M/S. LATHA MULTITECH ENTERPRISES vs MR.S.N.MOHAN KUMAR

Court
Karnataka High Court

- 1 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025
®


CNR: KAHC010080262025




IN THE HIGH COURT OF KARNATAKA AT BENGALURU


TH
DATED THIS THE 17 DAY OF NOVEMBER, 2026

BEFORE

THE HON'BLE MR. JUSTICE SURAJ GOVINDARAJ

CRIMINAL PETITION NO. 2071 OF 2025 (482(Cr.PC)

/ 528(BNSS)-)

BETWEEN:

1. M/S. LATHA MULTITECH ENTERPRISES
SHED NO. 14/SY NO. 112/2
TH
12 CROSS, DODDANNA
INDUSTRIAL ESTATE
LAGGERE VILLAGE
YESHWANTHAPURA HOBLI
BANGALORE 560091
REP BY ITS PROPRIETOR

2. MR. BHOJARAJU
AGED ABOUT 60 YEARS
SON OF LATE UGRE GOWDA
TH
R/AT NO. 43 35 CROSS
ND
2 BLOCK, RAJAJAINAGAR
BANGALORE 560010
…PETITIONERS
(BY SRI. MITTY NARASIMHA MURTHY.,ADVOCATE)

AND:

MR.S.N.MOHAN KUMAR
S/O SRI NARAYANAPPA
R/AT DAVALAGIRI
TH
NO. 1399 8 BLOCK
SIR M VISWESHWARAAIAH
BDA LAYOUT
BANGALORE 560091
…RESPONDENT
(RESPONDENT-SERVED)












Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 2 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025


THIS CRIMINAL PETITION IS FILED U/S 482 CR.PC (FILED U/S
528 BNSS) PRAYING TO CALL FOR THE RECORDS ON THE FILE OF
THE LXIII ADDL. CITY CIVIL AND SESSIONS JUDGE (CCH-64) AT
BENGALURU, AND TO QUASH THE ORDER DATED 05.10.2024 AND
CONSEQUENTLY QUASH THE ORDER DATED 09.02.2022 AND
29.04.2022 ON THE FILE OF TH XXII ADDITIONAL CHIEF
METROPOLITAN MAGISTRATE AT BANGALORE, AND CONSEQUENTLY,
DISMISS THE COMPLAINT FILED BY THE RESPONDENT IN
C.C.NO.13420/2022 AND ETC.

THIS CRIMINAL PETITION, COMING ON FOR ADMISSION, THIS
DAY, ORDER WAS MADE THEREIN AS UNDER:

CORAM: HON'BLE MR. JUSTICE SURAJ GOVINDARAJ

ORAL ORDER

1. A memo enclosing the notice dated 08.02.2022 has
been filed. The same is taken on record.

2. The petitioners are before this Court seeking for the
following reliefs:
a. Call for the records on the file of the LXIII Addl.
City Civil and Sessions Judge (CCH-64) at
Bengaluru, and to quash the order dated
05.10.2024 and consequently quash the order
dated 09.02.2022 and 29.04.2022 on the file of the
XXII Additional Chief Metropolitan Magistrate at
Bangalore, and consequently, dismiss the
complaint filed by the respondent in
c.c.no.13420/2022.

b. To grant such other relief’s as this Hon’ble Court
deems fit to grant in the facts and circumstances of
the case, in the interest of justice and equity.


Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 3 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025



3. Respondent No.2 instituted PCR No.3467/2022 under
Section 200 of the Code of Criminal Procedure, 1973,
read with Section 138 of the Negotiable Instruments
Act, 1881. The complaint was instituted on
09.02.2022. The sworn statement of the complainant
was recorded on 29.04.2022, pursuant to which
process came to be issued against the petitioner.
Aggrieved by the proceedings, the petitioner
preferred a Criminal Revision Petition in CRP
No.114/2023. The Revisional Court, by order dated
05.10.2024, dismissed the revision petition. It is
challenging the said order, as also the orders passed
by the Trial Court, that the petitioner is before this
Court.

4. Sri Mitty Narasimha Murthy, learned counsel for the
petitioner, submits as follows:

4.1. The first statutory notice was received by the
petitioner on 11.01.2022. Subsequently,
another notice dated 08.02.2022 came to be
issued. However, without waiting for the
mandatory period of 15 days from the date of
receipt of the second notice, the complaint was
instituted on 09.02.2022.
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 4 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025



4.2. Learned counsel submits that the complaint
was instituted before the expiry of the statutory
period contemplated under Section 138 of the
Negotiable Instruments Act. The defect goes to
the root of the maintainability of the complaint.
The Revisional Court ought to have set aside
the proceedings instead of permitting them to
continue.

4.3. Learned counsel further submits that the notice
dated 08.02.2022 contains a demand calling
upon the petitioner to pay the amount covered
by the dishonoured cheque. It is, therefore, not
merely a communication correcting an
inadvertent error, but a notice reiterating the
demand for payment. According to learned
counsel, the statutory period of 15 days would
have to be reckoned afresh from the date of
receipt of this notice. Since the complaint was
filed on 09.02.2022, it is contended that the
complaint is premature and the proceedings are
liable to be quashed.

