Mansi Brar vs Mohit Singh
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
st
Date of Decision: 01 October, 2026
# CNR No. DLHC010439432022
+ CONT.CAS(C) 1279/2022&CM APPL. 6324/2023
MANSI BRAR .....Petitioner
Through: Mr. Zeeshan Diwan and Mr. Harsha,
Advocates.
versus
MOHIT SINGH .....Respondent
Through: Mr. Saurabh Kirpal, Senior Advocate
with Mr. Rudra Pratap, Mr. Tushar
Randhawa, Mr. Rahul Sharma and Mr.
Ali Ibrahim, Advocates.
Respondent in-person .
CORAM:
HON'BLE MR. JUSTICE AMIT SHARMA
JUDGMENT
AMIT SHARMA, J.
1. The present petition under Sections 10 and 12 of the Contempt of
Courts Act, 1971, read with Article 215 of the Constitution of India, 1950,
seeks the following prayers: -
“A. Initiate proceedings and punish the Respondent/Contemnor
for contempt of Order dated 28.03.2022 passed by this Hon’ble
Court in OMP I COMM 58-62 of 2022; and/or
B. Any other order or direction that this Hon’ble Court feels
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 1 of 21
appropriate in the facts and circumstances of this case AND
FOR THIS ACT OF KINDNESS THE PETITIONER AS IN
DUTY BOUND SHALL EVER BE GARETFUL.”
2 . The present petition alleges wilful disobedience of the directions
contained in the judgment/order dated 28.03.2022 passed by learned
Coordinate Bench of this Court in O.M.P.(I)(COMM) No. 58-62/2022 in the
1
petitions filed under Section 9 of the Arbitration and Conciliation Act, 1996 ,
filed by the petitioner herein. In said petitions, on the statement of the counsel
for the respondents therein, following directions were passed by learned
Coordinate Bench: -
“9. Now that the Arbitral Tribunal has been appointed, Ms. Sehgal
on instructions, states that instant petitions can be treated as
applications under Section 17 of the Act and be decided
expeditiously by the learned Arbitrator. She further, on instructions,
states that till such time the Respondent shall maintain status quo
regarding the title and possession of the properties that are subject
matter of the aforenoted MoUs.
10. In light of the above-mentioned statement made by Ms. Sehgal,
the present petitions are disposed of — with a direction that the
Respondent shall maintain status quo in terms of the statement
by Ms. Sehgal, till such time the instant petitions are decided by
the learned Arbitrator as applications under Section 17 of the
Act .”
(emphasis supplied)
3 . During the course of hearing, before learned Predecessor Bench of this
Court on 23.11.2022, learned counsel for the petitioner had handed over an
order dated 19.05.2022 passed by learned Sole Arbitrator, disposing of the
application under Section 17 of the Arbitration and Conciliation Act 1996,
1
For short, ‘A&C Act’
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 2 of 21
filed by the petitioner, wherein it has been recorded as under: -
“Today, at the outset, Mr. Manav Gupta, Ld. Counsel appearing for
the Respondents, on instructions made a statement that in terms of
the said MOUs the Respondents cannot create any third party rights
in respect of the properties which are subject matter of the said
MOUs, without first obtaining the written consent of the Claimant
and therefore, the statement of the Respondents be taken on record
that the Respondents will not create any third party rights in any of
the properties which are subject matter of the said MOUs without
obtaining written consent of the Claimant and in addition, without
seeking leave of the Tribunal before creating such third party rights
in such properties. Mr. Manav Gupta also submits that his said
statement is without prejudice to the rights and contentions of the
Respondents in all these arbitration matters which have arisen out of
the said six MOUs.
The said statement made by Mr. Manav Gupta on behalf of the
Respondents is taken and accepted on record. In view of the said
statement made by Mr. Manav Gupta which shall remain binding on
the Respondents, the present applications filed by the Claimant
under section 17 of the Arbitration and Conciliation Act, in all these
arbitration matters are disposed of. It is made clear that the said
statement made by the Ld. Counsel for the Respondents shall be
without prejudice to the rights and contentions of the Respondents.”
