Starlight Systems (I) Limited Liability Partnership (Aormerly Know As Starlight Systems Pvt. Ltd. ) vs Mumbai Metropolitan Region Development Authority And 5 Ors
- Court
- Bombay High Court
- Case type
- WP
- Decided on
- 08-04-2026
<div> <b>2026:BHC-OS:8908-DB</b><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Shephali<br /> IN THE HIGH COURT OF JUDICATURE AT BOMBAY<br /> ORDINARY ORIGINAL CIVIL JURISDICTION<br /> WRIT PETITION NO. 2377 OF 2018<br /> Sunteck Realty Limited,<br /> (Formerly known as Starlight Systems (I) <br /> Private Limited and before that known as <br /> Starlight Systems (I) LLP) is a public <br /> limited company registered under the <br /> Companies Act, 1956 having its registered <br /> office at INS Building,<br /> Rafi Marg, New Delhi 110 001. …Petitioner<br /> ~ versus ~<br /> 1. Mumbai Metropolitan Region<br /> Development Authority,<br /> an authority established under the <br /> Mumbai Metropolitan Region <br /> Development Authority Act, 1974 and <br /> having its head office at Plot C-14 & C-<br /> 15 ‘E’ Block, Bandra Kurla Complex, <br /> Bandra (East), Mumbai 400 051.<br /> SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Digitally signed<br /> by SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Date: 2026.04.09<br /> 15:15:50 +0530<br /> 2. The Chairman,<br /> Mumbai Metropolitan Region <br /> Development Authority having its <br /> office at Plot C-14 & C-15 ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> 3. The Metropolitan Commissioner,<br /> Mumbai Metropolitan Region <br /> Development Authority having its <br /> office at Plot C-14 & C-15 ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> 4. The Additional Metropolitan <br /> Commissioner,<br /> Mumbai Metropolitan Region <br /> Page 1 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Development Authority having its <br /> office at Plot C-14 & C-15 ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> 5. The Land and Estate Manager,<br /> Mumbai Metropolitan Region <br /> Development Authority having its <br /> office at Plot C-14 & C-15 ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> 6. The Chief T & CP Division, Mumbai,<br /> Mumbai Metropolitan Region <br /> Development Authority having its <br /> office at Plot C-14 & C-15 ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051. …Respondents<br /> A PPEARANCES<br /> For the Petitioner Mr. Vikram Nankani, Senior <br /> Advocate, with Mr. Karan Bharioke, <br /> Dr. Sujay Kantawala, Mr. Viraj Parikh, <br /> Mr Parag Kabadi, Ms. Vidhi Porwal & <br /> Ms. Anshita Sethi, i/b DSK Legal.<br /> For Respondents-MMRDA Mr. Pravin Samdani, Senior Advocate,<br /> with Mr. Nishant Chotani, Mr. Nivit <br /> Srivastava, Ms. Sneha Patil, Ms. Aditi <br /> Sinha, Mr. Hrishikesh Joshi & Ms. <br /> Isha Vyas, i/b Maniar Srivastava <br /> Associates.<br /> CORAM : SHREE CHANDRASHEKHAR, CJ &<br /> SUMAN SHYAM, J.<br /> nd<br /> RESERVED ON : 22 JANUARY 2026.<br /> th<br /> PRONOUNCED ON : 8 APRIL 2026.<br /> JUDGMENT ( Per Suman Shyam, J) :- <br /> Page 2 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 1. Rule. Rule is made returnable forthwith. <br /> 2. By consent of the parties, the matter is taken up for final<br /> hearing.<br /> th<br /> 3. Assailing the Demand Notice dated 9 September 2014<br /> (Exhibit-S), the Petitioner has approached this Court inter -alia<br /> contending that the levy of penalty/additional premium by<br /> Respondent No.1–Mumbai Metropolitan Region Development<br /> Authority (“MMRDA”) upon the Petitioner on account of delay in<br /> completion of construction is contrary to the terms and conditions<br /> of the Lease Agreement and, therefore, arbitrary and illegal. The<br /> facts and circumstances, giving rise to the filing of the present<br /> Writ Petition, shorn of unnecessary details, are as hereunder.