A but the plaintiff is waiting for the hardcopy of the said drawing.
th
By a letter dated 5 February, 2019, the plaintiff has also requested
the defendant for providing drawings for electrical, plumbing, duct
details and other works which needs to be taken care of before casting
th
of slab. On 8 February, 2018, the plaintiff had again requested the
defendant to provide all the drawings as sought for by the plaintiff by
th th
its letter dated 19 May, 2018. On 13 February, 2019, the plaintiff
had again requested the defendant to provide balance set of drawings
while enumerating the discrepancies in the existing set of drawings
th
furnished by the defendant. On 14 February, 2019, the defendant
had issued a letter to the plaintiff responding to the queries raised by
th th
plaintiff in its email dated 13 February, 2019. On 11 March, 2019,
the plaintiff had requested the defendant to provide balance drawings
th
to the plaintiff. By an email dated 27 April, 2019, the plaintiff had
intimated the defendant that no provisions of “Chajja” have been made
in terms of the deliberation and discussions between the parties. All the
above mentioned correspondences have been marked as “Exhibit-E”
collectively.

13

21. It is admitted by the plaintiff that the defendants have released the
amount with respect to the Running Account Bill No. 1 to Running
th
Account Bill No. 8. The plaintiff had submitted 9 Running Account
th
Bills on 17 December, 2019 and thereafter the plaintiff had made
th
several correspondences with the defendant on 24 February, 2020,
th th st
25 March, 2020, 28 July, 2020, 21 August, 2020 but the defendant
th
has not paid the 9th Running Account Bill. By a letter dated 29
August, 2020, the defendant has admitted that one bill is remain
pending for lack of fund due to the Covid-19 situation and it will be
paid as soon as the condition will became normal. In the said letter, the
defendant has also requested the plaintiff to start executing the work of
the project as per direction, subsequently, payment will be made
accordingly. All the said correspondences are marked as “Exhibit-G”
collectively.

th
22. 9 Running Account Bill along with measurement sheets are marked
th
as “Exhibit-N” collectively. As per 9 RA Bill, the measurement sheet,
th
the measurement of the work was done on 30 September, 2019. After
th
submission of 9 RA bill, the plaintiff has submitted request to the
th
defendant for release of the said amount by a letter dated 17
December, 2019, and the same is marked as “Exhibit-G” but neither
the defendant has sent any reply nor has made any payment.

23. Clauses 7 and 8 of the Conditions of Contract reads as follows:

14

“ Clause 7. ---
No payment shall be made for works estimated to
cost less than rupees one thousand, till after the
whole of the work shall have been completed and a
certificate of completion given. But in the case of
work estimated to cost more than rupees one
thousand the contractor shall on submitting the bill
thereof be entitle to receive a monthly payment from
the Municipality proportionate to the part thereof then
approved and passed by

Payment on
Intermediate
Certificate to
be regarded
the Engineer-in-charge whose certificates of such approval and passing
of the sum so payable shall be final and conclusive, against the
contractor. According to the bill passed by the Engineer-in-charge
payment will be made by the Chairman to the contractor. But all such
intermediate payments shall be regarded as payments by way of
advance against the final payment only and not as payments by way
of advance against the final payment only and not as payments for
work actually done and completed and shall not preclude the requiring
of bad unsound, and imperfect or unskilful work to be removed and
taken away and reconstructed, or re-erected, or be considered as an
admission of the due performance of the contractor, or any part thereof,
in any respect, or the according of any claim, nor shall it conclude,
determine or affect in any way the powers of the Engineer-in-charge
under these conditions or any of them as to the final settlement and
adjustment of the accounts or otherwise or in any other way.very or
effect the contract. The final bill shall be submitted by the contractor
within one month of the date fixed for completion of the work, otherwise
the Engineer-In-charge's certificates of the measurement and of the total
amount payable for the work accordingly shall be final and binding on
all parties. The Engineer-in-charge. will be in no way responsible for
actual payment to the contractor but he will rather pass the bill and
send the bill to the Chairman for payment.

Clause 8. - A bill shall be submitted by the contractor each month on
or before the date filed by the Engineer-in-charge for all work executed
in the previous month, and the Engineer-in-
charge shall take or cause to be taken the
Submitted
monthly
requisite measurements for the purpose of having the sum verified,
and, the claim as far as admissible as adjusted, if possible, before
the expiry of ten days from the presentation of the bill. If the
contractor does not submit the bill within the time fixed as aforesaid
the Engineer-in-charge may dispute. subordinate to measure up the
said work in the presence of the contractor, whose countersignature
to the measurement list will be sufficient warrant; and the Engineer-
in-charge may prepare a bill from such list which shall be binding on
the contractor in all respects.

15

th
In terms of the said Clauses, the plaintiff has submitted 9 RA
Bill but neither the Engineer-in-Charge has disputed the same nor the
th
defendant has released the amount claimed in the 9 R.A. Bill.