4 . Learned counsel for the petitioner submitted that in contravention of
the aforesaid statements, third party rights have been created in respect of
certain properties which are subject matter of the MOUs entered into between
the parties. The details of sales made in contravention of the statement
recorded in the aforesaid order, have been given in the petition as under: -
S.No. MOU Date & DIAC No. Reserved Properties Sold to
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 3 of 21
1. 02.11.2017
DIAC/3 878/02-22
OMP (I) Comm No. 58/2022
KET-701
SEM-1512
HAR-003
Sunil Joshi
Sanjay Vineet Anjoo
Hemant Gupta
2. 27.07.2018
DIAC/3 879/02-22
OMP (I) Comm No. 59/2022
SEM-1503
HAR-006
Not Known
Narendra
3. 05.12.2018
DIAC/3 880/02-22
OMP (I) Comm No. 60/2022
OAK-1403 Sanjay Kumar
4. 12.06.2018
DIAC/3881/02-22
OMP (I) Comm No. 61/2022
GUL-003
AML-003
Not Known
Shahzaad
5. 08.09.2016
DIAC/3 882/02-22
OMP (I) Comm No. 62/2022
HAR-001
HAR-002
Kuldeep Kambhoj
Vikas Tiwari
5 . It is further submitted that the respondent herein-Mohit Singh is stated
to be the Managing Director/Promoter of the companies which are the
respondents in the ongoing arbitration proceedings and also a party to the
MOUs executed between the parties. It is further submitted that the
respondent herein had also executed a personal guarantee agreement(s)
whereby, he had personally guaranteed for the performance of M/s Shipra
Estate Limited & Jai Krishan Estates Developers Private Limited with regard
to the agreements/MoUs executed between the aforesaid companies and the
petitioner-Mansi Brar, and in the event such companies fails to make any
payment to the petitioner or fails to perform in any manner, the respondent-
guarantor had promised to make all payments to her.
6 . Subsequently, on 07.08.2025, the respondent was directed by this Court
to file an additional affidavit with respect to the status of the aforesaid
properties. In pursuance of said direction, affidavit dated 02.09.2025 was
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 4 of 21
placed on record by the respondent stating that, the properties forming part of
the MOUs, as mentioned hereinbefore, already stood sold prior to the passing
of directions vide order dated 28.03.2022 passed in O.M.P.(I)(COMM) No.
58-62/2022 . This Court vide order dated 03.09.2025 noted that in an affidavit
dated 01.04.2024 filed on behalf of the respondent in the present contempt
petition following averments have been made: -
“ PRELIMINARY OBJECTIONS
……..
2. The Petitioner herein by an ingenious presentation of facts has created
an illusion of a cause of action entitling the Petitioner to initiate Contempt
proceedings qua the Respondent. That the Respondent humbly submits
that the Petitioner has acted with mala fide by not disclosing the fact that a
settlement agreement dated 22nd February, 2023 was executed between
the parties for a total amount of Rs. 6,05,00,000/- qua the Memorandum of
Understanding executed between the parties. (Annexure P -7 to Annexure
P - 11 to the Petition). The true copy of the Settlement Agreement Dated
22nd February, 2023 between the parties is herein marked and annexed as
ANNEXURER-1.
3. Without prejudice to the foregoing preliminary objection, the
Respondent at the preliminary would like to state that the Respondent has
utmost regard to the Rule of Law and for the Majesty of this Hon 'ble
Court. It is the case of the Respondent that the Petitioner has instituted and
pursuing the present Contempt petition merely as a substitute to the
execution proceedings without exhausting the remedy for the execution of
the Arbitration Award, dated 29.12.2023, which has been challenged by
the Respondent in terms of procedure established by law. It is humbly
submitted that there is no wilful breach of the order, dated 04.03.2020,
inasmuch as the original terms and conditions have been novated and
altered in terms of the settlement agreement, dated 22.02.2023, pursuant to
which the Petitioner has already received substantial consideration of Rs.
3,00,00,000/- (Rupees three crores).”
7. It is pertinent to note here that, the aforesaid stand was not taken by the
respondent until vide order dated 07.08.2025, he was directed by this Court to
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 5 of 21
make a specific statement with regard to the status of the properties as
mentioned in MoUs executed between the parties. Learned counsel for the
petitioner has relied upon a judgment passed by Hon’ble Supreme Court in In
2
Re, Perry Kansagra , to contend that a person who makes a false statement
before the Court and makes an attempt to deceive the Court, interferes with
the administration of justice and is guilty of contempt of Court.
