Raghuveer Singh Chaudhary vs Gwalior Deveopment Authority

Court
Madhya Pradesh High Court

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
1 WP-2124-2008
IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR

BEFORE
HON'BLE SHRI JUSTICE MILIND RAMESH PHADKE
WRIT PETITION No. 2124 of 2008
CNR No.: MPHC030077832008
RAGHUVEER SINGH CHAUDHARY
Versus
GWALIOR DEVEOPMENT AUTHORITY AND OTHERS
Appearance:
Shri Anand Vinod Bhardwaj - Advocate for the petitioner.
Shri Raghvendra Dixit - Advocate for respondent No.1/Gwalior
Development Authority, Gwalior.
Shri J.S. Kaurav - Advocate for respondent No.2/Nehru Grah Nirman
Sahakari Samiti.
RESERVED ON :- 07/10/2026
DELIVERED ON :- 14/10/2026
ORDER
The present petition under Article 226 of the Constitution of India has
been preferred seeking, inter alia, a direction to respondent No.1-Gwalior
Development Authority (GDA) to grant permission for construction and/or
issue a No Objection Certificate in favour of the petitioner in respect of Plot
No.351 situated in City Centre Aavasiya Yojna, Gwalior. The petitioner haS
also questioned the action of respondent No.1, whereby the allotment of the
aforesaid plot in favour of respondent No.2-Society and the consequential
entries/transaction flowing therefrom were cancelled.
The case of the petitioner is that Plot No.351, situated in City Centre

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
2 WP-2124-2008
Aavasiya Yojna, Gwalior, was allotted by respondent No.1-GDA in favour

of respondent No.2-Nehru Grah Nirman Sahakari Samiti Maryadit, Gwalior.
On the basis of such allotment, respondent No.2-Society executed a sale-
deed dated 17.01.2001 in favour of the petitioner in respect of the said plot.
The petitioner claimed that having acquired the plot through the
aforesaid sale deed, he approached respondent No.1 for obtaining permission
to raise construction and/or for issuance of a No Objection Certificate. His
grievance is that respondent No.1, instead of recognizing the transaction in
his favour, initiated proceedings in relation to the allotment made in favour
of respondent No.2-Society and ultimately, cancelled the said allotment.
The record indicates that respondent No.1 had issued letters dated
19.01.2000 and 16.08.2000 in respect of certain plots, including Plot
Nos.340, 341, 351 and 352, in favour of respondent No.2-Society.
Subsequently, the matter was reconsidered by the Board of the GDA in its
meeting dated 14.08.2001. A show-cause notice dated 07.09.2001 was
issued, to which a reply was submitted, and thereafter the allotment made
pursuant to the aforesaid letters was cancelled by order dated 31.10.2001.
The dispute essentially arose from the question whether respondent
No.2-Society had any subsisting right under the earlier arrangement with the
erstwhile Town Improvement Trust, which could validly extend to allotment
of Plot No.351 situated in the City Centre Residential Scheme and,
consequently, whether the petitioner, claiming through the Society, can
compel respondent No.1 to recognize his transaction and issue a No
Objection Certificate.

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
3 WP-2124-2008
Learned counsel for the petitioner submitted that the petitioner is a

bona fide purchaser for consideration and the sale deed dated 17.01.2001 was
executed by respondent No.2-Society after Plot No.351 had been allotted in
favour of the Society by respondent No.1. It was further contended that the
petitioner cannot be made to suffer on account of a subsequent decision of
respondent No.1 to cancel the allotment, particularly when the transaction in
his favour had already taken place.
It was further submitted that the arrangement between the Society and
the erstwhile Town Improvement Trust contemplated development of the
plots and the petitioner, having derived his right through the Society, is
entitled to obtain permission for construction and/or the requisite No
Objection Certificate.
Learned counsel also submitted that before taking the decision
cancelling the allotment, the petitioner was not afforded a proper and
effective opportunity of hearing and the impugned action was consequently
violative of the principles of natural justice. The petitioner had acquired the
plot through a registered sale deed dated 17.01.2001 and, therefore, any
action adversely affecting his rights could not have been taken without
affording him a reasonable opportunity of hearing.
Per contra, learned counsel for respondent No.1-GDA submitted that
the agreement dated 01.09.1967 relied upon by the petitioner and the Society
related specifically to the Gandhi Road Scheme 2-B/3-B and didn't confer
upon respondent No.2-Society any right to seek allotment of plots from the
City Centre Residential Scheme.

