Steag Energy Services (India) Pvt. Ltd. vs Gspc Pipavav Power Company Ltd. (Gppc)

Court
Supreme Court
<div> 2026 INSC 295<br /> REPORTABLE <br /> IN THE SUPREME COURT OF INDIA <br /> CIVIL APPELLATE JURISDICTION <br /> <br /> <b>CIVIL APPEAL NO(S). OF 2026 </b><br /> <b>ARISING OUT OF SLP (C) NO(S). 30209-30210 OF 2025 </b><br /> <b> </b><br /> <b>M/S. STEAG ENERGY SERVICES </b><br /> <b>(INDIA) PVT. LTD. </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b>…APPELLANT(S) </b><br /> <b> </b><br /> <b>VERSUS </b><br /> <b> </b><br /> <b>GSPC PIPAVAV POWER COMPANY LTD. </b><br /> <b>(GPPC) &amp; ORS. </b> <b> </b> <b> </b> <b> </b> <b> </b> <b> </b> <b>…RESPONDENT(S) </b><br /> <b> </b><br /> <b>J U D G M E N T </b><br /> <b> </b><br /> 1. Leave granted. <br /> 2. These appeals arise out of the judgment and order passed by the <br /> High Court of Gujarat at Ahmedabad in Special Civil Application No. 7289 <br /> of 2025 and Special Civil Application No. 12328 of 2025. <br /> 3. Facts leading to filing of these appeals lie in a narrow compass. The <br /> first respondent GSPC PIPVAV Power Company Limited, (hereinafter <br /> referred to as GPPC) commissioned in the year 2013-2014 a gas based <br /> combined cycle power plant of 702.86 MW. In January 2025, GPPC <br /> floated a public tender inviting bids for operation and maintenance of the <br /> combined cycle power plants for an initial period of 5 years. <br /> Signature Not Verified<br /> Digitally signed by<br /> Jayant Kumar Arora<br /> Date: 2026.03.25<br /> 17:46:49 IST<br /> Reason:<br /> Page <b>1</b> of <b>17</b> <br /> <br /><br /> 4. The tender was based on Quality and Cost Building System (QCBS) <br /> in which weightage is given to <i>quality</i> as well as <i>cost</i> for the purpose of <br /> evaluation and grant of tender. Quality quotient would consider the <br /> technical strength/evaluation of the bidders wherein the financial <br /> capability of the bidder is taken into account as per the tender terms. The <br /> cost quotient considers the cost of the owner for hiring i.e. the financial bid <br /> submitted by the bidder. The weightage is 70% to the technical evaluation <br /> and 30% to the cost evaluation. The terms of the tender relating to <br /> evaluation of bids and award of contract is contained in clause 20.2 of the <br /> tender document. <br /> 5. It is necessary to reproduce clause 20 to the extent that it is relevant <br /> for our consideration: <br /> <i>“20.0 EVALUATION OF BIDS AND AWARD OF CONTRACT </i><br /> <i> </i><br /> <i>20.1 The Contract will be awarded to the competitive responsive </i><br /> <i>Bidder, with most optimized evaluated price, for five years, </i><br /> <i>offering the technically acceptable Bid in conformity with the </i><br /> <i>requirements of this enquiry specification. A responsive Bid is </i><br /> <i>one which accepts all terms and conditions of these </i><br /> <i>specifications and documents without any modifications. A </i><br /> <i>modification is one which affects in any way the prices, quality, </i><br /> <i>quantity of the Works or which limits in any way the </i><br /> <i>responsibilities or liabilities of the Bidder or any rights of the </i><br /> <i>Owner as required in these specifications. The decision of Owner </i><br /> <i>is final in this regard. </i><br /> <i> </i><br /> <i>20.2. i) Evaluation of offer/ proposal shall be done on Quality and </i><br /> <i>Cost Based System (QCBS) wherein the Technical Score i.e. </i><br /> <i>Marks Given During Unpriced Technical Bid Evaluation will be </i><br /> <i>allotted weightage of 70 % and the price proposal will be allotted </i><br /> <i>weightage of 30% as Mentioned below: </i><br /> Page <b>2</b> of <b>17</b> <br /> <br /><br /></div><table><thead><tr><th>S.No.</th><th>Parameter</th><th>Maximum&lt;br&gt;Marks&lt;br&gt;allotted</th><th>Documents to be attached&lt;br&gt;as an evidence to&lt;br&gt;substantiate the claim</th></tr></thead><tbody><tr><td>B</td><td>Technical Experience of&lt;br&gt;the bidder</td><td></td><td></td></tr><tr><td>3</td><td>Experience of planning&lt;br&gt;and supervising of&lt;br&gt;Major Overhaul, HGPI&lt;br&gt;and CI of 1 (one) GT&lt;br&gt;(GAS Turbine of ISO&lt;br&gt;rating more than 100&lt;br&gt;MW.