8. Per contra , learned Senior Counsel for the respondent has submitted
that the present petition is not maintainable in as much as there is no wilful
disobedience of the directions contained in the order dated 28.03.2022. It is
further submitted that after passing of the order dated 28.03.2022, the terms
and conditions of the said order were novated and altered by way of a
settlement agreement 22.02.2023 executed between the parties, and in
pursuance of said agreement, the petitioner has already received a substantial
consideration of Rs.3 Crores. It is further submitted that the amount in terms
of the settlement agreement 22.02.2023 could not be paid to the petitioner
owing to the reasons beyond the control of the respondent, and subsequently
arbitration proceedings between the parties were revived and same were
culminated by way of final Order/Award dated 29.12.2023 passed by learned
sole arbitrator whereby a sum of Rs. 6,05,00,000/- along with 12 per cent
interest was awarded in favour of the petitioner. It is the case of the
respondent that the present proceedings have been instituted as a substitute to
the execution proceedings without taking recourse to remedy for execution of
the Arbitral Award dated 29.12.2023. It is further submitted that an appeal
under Section 34 of the Arbitration and Conciliation Act, 1996, has also been
2
(2023) 16 Supreme Court Cases 631
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 6 of 21
filed by the respondent against the said award.
9. It is further the case of the respondent that the present petition is not
sustainable as the order dated 28.03.2022 was effective till such time, the said
petitions (OMPs) were treated as applications under Section 17 of the A&C
Act. As per respondent, the cause of action for filing the present petition was
vitiated when the petitioner, after passing of the order dated 28.03.2022, had
entered into a settlement agreement dated 22.02.2023. It is further submitted
that after the revival of the arbitration proceedings, the order dated
28.03.2022, which was in the nature of in a limited interim measure/order,
had merged with the final Award passed on 29.12.2023, and thus no question
of wilful disobedience has arisen. In view of these facts, it is prayed that the
present contempt proceedings be dismissed.
10. During the pendency of the present petition, this Court was apprised by
learned Senior Counsel for the respondent that the alleged
undertaking/statement as recorded in order dated 28.03.2022 was made on
behalf of ‘Shipra Estate Limited and Jai Krishna Estate Limited’ and the
respondent was not personally present in the Court on the said date of hearing.
It is further submitted that the said partnership firm-Shipra Estate Limited had
now been admitted to insolvency vide order dated 24.01.2024 passed by
learned adjudicating authority/NCLT and the same is under moratorium. It is
further submitted that the respondent was not directly dealing or involved
with the sales of flats of the firm-M/s Shipra Estate Limited & Jai Krishna
Estate Developers Limited, and same were led by one Ms. Shalini, who was
sales executive and was taking care of the affairs of the said firm and had
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 7 of 21
maintained the records of the flats. Learned Senior Counsel for the respondent
has further submitted that the latter has been undergoing personal insolvency
proceedings. Further, one of the partners of the said partnership firms has also
been admitted to insolvency proceedings.
11. Thereafter, on 19.12.2025, learned Senior Counsel appearing on behalf
of the respondent had submitted before this Court that the latter has given an
undertaking by way of an affidavit wherein, he had undertaken to pay a sum
of Rs. 1 Crore on 28.02.2026, and remaining sum of Rs.2 Crore 20 Lakhs on
or before 31.03.2026. Learned counsel for the petitioner had, however,
disputed the owed amount as mentioned in said affidavit of undertaking dated
18.12.2025. This Court to enable the respondent to abide by the said
undertaking had listed the matter for 02.03.2026 for payment of Rs. 1 Crore.
Thereafter on 30.03.2026, learned Senior Counsel for the respondent, on
instructions of the latter, who was present in Court that day, had submitted
that demand draft of Rs. 1 Crore shall be handed over to the petitioner during
the course of that day and 4 weeks’ time was sought to make the remaining
payment of Rs.2 Crore 20 Lakhs which was to be paid on or before
31.03.2026. In that view of the matter, this Court had listed the matter on
04.05.2026 for compliance. On 18.05.2026, learned Senior Counsel had
further submitted that the remaining amount which was to be paid by
31.03.2026 shall be positively paid before the next date of hearing. On such a
request, this Court had granted last and final opportunity to do the needful and
the matter was listed for 15.07.2026. On the said date, there was call for strike
in view of resolution by DHCBA for abstention from work. Subsequently on
28.07.2026, the matter could not be taken up for hearing due to paucity of
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 8 of 21
time, and the matter was listed for 21.08.2026. On the said date , i.e.,
21.08.2026, arguments on behalf of the parties had concluded, and the present
petition was kept for orders for today.