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
4 WP-2124-2008
It was further contended that the role of the erstwhile Town

Improvement Trust under the said agreement was confined to development
of the land covered by the particular arrangement in accordance with the
approved layout and recovery of development charges. The agreement did
not create any independent right in favour of the Society to claim plots
belonging to the Authority under another housing scheme.
It was next submitted that the subsequent allotment of Plot No.351,
along with other plots, was reconsidered by the competent authority and was
cancelled by order dated 31.10.2001. Consequently, the Society could not
confer upon the petitioner any better or subsisting right against the GDA on
the basis of the sale deed dated 17.01.2001.
Learned counsel for respondent No.2-Society supportted the
transaction in favour of the petitioner and submitted that the plots allotted in
the year 2000 were alternative plots, as certain plots covered by the earlier
arrangement were not available at the site. It was contended that the Society
had accordingly requested allotment of alternative plots and, pursuant
thereto, Plot No.351 and other plots were allotted by respondent No.1.
Heard counsel for the parties and perued the record.
The controversy essentially turns upon the nature and scope of the
agreement dated 01.09.1967, the subsequent allotment of Plot No.351 in
favour of respondent No.2-Society, and the effect of the subsequent
cancellation of such allotment upon the rights claimed by the petitioner on
the basis of the sale deed dated 17.01.2001.
The agreement dated 01.09.1967, placed on record as Annexure R-1/3,

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
5 WP-2124-2008
was entered into between the erstwhile Town Improvement Trust, Gwalior

and respondent No.2-Society in relation to the Gandhi Road Scheme 2-B/3-
B. A reading of the agreement makes it clear that the arrangement was
essentially concerned with development of the land covered by the said
scheme. The erstwhile Town Improvement Trust was required to undertake
the development works in accordance with the approved layout and the
Society was required to pay the requisite development charges. The
developed plots falling within the area covered by the arrangement were
thereafter to be made available to the Society for allotment to its members.
Thus, the obligation of the erstwhile Town Improvement Trust, and
consequently of respondent No.1-GDA, flowing from the said agreement
was with respect to development of the land covered by that particular
arrangement. The agreement does not contain any stipulation under which
respondent No.2-Society acquired an independent or vested right to demand
allotment of plots from any other scheme of the Authority.
This aspect assumes significance because the plot involved in the
present petition, namely Plot No.351, is situated in the City Centre Aavasiya
Yojna, whereas the agreement dated 01.09.1967 relates to the Gandhi Road
Scheme 2-B/3-B. No material has been brought on record by the petitioner to
demonstrate that the said agreement was subsequently extended to the City
Centre Residential Scheme or any independent agreement was executed
between respondent No.1 and respondent No.2 conferring upon the Society a
contractual right to obtain Plot No.351.
The stand taken by respondent No.2-Society itself indicates that the

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
6 WP-2124-2008
claim over the City Centre plots arose subsequently. According to the

