National Highways Authority Of India vs Oriental Structural Engineers Pvt. Ltd

Court
Delhi High Court

$~62
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 14.05.2026

+ O.M.P. (COMM) 51/2016, I.A. 11301/2021 (For placing on
record the renewed bank guarantee), I.A. 14222/2022 (For
placing on record the renewed bank guarantee), I.A.
18890/2023 (For placing on record the renewed bank guarantee)
& I.A. 36267/2024 (For placing on record the renewed bank
guarantee)

NATIONAL HIGHWAYS AUTHORITY OF INDIA
.....Petitioner
Through: Mr. Nikhil Mehta and Mr.
Harsh Vikram Trivedi,
Advocates

versus

ORIENTAL STRUCTURAL ENGINEERS PVT. LTD
.....Respondent
Through:

CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR

JUDGMENT (ORAL)

1. The present Petition has been instituted under Section 34 of the
1
Arbitration and Conciliation Act, 1996 by National Highways
2
Authority of India , seeking setting aside of the Arbitral Award
3
dated 18.11.2015 rendered by the learned Arbitral Tribunal in
4
disputes arising out of the Contract Agreement dated 29.09.2005
executed between the parties for the work pertaining to construction of

1
A&C Act
2
NHAI
3
Impugned Award
4
Agreement
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 1 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

the Jhansi Bypass Project on National Highway-25 in the State of
Uttar Pradesh, Package EW-II (UP-3).
2. The disputes adjudicated by the learned Arbitral Tribunal, at the
instance of the Respondent herein, principally arose in relation to three
claims, namely :
(i) Claim No. 1 - concerning payment of additional costs incurred
on account of wrongful recovery and subsequent non-payment
towards Construction Workers Welfare Cess, claimed as
additional expenditure arising due to subsequent legislation
5
under Conditions of Particular Application ;
(ii) Claim No. 2 - pertaining to compensation sought on account of
the prolongation of the contract period and delays allegedly
occasioned during execution of the project; and
(iii) Claim No. 3 - relating to non-payment for Tack Coat provided
pursuant to BOQ Item No. 4.02 above the DBM first layer.
3. The said claims ultimately culminated in the Impugned Award,
whereby the learned Arbitral Tribunal allowed the aforesaid claims in
favour of the Respondent.
4. Aggrieved by the findings and conclusions returned in the
Impugned Award insofar as the aforesaid claims are concerned, the
Petitioner, NHAI, has instituted the present petition before this Court
under Section 34 of the A&C Act.
5. At the outset, it is pertinent to note that the parties are ad idem
insofar as Claim Nos. 1 and 3 are concerned. Learned counsel
appearing on behalf of the parties, and particularly learned counsel for
the Petitioner, fairly submitted that the controversies arising under the

5
COPA
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 2 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

said claims are no longer res integra and stand authoritatively settled
by judicial precedents.
6. Insofar as Claim No. 1 is concerned, the same stands squarely
covered by the judgment of the Hon’ble Supreme Court in Prakash
6
Atlanta (JV) v. National Highways Authority of India . Likewise,
Claim No. 3 is stated to be governed by the judgment rendered by this
Court in National Highways Authority of India v. Ssangyong
Engineering & Construction Co. Ltd. - Oriental Structural
7
Engineers Ltd. (JV) .
7. Considering the aforesaid undisputed position, and in view of
the fact that the said issues were not pressed before this Court during
the course of arguments, this Court does not deem it necessary to
undertake any further examination of Claim Nos. 1 and 3 or the
findings returned thereon in the Impugned Award.
8. In view of the foregoing, the challenge in the present petition
substantially survives only in relation to Claim No. 2, pertaining to
compensation awarded on account of prolongation of the contract
period and delays in execution of the project, which accordingly forms
the subject matter of adjudication before this Court.

SUBMISSIONS ON BEHALF OF THE PARTIES:
9. Learned Counsel for the Petitioner submits that the Impugned
Award, insofar as it grants compensation in favour of the Respondent,
towards delay and prolongation costs, is patently illegal and contrary
to the terms of the Agreement.

6
2026 SCC OnLine SC 98
7
2012:DHC:8203
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 3 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

10. It is contended that the learned Arbitral Tribunal failed to
appreciate that the Respondent itself was responsible for the slow
progress of works. Learned counsel for the Petitioner further submits
that the contemporaneous correspondence exchanged between the
parties, including the communications issued by the Engineer, clearly
demonstrates that the delay was not only attributable solely to the
Petitioner.
11. Learned Counsel appearing on behalf of the Petitioner has
vehemently assailed the observations recorded by the learned Arbitral
Tribunal while adjudicating Claim No. 2 in the Impugned Award,
particularly the finding to the following effect:
“2.3.15 …………….
*
Notes of the AT:
*
4. All delays have been attributed to the Respondent and all interim
as well as final EOT have been recommended without LD..”