12. Heard learned counsel for the petitioner as well as learned Senior
Counsel for the respondent and perused the records.
13. At the very outset, the direction, for which non-compliance/wilful
disobedience has been alleged, as contained in order dated 28.03.2022 passed
by learned Co-ordinate Bench of this Court in OMP (I) (COMM) 58/2022
and other connected matters reads as under: -
"9. Now that the Arbitral Tribunal has been appointed, Ms. Sehgal
on instructions, states that instant petitions can be treated as
applications under Section 17 of the Act and be decided
expeditiously by the learned Arbitrator. She further, on instructions,
states that till such time the Respondent shall maintain status quo
regarding the title and possession of the properties that are subject
matter of the aforenoted MoUs.
10. In light of the above-mentioned statement made by Ms. Sehgal,
the present petitions are disposed of — with a direction that the
Respondent shall maintain status quo in terms of the statement by
Ms. Sehgal, till such time the instant petitions are decided by the
learned Arbitrator as applications under Section 17 of the Act.”
14. The case of the petitioner is that, in contravention of the aforesaid
statements, third party rights have been created in respect of certain properties
which were subject matter of the MOUs entered into between the parties. On
the other hand, the case of the respondent as per initial reply/affidavit dated
01.04.2024 filed in the present petition was that after passing of the order
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 9 of 21
dated 28.03.2022, the terms and conditions of the said order were novated and
altered by way of a settlement agreement 22.02.2023 executed between the
parties, and in pursuance of said agreement, the petitioner has already
received a substantial consideration of Rs.3 Crores. It is further submitted that
the amount in terms of the settlement agreement 22.02.2023 could not be paid
to the petitioner owing to the reasons beyond the control of the respondent,
and subsequently, arbitration proceedings between the parties were revived
and same were culminated by way of final Order/Award dated 29.12.2023
passed by learned sole arbitrator whereby a sum of Rs.6,05,00,000/- along
with 12 per cent interest was awarded in favour of the petitioner.
15. However, in pursuance of the direction given by this Court on
07.08.2025, an affidavit dated 02.09.2025 was placed on record by the
respondent stating as follows: -
“2. I say that that Shipra Estate Limited was one of the two partners
of the firm "Shipra Estate Limited & Jai Krishna Estate
Developers Limited" , which had undertaken the project i.e. “Shipra
Krishna Shristi”.
3. I say that the Flats which are subject matter of the present case
were sold to following customers on following dates, as reflected in
the available records i.e., the records obtained from the Ghaziabad
Development Authority -
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 10 of 21
4. I say that during the relevant period, Ms. Shalini Khanna was
working as the sales executive and was taking care of the affairs of
the firm and had maintained the records of the aforesaid Flats in the
office at Plot No. 9, Shipra Mall, Vaibhav Khand, Indirapuram,
Ghaziabad, Uttar Pradesh - 201104.
5. I say that at the time when the undertaking or statement was
made on behalf of Shipra Estate Limited and Jai Krishna Estate
Limited, I was not personally present in the court.
6. I say that Shipra Estate Limited was admitted to insolvency vide
order dated 24.01.2024 passed by the Ld. Adjudicating Authority,
NCLT, New Delhi.
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 11 of 21
7. I say that an Appeal was preferred against the said order before
the Hon'ble NCLAT, bearing no. Company Appeal (AT) (INS) 377
of 2024, and vide order dated 21.02.2024, further proceedings of
CIRP was stayed and subsequently vide order dated 30.07.2025, the
Appeal was dismissed and the Resolution Professional is in the
process of taking over of Shipra Estate Limited.
8. That the above information tendered is true to the best of my
knowledge and belief and is made bona-fide.”