<br /> 4. It appears from the record that this Writ Petition was<br /> originally instituted by M/s. Starlight Systems (I) LLP, which entity<br /> subsequently got converted into “Starlight Systems (I) Private<br /> th<br /> Limited”. Thereafter, in terms of the order dated 29 July 2024<br /> passed by the National Company Law Tribunal (“NCLT”), Mumbai<br /> Bench in CP(CAA)281/MB-III/2023 in CA (CAA) 180/MB-III/<br /> 2023, M/s. Starlight Systems (I) Private Limited was amalgamated<br /> Page 3 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> with M/s. Sunteck Realty Limited, i.e., the present Petitioner. In<br /> th<br /> terms of the order dated 5 May 2025, amendments were carried<br /> out in the Writ Petition. Accordingly, M/s. Sunteck Realty Limited<br /> was substituted as the Writ Petitioner in place of M/s. Starlight<br /> Systems (I) LLP.<br /> 5. In the month of November 2005, the Respondent No. 1,<br /> being the owner of the land, had invited bids to lease out Plot Nos.<br /> R-1.2 and R-1.3 admeasuring 3533.40 sq. mtrs. and 3533.27 sq.<br /> mtrs., respectively, situated at the Bandra-Kurla Complex (BKC).<br /> th<br /> On 30 December 2005, the original Petitioner had submitted its<br /> bid offering Rs.72,40,27,950/- (Rupees Seventy Two Crores Forty<br /> Lakhs Twenty Seven Thousand Nine Hundred Fifty only) for the<br /> Plot No. R-1.2 admeasuring 3533.40 sq. mtrs. and<br /> Rs.64,50,32,700/- (Rupees Sixty Four Crores Fifty Lakhs Thirty<br /> Two Thousand Seven Hundred only) for the Plot No. R-1.3<br /> admeasuring 3533.27 sq. mtrs. (7,066.67 sq. mtrs. in total)<br /> aggregating to Rs.136,90,60,650/- (Rupees One Hundred and<br /> Thirty Six Crores, Ninety Lakhs Sixty Thousand Six Hundred and<br /> Fifty ). The bid submitted by the Petitioner was accepted by<br /> th<br /> Respondent No.1 in its 115 meeting held on 3rd February 2006<br /> Page 4 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> under Resolution No.1070, thereby agreeing to grant Lease in<br /> respect of Plot Nos. R-1.2 and R-1.3 admeasuring 7,066.67 sq.<br /> mtrs. in total to the Petitioner.<br /> 6. The Respondent No. 1, being a body corporate and an<br /> independent statutory authority, was competent to enter into<br /> contract so as to lease out land received by it by way of grant from<br /> th<br /> the State Government. As such, on 27 July 2006, a registered<br /> Lease Deed was executed by and between the Petitioner and<br /> Respondent No.1, granting leasehold rights in respect of the<br /> aforesaid plots of land, for a period of 80 years, for construction of<br /> a building thereon with the permissible built-up area of 14,100 sq.<br /> mtrs. (Initial Built-up Area). The entire lease premium of<br /> Rs.136,90,60,650/- (Rupees One Hundred and Thirty Six Crores,<br /> Ninety Lakhs Sixty Thousand Six Hundred and Fifty only) was<br /> paid by the Petitioner prior to the execution of the Lease Deed.<br /> th<br /> 7. Article 2(a) of the Lease Deed dated 27 July 2006<br /> stipulates that no work shall commence till plans are approved by<br /> the Authority; Article 2(d) lays down that the construction shall be<br /> completed within a period of four years from the date of execution<br /> of the Lease Deed; Article 2(e) provides that failure to comply<br /> Page 5 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> with Article 2(d) would require extension of time, which may be<br /> permitted by the Metropolitan Commissioner on payment of<br /> additional premium at the prescribed rates.<br /> th<br /> 8. After the execution of the Lease Deed dated 27 July 2006,<br /> rd<br /> possession of the plots were handed over to the Petitioner on 3<br /> August 2006. At that time, 2.00 FSI was available in ‘G’ Block of<br /> Bandra-Kurla Complex. Accordingly, construction over the land so<br /> leased was proposed within the permissible built-up area of<br /> th<br /> 14,100 sq. mtrs. On 19 December 2006, building plans were<br /> submitted and application for Commencement Certificate (“CC”)<br /> up to plinth level was made by the Petitioner. The Commencement<br /> th<br /> Certificate (“CC”) was eventually issued on 13 August, 2007 for<br /> carrying out construction by utilising the built up area of 14,100<br /> sq. mtrs.