12. It has been contended that the aforesaid observation forms the
foundational basis for the learned Arbitral Tribunal’s determination on
Claim No. 2 and materially influences the findings returned with
respect to attribution of delay and the consequent entitlement arising
therefrom. Learned counsel for the Petitioner submits that the said
conclusion is erroneous, contrary to the material available on record,
inasmuch as the learned Arbitral Tribunal has allegedly failed to
properly appreciate the contemporaneous correspondence exchanged
between the parties, as well as the factual matrix governing the grant
of extensions of time.
13. It is submitted by the learned Counsel for the Petitioner that the
aforesaid finding is contrary to the contemporaneous record and
overlooks the material communications issued by the Engineer,
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 4 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

wherein only certain specific grounds were considered while
recommending interim extensions of time. It is contended that the
learned Arbitral Tribunal erroneously proceeded on the premise that
the entirety of the delay was attributable to the Petitioner despite the
existence of contractor-attributable delays reflected in the record.
14. Per contra , Mr. Anil K. Airi, learned Senior Counsel appearing
on behalf of the Respondent, has drawn the attention of this Court to
paragraphs 2.3.17 and 2.3.20 of the Impugned Award pertaining to
Claim No. 2, to contend that the Engineer had, from time to time,
8
recommended grant of interim as well as final Extension of Time up
to the actual date of completion of the project, i.e., 31.08.2010,
without levy of Liquidated Damages.
15. It is submitted that, notwithstanding such categorical
recommendations made by the Engineer, the Petitioner failed to take
any final decision with respect to the grant of EOT for an inordinate
and considerable period of time.
16. Learned Senior Counsel further submits that the learned
Arbitral Tribunal, upon due appreciation of the contractual
framework, contemporaneous records, and the material placed on
record, rightly concluded that the prolonged and continued inaction on
the part of the Petitioner in taking a final decision on the
recommendations for grant of EOT clearly established that the delays
in execution of the project were not attributable to the Respondent
herein. It is contended that, in view of such findings, the Respondent
could neither have been held liable for the delays nor disentitled from
claiming the consequential reliefs arising therefrom.

8
EOT
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 5 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

17. It is further submitted by the learned Senior Counsel that the
findings rendered by the learned Arbitral Tribunal are pure findings of
fact based on appreciation of evidence and contractual interpretation
and, therefore, do not warrant interference within the limited scope of
jurisdiction exercisable under Section 34 of the A&C Act.

ANALYSIS:
18. This Court has heard the learned counsel appearing for the
parties at length and, with their able assistance, has carefully perused
the Award and the other material placed on record.
19. At the outset, it is apposite to note that this Court is conscious
of the limited scope of its jurisdiction while examining an objection
petition under Section 34 of the A&C Act. The contours of judicial
intervention in such proceedings have been authoritatively delineated
and settled by a consistent and evolving line of precedents of the
Hon’ble Supreme Court.
20. In this regard, a three-Judge Bench of the Hon’ble Supreme
Court, after an exhaustive consideration of a catena of earlier
decisions, in OPG Power Generation (P) Ltd. v. Enexio Power
9
Cooling Solutions (India) (P) Ltd. , while dealing with the grounds of
conflict with the public policy of India and perversity, grounds which
have also been urged in the present case, made certain pertinent
observations, which are reproduced hereunder:
“ Relevant legal principles governing a challenge to an arbitral
award
30. Before we delve into the issue/sub-issues culled out above, it
would be useful to have a look at the relevant legal principles
governing a challenge to an arbitral award. Recourse to a court
against an arbitral award may be made through an application for
setting aside such award in accordance with sub-sections (2), (2-A)