5. Though notice has been issued to respondent No.2,
none has entered appearance on behalf of
respondent No.2.
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 5 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025



6. Heard Sri Mitty Narasimha Murthy, learned counsel
for the petitioner, and perused the material on
record.

7. The short question that arises for consideration is:

“Whether the communication dated
08.02.2022 constitutes a fresh statutory
notice under Section 138 of the
Negotiable Instruments Act, 1881,
requiring the complainant to wait for a
further period of 15 days, or is merely an
addendum/corrigendum to the earlier
notice received by the petitioner on
11.01.2022, so as to determine whether
the complaint instituted on 09.02.2022
was premature?”

8. The issuance of the cheque by the petitioner in
favour of respondent No.2 and its subsequent
dishonour are not in dispute. It is also not in dispute
that the first statutory notice was received by the
petitioner on 11.01.2022. The petitioner's contention
is that the subsequent communication dated
08.02.2022 constituted a fresh demand notice and
that the complaint filed on 09.02.2022 was,
therefore, premature.

9. A perusal of the communication dated 08.02.2022
indicates that it is expressly issued as an addendum
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 6 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025


to the earlier legal notice dated 11.01.2022. The
purpose of the addendum is to correct the error
relating to the branch particulars of the bank referred
to in the earlier notice. The original notice had
already communicated the demand in respect of the
dishonoured cheque. The addendum does not
introduce a new cheque, alter the amount demanded
or substitute the original demand with a different
one. It merely clarifies the bank branch particulars
set out in the earlier communication.

10. The Revisional Court has considered this very aspect
and concluded that the communication dated
08.02.2022 is only an addendum to the earlier
notice, clarifying the branch particulars of the bank,
and cannot be treated as a fresh statutory notice
under Section 138 of the Negotiable Instruments Act.
On examination of the two communications, this
Court finds no reason to disagree with the said
conclusion.

11. The fact that the addendum also reiterates the
demand for payment does not, by itself, convert it
into a fresh statutory notice. The character of a
communication has to be determined from its
contents and the purpose for which it was issued. In
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 7 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025


the present case, the demand had already been
communicated through the notice received on
11.01.2022. The subsequent communication only
corrects the branch particulars and does not replace
or supersede the original demand.

12. The statutory period of 15 days contemplated under
clause (c) of the proviso to Section 138 of the
Negotiable Instruments Act, therefore, has to be
reckoned from the date of receipt of the original
notice, namely, 11.01.2022. Excluding the date of
receipt, the period of 15 days expired on 26.01.2022.
The cause of action would arise upon the drawer
failing to make payment within the said period. The
complaint, having been instituted on 09.02.2022,
was thus presented after expiry of the statutory
period.

13. The petitioner's contention that the period of 15 days
should be reckoned afresh from 08.02.2022 proceeds
on the incorrect premise that the said communication
was a fresh notice. Once it is found to be only a
corrigendum to the original statutory notice, the
question of granting a further period of 15 days from
its date does not arise.
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 8 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025



14. It is necessary to clarify the legal position regarding a
complaint instituted before expiry of the statutory
period under Section 138 of the Negotiable
Instruments Act.

15. The complaint in the present matter was not
instituted within 15 days of receipt of the original
statutory notice. The subsequent communication
dated 08.02.2022, being only an addendum
correcting the bank branch particulars, did not give
rise to a fresh statutory period. The complaint was,
therefore, maintainable on the date of its institution
itself.

16. Even assuming that the communication dated
08.02.2022 constituted a fresh statutory notice, the
same would not, by itself, invalidate the proceedings.
The original statutory notice had been received by
the petitioner on 11.01.2022. The petitioner failed to
make payment within the statutory period of 15
days, and the cause of action under Section 138 of
the Negotiable Instruments Act had consequently
accrued upon expiry of that period. The complaint
instituted on 09.02.2022 was, therefore, founded on
a statutory demand in respect of which the requisite
period had already elapsed.
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 9 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025



17. The subsequent communication dated 08.02.2022
did not withdraw or supersede the original notice, nor
did it obliterate the cause of action that had already
accrued. Even treating the subsequent
communication as a fresh notice, the petitioner
cannot rely upon it to contend that the statutory
consequences flowing from the original notice stood
suspended or extinguished. The petitioner had
received the original demand, was afforded the
statutory opportunity to make payment and did not
avail himself of that opportunity. No prejudice was
caused to him by the subsequent communication.

18. The objection founded on the subsequent notice,
therefore, does not invalidate the complaint, which
was instituted after expiry of the statutory period
reckoned from the original notice.

19. In view of the above, the complaint instituted on
09.02.2022 cannot be said to be premature. The Trial
Court did not commit any error in proceeding with
the complaint, and the Revisional Court was justified
in rejecting the challenge. No ground is made out for
interference with the orders impugned in this
petition.

Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified

- 10 -
HC-KAR
NC: 2026:KHC:63723
CRL.P No. 2071 of 2025


CNR: KAHC010080262025


ORDER

i) The Criminal Petition is dismissed .

ii) The orders dated 09.02.2022 and 29.04.2022
passed by the XXII Additional Chief Metropolitan
Magistrate, Bengaluru, and the order dated
05.10.2024 passed by the LXIII Additional City
Civil and Sessions Judge (CCH-64), Bengaluru, are
sustained.

iii) The proceedings in C.C. No.13420/2022 shall
continue in accordance with law.
Digitally Signed By:
SURAJ GOVINDA RAJ
20/11/2026, 13:32, Bengaluru
Verified
(SURAJ GOVINDARAJ)
JUDGE


SR
List No.: 1 Sl No.: 12