16. Perusal of the aforesaid averments, particularly regarding the status of
the properties forming part of the MoUs shows that, the said properties/flats
were sold even prior to the passing of the order dated 28.03.2022 wherein on
the undertaking given by the respondent a direction to maintain status quo
regarding the title and possession of the properties that are subject matter of
the aforenoted MoUs was given.
17. Thereafter, an additional affidavit dated 13.10.2025 was placed on
record by the respondent, wherein it was stated as under: -
“1. I say that I am the erstwhile Managing Director of the Shipra
Estate Limited which is one of the two companies that constitutes
the partnership firm, M/s Shipra Estate Limited & Jai Krishna
Estate Developers Limited. I further say that Shipra Estate Limited
i.e., one of the partners of the Partnership Firm, was admitted to
Insolvency Proceedings vide order dated 24.01.2024 passed by Ld.
Adjudicating Authority in Company Petition (IB) No. 513 of 2022
and is under moratorium.
2. I say that at the time when the undertaking was given before
this Hon'ble Court on 28.03.2022, I was not directly dealing or
involved with the sales of flats of the firm, M/s Shipra Estate
Limited & Jai Krishna Estate Developers Limited, which is a
partnership firm and it was handled by the team of the firm
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 12 of 21
which was led by Ms. Shalini.
3. I say that the Group Companies of the Shipra consortium
including, Shipra Estate Limited are embroiled in multiple
litigations since 2001 before various forums including Arbitration,
SARFESI and IBC proceedings. I further state that Corporate
Office containing all records of the firm, M/s Shipra Estate
Limited & Jai Krishna Estate Developers Limited was situated
at Plot No. 9, Shipra Mall, Indirapuram, Ghaziabad. The said
Shipra Mall was illegally sold under SARFESI proceeding and
subsequent thereto the Corporate Office of the firm, M/s
Shipra Estate Limited & Jai Krishna Estate Developers
Limited has been sealed since, March 2023 and the proceedings
are pending before the Hon'ble DRT Lucknow.
4. I say that earlier details of the Subject Flats could not be
furnished before this Hon'ble Court as the Corporate Office of
the firm, M/s Shipra Estate Limited & Jai Krishna Estate
Developers Limited has been scaled under SARFESI
proceedings and all the records pertaining to the details of the
subject flats are also lying in the said premises.
5. I say that pursuant to the order dated 07.08.2025, passed by this
Hon'ble Court, application seeking certified copies of the deeds was
filed before the Ghaziabad Development Authority (GDA) seeking
details of the Subject Flats which was provided on 01.09.2025.
6. I say that once the aforesaid details of the Subject Flats were
received, I had filed the affidavit dated 02.09.2025, before this
Hon'ble Court.
7. I say that due to communication gap and without my
personal knowledge the aforesaid subject Flats were sold by the
Sales Team and I was not directly involved in the sales of the
subject Flats, and therefore, I relied upon the information
provided. to me by concerned responsible persons.
8. I further state that one Sh. Sachin Tomar was in charge of
keeping the records related to cases of M/s Shipra Estate Limited &
Jai Krishna Estate Developers. Sachin Tomar who was responsible
for providing all information with regard to the concerned assets
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 13 of 21
had informed me that all the properties were still under the title and
possession of M/s Shipra Estate Limited & Jai Krishna Estate
Developers Limited and that there was no market sale of the
Subject Flats to any third party. The said information was later also
affirmatively shared by Sachin Tomar on 16th May, 2022. (A True
Copy of the WhatsApp chat between me and Mr. Sachin Tomar is
annexed herewith and marked as Annexure R-1)
9. I say that I have utmost regard for this Hon'ble Court and the
legal system. The aforesaid undertaking was given due to an
inadvertent error on part of the Sales Team of the firm, M/s Shipra
Estate Limited & Jai Krishna Estate Developers Limited. I hereby
tender unconditional apology for the said mistake on my part with a
deep sense and feeling of remorse.”
(emphasis supplied)
18. The aforesaid stand of the respondent that he was not directly dealing
or involved with the sales of the flats of the partnership firm is contrary to the
records inasmuch as the subject MoUs were executed between the parties
from the period starting from 2016 to 2018. It is pertinent to note that the
respondent was well aware of the directions passed by learned Coordinate
Bench of this Court vide order dated 28.03.2022, and despite the same, the
exact status of the properties forming part of MoUs was not brought to the
knowledge of the learned Arbitrator in the arbitral proceedings. Perusal of the
record further shows that the respondent, besides the subject MoUs, had also
executed personal guarantee agreement for the performance of the said
MoUs/agreements executed between the partnership firms and the petitioner.
