M/S Slr Construction Pvt Ltd vs Gail India Ltd And Anr

Court
Delhi High Court

$~45
* IN THE HIGH COURT OF DELHI AT NEW DELHI
rd
Date of decision: 23 APRIL, 2026
IN THE MATTER OF:
+ O.M.P.(I) (COMM.) 173/2026
M/S SLR CONSTRUCTION PVT LTD .....Petitioner
Through: Mr. Rajesh Mohan Sinha, Mr.
Prateek Mohan Sinha, Ms. Namita
Sinha, Ms. Nandini Harsh, Mr.
Krishnendu Das, Advs.

versus

GAIL INDIA LTD AND ANR .....Respondents
Through: Mr. Deepayan Mandal, Mr. Mridul
Bansal, Mr. Naman Varma, Mr.
Aryan Ahmed, Advs. for GAIL

CORAM:
HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
JUDGMENT (ORAL)
I.A. 11120/2026 (Exemption)
Allowed, subject to all just exceptions.
O.M.P.(I) (COMM.) 173/2026
1. The present Petition under Section 9 of the Arbitration and
Conciliation Act, 1996 has been filed by the Petitioner principally for
securing and releasing the Petitioner’s admitted dues of Rs.2.08 crore;
protection against unlawful cross-recoveries; securing/release of retained
and guarantee amounts; and interim safeguarding of the larger arbitral claim
before commencement of arbitration under the dispute resolution clauses
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 1 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

contained in the contract entered into between the Petitioner and the
Respondent.
2. The present Petition arises out of a long chain of contractual disputes,
payment certification disputes, attempted cross-recoveries, and continued
withholding of admitted dues by GAIL, all rooted in the Terminal Station
Works (Part-E), Gorakhpur, under the Auraiya-Phulpur and Gorakhpur Spur
Lines of the Phulpur-Haldia Pipeline Phase-I Project.
3. The genesis of the dispute traces back to 15.06.2017, when GAIL
floated E-Tender No. 8000010840 for construction of four Sectionalizing
Valve terminals (SV-5G, SV-6G, SV-7G and SV-8G) along with a
Receiving Terminal at RT-HURL Gorakhpur. It is stated that the Petitioner
participated in the aforesaid tender and emerged as the successful bidder.
The Petitioner was awarded the Letter of Acceptance dated 28.05.2018. It is
stated that the work was to be completed within a period of eight months,
i.e. on or before 27.08.2018. However, it is stated that from inception the
project was plagued by serious impediments, including non-availability of
encumbrance-free sites despite, restricted access, waterlogging, pipeline
interferences, delayed drawings and interdependent delays attributable to the
larger integrated pipeline project. It is stated that the terminal works were
never standalone works capable of completion within eight months but were
intrinsically linked to the phased execution of the 165 km spur pipeline
project.
4. It is stated that as execution progressed, the project timeline kept
extending alongside the parent pipeline network. It is stated that the Gas
supply under the network commenced on 06.11.2020, the integrated project
was dedicated to the nation on 07.12.2021, and the RT-HURL terminal
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 2 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

operations commenced on 08.12.2021. Material on record indicates that
though valid extensions were granted up to 28.02.2022, and later up to
30.11.2022, disputes began surfacing regarding delayed processing of
rd
Running Account (RA) bills, especially the 23 RA Bill amounting to
approximately Rs.1.44 crores, allegedly withheld on pretexts of time
extension issues and arbitrary deductions by the Operations and
Maintenance team of the Respondent at Gorakhpur. The petitioner alleges
that from January 2022 onward, Respondent imposed obligations beyond
contractual scope, withheld payments through heavy retentions, and
continued to interfere with bill processing, causing severe financial
prejudice to the Petitioner. It is stated that the subject work was ultimately
recorded as completed on 30.11.2022, while the Defect Liability Period
expired on 29.11.2023. It is the case of the Petitioner that despite contractual
completion and commercial use of the assets, legitimate dues were not
released to the Petitioner and even the Performance Security of
Rs.54,03,960/- was encashed on 30.12.2024.
th
5. It is stated that on 14.02.2024, when the Petitioner raised its 24 and
Final Bill for Rs.4.32 crores, which was certified by the Project
Management Consultant (PMC), M/s MECON, on 25.02.2025 for a
cumulative contract value of approximately Rs.15.04 crores (excluding
GST), determining immediate payable amount of Rs.2,74,22,708.41/- apart
from retentions. It is stated that a Provisional Completion Certificate was
simultaneously issued by the GAIL. It is stated that the GAIL itself
acknowledged liability of the Petitioner by deducting TDS of Rs.3,89,219/-
on 31.03.2025, which, according to the Petitioner, is a recognition of
payable dues by GAIL. It is stated that instead of paying the certified
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 3 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