&lt;br&gt;Major Overhaul =&lt;br&gt;maximum 5 marks&lt;br&gt;individual&lt;br&gt;HGPI = maximum 3&lt;br&gt;marks individual&lt;br&gt;CI = maximum 2 marks&lt;br&gt;individual</td><td>10</td><td>Bidder shall submit copy of&lt;br&gt;work orders/execution&lt;br&gt;orders and relevant&lt;br&gt;completion/execution&lt;br&gt;certificate and complete&lt;br&gt;details of work issued by&lt;br&gt;the client duly certified by&lt;br&gt;notary public. Bidder has&lt;br&gt;to submit the details of&lt;br&gt;orders executed in last&lt;br&gt;seven years duly certified&lt;br&gt;by notary public.</td></tr><tr><td>4</td><td>Operation and&lt;br&gt;Maintenance of Sea&lt;br&gt;water system&lt;br&gt;experience for any one&lt;br&gt;plant for a period of 3</td><td>5</td><td>Bidder shall submit copy of&lt;br&gt;work orders/execution&lt;br&gt;orders and relevant&lt;br&gt;completion/execution&lt;br&gt;certificate and complete</td></tr></tbody></table><div><br /> Page <b>3</b> of <b>17</b> <br /> <br /><br /></div><table><thead><tr><th></th><th>years during the last 7&lt;br&gt;years.</th><th></th><th>details of work issued by&lt;br&gt;the client duly certified by&lt;br&gt;notary public. Bidder has&lt;br&gt;to submit the details of&lt;br&gt;orders executed in last&lt;br&gt;seven years duly certified&lt;br&gt;by notary public</th></tr></thead><tbody></tbody></table><div><br /> <i>iii. Bids from all the bidders shall be evaluated and point/mark </i><br /> <i>shall be allocated based on the documents submitted by the </i><br /> <i>bidders. Individual points/marks given for each criteria shall be </i><br /> <i>summed up to arrive at the total score/mark of each bidder. </i><br /> <i> </i><br /> <i>iv. Proposals from bidders who meet the techno-commercial </i><br /> <i>qualification criteria (based on the Bid Evaluation Criteria) as </i><br /> <i>defined in the tender documents and achieve as minimum </i><br /> <i>technical score (St) of 60 marks in the quality technical </i><br /> <i>parameters will be considered for further evaluation. The price </i><br /> <i>bids will only be opened for those bidders who meet the above </i><br /> <i>criteria. </i><br /> <i> </i><br /> <i>v. After opening of priced bids of all qualified bidders, the bidder </i><br /> <i>with the lowest cost (Fm) shall be given financial score (Sf) of </i><br /> <i>100 points. The relative financial score of other bidders shall be </i><br /> <i>computed as per the formulae given above. </i><br /> <i> </i><br /> <i>vi. The total score of the bidder shall be obtained by weighting </i><br /> <i>the combined quality/technical scores and cost scores and </i><br /> <i>adding them as follows. </i><br /> <i> </i> <i> </i> <i>S = (St x Tw) + (Sf x Fw) </i><br /> <i> </i><br /> <i> </i><br /> <i>22.0 Award Criteria </i><br /> <i> </i><br /> <i>22.1 GPPC will award the Contract to the Bidder whose Bid has </i><br /> <i>been determined to be fully responsive to the bidding documents </i><br /> <i>and evaluated as per the Bid evaluation criteria specified in this </i><br /> <i>tender” </i><br /> <br /> 6. On 23.01.2025 a pre-bid meeting was held. The writ petitioner did <br /> not participate in the same. Subsequently, we are informed that the writ <br /> petitioner neither raised any pre-bid queries nor expressed any concern <br /> Page <b>4</b> of <b>17</b> <br /> <br /><br /> about the evaluation method and proceeded to issue the Declaration of <br /> Unconditional Offer (DUO) dated 04.04.2025. <br /> 7. The bid document contemplated a three-stage bid evaluation <br /> namely (i) Preliminary Evaluation of Bid (ii) Evaluation of Technical Bid <br /> and (iii) Pre-Bid. Out of 4 bids that were submitted, 3 bidders qualified. <br /> They are the appellant, O&amp;M Solutions Pvt. Ltd. (hereinafter referred to <br /> as the writ petitioner) and another party. On evaluation while the writ <br /> petitioner got a score of 8 out of 10 marks with respect to technical <br /> experience, the appellant scored 10 out of 10 on this count. Finally, while <br /> the writ petitioner got a total score of 93 out of 100 in the technical <br /> evaluation, the appellant scored 95 of 100. the consultant Fichtner <br /> Consulting Engineers India Private Limited (hereinafter referred to as <br /> Fichtner) also, evaluated the price bid of all 3 technically qualified bidders <br /> as per the price bid evaluation report, in which the writ petitioner got a <br /> score of 95.09989831 and the appellant scored 95.4978453. After <br /> following the evaluation, the appellant was declared as the successful <br /> bidder. <br /> 8. The GPPC was anxious to execute the contract as the existing <br /> terms of contract was coming to an end in June. They felt it was necessary <br /> to award the contract to the successful bidder in a timely manner so that <br /> th<br /> the necessary handover/takeover can take place before 30 of June 2025. <br /> Page <b>5</b> of <b>17</b> <br /> <br /><br /> The tender document itself provided the schedule of mobilisation in <br /> Schedule D so that there could be a gradual and smooth take over and <br /> the new contractor deploys its staff and get acquainted with operation of <br /> plant and machinery for its maintenance. It was felt that for proper <br /> operation and maintenance of the plant and machinery, skilled personnel <br /> must be posted expeditiously so that they acquaint themselves before the <br /> operations commence. <br /> st<br /> 9. The Board of Directors of GPPC in their 81 Board meeting dated <br /> 05.05.2025 resolved to award the contract to the successful bidder, the <br /> appellant herein. GPPC thus issued the LOA on 09.06.2025 to the <br /> appellant. The appellant is also said to have accepted the offer. <br /> 10. At this stage, it may be relevant to refer to clause 20.04 and 20.05 <br /> of the tender document which relates to grant of LOA which is as under: <br /> <i>“ 20.4 Once the contract is awarded, the manpower requirement </i><br /> <i>as agreed shall be considered fixed as proposed in Form AA and </i><br /> <i>considered a guarantee by O&amp;M Contractor that he will fulfil his </i><br /> <i>obligations fully under the contract. No reduction in manpower </i><br /> <i>shall be subsequently allowed any increase manpower becoming </i><br /> <i>necessary by the O&amp;M Contractor to fulfil his obligations shall be </i><br /> <i>at his cost and risk. </i><br /> <i>20.5. After selection, a Letter of Intent (“LOl&quot;) shall be released </i><br /> <i>by the Owner to the selected Bidders. And one week time shall </i><br /> <i>be given for acceptance. Letter of Acceptance (&quot;LOA&quot;) by the </i><br /> <i>Bidder must be submitted within the stipulated period. No delay </i><br /> <i>shall be permitted, and in the event acceptance is not received </i><br /> <i>by stipulated date, the Bid Security of such Bidder shall be </i><br /> <i>appropriated by the Owner as mutually agreed genuine pre-</i><br /> <i>estimated compensation of damage suffered by the Owner on </i><br /> Page <b>6</b> of <b>17</b> <br /> <br /><br /> <i>account thereof, and the next eligible lowest Bidder may be </i><br /> <i>considered.” </i><br /> <i> </i><br /> 11. We are also informed that pursuant to the grant of LOA, the <br /> appellant mobilised its manpower and machinery and took over the plant <br /> and commenced work. Further, on 01.07.2025, even the formal contract <br /> is said to have been executed between GPPC and the appellant. <br /> 12. In the meanwhile, the writ petitioner approached the High Court by <br /> filing a writ petition initially challenging the tender evaluation process as <br /> 1<br /> arbitrary and violative of Article 14 of the Constitution. After GPPC issued <br /> LOA in favour of the appellant, the writ petitioner sought amendment of <br /> 2<br /> the original Prayer by substituting prayer ‘C’ for quashing of the LOA . <br /> <br /> <i>1</i><br /> <i> The petitioner, therefore, prays that – </i><br /> <i>A) Your Lordships be pleased to admit and allow petition; </i><br /> <i>B) Your Lordships may be pleased to issue appropriate writ, order or direction quashing and </i><br /> <i>setting aside the tender evaluation process as being arbitrary, unreasonable, against the Tender </i><br /> <i>and CVC Guidelines as well as being violative of Article 14 of the Constitution of India. </i><br /> <i>C) Your Lordships may be pleased to issue an appropriate writ, order or direction to Respondent </i><br /> <i>NO. 1 to call for a fresh tender removing the financial price restriction and conduct a fresh, fair, </i><br /> <i>and transparent evaluation process as per the Tender and CVC Guidelines. </i><br /> <i>D) In the alternative, issue an appropriate writ, order or direction, to call the evaluation records to </i><br /> <i>ensure that no manipulation has happened in the technical marks scoring after disclosure of </i><br /> <i>the financial proposals. </i><br /> <i>E) Pending