THE UNION OF INDIA vs M/S K.P. TRADING AND COMPANY
- Court
- Calcutta High Court
IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
[CIRCUIT BENCH AT PORT BLAIR]
PRESENT: THE HON'BLE JUSTICE MADHURESH PRASAD
AND
THE HON'BLE JUSTICE PRASENJIT BISWAS
FMAT(ARBAWARD)/2/2026
IA NO. CAN/2/2025
UNION OF INDIA … APPELLANT
VS.
M/S K.P. TRADING AND COMPANY … RESPONDENT
For the appellant : Mr. Rakesh Kumar
For the respondent : Mr. Tapan Kumar Das
Heard on : October 05, 2026
Judgment on : October 05, 2026
MADHURESH PRASAD , J.
1. The present appeal has been filed under Section 37 of the
Arbitration and Conciliation Act, 1996 (hereinafter referred as to the
1996 Act). It is the case of the appellant/Union of India that a tender
was awarded on 22.11.2010 to the respondent. The scope of the work
was part of Tsunami Rehabilitation Scheme to reclaim cultivable
agricultural land. The work consisted of reconstruction of Sea Dyke
in lieu of the Sea Dyke damaged during the 2004 Tsunami.
2. After award of the work, the respondent/claimant (hereinafter
referred to as the Company for clarity and convenience) before the
2
learned Arbitrator did not commence the work on the stipulated date
(01.12.2010) of commencement. In fact the work was not started even
till the stipulated date (31.08.2011) of completion, under the
agreement. On 23.03.2015, the appellant invoked Clause 3A of the
General Conditions of Contract (hereinafter referred as the GCC) to
foreclose the contract.
3. The Company thereafter invoked Clause 25 of the GCC
containing the arbitration clause and requested the Chief Engineer,
APWD for adjudication of his disputes and claim raised by the
Company.
4. The appellant took no steps for appointment of Arbitrator. The
Company thus, invoked Section 11 of the 1996 Act by moving the
High Court for appointment of an Arbitrator. The Sole Arbitrator was
thus appointed vide order dated 05.04.2016 by the High Court for
adjudication of the Company’s disputes. Due to inability of the
Arbitrator appointed by the High Court to take up the case, another
Arbitrator was appointed vide order dated 14.06.2016 by the High
Court, who proceeded to consider the Company’s claim.
5. Before the learned Arbitrator, the Company claimed that it had
deposited the Earnest Money Deposit (EMD) of Rs. 5,79,682/-
(Rupees five lakhs seventy nine thousand six hundred eighty two
only) and the Performance Guarantee (PG) being an amount of
Rs. 20,17,227/- (Rupees twenty lakhs seventeen thousand two
3
hundred twenty seven only). The EMD was deposited on 13.09.2010
whereas the PG was deposited on 18.11.2010.
6. Despite the deposits made by the Company, the work could not
commence as the site in question was allegedly not made available to
the Company. Such claim of the Company was considered by the
learned Arbitrator with reference to the conditions contained in the
NIT; and contract bearing Agreement No.16/Accts/EE/CD-III/2010-
11 along with the General Conditions of Contracts which formed part
of the agreement.
7. Condition No. 4 of the NIT contemplated that “ the site for the
work is available ”. The second option in Clause No. 4 stipulating that
the site for the work shall be made available, was struck off. The NIT
unambiguously held out an assurance that the site for the work was
available. Thus, Clauses 8 and 9 of the NIT allowed the tenderers to
inspect the drawing and documents pertaining to the work and also
to inspect and examine the site and its surrounding for satisfying
themselves as to nature of the ground and soil etc.
8. The learned Arbitrator also considered the stipulation in the
letter of acceptance dated 16.11.2010 that on receipt of the
Performance Guarantee Bond amount, the letter to commence the
work shall be issued and site of work shall be handed over. However,
the learned Arbitrator found that there was no document whatsoever
to show that the site was handed over to the Company. It was the
4
specific claim of the Company in their Statement of Claim that they
were repeatedly contacting the departmental official for handing over
of the site. Learned Arbitrator considered the letter dated 14.11.2011
to this effect.