9
(2025) 2 SCC 417
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 6 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section 34
has two clauses, ( a ) and ( b ). Clause ( a ) has five sub-clauses which
are not relevant to the issues raised before us. Insofar as clause ( b )
is concerned, it has two sub-clauses, namely, ( i ) and ( ii ). Sub-
clause ( i ) of clause ( b ) is not relevant to the controversy in hand.
Sub-clause ( ii ) of clause ( b ) provides that if the Court finds that the
arbitral award is in conflict with the public policy of India, it may
set aside the award.
Public policy
31. “Public policy” is a concept not statutorily defined, though it
has been used in statutes, rules, notification, etc. since long, and is
also a part of common law. Section 23 of the Contract Act, 1872
uses the expression by stating that the consideration or object of an
agreement is lawful, unless, inter alia, opposed to public policy.
That is, a contract which is opposed to public policy is void.
*
35. In Renusagar Power Co. Ltd. v. General Electric Co. , 1994
Supp (1) SCC 644 , a three-Judge Bench of this Court observed
that the doctrine of public policy is somewhat open—textured and
flexible. By citing earlier decisions, it was observed that there are
two conflicting positions which are referred to as the “narrow
view” and the “broad view”. According to the narrow view, courts
cannot create new heads of public policy whereas the broad view
countenances judicial law making in these areas. In the field of
private international law, it was pointed out, courts refuse to apply
a rule of foreign law or recognise a foreign judgment or a foreign
arbitral award if it is found that the same is contrary to the public
policy of the country in which it is sought to be invoked or
enforced. However, it was clarified, a distinction is to be drawn
while applying the rule of public policy between a matter governed
by domestic law and a matter involving conflict of laws. It was
observed that the application of the doctrine of public policy in the
field of conflict of laws is more limited than that in the domestic
law and the courts are slower to invoke public policy in cases
involving a foreign element than when a purely municipal legal
issue is involved. It was held that contravention of law alone will
not attract the bar of public policy, and something more than
contravention of law is required.
*
37. What is clear from above is that for an award to be against
public policy of India a mere infraction of the municipal laws of
India is not enough. There must be, inter alia, infraction of
fundamental policy of Indian law including a law meant to serve
public interest or public good.
*
40. In ONGC Ltd. v. Western Geco International Ltd. , (2014) 9
SCC 263, paras 35, 38 & 39 , which also related to the period prior
to the 2015 Amendment of Section 34(2)( b )( ii ), a three-Judge
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 7 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

Bench of this Court, after considering the decision in ONGC
Ltd. v. Saw Pipes Ltd. , (2003) 5 SCC 705 , without exhaustively
enumerating the purport of the expression “fundamental policy of
Indian law”, observed that it would include all such fundamental
principles as providing a basis for administration of justice and
enforcement of law in this country. The Court thereafter
illustratively referred to three fundamental juristic principles,
namely:
( a ) that in every determination that affects the rights of a citizen or
leads to any civil consequences, the court or authority or quasi-
judicial body must adopt a judicial approach, that is, it must act
bona fide and deal with the subject in a fair, reasonable and
objective manner and not actuated by any extraneous
consideration;
( b ) that while determining the rights and obligations of parties the
court or Tribunal or authority must act in accordance with the
principles of natural justice and must apply its mind to the
attendant facts and circumstances while taking a view one way
or the other; and
( c ) that its decision must not be perverse or so irrational that no
reasonable person would have arrived at the same.
41. In Associate Builders v. DDA , (2015) 3 SCC 49 , a two-Judge
Bench of this Court, held that audi alteram partem principle is
undoubtedly a fundamental juristic principle in Indian law and is
enshrined in Sections 18 and 34(2)( a )( iii ) of the 1996 Act. In
addition to the earlier recognised principles forming fundamental
policy of Indian law, it was held that disregarding:
( a ) orders of superior courts in India; and
( b ) the binding effect of the judgment of a superior court would
also be regarded as being contrary to the fundamental policy of
Indian law.
Further, elaborating upon the third juristic principle (i.e. qua
perversity), as laid down in ONGC Ltd. v. Western Geco
International Ltd. , (2014) 9 SCC 263 , it was observed that where:
( i ) a finding is based on no evidence; or
(ii) an Arbitral Tribunal takes into account something irrelevant to
the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision, such decision
would necessarily be perverse[ Associate Builders case , (2015)
3 SCC 49, para 31 ].
To this a caveat was added by observing that when a court applies
the “public policy test” to an arbitration award, it does not act as a
court of appeal and, consequently, errors of fact cannot be
corrected; and a possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the ultimate master of
the quantity and quality of evidence to be relied upon when he
delivers his arbitral award. It was also observed that an award
based on little evidence or on evidence which does not measure up
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 8 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