Admission, Final hearing and Disposal of this Petition Restrain the Respondent No. 1 </i><br /> <i>and its agents or employees from issuing a Letter of Award (LOA) or entering into any contract </i><br /> <i>with </i> <i>any </i> <i>party </i> <i>pursuant </i> <i>to </i> <i>and </i> <i>pertaining </i> <i>to </i> <i>the </i> <i>impugned </i> <i>Tender </i> <i>No. </i><br /> <i>GPPC/COM/CCPP?O&amp;M/2024-25/12, until the final disposal of this petition. </i><br /> <i>F) Your Lordship may be please to pass any other orders that may be deemed fit and proper, in </i><br /> <i>interest of justice and equity. </i><br /> <i> </i><br /> <i>2</i><br /> <i> C. Your Lordships may be pleased to issue an appropriate writ, order or direction quashing and setting </i><br /> <i>th</i><br /> <i>aside the Letter of Intent/Letter of Award dated 9</i> <i> June 2025 issued to respondent no. 3 i.e. Steag </i><br /> <i>Energy Services (India) Pvt Ltd. by respondent no. 1 i.e. GSPC PIPAVAV Power Company Limited </i><br /> <i>(GPPC) and direct the Respondent No. 1 to issue the LOI to the petitioner as the successful bidder. </i><br /> Page <b>7</b> of <b>17</b> <br /> <br /><br /> 13. Pending disposal of the writ petition, the Court directed GPPC to <br /> have the technical bid re-evaluated by its consultant, Fichtner and submit <br /> a report on the allocation of marks after hearing all the parties. While there <br /> was no stay of the contract executed in favour of the appellant, the Court <br /> ordered that it shall be subject to further orders of the Court. <br /> 14. Pursuant to the directions of the Court, GPPC filed an affidavit, <br /> placing on record the report of the consultant dated 14.08.2025. <br /> Paragraph 2.2.1 of the report submitted by the consultant is as follows: <br /> <i>“ 2.2.1 …STEAG will be allotted 8 marks out of 10 towards item </i><br /> <i>3 of Clause 20.2B. The marks allotted is based on Experience of </i><br /> <i>planning and supervising of two (2) numbers of HGPI and one </i><br /> <i>(1) number of Cl during the period of last seven (7) years i.e. from </i><br /> <i>01.01.2018 to 31.12.2024. The earlier allotted marks to STEAG </i><br /> <i>was 10 and during the re-evaluation it is found that one (1) out of </i><br /> <i>three (3) numbers of HGPI earlier claimed by STEAG is carried </i><br /> <i>out beyond the evaluation period which was not evident in the </i><br /> <i>document earlier submitted by STEAG.” </i><br /> <i> </i><br /> 15. It is evident from the record that the appellant was initially allocated <br /> 10 out of 10 marks for item no. 3 of clause 20.2(1)(B) relatable to <br /> “Experience of Planning and Supervising of Major Overhaul, HGPI and CI <br /> of 1 (one) GT (Gas Turbine of ISO rating more than 100 MW). However, <br /> this marks stood revised to 8 marks. Consequently, the status of the two <br /> competing bidders, the appellant and the writ petitioner, was altered, <br /> resulting in a tie between them. This is because with reduction of 2 marks <br /> Page <b>8</b> of <b>17</b> <br /> <br /><br /> under 20.2(1)(B) the two competing bidders achieved the technical score <br /> of 93. <br /> 16. On the basis of the report submitted by the consultant, the High <br /> Court simply proceeded to evaluate and determine the competing claims <br /> of the appellant and the writ petitioner. For this purpose, the following <br /> comparative chart was reproduced in the High Court order; <br /></div><table><thead><tr><th>S.No</th><th>Bidder&lt;br&gt;Name</th><th>Technical Score&lt;br&gt;(St)</th><th>Price&lt;br&gt;Quoted (F)</th><th>S = (St.Xtw)+(SfXFw)</th></tr></thead><tbody><tr><td>1.</td><td>OMS</td><td>93</td><td>196555668</td><td>95.09989831</td></tr><tr><td>2.</td><td>STEAG</td><td>93</td><td>196569120</td><td>95.0978453</td></tr></tbody></table><div><br /> 17. When the technical score of the appellant and the writ petitioner <br /> stood at 93 each, the High Court examined the prices quoted by the writ <br /> petitioner and the appellant being Rs. 19,65,55,668 and Rs.19,65,69,120 <br /> respectively. Solely based on the marginal difference in the price, the High <br /> Court allowed the writ petition, quashed and set aside the LOA and <br /> contract awarded to the appellant. It directed the GPPC to proceed further <br /> and award the contract to the writ petitioner. For achieving this purpose, <br /> the High Court relied