9. The learned Arbitrator further considered the correspondences
to the effect that the appellant itself was asking the Agricultural
Department to hand over the site to PWD. This communication is
dated 31.10.2010. Learned Arbitrator also considered the other
documents such as communication dated 10.01.2011 and letter
dated 15.03.2011 from the Executive Engineer, PWD to the
Agricultural Department wherefrom it emerged that demarcation of
land at this location was not done. It also emerges that the land was
not physically handed over to the PWD. This state of affair is
apparent from successive communication being the Executive
Engineer’s letter date 20.07.2011; and communication dated
01.08.2011 from the Agriculture Department asking the Forest
Department for NOC.
10. Under these circumstances, the appellant itself granted a
provisional extension on 24.07.2012, extending the time for
completion of the work upto 31.08.2012. The learned Arbitrator
found that the appellant issued the letter dated 23.03.2015, 2 ½
years thereafter, in purported exercise of discretion under Clause 3A
of the GCC which reads:
5
“ CLAUSE 3A
In case, the work cannot be started due to reasons not within the
th
control of the contractor within 1/8 of the stipulated time for
completion of work, either party may close the contract in such
eventuality, the Earnest Money Deposit and the Performance
Guarantee contract shall be refunded, but no payment on account of
interest, loss of profit or damage etc shall be payable at all.”
11. Considering these facts and circumstances emanating from the
record the learned Arbitrator found the work could not be started due
to the reason not within the control of the Company. As a matter of
fact the learned Arbitrator found a clear statement in this regard in
the letter dated 23.03.2015 invoking Clause 3A of the GCC,
foreclosing the agreement. The factual finding regarding the site not
having made available to the Company therefore was based on
materials considered by the learned Arbitrator in the form of
correspondence placed either by the Company or by the appellant in
the arbitral proceeding.
12. The learned Arbitrator also considered that the Clause 3A of
the GCC extracted above provided an option to either parties to
foreclose the agreement by invoking this clause in the event the work
could not be started by the contractor within 1/8 of the stipulated
time for the completion of the work, due to reason not within the
control of the contractor.
13. The learned Arbitrator thus concluded that Clause 3A provided
an option of an early exit within a reasonable time from the date of
commencement of the work. The appellant was conscious from the
6
date of the execution of the agreement that the site was not available
with them. The learned Arbitrator also found that despite their
pursuing the matter before the authorities namely Agriculture
Department and Forest Department, the site could not be handed
over. Under the circumstances, learned Arbitrator held that the
appellant was under an obligation to foreclose the contract under
Clause 3A of GCC, without any further delay. The learned Arbitrator
thus held that the Company could not be in any manner held liable
for such lapses of not handing over the site to the Company, so as to
disentitle the Company from the claim raised by it.
14. The appellant’s denial of interest on loss of profit or damages
as contemplated under Clause 3A could be sustained only if they had
invoked the Clause 3A in terms of the letter and spirit of the Clause
3A i..e within 1/8 of the stipulated period of contract, which the
appellant did not do. In fact the appellant granted one extension on
24.07.2012, for completion of work till the extended date, i.e.
31.08.2012. The site was still not handed over to the Company for
executing the work. However, the appellant did not foreclose the
agreement till about 2 ½ years thereafter. The liability of the
appellant was therefore clearly established by the learned Arbitrator
with reference to the terms and conditions in the NIT, agreement and
GCC and also correspondence adduced before the learned Arbitrator.
7
15. The findings therefore did not merit any interference by the
Court exercising jurisdiction under Section 34 of the Act. We find no
infirmity in such consideration by the learned Arbitrator or by the
Court exercising jurisdiction under Section 34 of the Act.
16. We therefore proceeded to consider the case of the appellant
that the extent of claim allowed and quantification of loss was not
sustainable.
17. We find that after submission of the statement of claim and
counter statement of facts, the submission of the parties and after
giving them opportunity of leading their evidences in support of their
respective claims, the arbitrator proceeded to decide the following 8
claims made by the claimant:-
(i) Claim No. 1 Interest on Earnest Money Deposit of Rs.
5,79,682.00 (Rupees five lakhs seventy nine
thousand six hundred eighty two) which
remained blocked from 13.09.2010 to
23.03.2015 @14% per annum.
Rs. 3,65,120.00
(ii) Claim No. 2 Losses incurred due to blockage of margin
money deposited with bank for obtaining
Performance Guarantee @ 14% per annum on
Rs. 5,04,307.00 (Rupees five lakhs four
thousand three hundred seven only) from
18.11.2011 to 23.03.2015.