In the said MoUs, it is clearly mentioned that the partnership firm-M/s Shirpa
Estate Limited & Jai Krishan Estates Developers Private Limited has
executed said MoU with the petitioner through its authorised signatory Mohit
Singh- respondent herein. The affidavit dated 02.09.2025 clearly shows that
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 14 of 21
the units/flats forming part of the MoUs executed between the petitioner and
the partnership firm were sold even prior to the passing of order dated
28.03.2022. This clearly shows that the statement made by learned counsel for
the respondent, on instructions of the latter, as recorded in order dated
28.03.2022 passed in aforesaid OMPs, that respondent shall maintain status
quo regarding the title and possession of the properties which were subject
matter of the aforesaid MoUs, was incorrect inasmuch as the flats/units which
formed part of MoUs executed with the petitioner were already sold even
prior to giving of such undertaking before learned Coordinate Bench of this
Court.
19. During the pendency of the present petition, after being confronted with
the aforesaid fact, the respondent has placed on record 2nd additional affidavit
dated 16.10.2025, showing his inability to sell the unit/flat which was
assigned to the petitioner, due to the ongoing CIRP proceedings against one
of the partners of the aforesaid firms. In the said affidavit, it was stated as
under: -
“1. I say that M/s Shipra Estate Limited & Jai Krishna Estate
Developers Limited, the partnership firm was constituted on 03rd
December, 2004, wherein one of the partners i.e., Shipra Estate
Limited is the operating partner of the firm.
2. I say that one Flat in the project Shipra Krishna Shrishti, i.e., Flat
bearing no. SEM-1503, assigned to Ms. Mansi Brar under MOU
dated 27.07.2018, before the Corporate Insolvency Proceedings
were initiated qua Shipra Estate Limited, vide order dated
24.01.2024 passed by the Ld. Adjudicating Authority in Company
Petition (IB) No. 513 of 2022.
3. I further say that due to the ongoing Corporate Insolvency
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 15 of 21
Resolution proceedings against one of the partners, the firm i.e..
M/s Shipra Estate Limited & Jai Krishna Estate Developers Limited
was not able to sell the aforesaid Flat.
4. I say that the said Flat can be sold for an amount of Rs.
2,00,00,000/- Approx (Rupees Two Crores) and the amount could
be furnished to the Petitioner herein if permitted by this Hon'ble
Court. I further say that the 'Shipra Group' is also trying to conclude
an investment business transaction which would enable the Firm to
repay the Petitioner and the inability to repay the Petitioner herein
is not intentional.”
20. Thereafter, by way of affidavit dated 18.12.2025, following
undertaking was given to this Court: -
“1. That I am the erstwhile Managing Director of M/s Shipra Estate
Limited which is one of the two companies that constitutes the
partnership firm, M/s Shipra Estate Limited & Jai Krishan Estate
Developers Limited.
2. I further state that M/s Shipra Estate Limited i.e., one of the
partners of the Partnership Firm, was admitted into Insolvency
Proceedings vide order dated 24.01.2024 passed by the Ld.
Adjudicating Authority, National Company Law Tribunal
("NCLT") in Company Petition (IB) No. 513 of 2022 and is under
moratorium. (A True Copy of the order dated 24.01.2024 passed
by the Ld. Adjudicating Authority, National Company Law
Tribunal in Company Petition (IB) No. 513 of 2022 is annexed
herewith and marked as ANNEXURE R–1).
3. It is submitted that I, am also undergoing personal insolvency
proceedings, vide order dated 04.09.2024, passed by the NCLT in
Company Petition (IB) No. 58 of 2021. (A True Copy of the order
dated 04.09.2024 passed by the NCLT is annexed herewith and
marked as ANNEXURE R-2).
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 16 of 21
4. It is further submitted that I am willing to amicably settle all the
disputes with Petitioner herein but owing to the aforesaid personal
insolvency proceedings and the subsequent moratorium, there is a
certain delay in settling the disputes with the Petitioner herein.