in quality to a trained legal mind would not be held to be invalid on
that score. Thus, once it is found that the arbitrator's approach is not
arbitrary or capricious, it is to be taken as the last word on facts.
The 2015 Amendment in Sections 34 and 48
42. The aforementioned judicial pronouncements were all prior to
the 2015 Amendment. Notably, prior to the 2015 Amendment the
expression “in contravention with the fundamental policy of Indian
law” was not used by the legislature in either Section 34(2)( b )( ii ) or
Section 48(2)( b ). The pre-amended Section 34(2)( b )( ii ) and its
Explanation read:
*
44. By the 2015 Amendment, in place of the old Explanation to
Section 34(2)( b )( ii ), Explanations 1 and 2 were added to remove
any doubt as to when an arbitral award is in conflict with the public
policy of India.
45. At this stage, it would be pertinent to note that we are dealing
with a case where the application under Section 34 of the 1996 Act
was filed after the 2015 Amendment, therefore the newly
substituted/added Explanations would apply [ SsangyongEngg. &
Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
46. The 2015 Amendment adds two Explanations to each of the
two sections, namely, Section 34(2)( b )( ii ) and Section 48(2)( b ), in
place of the earlier Explanation. The significance of the newly
inserted Explanation 1 in both the sections is two-fold. First, it does
away with the use of words : ( a ) “ without prejudice to the
generality of sub-clause (ii) ” in the opening part of the pre-
amended Explanation to Section 34(2)(b)(ii); and (b) “ without
prejudice to the generality of clause (b) of this section ” in the
opening part of the pre-amended Explanation to Section 48(2)( b );
secondly, it limits the expanse of public policy of India to the three
specified categories by using the words “ only if ”.
Whereas, Explanation 2 lays down the standard for adjudging
whether there is a contravention with the fundamental policy of
Indian law by providing that a review on merits of the dispute shall
not be done. This limits the scope of the enquiry on an application
under either Section 34(2)( b )( ii ) or Section 48(2)( b ) of the 1996
Act.
47. The 2015 Amendment by inserting sub-section (2-A) in Section
34, carves out an additional ground for annulment of an arbitral
award arising out of arbitrations other than international
commercial arbitrations. Sub-section (2-A) provides that the Court
may also set aside an award if that is vitiated by patent illegality
appearing on the face of the award. This power of the Court is,
however, circumscribed by the proviso, which states that an award
shall not be set aside merely on the ground of an erroneous
application of the law or by reappreciation of evidence.
48. Explanation 1 to Section 34(2)( b )( ii ), specifies that an arbitral
award is in conflict with the public policy of India, only if :
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 9 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

( i ) the making of the award was induced or affected by fraud or
corruption or was in violation of Section 75 or Section 81; or
( ii ) it is in contravention with the fundamental policy of Indian law;
or
( iii ) it is in conflict with the most basic notions of morality or
justice.
49. In the instant case, there is no allegation that the making of the
award was induced or affected by fraud or corruption, or was in
violation of Section 75 or Section 81. Therefore, we shall confine
our exercise in assessing as to whether the arbitral award is in
contravention with the fundamental policy of Indian law, and/or
whether it conflicts with the most basic notions of morality or
justice. Additionally, in the light of the provisions of sub-section
(2-A) of Section 34, we shall examine whether there is any patent
illegality on the face of the award.
50. Before undertaking the aforesaid exercise, it would be apposite
to consider as to how the expressions:
( a ) “in contravention with the fundamental policy of Indian law”;
( b ) “in conflict with the most basic notions of morality or justice”;
and
( c ) “patent illegality” have been construed.
In contravention with the fundamental policy of Indian law
51. As discussed above, till the 2015 Amendment the expression
“in contravention with the fundamental policy of Indian law” was
not found in the 1996 Act. Yet, in Renusagar Power Co.
Ltd. v. General Electric Co. , 1994 Supp (1) SCC 644 , in the
context of enforcement of a foreign award, while construing the
phrase “contrary to the public policy”, this Court held that for a
foreign award to be contrary to public policy mere contravention of
law would not be enough rather it should be contrary to:
( a ) the fundamental policy of Indian law; and/or
( b ) the interest of India; and/or
( c ) justice or morality.
*
55. The legal position which emerges from the aforesaid discussion
is that after “the 2015 Amendments” in Section 34(2)( b )( ii ) and
Section 48(2)( b ) of the 1996 Act, the phrase “in conflict with the
public policy of India” must be accorded a restricted meaning in
terms of Explanation 1 . The expression “in contravention with the
fundamental policy of Indian law” by use of the word
“fundamental” before the phrase “policy of Indian law” makes the
expression narrower in its application than the phrase “in
contravention with the policy of Indian law”, which means mere
contravention of law is not enough to make an award vulnerable.
To bring the contravention within the fold of fundamental policy of
Indian law, the award must contravene all or any of such
fundamental principles that provide a basis for administration of
justice and enforcement of law in this country.
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 10 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