Rs. 8,22,020.00
8
(iii) Claim No. 3 Damages/Lossess on account of Head Office
expenses due to prolongation of contract plus
interest @ 14% per annum from the date of
foreclosure.
Rs. 72,62,017.00
(iv) Claim No. 4 Losses of profit due to non-execution of
contract plus interest @ 14% per annum
thereupon.
Rs. 90,84,784.00
(v) Claim No. 5 Damages/Losses due to idling of Machinery and
T&P and site overhead expenses for four
months plus interest thereupon @ 14% for 48
months.
Rs. 20,97,916.00
(vi) Claim No. 6 Cost of boulders procured and transported but
could not be used due to foreclosure plus
interest @ 14% per annum for two years.
Rs. 1,28,57,600.00
(vii) Claim No. 7 Interest @ 14% per annum on all the claims
from date of foreclosure till actual date of
payment.
(viii) Claim No. 8 Cost of arbitration
Rs. 3,00,000.00
18. The Arbitrator considered the claims in the following terms:
(i) Claim No. 1 Interest on the amount of Rs. 5,79,682.00
(Rupees five lakhs seventy nine thousand six
hundred eighty two only) @ 8.5% per annum
(being average rate of bank interest prevalent
during period in question) as reasonable
9
amount for the period from 13.09.2010 to
23.03.2015 quantified at Rs. 2,22,876.00
(Rupees two lakhs twenty two thousand eight
hundred seventy six only).
(ii) Claim No. 2 was allowed to the extent of Rs. 1,22,006.00
(Rupees one lakh twenty two thousand and six
only) in favour of the claimant against this
claim.
(iii) Claim No. 3 was allowed to the extent of Rs. 5,00,000.00
(Rupees five lakhs only) to the claimant against
this claim.
(iv) Claim No. 4 was allowed to the extent of Rs 12,85,982.00
(Rupees twelve lakhs eighty five thousand nine
hundred eighty two only) to the claimant
against this claim
(v) Claim No. 5 was disallowed by the learned Arbitrator.
(vi) Claim No. 6 was also disallowed by the learned Arbitrator.
(vii) Claim No. 7 was considered in the following terms – the
claimant was found entitled to simple interest @
8% per annum on the awarded amounts under
the claims no.1,2,3 & 4 from 18.11.2015, i.e.
the date of on which the dispute was arose, till
the date of the award. Learned Arbitrator
further held that no further interest will be
payable if the awarded amount including
interest and costs is paid to the claimant within
60 days of issue date of award. Thereafter it will
carry interest @ 9% PA from date of award till
date of payment.
(viii) Claim No. 8 being the cost of the arbitration was allowed to
the extent of Rs. 3,00,000.00 (Rupees three
lakhs only) in favour of the claimant.
10
19. Insofar as the two counter claims raised by the petitioner/
appellant, the same was rejected in the following terms:
“ My decision on counter claims no. 1 and 2;
1. The counter claims have never been raised earlier nor been
referred to arbitration by competent authority under the
agreement/court.
2. It has been established that respondent was in breach of
contract. Therefore he is not entitled to claim any
losses/damages from the claimant contractor.
3. The losses claimed are not even remotely substantiated. It is
not the case that respondent was granted money on interest
bearing loan. Also government deposits do not earn interest
normally. No details of actual losses are given. As far as
staff is concerned, he has failed to establish that any staff
was employed exclusively for this project.”
20. It is thus obvious that against a total claim of Rs.
3,27,89,457/- (Rupees three crores twenty seven lakhs eight nine
thousand four hundred fifty seven only), the learned Arbitrator
awarded the claim to the tune of Rs. 24,30,834/- (Rupees twenty four
lakhs thirty thousand eight hundred thirty four only).
21. Aggrieved by the award, the present appellant assailed the
same under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter referred to as ‘1996 Act’) in Other Suit No. 02 of 2018.
The same was considered by the Court of Additional District Judge,
South Andaman District who found no reason to interfere with the
award in exercise of jurisdiction of Section 34 of 1996 Act. The Suit
was thus dismissed on contest but without there being any order as
11
to costs. The award dated 15.09.2017 of the learned Arbitrator was
affirmed.