on 20.2 (vi) which provided that “The bidder with the <br /> highest total score (S) shall be considered for award of job.” <br /> 18. The High Court’s decision clearly indicates that there is no <br /> arbitrariness or illegality in the actions taken by the owner “GPPC” or its <br /> Page <b>9</b> of <b>17</b> <br /> <br /><br /> consultant in fact the High Court records that the total score of the writ <br /> petitioner is marginally higher and also that the difference in miniscule. <br /> The relevant portion of the High Court’s Order is as follows: <br /> <i>“47. In the present case, as noted hereinabove, the total score </i><br /> <i>&quot;S&quot; of the petitioner - O &amp; M is marginally higher than that of the </i><br /> <i>respondent No.3, though the difference is minuscule, being </i><br /> <i>95.09989831 as against 95.0978453 i.e. the difference of </i><br /> <i>0.00205301, this Court cannot ignore the conditions of Clause </i><br /> <i>(VI) and validate the contract awarded to the respondent No.3-</i><br /> <i>STEAG. The recitals of the bid document do not permit the </i><br /> <i>course suggested by respondent No.3-STEAG of matching the </i><br /> <i>price bid by reduction.” </i><br /> <br /> 19. Mr. D.V.S. Somayajulu, learned senior counsel appearing on behalf <br /> of the appellant, relied on the decision of this Court in <i>Afcons </i><br /> 3<br /> <i>Infrastructure Ltd. </i> v <i>. Nagpur Metro Rail Corpn. Ltd.</i> to submit that the <br /> High Court committed a serious error in interfering with the decision, <br /> particularly when the difference between the appellant and the writ <br /> petitioner is marginally higher. The relevant portions of this precedent are <br /> as follows: <br /> <i>“11. Recently, in Central Coalfields Ltd. v. SLL-SML (Joint </i><br /> <i>Venture Consortium) [Central Coalfields Ltd. v. SLL-SML (Joint </i><br /> <i>Venture Consortium), (2016) 8 SCC 622 : (2016) 4 SCC (Civ) </i><br /> <i>106 : (2016) 8 Scale 99] it was held by this Court, relying on a </i><br /> <i>host of decisions that the decision-making process of the </i><br /> <i>employer or owner of the project in accepting or rejecting the bid </i><br /> <i>of a tenderer should not be interfered with. Interference is </i><br /> <i>permissible only if the decision-making process is mala fide or is </i><br /> <i>intended to favour someone. Similarly, the decision should not be </i><br /> <i>interfered with unless the decision is so arbitrary or irrational that </i><br /> <i>the Court could say that the decision is one which no responsible </i><br /> <br /> 3<br /> (2016) 16 SCC 818 <br /> Page <b>10</b> of <b>17</b> <br /> <br /><br /> <i>authority acting reasonably and in accordance with law could </i><br /> <i>have reached. In other words, the decision-making process or </i><br /> <i>the decision should be perverse and not merely faulty or incorrect </i><br /> <i>or erroneous. No such extreme case was made out by GYT-TPL </i><br /> <i>JV in the High Court or before us. </i><br /> <i>(…) </i><br /> <i>13. In other words, a mere disagreement with the decision-</i><br /> <i>making process or the decision of the administrative authority is </i><br /> <i>no reason for a constitutional court to interfere. The threshold of </i><br /> <i>mala fides, intention to favour someone or arbitrariness, </i><br /> <i>irrationality or perversity must be met before the constitutional </i><br /> <i>court interferes with the decision-making process or the </i><br /> <i>decision.” </i><br /> <br /> 20. In similar circumstances, while considering the scope of judicial <br /> 4<br /> review, this Court in <i>Montecarlo Ltd.</i> v. <i>NTPC Ltd,</i> expressed a word of <br /> caution emphasising that judicial review should be confined to ensuring <br /> that there is no arbitrariness or mala fide in the process of evaluation. The <br /> relevant portions of the judgement are reproduced below: <br /> “ <i>26. We respectfully concur with the aforesaid statement of law. </i><br /> <i>We have reasons to do so. In the present scenario, tenders are </i><br /> <i>floated and offers are invited for highly complex technical </i><br /> <i>subjects. It requires understanding and appreciation of the nature </i><br /> <i>of work and the purpose it is going to serve. It is common </i><br /> <i>knowledge in the competitive commercial field that technical bids </i><br /> <i>pursuant