Society, certain plots covered by the earlier arrangement were not available
at the spot and, therefore, it approached respondent No.1 by letter dated
03.08.1999 seeking alternative plots. Pursuant thereto, respondent No.1
issued letters dated 19.01.2000 and 16.08.2000 in respect of Plot Nos.340,
341, 351 and 352. Thus, even according to respondent No.2, the claim to Plot
No.351 was founded upon the subsequent allotment made by respondent
No.1 and not upon any direct entitlement flowing from the agreement dated
01.09.1967.
The subsequent allotment, however, did not remain operative. The
Board of respondent No.1 considered the matter in its meeting dated
14.08.2001. Thereafter, a show-cause notice dated 07.09.2001 was issued in
relation to the proposed cancellation. The record further shows that a reply
was submitted on behalf of the petitioner on 19.09.2001. The matter was
thereafter concluded by order dated 31.10.2001, whereby the allotment made
pursuant to the letters dated 19.01.2000 and 16.08.2000 was cancelled.
Learned counsel for the petitioner has specifically contended that the
petitioner was not afforded an adequate and effective opportunity of hearing
before the allotment was cancelled and the action of respondent No.1 was
consequently vitiated by violation of the principles of natural justice. The
said submission has been considered.
The material available on record, however, does not establish a case of
complete denial of opportunity of hearing. A show-cause notice dated
07.09.2001 was issued and the petitioner submitted his reply thereto on

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
7 WP-2124-2008
19.09.2001. Thus, the petitioner was put to notice of the proposed action and

was afforded an opportunity to place his objections before the authority. The
fact that the ultimate decision was adverse to the petitioner, by itself, cannot
be treated as denial of opportunity of hearing. No sufficient material has been
brought on record to establish that the petitioner was prevented from
submitting his objections or the decision was taken behind his back without
considering the response submitted by him.
The Court is, therefore, unable to accept the plea that the impugned
action is liable to be set aside merely on the ground of complete denial of
opportunity of hearing.
The more fundamental difficulty in the petitioner's case, however, lies
elsewhere. The petitioner derives his claim through respondent No.2-Society.
The sale deed dated 17.01.2001 was executed by the Society in favour of the
petitioner after the allotment of Plot No.351 by respondent No.1, but before
the subsequent cancellation dated 31.10.2001. The petitioner has not been
able to demonstrate any independent source of title or statutory or
contractual right against respondent No.1 apart from the right claimed
through the Society.
The sale deed was executed by respondent No.2-Society and not by
respondent No.1-GDA. Consequently, the petitioner cannot, merely on the
strength of a transaction to which respondent No.1 was not a party, seek a
writ compelling the GDA to recognize the transaction and issue a No
Objection Certificate or construction permission, particularly when the
allotment from which the Society itself claimed its right was subsequently

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
8 WP-2124-2008
cancelled.

It is well settled that a writ of mandamus presupposes the existence of
a subsisting legal right in favour of the petitioner and a corresponding legal
or public duty upon the respondent. In the present case, no provision of the
agreement dated 01.09.1967, nor any other statutory or contractual provision
brought on record, establishes a continuing obligation upon respondent No.1
to issue a No Objection Certificate or construction permission in favour of
the petitioner in respect of Plot No.351 after cancellation of the allotment in
favour of respondent No.2.
This Court is also not required, in the present writ proceedings, to
finally determine the inter se rights of the petitioner and respondent No.2-
Society arising out of the sale deed dated 17.01.2001. Whether the Society
possessed a transferable and marketable right in Plot No.351 at the time of
execution of the sale deed, whether the Society was competent to transfer the
plot to the petitioner, and what consequences follow from the subsequent
cancellation of the allotment are questions which concern the rights and
liabilities arising between the petitioner and the Society. Such questions, if
required to be adjudicated on the basis of evidence, are appropriately left
open for consideration by the competent forum in proceedings otherwise
maintainable in law.
There is also considerable delay in approaching this Court. The
cancellation order was passed on 31.10.2001, whereas the present writ
petition was instituted only on 07.05.2008, after a lapse of nearly seven
years. Significantly, the petitioner was aware of the proceedings preceding

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
9 WP-2124-2008
the cancellation and had submitted his reply to the show-cause notice.