22. The appellant is thus before us in the present proceeding under
Section 37 of the 1996 Act.
23. The learned advocate for the appellant submitted that since the
Claim No. 5 (damages) was rejected, the award of the Arbitrator
inasmuch as it allowed the Claim No. 4 under the head loss of profit
is unsustainable.
24. It is submitted that the claimant did not adduce any evidence
whatsoever in support of Claim No. 4. Merely by relying on Section 73
of the 1872 Act, the claim to loss of profit was allowed. The claim is
unsustainable since the learned Arbitrator found no evidence as
regards any deployment of resources by the claimant; and rejected
the claim No.5, for damages.
25. In absence of any basis for quantification of loss of profit, the
Claim No. 4 could not have been allowed. It is argued that Section 73
of the 1872 Act itself contemplates such compensation not to be
given for any remote and indirect loss or damage sustained by reason
of breach of contract.
26. Insofar as claim of the various deposits made by the claimant,
learned counsel for the appellant has not raised any dispute, he has
fairly submitted that the deposits were made by the claimant. Since
12
the appellant invoked Clause 3A of the GCC, the claimants were
entitled to refund of the amounts.
27. Disputing the award of the Arbitrator insofar as it allowed the
Claim No. 4. It is submitted that the decision of the Arbitrator in this
regard is perverse and unsustainable since such conclusion of the
Arbitrator cannot be reconciled with the conclusion of the Arbitrator
with respect to Claim No. 5 being under the head of damage/losses
due to idling of machinery and expenditure incurred over deployment
of resources. In support of his submission learned counsel for the
appellant has relied upon a decision of the Apex Court in the case of
Batliboi Environmental Engineers Limited vs. Hindustan
Petroleum Corporation limited and another reported in (2024) 2
SCC 375 . The judgment of the Apex Court is dated 21.09.2023. The
learned counsel relied upon paragraph Nos. 23, 29 to 39 of the said
judgment to submit that when a claim is made to loss of profit as
made by the claimant herein, the claimant has to prove that there
was other work available that he could have secured if not for the
delay. The same has to be proved with reference to invitations to
tender in which the claimant could not participate due to insufficient
capacity to undertake other work; or by books of accounts to
demonstrate a drop in turnover. If loss of turnover resulting from
delay is not established, the contractor would not be entitled to loss
of profit.
13
28. In the instant case, the Arbitrator already awarded the
interest on the amounts deposited. In absence of any material to
prove that a loss of profit has occasioned, the award of the Arbitrator
in respect of Claim No. 4 under the head loss of profit is
unsustainable.
29. Recognizing the limitation of an Appellate Court in respect of
an arbitral award as per Sections 34 and 37 of the 1996 Act, it is
submitted by learned counsel for the appellant that in the case of
Batliboi Environmental Engineers Limited (supra), the Apex Court
has clearly held that in paragraph Nos. 45 to 48, which are as
follows:-
“45. Referring to the third principle in Western Geco, it was explained
that the decision would be irrational and perverse if (a) it is based on
no evidence; (b) if the arbitral tribunal takes into account something
irrelevant to the decision which it arrives at; or (c) ignores vital
evidence in arriving at its decision. The standards prescribed in Excise
and Taxation Officer-cum-Assessing Authority v. Gopi Nath & Sons37
and Kuldeep Singh v. Commissioner of Police38 should be applied and
relied upon, as good working tests of perversity. In Gopi Nath & Sons it
has been held that apart from the cases where a finding of fact is
arrived at by ignoring or excluding relevant materials or taking into
consideration irrelevant material, the finding is perverse and infirm in
law when it outrageously defies logic as to suffer from vice of
irrationality. Kuldeep Singh clarifies that a finding is perverse when it
is based on no evidence or evidence which is thoroughly unreliable
and no reasonable person would act upon it. If there is some evidence
which can be acted and can be relied upon, however compendious it
may be, the conclusion should not be treated as perverse. This Court
in Associate Builders emphasised that the public policy test to an
arbitral award does not give jurisdiction to the court to act as a court of
appeal and consequently errors of fact cannot be corrected. Arbitral
tribunal is the ultimate master of quality and quantity of evidence. An
award based on little evidence or no evidence, which does not
measure up in quality to a trained legal mind would not be held to be
invalid on this score. Every arbitrator need not necessarily be a person
trained in law as a Judge. At times, decisions are taken acting on
equity and such decisions can be just and fair should not be
overturned under Section 34 of the A&C Act on the ground that the
14
arbitrator’s approach was arbitrary or capricious. Referring to the third
ground of public policy, justice or morality, it is observed that these are
two different concepts. An award is against justice when it shocks the
conscience of the court, as in an example where the claimant has
restricted his claim but the arbitral tribunal has awarded a higher
amount without any reasonable ground of justification. Morality would
necessarily cover agreements that are illegal and also those which
cannot be enforced given the prevailing mores of the day. Here again
interference would be only if something shocks the court’s conscience.