56. Without intending to exhaustively enumerate instances of such
contravention, by way of illustration, it could be said that:
( a ) violation of the principles of natural justice;
( b ) disregarding orders of superior courts in India or the binding
effect of the judgment of a superior court; and
( c ) violating law of India linked to public good or public interest,
are considered contravention of the fundamental policy of
Indian law.
However, while assessing whether there has been a contravention
of the fundamental policy of Indian law, the extent of judicial
scrutiny must not exceed the limit as set out in Explanation 2 to
Section 34(2)( b )( ii ).
*
Patent illegality
65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
inserted by the 2015 Amendment, provides that an arbitral award
not arising out of international commercial arbitrations, may also
be set aside by the Court, if the Court finds that the award is visited
by patent illegality appearing on the face of the award. The proviso
to sub-section (2-A) states that an award shall not be set aside
merely on the ground of an erroneous application of the law or by
reappreciation of evidence.
66. In ONGC Ltd. v. Saw Pipes Ltd. , (2003) 5 SCC 705 , while
dealing with the phrase “public policy of India” as used in Section
34, this Court took the view that the concept of public policy
connotes some matter which concerns public good and public
interest. If the award, on the face of it, patently violates statutory
provisions, it cannot be said to be in public interest. Thus, an award
could also be set aside if it is patently illegal. It was, however,
clarified that illegality must go to the root of the matter and if the
illegality is of trivial nature, it cannot be held that award is against
public policy.
67. In Associate Builders v. DDA , (2015) 3 SCC 49 , this Court
held that an award would be patently illegal, if it is contrary to:
( a ) substantive provisions of law of India;
( b ) provisions of the 1996 Act; and
( c ) terms of the contract [See also three-Judge Bench decision of
this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd. ,
(2022) 2 SCC 275 ].
The Court clarified that if an award is contrary to the substantive
provisions of law of India, in effect, it is in contravention of
Section 28(1)( a ) of the 1996 Act. Similarly, violating terms of the
contract, in effect, is in contravention of Section 28(3) of the 1996
Act.
68. In SsangyongEngg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 this Court specifically dealt with the 2015
Amendment which inserted sub-section (2-A) in Section 34 of the
1996 Act. It was held that “patent illegality appearing on the face
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 11 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

of the award” refers to such illegality as goes to the root of matter,
but which does not amount to mere erroneous application of law. It
was also clarified that what is not subsumed within “the
fundamental policy of Indian law”, namely, the contravention of a
statute not linked to “public policy” or “public interest”, cannot be
brought in by the backdoor when it comes to setting aside an award
on the ground of patent illegality [ See SsangyongEngg. &
Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 ]. Further, it
was observed, reappreciation of evidence is not permissible under
this category of challenge to an arbitral award
[See SsangyongEngg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 ].
Perversity as a ground of challenge
69. Perversity as a ground for setting aside an arbitral award was
recognised in ONGC Ltd. v. Western Geco International Ltd. ,
(2014) 9 SCC 263 . Therein it was observed that an arbitral decision
must not be perverse or so irrational that no reasonable person
would have arrived at the same. It was observed that if an award is
perverse, it would be against the public policy of India.
70. In Associate Builders v. DDA , (2015) 3 SCC 49 certain tests
were laid down to determine whether a decision of an Arbitral
Tribunal could be considered perverse. In this context, it was
observed that where:
( i ) a finding is based on no evidence; or
( ii ) an Arbitral Tribunal takes into account something irrelevant to
the decision which it arrives at; or
( iii ) ignores vital evidence in arriving at its decision, such decision
would necessarily be perverse.
However, by way of a note of caution, it was observed that when a
court applies these tests it does not act as a court of appeal and,
consequently, errors of fact cannot be corrected. Though, a possible
view by the arbitrator on facts has necessarily to pass muster as the
arbitrator is the ultimate master of the quantity and quality of
evidence to be relied upon. It was also observed that an award
based on little evidence or on evidence which does not measure up
in quality to a trained legal mind would not be held to be invalid on
that score.
71. In SsangyongEngg. & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 , which dealt with the legal position post the 2015
Amendment in Section 34 of the 1996 Act, it was observed that a
decision which is perverse, while no longer being a ground for
challenge under “public policy of India”, would certainly amount to
a patent illegality appearing on the face of the award. It was
pointed out that an award based on no evidence, or which ignores
vital evidence, would be perverse and thus patently illegal. It was
also observed that a finding based on documents taken behind the
back of the parties by the arbitrator would also qualify as a decision
based on no evidence inasmuch as such decision is not based on
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 12 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