amount, GAIL withheld the said amount by linking it to disputes in other
separate contracts (DDPL Part-A and Part-B), which, according to the
Petitioner, had nothing to do with the contract in question. It is stated that
DDPL Part-A and Part-B contracts were terminated by the GAIL by issuing
letters dated 20.03.2025 and 22.03.2025, and an attempt was made by GAIL
to recover the alleged losses from those contracts by adjusting them against
money payable in the present contract.
6. Aggrieved by this, the petitioner approached this Court by filing a
Petition, being O.M.P.(I)(COMM.) 191/2025, under Section 9 of the
Arbitration Act. The said Petition was disposed of on 23.05.2025 on the
undertaking furnished by GAIL that no recovery would be made from other
contracts of the Petitioner. It is stated that relying on that undertaking, the
petitioner sought reprocessing of its certified final RA bill through letter
dated 20.07.2025, whereafter PMC, M/s MECON re-endorsed the bill on
06.08.2025 and issued a revised Provisional Completion Certificate. It is
stated that although a revised payable figure of Rs.2,61,18,840.17/- was
initially reflected, an arbitrary deduction of Rs.53,82,187.60/- was allegedly
imposed on the Petitioner the very same day by the Engineer-in-Charge,
resulting in a net certified and admitted payable sum of Rs.2,08,07,652.57/-,
while substantial retentions were kept pending.
7. It is stated that the said amount has yet not been released by the
Respondent despite the Respondent availing GST input credit on the same.
The Petitioner has, therefore, filed the present petition seeking interim
protection and release of admitted amounts before commencement of
arbitration under the contract.
8. It is the case of the Petitioner that the amount of Rs.2,08,07,652.57/-
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 4 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

has been unduly and unjustifiably withheld by the Respondent/GAIL and the
said amount must be released.
9. Section 9 of the Arbitration and Conciliation Act, under which the
present Petition has been filed, is reproduced hereinbelow and the same
reads as under:
“ Section 9 — Interim measures, etc. by Court

(1) A party may, before, or during arbitral proceedings
or at any time after the making of the arbitral award
but before it is enforced in accordance with section 36,
apply to a Court—

(i) for the appointment of a guardian for a minor
or person of unsound mind for the purposes of
arbitral proceedings; or

(ii) for an interim measure of protection in respect
of any of the following matters, namely:—

(a) the preservation, interim custody or sale
of any goods which are the subject-matter of
the arbitration agreement;

(b) securing the amount in dispute in the
arbitration;

(c) the detention, preservation or inspection
of any property or thing which is the subject-
matter of the dispute in arbitration, or as to
which any question may arise therein and
authorising for any of the aforesaid purposes
any person to enter upon any land or
building in the possession of any party, or
authorising any samples to be taken or any
observation to be made, or experiment to be
tried, which may be necessary or expedient
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 5 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

for the purpose of obtaining full information
or evidence;

(d) interim injunction or the appointment of
a receiver;

(e) such other interim measure of protection
as may appear to the Court to be just and
convenient, and the Court shall have the
same power for making orders as it has for
the purpose of, and in relation to, any
proceedings before it.

(2) Where, before the commencement of arbitral
proceedings, a Court passes an order for any interim
measure of protection under sub-section (1), the
arbitral proceedings shall be commenced within a
period of ninety days from the date of such order or
within such further time as the Court may determine.

(3) Once the arbitral tribunal has been constituted, the
Court shall not entertain an application under sub-
section (1), unless the Court finds that circumstances
exist which may not render the remedy provided under
section 17 efficacious. ”

10. In the opinion of this Court, the relief sought in the present petition
does not warrant exercise of jurisdiction under Section 9 of the Arbitration
and Conciliation Act, 1996. Though the Petitioner seeks to characterize the
prayer as one for securing the amount in dispute, the substance of the
petition is for release/payment of alleged contractual dues. Section 9 of the
Arbitration Act is intended for interim measures of protection and not as a
substitute for adjudication of monetary claims or for granting final monetary
relief at a preliminary stage. The disputes raised by the Petitioner as to
Signature Not Verified
O.M.P.(I) (COMM.) 173/2026 Page 6 of 7

Signed By:RAHUL
SINGH
Signing Date:12.05.2026
20:25:28

wrongful withholding, deductions, retentions and alleged cross-adjustments
require adjudication in accordance with the dispute resolution mechanism
agreed between the parties.
11. No material has been placed before this Court to demonstrate any
exceptional circumstance justifying an order securing the amount claimed,
such as any imminent dissipation of assets, frustration of the arbitral remedy,
or circumstances rendering the eventual arbitral award incapable of
enforcement. In the absence of such circumstances, a mere claim for
payment of contractual dues cannot be converted into proceedings under
Section 9. The Petitioner must first invoke the dispute resolution clause
under the contract and pursue appropriate arbitral remedies in accordance
with law.
12. This Court is, therefore, not inclined to grant the relief prayed for
under Section 9.
13. The Petition is accordingly dismissed, leaving it open to the Petitioner
to invoke arbitration and avail such remedies as may be available in law.
Pending applications, if any, also stand dismissed.


SUBRAMONIUM PRASAD, J
APRIL 23, 2026