Further, ‘patent illegality’ refers to three sub-heads: (a) contravention
of substantive law of India, which must be restricted and limited such
that the illegality must go to the root of the matter and should not be of
a trivial nature. Reference in this regard was made to clause (a) to
Section 28(1) of the A&C Act, which states that the dispute submitted
to arbitration under Part I shall be in accordance with the substantive
law for the time being in force. The second sub-head would be when
the arbitrator gives no reasons in the award in contravention with
Section 31(3) of the A&C Act. The third sub-head deals with
contravention of Section 28(3) of the A&C Act which states that the
arbitral tribunal shall decide all cases in accordance with the terms of
the contract and shall take into account the usage of the trade
applicable to the transaction. This last sub-head should be understood
with a caveat that the arbitrator has the right to construe and interpret
the terms of the contract in a reasonable manner. Such interpretation
should not be a ground to set aside the award, as the construction of
the terms of the contract is finally for the arbitrator to decide. The
award can be only set aside under this sub-head if the arbitrator
construes the award in a way that no fair-minded or reasonable
person would do.
46. As observed previously, we need not examine the amendment
made to the A&C Act vide Act No. 3 of 2016 with retrospective effect
from 23.10.2015 and the judgments that deal with the amended
Section 34 of the A&C Act. Pertinently, the amendment to Section 34 of
the A&C Act was effected, pursuant to the observations of the
Supplementary Report to Report No. 246 on Amendments to Arbitration
and Conciliation Act, 1996 by the Law Commission of India, titled
‘Public Policy – Developments post-Report No. 246’ published in
February 2015. This Supplementary Report observed that the power to
review an arbitral award on merits under Section 34 of the A&C Act,
as elucidated in the case of Western Geco, subsequently followed in
Associate Builders, is contrary to the object of the A&C Act and
international practice on minimization of judicial intervention. A
reference can also be conveniently made to MMTC Ltd. v. Vedanta
Ltd.,39 and Ssangyong Engg. & Construction Co. Ltd. v. National
Highways Authority of India which examine the scope of intervention
of courts under Section 34 of the A&C Act as amended by Act No. 3 of
2016. MMTC Ltd. and Ssangyong Engg., and other judgments which
deal with the amended Section 34 of the A&C Act that are not
applicable in the present case.
47. We have extensively analysed the award, its patent flaws and
illegalities which emanate from it, like the manifest lack of reasoning in
15
arriving at the conclusions and the calculation of amounts awarded,
which, in fact, amount to double or part-double payments, besides
being contradictory etc. In view of our aforesaid reasoning, the award
has been rightly held to be unsustainable and set aside by the division
bench of the High Court exercising power and jurisdiction under
Section 37 read with Section 34 of the A & C Act.
48. In view of the aforesaid discussion, the appeal is dismissed
without any order as to costs.”
30. It is submitted that considering the earlier judgments delivered
by the Apex Court holding the field till date, the Apex Court in the
judgment of Batliboi Environmental Engineers Limited (supra),
has held that patent flaws and illegalities which emanate from an
award, like the manifest lack of reasoning in support of the
conclusions and the amounts awarded as in the instant case, would
suffice to set aside an arbitral award by exercising of jurisdiction
under Sections 34 and 37 of the 1996 Act.
31. Learned counsel for the Company has relied upon three
decisions, which are as follows:-
(i) Mohd. Salamatullah and other vs. Government of
Andhra Pradesh reported in AIR 1977 SC 1481 .
(ii) A.T. Brij Paul Singh and other vs. State of Gujarat
reported in AIR 1984 SC 1703 .