<br /> 9. Upon commencement of excavation and foundation work, it<br /> was discovered that there were pre-existing underground<br /> reinforced cement concrete piles and sub-structures across the<br /> entire plot. It was further detected that earlier, a textile market<br /> building had been proposed on the same plots for which, pile<br /> foundation work had also been undertaken but the project was<br /> Page 6 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> later abandoned. The Writ Petitioner has alleged that there was no<br /> disclosure of the said fact by the Respondent No. 1 in the tender<br /> documents or in the Lease Deed.<br /> 10. In view of the pre-existing piles and sub-structures,<br /> excavation and foundation works undertaken by the Petitioner<br /> th<br /> pursuant to the CC dated 13 August,2007 got materially affected.<br /> The Petitioner was, therefore, compelled to alter the structural<br /> design from pile foundation to open foundation. That apart,<br /> during the course of excavation, the Respondent No.1 had also<br /> under taken construction of an internal road abutting the plots.<br /> Consequently, the Petitioner had to temporarily back-fill soil to<br /> prevent collapse of the structures and thereafter, resume<br /> excavation, post-monsoon. In the above process, considerable time<br /> was lost for reasons which were not attributable to the Petitioner.<br /> th<br /> 11. Situated thus, on 19 March 2008, the Petitioner had<br /> addressed a letter to the Respondent No.1 informing the<br /> authorities about the pre-existing piles while requesting for<br /> extension of time for completion of the construction without levy<br /> of premium. However, despite receipt of such request no decision<br /> on the same was communicated to the Petitioner.<br /> Page 7 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 12. In the meantime, the Government of Maharashtra had<br /> nd<br /> passed a Resolution dated 2 May, 2008 enhancing the<br /> permissible FSI in ‘G’ Block of Bandra-Kurla Complex from 2.00 to<br /> 4.00. In view of the said Resolution, the Respondent No.1 had<br /> offered additional built-up area to the existing lessees.<br /> 13. With a view to avail the benefit under the Resolution dated<br /> nd<br /> 2 May, 2008, the Petitioner had submitted amended plans on<br /> th<br /> 29 August, 2008 proposing to incorporate two basements so as to<br /> consume the additional FSI which had become available in view of<br /> nd<br /> the aforesaid Resolution dated 2 May,2008. <br /> nd th<br /> 14. In the wake of the Resolution dated 2 May 2008, on 10<br /> September 2008, the Respondent No.1 had allotted two adjoining<br /> plots being R-1.1 and R-1.4 to the Petitioner. As such, by letter<br /> th <br /> dated 4 December 2008, additional built-up area of 14,100 sq.<br /> mtrs. was allotted to the Petitioner against payment of<br /> Rs.92,07,30,000/- (Ninety Two Crores Seven Lakhs Thirty<br /> Thousand only). The amended Commencement Certificate was,<br /> th th<br /> thereafter, issued on 11 June 2009. Subsequently, in its 125<br /> rd<br /> Meeting held on 3 August 2009, the Respondent No.1 had<br /> further extended the scheme for allotment of additional built-up<br /> Page 8 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> th<br /> area. Accordingly, by the letter dated 25 November 2009, further<br /> additional built-up area of 14,000 sq. mtrs. was allotted to the<br /> Petitioner against payment of Rs.91,42,00,000/- (Ninety One<br /> Crores Forty Two Lakhs only). In this manner, the total additional<br /> built-up area eventually allotted to the Petitioner was 28,100 sq.<br /> mtrs., thus, increasing the total permissible built-up area in the<br /> same building from 14,100 sq. mtrs to 42,200 sq. mtrs. <br /> 15. In the wake of allotment of the additional built-up area, as<br /> aforesaid, the Petitioner was required to submit revised plans and<br /> also apply for clearance/approval from the other statutory<br /> authorities so as to consume the additional built up area on the<br /> same plot and within the same building. However, the said process<br /> could move ahead only after receipt of Environment Clearance.