Despite such knowledge, he did not challenge the action of respondent No.1
for several years. No satisfactory explanation for this prolonged delay has
been demonstrated.
Though delay and laches do not constitute an absolute bar to the
exercise of jurisdiction under Article 226 of the Constitution, they are highly
relevant while exercising the discretionary and equitable jurisdiction of the
Court. In the present facts, the unexplained delay assumes greater
significance because the relief sought by the petitioner is not merely
declaratory in nature but seeks a positive direction against a public authority
to recognize a transaction and permit construction on the basis of an
allotment which had already been cancelled.
The Court also cannot overlook that the petitioner seeks, in substance,
enforcement against respondent No.1 of a right claimed through respondent
No.2-Society. The GDA was not the executant of the sale deed dated
17.01.2001. Therefore, any grievance arising out of the petitioner's purchase,
including any loss allegedly suffered by him on account of the subsequent
cancellation of the Society's allotment, cannot by itself create a public or
statutory duty upon the GDA which can be enforced through a writ of
mandamus.
In these circumstances, this Court finds that the petitioner has failed to
establish a subsisting enforceable legal right against respondent No.1 in
respect of Plot No.351. The agreement dated 01.09.1967 cannot be construed
as the source of such a right, as it relates to the Gandhi Road Scheme 2-B/3-

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
10 WP-2124-2008
B and does not govern the City Centre Residential Scheme. No separate

agreement or other legally enforceable instrument conferring upon
respondent No.2 an entitlement to Plot No.351 has been brought on record.
The subsequent allotment in favour of the Society was cancelled before the
present petition was instituted, and the petitioner has not established any
independent right against the GDA surviving such cancellation.
For the foregoing reasons, this Court is of the considered view that the
petitioner has failed to establish any legal right against respondent No.1-
Gwalior Development Authority corresponding to a legal or statutory duty
on its part to issue a No Objection Certificate or grant permission for
construction over Plot No.351, City Centre Aavasiya Yojna, Gwalior.
The plea of violation of principles of natural justice also does not merit
acceptance, since the record demonstrates that a show-cause notice was
issued to the petitioner and a reply was submitted before the cancellation
order was passed. The petitioner has further approached this Court after an
unexplained lapse of nearly seven years from the date of cancellation, which
is an additional circumstance weighing against exercise of the discretionary
jurisdiction under Article 226 of the Constitution.
Consequently, no case is made out for issuance of a writ of mandamus
directing respondent No.1 to recognize the petitioner's transaction with
respondent No.2-Society or to issue a No Objection Certificate/construction
permission on that basis. The relief sought by the petitioner, therefore, cannot
be granted.
Accordingly, the writ petition is dismissed. It is, however, clarified that

NEUTRAL CITATION NO. 2026:MPHC-GWL:30885
11 WP-2124-2008
this Court has not expressed any final opinion on the validity, enforceability

or legal consequences of the sale deed dated 17.01.2001 executed by
respondent No.2-Society in favour of the petitioner. This Court has also not
adjudicated upon any independent civil or other legal right which the
petitioner may have against respondent No.2-Society or any other person
arising out of the said transaction.
The petitioner shall, therefore, be at liberty to avail such remedy as
may be available to him against the concerned Society or any other person in
accordance with law. If any such proceedings are initiated, the competent
forum shall consider the same independently, on its own merits and strictly
in accordance with law, without being influenced by any observation made
in the present order.
Needless to observe, all questions relating to maintainability,
limitation, delay, jurisdiction and merits shall remain open for consideration
by the competent forum.
No order as to costs.
(MILIND RAMESH PHADKE)
JUDGE
PAWAN
KUMAR
pwn*

Digitally signed by PAWAN KUMAR DN: c=IN, o=HIGH COURT OF MADHYA PRADESH BENCH AT
GWALIOR, 2.5.4.20=b864d1ab4ace2215bfcf3ab301c34d631287f1b1cdd90b4a
49f265f02d9d593f, ou=HIGH COURT OF MADHYA PRADESH BENCH AT GWALIOR,CID - 7064434, postalCode=474001, st=Madhya
Pradesh, serialNumber=61b9d129971d2ea4fd4455ed49ea436ea65e26164be
eed89153191c56e98ce21, cn=PAWAN KUMAR Date: 2026.10.15 11:02:09 +05'30'