5. That, with the permission of this Hon'ble Court, I undertake to
pay a sum of Rs. 1,00,00,000/- (Rupees One Crore Only) on or
before 28th February, 2026 and the remaining Rs. 2,20,00,000/-
(Rupees Two Crores Twenty Lakhs) on or before 31st March,
2026 to the Petitioner or as may be directed by this Hon'ble Court.
6. I further state that I have utmost regard for this Hon'ble Court and is
ready to abide by any further orders which this Hon'ble Court may
pass in the interest of justice.”
(emphasis supplied)
21. In pursuance of the aforesaid undertaking given to this Court, the
respondent has paid a sum of Rs.1,00,00,000/- to the petitioner by way of
Demand Draft on 30.03.2026. Thereafter, 4 weeks’ time was sought to make
the remaining payment of Rs.2,20,00,000/- on or before 31.03.2026.
However, no such payment was made by the respondent, despite the fact that
the matter was listed on several occasions on 04.05.2026, 18.05.2026,
15.07.2026, 28.07.2026 as well as on 21.08.2026. This Court has given
several opportunities to the respondent to abide by the undertaking given by
way of an affidavit dated 18.12.2025 to this Court and to make payment;
however, even after 31.03.2026, despite several hearings, the same has not
been honoured by him. Even on 21.08.2026, before this Court, the
respondent, who was present in person before this Court had made a
statement that he will abide by his undertaking, but the conduct of the
respondent shows that despite opportunities the same has not been complied
with.
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 17 of 21
22. Regarding the stand of personal insolvency proceedings going on
against the respondent, it is pertinent to note that in the affidavit of
undertaking dated 18.12.2025 given before this Court, the respondent had
himself undertaken to pay Rs.3,20,00,000/- to the petitioner in the manner
stated in the said affidavit. Further, there is also an averment to the effect, in
the said affidavit, that the respondent is going under personal insolvency
proceedings before the NCLT. Despite the same, the respondent being well
aware of the insolvency proceedings pending against him, had given
undertaking before this Court for paying the amount, which has not been done
by him till date.
23. The Hon’ble Supreme Court in In Re, Perry Kansagra ( supra ) has
observed and held as under: -
“ 15. The second set of decisions relied upon by Ms Mathur are on the
point whether tendering of affidavits and undertakings containing false
statement would amount to criminal contempt or not. At this stage, we
may extract the following paragraphs from the decision of this Court in
ABCD v. Union of India [ ABCD v. Union of India , (2020) 2 SCC 52 :
(2020) 1 SCC (Cri) 526] which had considered some of the previous
decisions of this Court on the point : (SCC pp. 61-63, paras 15-18)
“ 15 . Making a false statement on oath is an offence punishable
under Section 181IPC while furnishing false information with
intent to cause public servant to use his lawful power to the injury
of another person is punishable under Section 182IPC. These
offences by virtue of Section 195(1)( a )( i ) of the Code can be taken
cognizance of by any court only upon a proper complaint in writing
as stated in said section. In respect of matters coming under Section
195(1)( b )( i ) of the Code, in Pushpa Devi M. Jatia v. M.L.
Wadhawan [ Pushpa Devi M. Jatia v. M.L. Wadhawan , (1987) 3
SCC 367 : 1987 SCC (Cri) 526] prosecution was directed to be
launched after prima facie satisfaction was recorded by this Court.
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 18 of 21
16 . It has also been laid down by this Court in Chandra Shashi v.
Anil Kumar Verma [ Chandra Shashi v. Anil Kumar Verma , (1995)
1 SCC 421 : 1995 SCC (Cri) 239] that a person who makes an
attempt to deceive the court, interferes with the administration of
justice and can be held guilty of contempt of court. In that case a
husband who had filed a fabricated document to oppose the prayer
of his wife seeking transfer of matrimonial proceedings was found
guilty of contempt of court and sentenced to two weeks'
imprisonment. It was observed as under : (SCC pp. 423-24 & 427,
paras 1-2 & 14)
‘ 1 . The stream of administration of justice has to remain
unpolluted so that purity of court's atmosphere may give vitality
to all the organs of the State. Polluters of judicial firmament are,
therefore, required to be well taken care of to maintain the
sublimity of court's environment; so also to enable it to
administer justice fairly and to the satisfaction of all concerned.