<br /> The revised environmental clearance applied for by the Petitioner<br /> th<br /> was granted on 14 June 2011, revised height clearance from the<br /> th<br /> Airports Authority of India was granted on 7 December 2010 and<br /> th<br /> revised clearance by the High-Rise Committee was granted on 5<br /> March 2014.<br /> th<br /> 16. On 13 April 2010, the Respondent No.1 had granted<br /> permission for amalgamation of Plot Nos. R-1.2 and R-1.3 with<br /> Page 9 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> the adjoining Plot Nos. R-1.1 and R-1.4 for joint development of<br /> the plot as a single larger plot with a common Commencement<br /> Certificate.<br /> th<br /> 17. On 25 June 2010, the Petitioner addressed a letter to the<br /> Respondent No. 1 seeking extension of time for completion of<br /> construction of the Initial Built-up Area, till December 2013.<br /> However, on this occasion also, no decision, on such request for<br /> extension of time was communicated to the Petitioner.<br /> th<br /> 18. On 29 July 2011, further Commencement Certificate was<br /> issued to the Petitioner, permitting construction of the proposed<br /> total built-up area of 28,332.04 sq. mtrs. Based on the same,<br /> th<br /> construction up to the 7 floor, corresponding to the Initial Built-<br /> up Area of 14,100 sq., mtrs. was completed by the Petitioner on<br /> th<br /> 18 February 2014 which fact is discernible form the architect’s<br /> certification.<br /> 19. Since the Respondent No 1 was demanding payment of<br /> additional premium/penalty for granting extension of time, hence,<br /> st<br /> on 21 January 2014, a meeting was held between the Petitioner<br /> and the officers of Respondent No.1 to discuss the issue.<br /> Page 10 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> rd<br /> Thereafter, an undertaking dated 23 January 2014 was<br /> submitted by the Petitioner agreeing to pay the additional<br /> premium as a condition for issuance of further Commencement<br /> th<br /> Certificates. However, by issuing letter dated 6 February 2014,<br /> the Petitioner had set out the reasons for the delay in completing<br /> the construction which included pre-existing piles and revised<br /> approvals. <br /> th<br /> 20. In response to the above, by letter dated 18 February 2014,<br /> the Respondent No.1 had called for further particulars, which<br /> rd<br /> were also furnished by the Petitioner on 3 March 2014.<br /> rd<br /> 21. On 23 May 2014, the Respondent No.1 had issued further<br /> nd<br /> Commencement Certificate for construction upto 2 level<br /> st<br /> basement+part silt and part ground+podium+service floor+ 1<br /> th<br /> to 17 floors above plinth level. However, a condition was<br /> imposed in the said Commencement Certificate to the effect that<br /> additional lease premium for extension of time shall be paid by<br /> the Petitioner before issuance of Part Occupation Certificate as<br /> th<br /> assured in the letter dated 14 April,2014. The Petitioner applied<br /> th<br /> for Part Occupation Certificate on 30 May 2014.<br /> Page 11 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 22. It appears that in response to the request made by the<br /> Petitioner for extension of time to complete the construction, the<br /> Respondent No. 1 had taken a decision to grant extension of time<br /> for the delay of 11 months on condition of payment of additional<br /> premium of Rs.52,80,98,641/-. Accordingly, the Petitioner had<br /> th<br /> addressed letter dated 4 September 2014 depositing the<br /> additional premium of Rs.52,80,98,641/- (Rupees Fifty Two<br /> Crores Eighty Lakhs Ninety Eight Thousand Six Hundred and Forty<br /> One only) under protest and without prejudice to its right to<br /> contest the aforesaid decision as well as for getting the benefit of<br /> extension of time from four years to six years. In the said letter,<br /> the Petitioner had once again highlighted the reasons for the delay<br /> which were not attributable to the Petitioner.