M/S Rohit Traders A Proprietoship Firm vs The State Of Madhya Pradesh

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-JBP:92584
1 WP-45725-2026
IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR

BEFORE
HON'BLE SHRI JUSTICE ALPESH Y. KOGJE,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VIVEK JAIN
th
ON THE 20 OF NOVEMBER, 2026
WRIT PETITION No. 45725 of 2026
CNR No.: MPHC010812982026
M/S ROHIT TRADERS A PROPRIETOSHIP FIRM
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri Dileep Kumar Pandey - Advocate for the petitioner.
Shri Piyush Jain - Govt. Advocate for the respondents / State.
ORDER
Per: Justice Vivek Jain
The present petition has been filed seeking the following reliefs:-
(i) That, by issuance of writ in the nature of Certiorari,
Hon’ble Court be pleased to quash recommendation of

termination of contract ( )105 (Annexure-P/8) in its
प नं.
entirety.
(ii) That, by issuance of writ in the nature of
Prohibition, Hon’ble Court be pleased to restrain the
respondents from giving effect to the recommendation
of termination of contract 105.
प नं
(iii) Any other order as may be found fit and necessary
may also kindly be passed in favour of the petitioner.
2. The petitioner is aggrieved by the proforma No. 105 (Annexure P-
Signature Not Verified
Signed by: NAVEEN KUMAR
SARATHE
Signing time: 20-11-2026
18:07:45

NEUTRAL CITATION NO. 2026:MPHC-JBP:92584
2 WP-45725-2026
8) issued by some functionaries of the respondent Department, whereby

recommendation has been made for termination of contract of the petitioner
under clause 27.2(g) of the contract.
3. The counsel for the petitioner has argued that the petitioner was
granted the work of renovation and upgradation of Surkhi Podi Reservoir
which is owned by Department of Water Resources, Government of Madhya
Pradesh. The counsel for petitioner submits that the respondents No.3 to 6
have issued the recommendation for termination of contract without giving
any opportunity of hearing and this action of the respondents is violative of
principles of natural justice. Even otherwise, clause 27.2 (g) of the agreement
is not applicable to the case of the petitioner as he is not engaged in corrupt
or fraudulent practices in the manner of execution of the agreement. The
work was completed and despite that the recommendation for termination of
contract has been made.
4. Per contra, the counsel for the State has argued that the petition is
premature and even otherwise, no grounds are made out to interfere in the
matter as the disputes are purely contractual in nature. It is pointed out by
counsel for the State that the impugned proforma No.105 is only
recommendation for termination of contract and at present there is no final
order against the petitioner. Even if there is existence of an order then clause
12 of the tender document clearly lays down the dispute resolution
mechanism which can be resorted to and availed by the petitioner.
5. Upon hearing counsel for the rival parties and on perusal of the
documents placed on record, this Court has observed that what is challenged
Signature Not Verified
Signed by: NAVEEN KUMAR
SARATHE
Signing time: 20-11-2026
18:07:45

NEUTRAL CITATION NO. 2026:MPHC-JBP:92584
3 WP-45725-2026
in the present petition is a recommendation for termination of contract.

Therefore, since only a recommendation for termination of contract has been
made by the concerned authority, therefore, at this stage, the petitioner does
not seem to have a valid cause of action and the petition seems to have been
filed in anticipation of an order of termination. No indulgence can be made
in an petition filed in anticipation of an order.
6. The allegation against the petitioner was of having encashed and
closed the FDRs submitted to the Department towards performance security
and additional performance security. In response to the notice dated
14.08.2026, the petitioner submitted a reply dated 18.08.2026 and admitted
that he has got the FDRs of performance security and additional performance
security encashed and closed. Thereafter, the petitioner has submitted a
representation to the Chief Engineer which is placed on record as Annexure
P-5 dated 25.09.2026 requesting the Chief Engineer to foreclose the contract
without any punitive action.
7. Be that as it may be, but at present there is no order against the
petitioner. Even if the respondents pass an order against the petitioner, then
also he would be having ample opportunities available to him to raise the
disputes as per dispute resolution system laid down in the tender document.
As per para-12 of the tender document, the following dispute resolution
mechanism has been laid down :-
12. Dispute Resolution System
12.1 No dispute can be raised except before the
Competent Authority as defined in Contract Data in
writing giving full description and grounds of dispute. It
is clarified that merely recording protest while accepting
Signature Not Verified
Signed by: NAVEEN KUMAR
SARATHE
Signing time: 20-11-2026
18:07:45

NEUTRAL CITATION NO. 2026:MPHC-JBP:92584
4 WP-45725-2026
measurement and/or payment shall not be taken as
raising a dispute.
12.2 No dispute can be raised after 45 days of its first
occurrence. Any dispute raised after expiry of 45 days
of its first occurrence shall not be entertained and the
Employer shall not be liable for claims arising out of
such dispute.
12.3 The Competent Authority shall decide the matter
within 45 days.
12.4 Appeal against the order of the Competent
Authority can be preferred within 30 days to the
Appellate Authority as defined in the Contract Data.
The Appellate Authority shall decide the dispute within
45 days.
12.5 Appeal against the order of the Appellate
Authority can be preferred before the Madhya Pradesh
Arbitration Tribunal constituted under Madhya Pradesh
Madhyastham Adhikaran Adhiniyam, 1983.
12.6 The Contractor shall have to continue execution
of the Works with due diligence notwithstanding
pendency of a dispute before any authority or forum.

8. There is a complete mechanism to raise the dispute before the
competent authority who shall decide the same, thereafter to approach the
appellate authority if the party feels aggrieved by the decision of competent
authority. After decision of appellate authority, further remedy can be
availed before MP Arbitration Tribunal constituted under MP Madhyastham
Adhikaran Adhiniyam, 1983.
9. Therefore, there is an availability of complete mechanism under the
contract and in case any order of termination of contract is passed against the
petitioner, then he would be having a remedy to take recourse to remedies as
Signature Not Verified
Signed by: NAVEEN KUMAR
SARATHE
Signing time: 20-11-2026
18:07:45

NEUTRAL CITATION NO. 2026:MPHC-JBP:92584
5 WP-45725-2026
per clause 12 of the contract as quoted above.

10. In view of above, this Court does not see any good ground to
interfere in the matter at this stage and also on ground of availability of
alternative remedies under the contract. Therefore, the petition stands
dismissed with liberty to the petitioner to take recourse to remedies as per
clause 12 of the contract tender document on arising of a valid cause of
action.
(ALPESH Y. KOGJE)
(VIVEK JAIN)
CHIEF JUSTICE
JUDGE