(iii) Unreported decision of the Division Bench of the Bombay
High Court in the case of M/s Jeevat Construction vs.
Union of India and others in Appeal No. 755 of 2005
decided on 07.02.2017.
16
32. By relying upon the decision in the case Mohd. Salamatullah
and other (supra), it is submitted that this Court should not
investigate into claims awarded by the Arbitrator de novo.
33. Referring to the decision of A.T. Brij Paul Singh and other
(supra), it is submitted that once it is held that the appellant was in
breach of contract, the expenditure incurred by the petitioner being
corroborated by the various receipts, which we have referred to
above, the petitioner would be entitled to a loss of expected profit in
the work. He has also relied upon paragraph No. 11 of this judgment
to submit that the award towards loss of profit is not only reasonable
but a lesser quantification. The Arbitrator has not awarded the 15%
claimed by the Company, but awarded 3.75% only. It is thus
apparent that the arbitrator has admitted the claim for loss of profit
after due consideration and upto a real and reasonable extent.
34. The judgment of the Bombay High Court in the case of M/s
Jeevat Construction (supra) has also been placed by the learned
counsel. He has referred to paragraph no. 17 to reiterate the same
submission that where there was breach of contract and wrongful
termination, the party who is not in default, in the present case being
the Company is entitled to recover the damages.
35. This court has to accord consideration to the rival submissions
within the limited purview of interference in an arbitral award within
the scope of Sections 34 and 37 of the 1996 Act. There are decisions
17
galore based on the statutory provisions contained in the above two
noted sections of the 1996 Act, reiterating the limited scope of
appellate jurisdiction. We therefore are required to confine ourselves
within the well established limits as an appellate court in respect of
an arbitral award.
36. The submission of the appellant that the conclusion in respect
of Claim No. 4 cannot be at variance with the conclusion in respect of
Claim No.5, in our opinion, does not hold water. The Claim No.5 is
with regard to damages and loss due to idling of machineries, Tools
and Plants and site over head expenses for the entire period. The
claim under this head is also based on alleged procurement of
unskilled, semi-skilled, highly skilled workers from the mainland but
there is no material and evidence in support of this distinct claim.
However, insofar as Claim No.4 is concerned, the claimant has
produced income tax returns showing a steady decline in the gross
total income starting from the years 2010-2011 to 2015-2016. It is
also not in dispute that the tender amount was inclusive of a margin
of 15% as percentage on cost of materials and labour to cover all
overheads and profits.
37. The court is also required to consider the fact that the
appellant has invoked Clause 3A to foreclose the contract much
beyond 1/8 of the stipulated time for completion of work. Clause 3A
was required to be invoked within a month from the stipulated date of
18
commencement (1.12.2010). However, we find that the same was
invoked on 23.03.2015, more than four years after the stipulated
date of commencement.
38. It is apparent that the authorities have resorted to Clause 3A
even though the clause was not available to foreclose the contract
th
beyond 1/8 of the stipulated time for completion of the work. The
same has obviously been done on extraneous consideration to avoid
the obligations arising out of foreclosure of the contract under Clause
13 of the GCC.
39. The breach of contract by the appellant is thus undeniable in
view of the facts and circumstances on record. The circumstances,
therefore, does give rise to a claim under Section 73 of the 1872 Act
in favour of the claimant for loss of profits. The same is distinct from
the damages sought to be quantified by the claimant under Claim No.
5. The Arbitrator has held that the work could not be performed on
account of breach of contract by the employer. However, the learned
Arbitrator did not accept the Company’s plea regarding deployment of
any material on site, including labour.
40. The Arbitrator as well as the court exercising the jurisdiction
under Section 34 of the 1996 Act have rightly excluded such claims
while quantifying the amount of loss of profit and limited the amount
of loss of profit only to the extent of 3.75% of the net contract amount
19
(4,03,44,539/- Rupees four crores three lakhs forty four thousand
five hundred and thirty nine only) quantified at Rs. 12,85,982/-
(Rupees Twelve lakhs eight five thousand nine hundred eighty two
only) as a reasonable profit.
41. We are in agreement with the submission of the learned
counsel for the Company that the employer has not challenged the
award of the arbitrator on any of the grounds, available for
challenging an award as contemplated in Sections 34(2) or (2-A) of
the 1996 Act. No ground whatsoever has been raised under Section
34 which is obvious from a bare reading of the application filed under
Section 34 of the 1996 Act, raising a limited challenge to the award in
respect to Claim No. 4.