<br /> th<br /> 23. By the communication dated 9 September 2014, the<br /> Respondent No.1 had informed the Petitioner that extension of<br /> th<br /> time for completion of construction was being granted upto 6<br /> June, 2014 subject to payment of additional premium, calculated<br /> at the rate of 10% of the lease premium. The said communication<br /> had further clarified that the additional premium payable had<br /> been adjusted against the amount of Rs.52,80,98,641/- (Rupees<br /> Page 12 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Fifty Two Crores Eighty Lakhs Ninety Eight Thousand Six Hundred<br /> th<br /> and Forty One only) earlier paid by the Petitioner on 4<br /> September, 2014 towards the said demand, together with interest,<br /> after deduction of TDS amounting to Rs.1,24,88,251/- (Rupees<br /> One Crore Twenty Four Lakhs Eighty Eight Thousand Two<br /> Hundred and Fifty One only) on the interest component. <br /> th<br /> 24. Thereafter, Part Occupation Certificate up to the 7 floor<br /> th<br /> was issued on 17 October 2014. Subsequently, full Occupation<br /> th<br /> Certificate in respect of the building came to be issued on 9<br /> November 2015. <br /> 25. Having regard to the nature of controversy involved in this<br /> proceeding, we deem it appropriate to reproduce the impugned<br /> th<br /> letter dated 9 September 2014 as hereunder for ready reference:-<br /> EXHIBIT = ‘S’<br /> MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY<br /> _________________________________________________________ <br /> No.LC/BKC(G)SSILLP/R1.2 & R1.3/1263/2014 Date: 09/09/2014<br /> To,<br /> M/s. Starlight Systems (I) LLP,<br /> th<br /> 5-9 Floor, Housefin Bhavan,<br /> C-21, Bandra-Kurla Complex,<br /> Bandra (East), Mumbai – 400 051.<br /> Sub: Allotment of Plot No. R1.3 in ‘G’ Block of BKC<br /> -Grant of extension in completing the construction<br /> of the building.<br /> Page 13 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Ref.: Your letter addressed to Town & Country Planning<br /> Division, dated 25/06/2010.<br /> Sir,<br /> With reference to your letter under reference on the<br /> subject mentioned above, I am directed to inform you that the<br /> Plot No.R1.2 & R1.3 in ‘G’ Block of BKC has been allotted to you<br /> under the Lease Deed executed on 27/07/2006. The Article 2(d)<br /> and 2(e) of the said Lease Deed provides that the Lessee has to<br /> commence and complete the construction work of the building on<br /> the leased plot within a period of 4 years from the date of lease<br /> and if it could not be completed within the said period for the<br /> reason beyond control of the Lessee, the Metropolitan<br /> Commissioner is empowered to permit extension of such time on<br /> st nd<br /> payment of additional premium@25% for 1 year, 35% for 2<br /> rd<br /> year & 40% for 3 year. The stipulated construction period of 4<br /> years has been expired on 26/07/2010.<br /> 2. The Authority vide its Resolution No. 1140 & 1227 passed<br /> th th<br /> in its 120 & 126 meeting held on 24/12/2007 & 09/02/2010<br /> respectively has given its approval to revise the rate of additional<br /> premium to be charged for extended period in completing the<br /> construction on the building as follows:-<br /> a) To revise the rate of additional premium to be charged for<br /> extended period in completing the construction as per<br /> Article 2(e) of the Lease Deed as follows:-<br /> i) All the Govt. & Public - 5% of the lease premium per<br /> Sector year till they complete the<br /> construction.<br /> ii) Semi Govt. & Public Sector<br /> Organizations and Private<br /> Sector Organizations <br /> - i) Upto 3 years - 10% of the<br /> lease premium per year.<br /> ii) Beyond 3 years till they<br /> complete the construction<br /> -15% of the lease<br /> premium per year. <br /> b) To charge the additional premium in proportion to the<br /> built-up area of which construction is incomplete i.e. to<br /> exclude the built-up area of which OC is issued.<br /> c) To charge the additional premium proportionately for the<br /> extended period of completion of the construction.