Umed Singh And Ors vs Sri Chand Fleria And Ors
- Court
- Delhi High Court
$~33
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: 29 May, 2026
+ CS(OS) 328/2026, CCP(O) 62/2026 & I.A. 15501/2026
UMED SINGH AND ORS. .....Plaintiffs
Through: Mr. Rajesh Gupta and Mr. Manpreet
Singh, Advs.
M: 9810087071
versus
SRI CHAND FLERIA AND ORS. .....Defendants
Through: Mr. Insaaf Duggal and Mr. Rahul
Gujral, Advs.
M: 9999234874
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
MINI PUSHKARNA, J. (ORAL):
I.A. 15501/2026 (For exemption from filing original and certified copies)
1. The present is an application under Section 151 of the Code of Civil
Procedure, 1908 (“CPC”) on behalf of the plaintiffs, seeking exemption
from filing original and certified copies of documents.
2. Exemption allowed, subject to all just exceptions.
3. The plaintiffs shall file the original and certified copies of the
documents, whenever the same is required.
4. Application stands disposed of.
CCP(O) 62/2026
5. The present petition has been filed on behalf of the defendants against
the plaintiffs/contemnors for wilful and deliberate violation of the order
th
dated 15 April, 2026 passed by this Court, wherein, in paragraph 28, it was
clarified that the construction, if authorized, may continue and be completed,
however, no third-party rights shall be created or possession of the suit land
Signature Not Verified
Page 1 of 5
Digitally Signed
By:HARIOM SHARMA
Signing Date:30.05.2026
19:48:45
shall be parted with.
6. Learned counsel appearing for the defendants submits that despite the
same, the plaintiffs herein filed a complaint with the Sub-Divisional
Magistrate (“SDM”), Mundka against the defendants herein as if the
defendants were carrying out the unauthorized constructions in the suit
property.
7. Issue notice. Notice is accepted by learned counsel appearing for the
rd
plaintiffs, who has handed over to this Court a letter dated 23 April, 2026,
issued by the Assistant Engineer (Building), Narela Zone, Municipal
Corporation of Delhi (“MCD”). The said letter is reproduced as under:
Signature Not Verified
Page 2 of 5
Digitally Signed
By:HARIOM SHARMA
Signing Date:30.05.2026
19:48:45
8. By referring to the aforesaid letter, learned counsel appearing for the
plaintiffs submits that the construction, being carried out by the defendants
was unauthorized, on account of which, the same has been booked by the
MCD.
th
9. This Court notes that vide order dated 15 April, 2026, this Court had
categorically recorded that the construction in the suit property can be
carried out by the defendants herein only if the same is authorized.
th
Paragraph 28 of the order dated 15 April, 2026 is reproduced as under:
“xxx xxx xxx
xxx xxx xxx”
10. Thus, in case, the construction carried out by the defendants is
unauthorized and the same already stands booked, no contempt can be said
to have been carried out by the plaintiffs.
11. This Court notes the submission made by learned counsel appearing
for the defendants that a copy of the letter from the MCD with regard to the
unauthorized construction has never been received by them.
12. Learned counsel appearing for the defendants relies upon the
judgment of the Supreme Court in the case of Israr Ahmad Khan Versus
Amarnath Prasad and Ors., MANU/SC/0203/2026, and in particular relies
upon paragraph 24 of the same, which is reproduced as under:
“xxx xxx xxx
Signature Not Verified
Page 3 of 5
Digitally Signed
By:HARIOM SHARMA
Signing Date:30.05.2026
19:48:45
xxx xxx xxx”
13. This Court takes notes of the aforesaid judgment in the case of Israr
Ahmad Khan (Supra), as relied upon by the defendants, wherein, it is
categorically stated that while dealing with a contempt petition, the Court
has to assess as to whether the decision, of which contempt is alleged, has
been complied with or not.
14. In the present case, it is clear that the construction in the suit property
was allowed to be carried out by the defendants herein only if the same was
authorized. Since, it has come on record before this Court that the
construction being carried out by the defendants was unauthorized, no case
Signature Not Verified
Page 4 of 5
Digitally Signed
By:HARIOM SHARMA
Signing Date:30.05.2026
19:48:45
of contempt can be made out against the plaintiffs. Rather, by carrying out
such an act of authorized construction, the defendants are the ones, who
have not complied with the directions of this Court.
15. Be that as it may, since it has come on record before this Court that
the construction being carried out by the defendants was in the nature of
unauthorized construction, no construction can be carried out by the
defendants in the suit property, and the plaintiffs cannot be considered to be
th
in contempt of the order dated 15 April, 2026, passed by this Court.
16. Noting the aforesaid, the present petition is accordingly, disposed of.
MINI PUSHKARNA, J
MAY 29, 2026/KR