24. The plaintiff has deposited an amount of Rs. 41,13,041/- being an
st
earnest money deposit as per tender condition on 21 November, 2017
and the same is marked as “Exhibit-A”. From the RA Bills No.1 to 8, the
defendant has deducted an amount of Rs. 45,59,116/- being the
security deposit and the same is marked as “Exhibit-K” collectively. The
plaintiff also requested the defendant for release of earnest money
deposit and security deposit but the defendant failed to release the
same in favour of the plaintiff.

25. It is also the case of the plaintiff that the plaintiff has executed extra/
additional work beyond the contract as per the advice of the defendant
and on completion of additional work, the plaintiff has abstract of the
work executed by the plaintiff total amounting to Rs. 62,18,386.84 and
the same are marked as “Exhibit-O”. The defendant has neither
disputed the additional work executed by the plaintiff as mentioned in
the abstract of the work nor has paid the amount to the additional
work executed by the plaintiff. The plaintiff has also made several
correspondences with the defendant but no payment is released.
Supplementary work is defined in Clause 28 of the Conditions of
Contract, which reads as follows:
“ 28. Any intem of work which can legitimately
be considered as not stipulated in the schedule of
probable items of work but becomes necessary as a

16

supplementary items reasonable contingent item
during actual execution of the work will have to be
done by the contractor when so desired by the
Engineer-in-charge.

The rate of a supplementary item shall be
derived to the maximum extent possible from the
rates of the accepted items of works appearing in
the schedule of probable items.

To complete the analysis if necessary the
rates appearing in the P.W.D. Schedule (as defined
in clause I of the special terms and conditions) shall
be applicable for the portion remaining after
application of the principles laid down in the
preceeding paragraph.

In Case, extra Items do not appear in the
"Specified schedule" such class of works will be
paid at the rates entered in the schedule of the
Eastem Circle P.W.D. which was in vogue on the
last date of the dropping of the tender.

If the analysis cannot be completed even after
application of the principles laid down in the
preceeding 3 paragraphs, the balance shall be
determined from the then market rates (i.e: the
market rates on the last date of dropping of the
tender) of materials and labour, plus profit and
overhead charges which (both together) shall be
taken as 10 (ten) percent on the cost of labour and
materials (excluding materials that may be
supplied by the Deptt.)

Contractual percentage should be applied over
the rates or the portion of the rates which have
been derived from rates of specific period schedule
of probable items, the specified schedule 199 9 or
the Eastern Circle schedule, P.W.D. No contractual
percentage is However, applicable on the rates or
the portion of the rates analysed on the basis of the
then market rate, But for the facility or preparing
bill, such rates based on market rates should be so
adjusted that the contractual precentage can be
applied over the gross amount of the bills.

Claims to the supplementary Items shall not
be entertained unless supported by entries in the
work-order book or by any written order.

17

26. The plaintiff has made all together four claims against the defendant.
th
Claim No.1 is non-payment of 9 RA Bill total amounting to Rs.
th
39,09,330.24/-. 9 RA Bill is marked as “Exhibit-N”. the said bill
contains the details of the work executed by the plaintiff. Even after
receipt of the said bill, the defendant has neither raised any dispute nor
payments were released.

27. The claim no.2 is additional work/ supplementary work executed by
the plaintiff to the extent of Rs. 62,18,386.84. The plaintiff has
submitted its bill and is marked as “Exhibit-O”. The said bill also
received by the office of the defendant but neither any objection/
dispute is raised nor the payment was made.

28. The claim no.3 is the security deposit of Rs. 45,59,116/- which was
deducted from the RA Bill Nos. 1 to 8 of the petitioner as per the terms
of the contract. The plaintiff also claimed Rs. 41,13,041/- being the
Earnest Money Deposit. After termination of contract, the plaintiff has
made request for release of the said amount but the defendant has not
released the same. It is not the case of the defendant that upon
termination of contract, the EMD and Security Deposit is forfeited.

29. Claim no. 4 is with regard to the compensation on account of loss
suffered by the plaintiff to the tune of Rs. 73,86,535/- .

30. Considering the pleading, evidence of the plaintiff and the documents
relied by the plaintiff, this Court finds that the plaintiff has proved its
case with respect of claim nos. 1, 2 and 3 but the plaintiff failed to

18

prove with regard to claim no.4. The plaintiff is entitled to get an
th
amount of Rs. 39,09,330.24/- being the claim in respect of 9 RA Bill,
Rs. 62,18,386.84 being the amount of the supplementary/ additional
work executed by the plaintiff, Rs. 45,59,116/- being the Security
Deposit deducted by the defendant from RA Bills No. 1 to 8 and Rs.
41,13,041/- being the earnest money deposit made by the plaintiff,
total amounting to Rs. 1,87,99,874.08. The plaintiff is also entitled to
get interest at the rate of 10% per annum from the date of filing of the
suit till the realisation of the total amount.

31. The defendant is directed to pay an amount of Rs.1,87,99,874.08 to the
plaintiff along with interest at the rate of 10% per annum from the date
of filing of the suit till the realisation of the total amount.

32. C.S. (Com) No. 8 of 2023 is disposed of . Decree be drawn accordingly.

(Krishna Rao, J.)