evidence led by the parties, and therefore, would also have to be
characterised as perverse [ See SsangyongEngg. & Construction
Co. Ltd. v. NHAI , (2019) 15 SCC 131 ].
72. The tests laid down in Associate Builders v. DDA , (2015) 3
SCC 49 to determine perversity were followed in SsangyongEngg.
& Construction Co. Ltd. v. NHAI , (2019) 15 SCC 131 and later
approved by a three-Judge Bench of this Court in Patel Engg.
Ltd. v. North Eastern Electric Power Corpn. Ltd. , (2020) 7 SCC
167 .
73. In a recent three-Judge Bench decision of this Court in DMRC
Ltd. v. Delhi Airport Metro Express (P) Ltd. , (2024) 6 SCC 357 ,
the ground of patent illegality/perversity was delineated in the
following terms: (SCC p. 376, para 39)
“ 39 . In essence, the ground of patent illegality is available
for setting aside a domestic award, if the decision of the
arbitrator is found to be perverse, or so irrational that no
reasonable person would have arrived at it; or the
construction of the contract is such that no fair or
reasonable person would take; or, that the view of the
arbitrator is not even a possible view. A finding based on
no evidence at all or an award which ignores vital
evidence in arriving at its decision would be perverse and
liable to be set aside under the head of “patent illegality”.
An award without reasons would suffer from patent
illegality. The arbitrator commits a patent illegality by
deciding a matter not within its jurisdiction or violating a
fundamental principle of natural justice.”
Scope of interference with an arbitral award
74. The aforesaid judicial precedents make it clear that while
exercising power under Section 34 of the 1996 Act the Court does
not sit in appeal over the arbitral award. Interference with an
arbitral award is only on limited grounds as set out in Section 34 of
the 1996 Act. A possible view by the arbitrator on facts is to be
respected as the arbitrator is the ultimate master of the quantity and
quality of evidence to be relied upon. It is only when an arbitral
award could be categorised as perverse, that on an error of fact an
arbitral award may be set aside. Further, a mere erroneous
application of the law or wrong appreciation of evidence by itself is
not a ground to set aside an award as is clear from the provisions of
sub-section (2-A) of Section 34 of the 1996 Act.
75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd. ,
(2019) 20 SCC 1 , paras 27-43, a three-Judge Bench of this Court
held that courts need to be cognizant of the fact that arbitral awards
are not to be interfered with in a casual and cavalier manner, unless
the court concludes that the perversity of the award goes to the root
of the matter and there is no possibility of an alternative
interpretation that may sustain the arbitral award. It was observed
that jurisdiction under Section 34 cannot be equated with the
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 13 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

normal appellate jurisdiction. Rather, the approach ought to be to
respect the finality of the arbitral award as well as party's autonomy
to get their dispute adjudicated by an alternative forum as provided
under the law.
*
Scope of interference with the interpretation/construction of a
contract accorded in an arbitral award
84. An Arbitral Tribunal must decide in accordance with the terms
of the contract. In a case where an Arbitral Tribunal passes an
award against the terms of the contract, the award would be
patently illegal. However, an Arbitral Tribunal has jurisdiction to
interpret a contract having regard to terms and conditions of the
contract, conduct of the parties including correspondences
exchanged, circumstances of the case and pleadings of the parties.
If the conclusion of the arbitrator is based on a possible view of the
matter, the Court should not intefere [See: SAIL v. Gupta Brother
Steel Tubes Ltd. , (2009) 10 SCC 63; Pure Helium India (P)
Ltd. v. ONGC , (2003) 8 SCC 593; McDermott International
Inc. v. Burn Standard Co. Ltd. , (2006) 11 SCC 181; MMTC
Ltd. v. Vedanta Ltd. , (2019) 4 SCC 163 ]. But where, on a full
reading of the contract, the view of the Arbitral Tribunal on the
terms of a contract is not a possible view, the award would be
considered perverse and as such amenable to interference [ South
East Asia Marine Engg. & Constructions Ltd. v. Oil India Ltd. ,
(2020) 5 SCC 164 ].
Whether unexpressed term can be read into a contract as an
implied condition
85. Ordinarily, terms of the contract are to be understood in the
way the parties wanted and intended them to be. In agreements of
arbitration, where party autonomy is the grund norm , how the
parties worked out the agreement, is one of the indicators to
decipher the intention, apart from the plain or grammatical meaning
of the expressions used [ B ALCO v. Kaiser Aluminium Technical
Services Inc. , (2016) 4 SCC 126 ].
86. However, reading an unexpressed term in an agreement would
be justified on the basis that such a term was always and obviously
intended by the parties thereto. An unexpressed term can be
implied if, and only if, the court finds that the parties must have
intended that term to form part of their contract. It is not enough for
the court to find that such a term would have been adopted by the
parties as reasonable men if it had been suggested to them. Rather,
it must have been a term that went without saying, a term necessary
to give business efficacy to the contract, a term which, although
tacit, forms part of the contract [ Adani Power (Mundra)
Ltd. v. Gujarat ERC , (2019) 19 SCC 9 ].
87. But before an implied condition, not expressly found in the
contract, is read into a contract, by invoking the business efficacy
doctrine, it must satisfy the following five conditions:
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 14 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