to the notice inviting tenders are scrutinized by the </i><br /> <i>technical experts and sometimes third party assistance from </i><br /> <i>those unconnected with the owner’s organization is taken. This </i><br /> <i>ensures objectivity. Bidder’s expertise and technical capability </i><br /> <i>and capacity must be assessed by the experts. In the matters of </i><br /> <i>financial assessment, consultants are appointed. It is because to </i><br /> <i>check and ascertain that technical ability and the financial </i><br /> <i>feasibility have sanguinity and are workable and realistic. There </i><br /> <i>is a multi-prong complex approach; highly technical in nature. </i><br /> <i>The tenders where public largesse is put to auction stand on a </i><br /> <i>different compartment. Tender with which we are concerned, is </i><br /> <i>not comparable to any scheme for allotment. This arena which </i><br /> <i>we have referred requires technical expertise. Parameters </i><br /> <br /> 4<br /> (2016) 15 SCC 272 <br /> Page <b>11</b> of <b>17</b> <br /> <br /><br /> <i>applied are different. Its aim is to achieve high degree of </i><br /> <i>perfection in execution and adherence to the time schedule. But, </i><br /> <i>that does not mean, these tenders will escape scrutiny of judicial </i><br /> <i>review. Exercise of power of judicial review would be called for if </i><br /> <i>the approach is arbitrary or malafide or procedure adopted is </i><br /> <i>meant to favour one. The decision making process should clearly </i><br /> <i>show that the said maladies are kept at bay. But where a decision </i><br /> <i>is taken that is manifestly in Page 29 29 consonance with the </i><br /> <i>language of the tender document or subserves the purpose for </i><br /> <i>which the tender is floated, the court should follow the principle </i><br /> <i>of restraint. Technical evaluation or comparison by the court </i><br /> <i>would be impermissible. The principle that is applied to scan and </i><br /> <i>understand an ordinary instrument relatable to contract in other </i><br /> <i>spheres has to be treated differently than interpreting and </i><br /> <i>appreciating tender documents relating to technical works and </i><br /> <i>projects requiring special skills. The owner should be allowed to </i><br /> <i>carry out the purpose and there has to be allowance of free play </i><br /> <i>in the joints.” </i><br /> <i> </i><br /> 21. The emphasis in the above referred decision is on two principles, <br /> the first being the <i>principle of restraint </i> in judicial review of contractual <br /> matters and the second being the <i>freedom of contract </i> permitting <br /> allowance of free play in the joints. <br /> <i> </i><br /> 22. Ms. Meenakshi Arora, learned senior counsel supporting the <br /> decision of the High Court raised an important point that as tender <br /> mandates a maximum and a minimum benchmark within which tenderers <br /> could bid, the difference in the price would naturally be marginal. She <br /> would submit that it is therefore compelling, rather inevitable that <br /> difference in the price of competing bidders will be very less. This is true, <br /> particularly when highly competitive bidding takes place. However, the <br /> judicial <b> </b> solution for such problems arising out of the fierce competition <br /> Page <b>12</b> of <b>17</b> <br /> <br /><br /> between competing bidders is not to be found in the mathematical <br /> precision or application of rigid formulae. While scrutinizing the process <br /> by which evaluation is undertaken, courts must ensure a measure of <br /> reason and integrity so that the action is not fraught by illegality or <br /> arbitrariness. Judicial review must balance justice with flexibility, and this <br /> would require the courts to exercise a nuanced discretion between <br /> multiple outcomes and binary choices. In the process the judicial wisdom <br /> to subserve the purpose and object of the tendering process should not <br /> be lost. Without this approach, it will be difficult to balance certainty in <br /> market with fair play in action, in other words to maintain the equilibrium <br /> between the need for order and quest for justice. <br /> 23. There is yet another point that Ms. Meenakshi Arora raised to <br /> sustain the decision impugned before us, which is that the High Court has <br /> merely applied the contractual condition for selecting the writ petitioner <br /> and no more. Answer to this question again takes us back to the approach <br /> that the judicial review proceeding should adopt while considering highly <br /> 5<br /> competitive bids. In its precedents, this court has emphasized that “using <br /> <br /> 5<br /> <i>Tata Motors Ltd. v. Brihan Mumbai Electric Supply &amp; Transport Undertaking (BEST)</i> , (2023) 19 SCC <br /> 1: <br /> <b> </b><br /> <b>50.