42. The said award therefore in respect Claim No. 4 is quantified by
the arbitrator acting on the basis of the net contract amount and
calculating the percentage on loss of profits as 3.75% component
above the net contract amount. It has excluded the remaining
margin over and above the net contract amount also implicit within
the 15% margin over and above the net contract amount as found in
Clause 2(x) of schedule F of the contract, which reads as follows:-
“ 2 (x) Percentage on cost of materials and
Labour to cover all overheads and profits 15%”
43. Thus, it cannot be said that the arbitrator has arrived at the
quantification in respect of loss of profits arbitrarily or in a whimsical
20
manner. The approach appears to be bonafide, fair and reasonable
without being actuated by any extraneous consideration. In the
circumstances the court exercising jurisdiction under Section 34 of
1996 Act, has rightly not substituted its own opinion by interfering
with the award in this regard. Insofar as the Claim No. 5 regarding
damages, the conclusion of the arbitrator in this regard was rightly
based on an assessment of parameters relevant to damages since the
damages was claimed due to idling of machinery, tools and plants
and site overhead expenses for entire period. This claim also included
expenditure over procurement of man power. The arbitrator has thus
rightly concluded that since the site had never been handed over and
work never commenced, the damages or loss claimed on account of
idling of man power, machinery or expenses incurred over them
without any materials in support thereof, could not be accepted.
44. We therefore are not inclined to accept the submission of the
learned counsel for the appellant that the Claim No. 4 under the
heading loss of profit could not have been allowed since the arbitrator
had rejected the Claim No. 5 for damages. In view of the above
discussion, we find the nature of the two claims to be distinct and
based on different parameters, in the present facts and
circumstances as emanating from the records.
45. In view of the facts and materials on record, we find that there
is no scope for the appellant to rely upon the decision of the Apex
21
Court in the case of Batliboi Environmental Engineers Limited
(supra) even though the legal proposition in the said judgment is
undeniable and is binding upon this court.
46. In the case before the Apex Court, it is apparent that there was
no basis for quantification and the judgment was passed in a set of
facts and circumstances where there was manifest lack of reasoning
in arriving at the conclusion and the calculation of the amount
awarded by the arbitrator. In the case of Batliboi Environmental
Engineers Limited (supra), the Apex Court has found the decision to
award loss of overheads and loss of profit/profitable, and its
quantification to be unsustainable as observed by Apex Court in
paragraph 28 of the judgment, which reads as follows:-
“28. The Arbitral tribunal in the present case has given complete go by
to these principles well in place, overlooked care and caution required
and taken a one-sided view grossly and abnormally inflated the
damages. The figures quoted in paragraph 11 supra show the
overstatement and aggrandizement in awarding Rs. 1,57,37,666/-,
towards loss of overheads and loss of profits/profitability, in a
contract of Rs. 5,74,35,213/-. Rs.1,21,95,859.68/- was paid for the
work done within the term. Rs. 2,92,07,619.13 was paid for the work
done post the term. Thus, Rs. 4,14,03,478.81/- was paid for 80% of
the work. The balance was Rs.1,14,87,042.00/. The amount awarded
towards loss of overheads and profits/profitability is Rs.1,57,37,666/-
. No justification for computation of the loss is elucidated or can be
expounded. Even if one were to rely upon the chart given by the BEEL,
and ignore the contradictions in findings, the amount awarded is
highly disproportionate and exorbitant. It is clearly a case of
overlapping or at least a part doubling of the loss/damages.”
47. The present case is however different in facts and
circumstances. As we have noted hereinabove, the award in respect
of loss of profit is after arriving at a conclusion regarding breach of
22
contract by the employer, which we find to be sustainable. The
quantification also is after meticulous examination of the tender
amount, the net contract amount, the margin in between the net
contract amount and the tender amount and the various components
of margin within the 15% margin between the net contract amount
and the tender amount. Out of this 15%, the arbitrator has found the
rd
award of 1/3 , i.e, 3.75% to be a reasonable quantification. In our
opinion the same requires no interference.