( a ) it must be reasonable and equitable;
( b ) it must be necessary to give business efficacy to the contract,
that is, a term will not be implied if the contract is effective
without it;
( c ) it must be obvious that “it goes without saying”;
( d ) it must be capable of clear expression;
( e ) it must not contradict any terms of the contract [ Nabha Power
Ltd. v. Punjab SPCL , (2018) 11 SCC 508 , followed in Adani
Power case , (2019) 19 SCC 9 ].
(emphasis supplied)

21. At the outset, this Court deems it apposite to take note of the
categorical findings returned by the learned Arbitral Tribunal,
particularly in paragraph nos. 2.3.17 and 2.3.20 of the Impugned
Award pertaining to Claim No. 2, while dealing with the objections
now sought to be raised by the Petitioner. The said findings assume
considerable significance, inasmuch as the learned Arbitral Tribunal
has comprehensively examined the issue relating to EOT, attribution
of delay, levy of Liquidated Damages, and the consequential
entitlement of the Respondent to additional costs arising out of
prolongation of the contract period. The relevant extracts of the
Impugned Award are reproduced herein below:
“ 2.3.17 The Respondent, during oral hearings, had stated that the
EOT case is lying with the NHAI (HQ). It is now more than 5
years since the Engineer's recommendation of the EOT was
forwarded to the Respondent. In absence of the contractual
requirement of the approval of the NHAI to the EOT recommended
by the Engineer, the Engineer has not finally determined the EOT.
*
2.3.20 Now, the work is not in progress, having been completed
more than 5years back, the opportunity to issue a show cause
notice, even if there had been any valid reason for issuing such a
notice, has been totally lost. NHAI is, thus, not in a legal position
to levy any LD. Therefore, the Arbitral Tribunal is of the view that
the Claimant is entitled to grant of EOT upto the date of
completion i.e. upto 31-08-2010 without levy of LD, even though it
is yet to be formally approved by NHAI, which will now be only a
contractual requirement, before the Engineer or NHAI can formally
communicate it to the Claimant. Various reasons of delay as
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 15 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

brought out hereinabove have been analysed by the AT and: it has
found that the delays are attributable to the Respondent. AT agrees-
with the Extension of Time (EOT) upto 31-08-2010 without LD ,
as finally recommended by the Engineer vide his letters dated 18-
09-2010 (Ex. C-2/54) and 24-09-2010 (Ex. C-2/55); o giving
reasons of delay as (i) ROB.s block not provided by Railways as
per schedule , (ii) 0 Work suspended due to stretch Km. 96+850 to
98+000 objected by Army Aviation Q Authority as "No
Construction Zone" .and (iii) Land acquisition i.e. delay in award
declaration and disbursement of compensation by the Competent
Authority , Jhansi The EOT has been recommended under Clause
44 of OA by the Engineer for 832 days Q i.e. from 21-05-2008 to
31-08-2010 against 955 days claimed by the Contractor However,
the Engineer, while making recommendation, has stated, "There
shall be no additional cost/compensation or any additional claim
except normal escalation /price adjustment where admissible as per
contract" but has not assigned any reason to deny the additional
cost/compensation which is payable as per specific provisions in
the .CA because the events necessitating EOT fall under Clauses
12.2, 40.2 & 42.2 of CA, which also necessitate determination of
additional cost on account of these reasons of delays besides
Extension of Time . Moreover, the Sections 54 & 73 of the 'Indian
Contract Act ,1872 also recognize payment of compensation to a
party in case of breach of the contract by the other party. The AT is
of the view that the Engineer's failure to determine the additional
cost cannot O disentitle the Contractor from his claim for
compensation/additional cost on account of O these delays. The
AT, therefore, holds that the Claimant is entitled to EOT upto 31-
08- 0 2010without LD as well as additional cost on account of the
delay of 832 days mentioned above.”

22. The findings recorded in the afore-extracted portions of the
Impugned Award, in the considered opinion of this Court,
categorically negate the submissions advanced on behalf of the
Petitioner. A careful reading of the said findings demonstrates that the
learned Arbitral Tribunal has returned clear, cogent, and reasoned
conclusions explaining why the delays in execution of the project
could not have been attributed to the Respondent herein. The learned
Tribunal has specifically identified the causes of delay, analysed the
contemporaneous material placed on record, and thereafter concluded
that the impediments leading to prolongation of the project arose due
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 16 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