</b> (…) In contracts involving technical issues the courts should be even more reluctant because <br /> most of us in Judges&#x27; robes do not have the necessary expertise to adjudicate upon technical issues <br /> beyond our domain. The courts should not use a magnifying glass while scanning the tenders and make <br /> every small mistake appear like a big blunder. In fact, the courts must give “fair play in the joints” to the <br /> government and public sector undertakings in matters of contract. Courts must also not interfere where <br /> Page <b>13</b> of <b>17</b> <br /> <br /><br /> a magnifying glass while scanning the tenders and make every small <br /> mistake appear like a big blunder.” <br /> 24. It is rather strange that in the whole process of judicial Scrutiny the <br /> contesting contractors as well as the Court lost sight of the needs and <br /> requirements of the Owner. It is not uncommon that when judicial review <br /> proceedings are invoked by one or the other parties the entire focus of the <br /> court is in choosing the most eligible party. This enquiry is necessary, <br /> however judicial review courts cannot ignore the needs of the owner(s), <br /> the speed at which they would want the appropriate contractor to be <br /> identified and other considerations that weigh in their endeavour. Let’s <br /> take this very case, GPPC floated the tender way back in January 2025 <br /> and LOA itself was granted on 09.06.2025 from which date more than a <br /> <br /> such interference will cause unnecessary loss to the public exchequer. (See <i>Silppi Constructions </i><br /> <i>Contractors</i> v. <i>Union of India</i> [ <i>Silppi Constructions Contractors</i> v. <i>Union of India</i> , (2020) 16 SCC 489] .) <br /></div><table><thead><tr><th>55.</th><th>Ordinarily, a writ court should refrain itself from imposing its decision over the decision of the</th></tr></thead><tbody><tr><td>employer as to whether or not to accept the bid of a tenderer unless something very gross or palpable</td><td></td></tr><tr><td>is pointed out. The court ordinarily should not interfere in matters relating to tender or contract. To set</td><td></td></tr><tr><td>at naught the entire tender process at the stage when the contract is well underway, would not be in</td><td></td></tr><tr><td>public interest. Initiating a fresh tender process at this stage may consume lot of time and also loss to</td><td></td></tr><tr><td>the public exchequer to the tune of crores of rupees. The financial burden/implications on the public</td><td></td></tr><tr><td>exchequer that the State may have to meet with if the Court directs issue of a fresh tender notice, should</td><td></td></tr><tr><td>be one of the guiding factors that the Court should keep in mind. This is evident from a three-Judge</td><td></td></tr><tr><td>Bench decision of this Court in</td><td></td></tr></tbody></table><table><tbody><tr><td></td><td></td><td>Even when some defect is found in the decision-making process, the court must exercise</td></tr><tr><td>its discretionary powers under Article 226 with great caution and should exercise it only in furtherance</td><td></td><td></td></tr><tr><td>of public interest and not merely on the making out of a legal point. The court should always keep the</td><td></td><td></td></tr><tr><td>larger public interest in mind in order to decide whether its intervention is called for or not. Only when it</td><td></td><td></td></tr><tr><td>comes to a conclusion that overwhelming public interest requires interference, the court should</td><td></td><td></td></tr><tr><td>interfere.