2 . Anyone who takes recourse to fraud, deflects the course of
judicial proceedings; or if anything is done with oblique motive,
the same interferes with the administration of justice. Such
persons are required to be properly dealt with, not only to punish
them for the wrong done, but also to deter others from indulging
in similar acts which shake the faith of people in the system of
administration of justice.
*
14 . The legal position thus is that if the publication be with intent
to deceive the court or one made with an intention to defraud, the
same would be contempt, as it would interfere with
administration of justice. It would, in any case, tend to interfere
with the same. This would definitely be so if a fabricated
document is filed with the aforesaid mens rea. In the case at hand
the fabricated document was apparently to deceive the court; the
intention to defraud is writ large. Anil Kumar is, therefore, guilty
of contempt.’
17 . In K.D. Sharma v. SAIL [ K.D. Sharma v. SAIL , (2008) 12 SCC
481] it was observed : (SCC p. 493, para 39)
‘39. If the primary object as highlighted in Kensington Income
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 19 of 21
Tax Commissioners [R. v. General Commissioners for Purposes
of Income Tax Acts for District of Kensington, ex p Princess
Edmond De Polignac, (1917) 1 KB 486 : 86 LJKB 257 : 116 LT
136 (CA)] is kept in mind, an applicant who does not come with
candid facts and “clean breast” cannot hold a writ of the court
with “soiled hands”. Suppression or concealment of material
facts is not an advocacy. It is a jugglery, manipulation,
manoeuvring or misrepresentation, which has no place in
equitable and prerogative jurisdiction. If the applicant does not
disclose all the material facts fairly and truly but states them in a
distorted manner and misleads the court, the court has inherent
power in order to protect itself and to prevent an abuse of its
process to discharge the rule nisi and refuse to proceed further
with the examination of the case on merits. If the court does not
reject the petition on that ground, the court would be failing in its
duty. In fact, such an applicant requires to be dealt with for
contempt of court for abusing the process of the court.’
18. In Dhananjay Sharma v. State of Haryana [ Dhananjay Sharma
v. State of Haryana , (1995) 3 SCC 757 : 1995 SCC (Cri) 608] filing
of a false affidavit was the basis for initiation of action in contempt
jurisdiction and the persons concerned were punished.”
Thereafter, in suo motu exercise of power, proceedings in contempt
jurisdiction were initiated against the said petitioner.
16. It is thus well settled that a person who makes a false statement
before the court and makes an attempt to deceive the court,
interferes with the administration of justice and is guilty of contempt
of court. The extracted portion above clearly shows that in such
circumstances, the court not only has the inherent power but it
would be failing in its duty if the alleged contemnor is not dealt with
in contempt jurisdiction for abusing the process of the court .”
(emphasis supplied)
24. In the present case, during the course of proceedings, it has come on
record that, at the time of passing of order dated 28.03.2022 in
O.M.P.(I)(COMM) Nos. 58-62/2022, by way of which, it was directed that
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05
CONT.CAS(C) 1279/2022 Page 20 of 21
status quo will be maintained, the subject properties already stood sold. In the
reply to the present petition, the respondent did not disclose this fact, and had
taken different grounds in his defence. In the considered opinion of this
Court, the respondent had made an incorrect statement with respect to
maintenance of status quo . It was only on the direction of this Court to the
respondent to make a specific statement with regard to the status of the
properties, the exact status of the properties was disclosed by him by affidavit
dated 02.09.2025, and it emerged that the aforesaid order dated 28.03.2022
was passed based on such non-disclosure/material suppression.
25. Even otherwise, the undertaking given to this Court by the respondent
by affidavit dated 18.12.2025 to pay Rs.3,20,00,000/- on or before
31.03.2026 for settling his outstanding disputes with the petitioner has not
been complied with, despite several opportunities. Thus, the respondent has
also wilfully breached the said undertaking as well.
26. In view of the aforesaid facts and circumstances, the respondent is held
guilty of ‘civil contempt’ under Section 2 (b) of the Contempt of Courts Act,
1971.
27. Judgment be uploaded on the website of this Court, forthwith.
AMIT SHARMA
(JUDGE)
OCTOBER 01, 2026/ nk/kr/ns
Signature Not Verified
Signed By:BHASKAR
SINGH RAWAT
Signing Date:01.10.2026
19.05