to factors beyond the control of the Respondent and were attributable
to the acts and omissions of the authorities concerned.
23. This Court has also carefully perused the remaining portions of
the discussion and analysis undertaken by the learned Arbitral
Tribunal while adjudicating Claim No. 2 of the Impugned Award and
finds that the learned Tribunal carried out an extensive, detailed, and
nuanced examination of the disputes arising between the parties before
rendering its findings. The Impugned Award reflects a comprehensive
appreciation not merely of isolated contractual clauses, but of the
entire factual matrix governing the dispute, including the
contemporaneous correspondence exchanged between the parties, the
conduct of the parties during execution of the project, the
recommendations made by the Engineer from time to time, the
contractual scheme governing grant of EOT, and the evidence
adduced before the learned Tribunal.
24. This Court finds substance in the reasoning adopted by the
learned Tribunal that the Respondent could not have been expected to
await a formal decision on EOT from the Petitioner indefinitely. The
record reveals that the Respondent had periodically sought EOT
together with consequential costs commencing from 03.06.2008,
whereas the Engineer had been recommending interim EOT from as
early as 13.07.2007 without the levy of Liquidated Damages.
25. The chronology of correspondence considered by the learned
Tribunal further reveals that vide communications dated 18.09.2010
and 24.09.2010, the Engineer ultimately recommended extension upto
the actual date of completion i.e., 31.08.2010. Despite such repeated
recommendations, the Petitioner admittedly failed to take any final
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 17 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

decision on the issue for more than five years, when the Impugned
Award was passed.
26. The learned Tribunal was therefore justified in observing that a
contracting party cannot remain indolent for years together, keep the
issue in a state of uncertainty, and thereafter seek to prejudice the
opposite party on the ground that the EOT had not attained formal
approval. Such a contention, if accepted, would strike at the very
commercial efficacy of infrastructure contracts and render the
contractual dispute resolution mechanism otiose.
27. This Court further finds that the learned Tribunal correctly
appreciated the contractual provisions governing possession of the site
and delays attributable thereto. Clauses 42.2 of the GCC
unequivocally cast an obligation upon the Employer to provide
possession of such portions of the site and such access thereto as
would enable the Contractor to proceed with the execution of the
works in accordance with the programme contemplated under the
Contract. The learned Tribunal, after considering the
contemporaneous record, arrived at the conclusion that the site was
not handed over in an encumbrance-free and workable condition
within the contractual timelines.
28. The material considered by the learned Tribunal demonstrated
that portions of the land continued to remain unavailable on account of
pending acquisition, delayed declaration of awards, and delayed
disbursement of compensation by the competent authorities. The
learned Tribunal was therefore justified in concluding that the delays
attributable to non-availability of site and land acquisition were
squarely referable to the Petitioner and not to the Respondent.
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 18 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

29. This Court also cannot lose sight of the fact that the Engineer’s
recommendations, which now form the subject matter of challenge by
the Petitioner, were never rejected contemporaneously by the
Petitioner itself. The Petitioner, despite being the beneficiary of
repeated consultations and recommendations under the contractual
framework, chose to maintain complete silence for years. Having
consciously failed to act upon the Engineer’s recommendations at the
relevant stage, the Petitioner cannot now selectively rely upon
portions of the record in an attempt to reopen factual determinations
already rendered by the learned Tribunal.
30. This Court further notes that the learned Tribunal did not
proceed mechanically in quantifying compensation. The Award
reflects a detailed analysis of the various heads of claim, including
overheads, financing costs, additional material costs, and prolongation
expenses. In view thereof, the methodology adopted by the learned
Tribunal, therefore, cannot be said to be arbitrary or unsupported by
evidence.
31. It is well settled that the jurisdiction of this Court under Section
34 of the A&C Act does not permit a re-appreciation of evidence as
though sitting in appeal over the Award. The view adopted by the
learned Tribunal is clearly a plausible and legally sustainable view
arising from the material placed before it. Merely because another
interpretation may also be possible would not justify interference
under Section 34 of the A&C Act.
32. Accordingly, in the considered opinion of this Court, no patent
illegality, perversity, jurisdictional infirmity, or conflict with the
fundamental policy of Indian law is discernible from the impugned
Award. The challenge mounted by the Petitioner is essentially an
Signature Not Verified
O.M.P. (COMM) 51/2016 Page 19 of 20

Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:20.05.2026
19:34:11

invitation to this Court to revisit pure findings of fact already
adjudicated upon by the learned Tribunal after exhaustive
consideration of the record, which is impermissible in the exercise of
jurisdiction under Section 34 of the A&C Act.

CONCLUSION:
33. In view of the foregoing discussion, this Court is of the
considered opinion that the Impugned Arbitral Award dated
18.11.2015 does not suffer from any infirmity warranting interference
under Section 34 of the A&C Act.
34. Accordingly, the present instituted by NHAI stands dismissed.
Consequently, the Impugned Award is upheld.
35. All pending application(s), if any, also stand disposed of in the
aforesaid terms.
36. No order as to costs.


HARISH VAIDYANATHAN SHANKAR, J.
MAY 14, 2026/rk/kv/kr


Signature Not Verified
O.M.P. (COMM) 51/2016 Page 20 of 20