</td><td></td><td></td></tr></tbody></table><div><br /> Page <b>14</b> of <b>17</b> <br /> <br /><br /> year has already passed. Who is to account for the delay in the execution <br /> of the contract and commencement of the work? <br /> 25. It is true that the tender document specifically provides that “The <br /> bidder with the highest total score (S) shall be <b>considered</b> for award of <br /> job”. It is important to note that the entity to consider is the ‘Owner’ and <br /> not the court. It is for the reason that while considering the competing <br /> scores the owner must have the necessary “Fair play in the Joints”. We <br /> may note that tender document itself provides that GPPC has a right to <br /> accept any bid and to reject any or all bids. Clause 23.0 and 23.1 is as <br /> follows; <br /> <i>“23.0 GPPC&#x27;S RIGHT TO ACCEPT ANY BID AND TO REJECT </i><br /> <i>ANY OR ALL BIDS </i><br /> <i>23.1 GPPC reserves the right to accept or reject any Bid, and </i><br /> <i>to cancel the bidding process and reject all bids, at any time prior </i><br /> <i>to the award of Contract, without thereby incurring any liability to </i><br /> <i>the affected Bidder or bidders or any obligation to inform the </i><br /> <i>affected Bidder or bidders of the grounds for the GPPC’s action.” </i><br /> <i> </i><br /> 26. The final choice is of the owner, and it is for the owner to take the <br /> final decision with necessary flexibility and pragmatism. While exercising <br /> judicial review of contractual matters, constitutional courts do not exercise, <br /> should not exercise ex-ante jurisdiction to pre-empt executive actions. On <br /> this count, High Court has exceeded the first principle of judicial restraint <br /> in contractual matters. <br /> Page <b>15</b> of <b>17</b> <br /> <br /><br /> 27. Having considered the matter in detail, we are of the opinion that <br /> there was no justification to interfere with the grant of LOA dated <br /> 09.06.2025, followed by the execution of the contract on 01.07.2025. Even <br /> otherwise, when the report of the consultant was placed before the Court, <br /> considering the marginal difference between the appellant and the writ <br /> petitioner, the High Court should have restrained from interfering. The <br /> High Court’s observation that “ <i>since the learned advocate Mr. Aspi M. </i><br /> <i>Kapadia, appearing for GSPC agreed to the re-evaluation of the marks </i><br /> <i>through its consultant (…) directed the consultant to prepare a fresh report </i><br /> <i>on the allocation of marks after hearing the respective parties</i> ” cannot be <br /> an additional ground for an intense inquiry. When constitutional courts <br /> seek further scrutiny of contested fact, counsels appearing for the <br /> Government or its instrumentalities co-operate with the court, which is an <br /> important facet of good practices at the bar. Even before this court Mr. <br /> Aspi M. Kapadia assisted us with a straight bat and left the decision to the <br /> court. However, we believe that the burden is always on the court and the <br /> decision to interfere with the process must be based on settled principles <br /> that we have indicated hereinabove. <br /> 28. As regards the other submission of Mr. Somayajulu, with respect to <br /> the claim of additional 5 marks under clause 4 of 20.02 (B) <i>towards </i><br /> <i>operation and maintenance of sea water system experience</i> of the <br /> Page <b>16</b> of <b>17</b> <br /> <br /><br /> appellant, we see no justification whatsoever to interfere with the well-<br /> considered decision of the High Court. The findings of the High Court as <br /> regards clause 4 are based on true and correct fact and reasonable <br /> interpretation of the tender Document. We, therefore, reject this <br /> submission and the Civil Appeal arising out of Special Civil Application No. <br /> 12328 of 2025 stands dismissed. <br /> 29. In view of the above analysis, we are of the opinion that the Letter <br /> of Award (LOA) dated 09.06.2025 followed by the execution of the <br /> contract dates 01.07.2025 by GPPC in favour of the appellant should be <br /> upheld. GPPC can now proceed to have the contract performed without <br /> any hindrance. <br /> 30. The Civil Appeal arising out of Special Civil Application No. 7289 of <br /> 2025 is allowed and judgment and order passed by the High Court is set <br /> aside. <br /> 31. There shall be no order as to costs. <br /> <br /> ………………………………....J. <br /> [ <b>PAMIDIGHANTAM SRI NARASIMHA</b> ] <br /> ………………………………....J. <br /> [ <b>ALOK ARADHE</b> ] <br /> <b>NEW DELHI; </b><br /> <b>MARCH 25, 2026. </b><br /> Page <b>17</b> of <b>17</b> <br /> </div>