Ashok Kumar vs Ms Nandini Paliwal And Ors

Court
Delhi High Court

$~2 to 4
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of Decision: 13.05.2026
+ CONT.CAS(C) 383/2025, CM APPL. 12694/2026
ASHOK KUMAR .....Petitioner
versus
MS NANDINI PALIWAL AND ORS. .....Respondent
3
+ CONT.CAS(C) 385/2025, CM APPL. 12804/2026
SUSHMITA BISWAS .....Petitioner
versus
MS NANDINI PALIWAL AND ORS. .....Respondent
4
+ CONT.CAS(C) 836/2025, CM APPL. 12695/2026
SHASHI SAINI .....Petitioner
versus
MS.NANDINI PALIWAL AND ORS. .....Respondent

Presence :
Mr. Sourabh Ahuja and Mr. Keshav Singh, Advs. for petitioner
in item nos. 2 to 4.
Mr. B. S. Rawat, CI DTTE for respondents in item nos.2 to 4.
Ms. Avnish Ahlawat, SC, Mr. Nitesh Kumar Singh, Ms. Aliza
Alam and Mr. Mohnish Sehrawat, Advs. for DTTE.
Mr. Shivendra Singh, Adv. for DSEU in item nos.2 – 4.

CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA

SACHIN DATTA, J. (ORAL)


1. The present petitions have been filed by the petitioners alleging wilful
disobedience/non-compliance with the directions contained in the judgment/
order dated 28.01.2025 passed in W.P.(C) 12189/2021 & connected matters.
The said petitions were disposed of, inter alia , in the following terms:
Signature Not Verified
CONT.CAS(C) 383/2025 and connected matters Page 1 of 4

Digitally Signed By:ROHIT
KUMAR PATEL
Signing Date:18.05.2026
10:32:04

2. It transpires that after the aforesaid judgment/order was passed, an
Office Order dated 03.10.2025 came to be issued by the Department of
Training and Technical Education, GNCTD, which reads as under:

Signature Not Verified
CONT.CAS(C) 383/2025 and connected matters Page 2 of 4

Digitally Signed By:ROHIT
KUMAR PATEL
Signing Date:18.05.2026
10:32:04

3. It can be seen that although Selection Grade has been granted to each
of the petitioners from the date mentioned in the aforesaid judgment/order,
the requisite financial benefits have not been disbursed.
4. During the course of hearing, learned counsel for the respondents
submits that for the purpose of disbursal of the financial benefits, the
petitioners are required to exercise an option to indicate the date on which
they would prefer to avail the increment admissible to them.
5. It is made clear to the respondents that the financial benefits (in terms
of the Rules prevalent at the relevant point of time) to which the petitioners
are entitled shall be computed on the basis that increments to which the
petitioners are entitled in the usual course, are granted at the earliest
opportunity.
6. It is assured and undertaken by Dr. M.K. Gupta, Joint Director
(Legal), who is present in Court, that the requisite financial benefits accruing
to the petitioners shall be computed accordingly and disbursed latest within
a period of 3 weeks from today. The said statement is taken on record.
7. Learned counsel for the petitioners submits that there is another
additional aspect of the matter. He submits that in the usual course,
petitioners are also required to be considered for upgradation to Selection
Grade-II with effect from expiry of 3 months from the date on which
Selection Grade-I was given to the petitioners. Let the said aspect be also
adjudicated and for this purpose a Review DPC be held.
8. If the petitioners are found eligible for the Selection Grade-II, the

additional financial benefits accruing thereby shall also be granted to the
petitioners. Let the said exercise be completed as expeditiously as possible
Signature Not Verified
CONT.CAS(C) 383/2025 and connected matters Page 3 of 4

Digitally Signed By:ROHIT
KUMAR PATEL
Signing Date:18.05.2026
10:32:04

and in any event, within a period of 12 weeks from today.
9. The respondents are expected to comply with the aforesaid directions
within the timeline indicated hereinabove.
10. The present petitions stand disposed of in the above terms.
11. In case the aforesaid timeline is not adhered to, the same shall be
construed as wilful disobedience of the orders passed by this Court on the
part of the respondents, entailing severe actions against the concerned
officials of the respondents, under the Contempt of Courts Act, 1971.
12. In case of non-compliance, the petitioners shall be at liberty to revive
the present petitions.
13. In case the aforesaid timeline is not adhered to, the same shall be

construed as wilful disobedience of the orders passed by this Court on the
part of the respondents, entailing severe actions against the concerned
officials of the respondents, under the Contempt of Courts Act, 1971.

SACHIN DATTA, J
MAY 13, 2026/ at/ss





Signature Not Verified
CONT.CAS(C) 383/2025 and connected matters Page 4 of 4

Digitally Signed By:ROHIT
KUMAR PATEL
Signing Date:18.05.2026
10:32:04