48. From decision of the Apex Court in the case of Batliboi
Environmental Engineers Limited (supra), we find that the extent
of a “second look by the courts under Section 34” of the 1996 Act has
been considered in paragraphs 31 and 32:-
“31. The scope and ambit of the court’s power to review the
awards under Section 34 of the A&C Act has been contentious
viz., on the interpretation to the expression ‘in conflict with the
public policy of India’. There have been legislative interventions
as well as judicial pronouncements. In the context of the present
case, we are required to interpret the provisions as they existed
on the date on which the objections to the award were filed i.e.,
on 21.06.1999. Accordingly, the amendment introduced to
Section 34 of the A&C Act vide Act No. 3 of 2016 with
retrospective effect from 23.10.2015 and the judgments of this
Court examining the amended Section 34 of the A&C Act need
not be examined.
32. Post award interference and the extent of the second look
by the courts under Section 34 of the A&C Act has been a
subject matter of perennial parley. The foundation of arbitration
is party autonomy. Parties have the freedom to enter into an
agreement to settle their disputes/claims by an arbitral
tribunal, whose decision is binding on the parties. It is argued
that the purpose of arbitration is fast and quick one-stop
adjudication as an alternative to court adjudication, and
therefore, post award interference by the courts is unwarranted,
and an anathema that undermines the fundamental edifice of
arbitration, which is consensual and voluntary departure from
23
the right of a party to have its claim or dispute adjudicated by
the judiciary. The process is informal, and need not be
legalistic. Per contra, it is argued that party autonomy should
not be treated as an absolute defence, as a party despite
agreeing to refer the disputes/claims to a private tribunal
consensually, does not barter away the constitutional and basic
human right to have a fair and just resolution of the disputes.
The court must exercise its powers when the award is unfair,
arbitrary, perverse, or otherwise infirm in law. While arbitration
is a private form of dispute resolution, the conduct of arbitral
proceedings must meet the juristic requirements of due process
and procedural fairness and reasonableness, to achieve a
‘judicially’ sound and objective outcome. If these requirements,
which are equally fundamental to all forms of adjudication
including arbitration, are not sufficiently accommodated in the
arbitral proceedings and the outcome is marred, then the award
should invite intervention by the court.”
49. At this juncture the learned advocate for the Company
submitted that several similar tenders were issued for construction of
Dykes/humes etc. after 2004 Tsunami. The modus adopted by the
petitioner/appellant in the present case for invoking Clause 3A of the
GCC to foreclose the contract after failing to hand over the site in
question for carrying out the tender works, and the terms and
conditions of contract were also identical in the works allotted to the
tenderers, including M/s S. Bose. The claim of M/s S. Bose was also
allowed by the learned Arbitrator.
50. The question which arose for the consideration in the present
case before the learned Arbitrator are one and the same, as arose for
the consideration in the case of Executive Engineer, CD-III, APWD
Department, Andaman and Nicobar Administration vs. M/s S.
Bose and others in FMAT(ABAWARD)/2/2024 wherein a Coordinate
bench refused to interfere with the award of the sole Arbitrator and
24
the order passed by the Court considering the appeal under Section
34 of the 1996 Act.
51. The learned advocate for the appellant is not in a position to
draw any points of distinction between the present case and the case
of M/s S. Bose and others (supra). The present Company therefore,
in our opinion is entitled to benefit of the judgment in the case of M/s
S. Bose , which applied to the facts and circumstances of the present
case.
52. We are further informed that the judgment of the Coordinate
bench in the case of M/s S. Bose & others (supra) in
FMAT(ABAWARD)/2/2024 was assailed by the appellant before the
Hon’ble Apex Court in Special Leave Petition (Civil) Diary No.
32663/2025. The SLP was dismissed on 08.09.2025.
53. We do not find the award of the arbitrator to be suffering from
any lack of reasoning, absence of any material in support of the
claim, or any infirmity in the above noted facts and circumstances, to
arrive at a conclusion regarding the amount to be quantified towards
loss of profit. We therefore find no reason to interfere with the award
of the sole arbitrator or the order passed by the Court considering the
appeal under Section 34 of the 1996 Act.
54. The appeal is accordingly dismissed.
55. Any application pending stands disposed of.
25
56. All parties are directed to act on a server copy of this order duly
downloaded from the official website of this Court.
( Madhuresh Prasad, J. )
I agree.
( Prasenjit Biswas, J. )