<br /> Page 14 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 3. You are further informed that after due consideration of<br /> the issue represented by you about excavation of the Piles exists<br /> in the plot under reference & further request made to exclude the<br /> period required for excavation of the said Piles, the time lost by<br /> virtue of demolition of existing piles, foundation and resorting to<br /> open foundation were submitted to Town & Country Planning<br /> Division of this Authority and on confirmation by them in<br /> consultation with Engineering Division of this Authority & as<br /> recommended by them the Hon. Metropolitan Commissioner has<br /> given approval to condone the delay in completing the<br /> constructions of building on the plot under reference for a period<br /> of 11 months from 27/07/2010 to 26/06/2011.<br /> 4. The Cliet Town & Country Planning Division of this<br /> Authority has informed that the date of completion construction<br /> th<br /> upto 7 floor on the plot under reference within the basic FSI as<br /> per Lease Deed is 06/06/2014.<br /> 5. Considering the above, the Metropolitan Commissioner is<br /> pleased to grant you an extension in completing the construction<br /> of the building intended to be constructed on the Plot as stated<br /> above for a period from 27/06/2011 to 06/06/2014 by charging<br /> additional premium @ 10% of the lease premium p.a. payable in<br /> advance in proportion of the extended period.<br /> 6. You are also further informed that the payment of<br /> Rs.51,56,10,426/- made by you vide Receipt No.847110, dated<br /> 04/09/2014 being an amount of additional premium along with<br /> interest after deducting TDS on the interest being<br /> Rs.1,24,88,215/- has been adjusted as shown in the statement<br /> enclosed with this letter & there is an excess amount of Rs.181/-<br /> paid by you towards interest.<br /> 7. This letter issue with the approval of the Metropolitan<br /> Commissioner.<br /> Yours faithfully,<br /> Sd/-<br /> (S. K. Desai) <br /> LANDS & ESTATE MANAGER (I)<br /> MMRDA<br /> th<br /> 26. It would be significant to note here-in that on 5 November<br /> 2015, a Supplementary Lease Deed was executed by and in<br /> Page 15 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> between the parties, incorporating the stipulation that the<br /> additional built-up area was an integral part of the demised<br /> premises. Article 5 of the Supplementary Lease Deed had inter alia<br /> mentioned that there is “no time-limit”, for completion of<br /> construction of the building by using the additional built-up area.<br /> 27. It further appears that in view of delay caused in securing<br /> various statutory approvals for carrying out the constructions, the<br /> st nd<br /> Respondent No 1, in its 131 Meeting held on 22 October 2012,<br /> had considered granting extension of time to the Lessees for<br /> completion of the construction from four years to six years,<br /> th<br /> Ultimately, in its 138th Meeting held on 26 August 2015, the<br /> Respondent No.1 had adopted Resolution No. 1347 to amend<br /> Article 2(d) so as to provide time upto 6 (six) years for completion<br /> of construction, but made the same applicable only to the lease<br /> th<br /> deeds executed after 26 August 2015.<br /> th<br /> 28. The Petitioner had submitted a representation dated 20<br /> th<br /> February 2018 seeking revocation of the Notice dated 9<br /> September 2014 and had also sought refund of sum of<br /> Rs.52,80,98,641/- with interest. However, there has been no<br /> response to the said request.<br /> Page 16 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 29. Under the aforesaid circumstances, the present Writ Petition<br /> th<br /> has been filed assailing the Notice dated 9 September 2014, thus<br /> seeking a direction from this Court for refund of the amount of<br /> Rs.52,80,98,641/- paid as penalty/additional premium by the<br /> Petitioner under protest for granting extension of time for<br /> completion of the construction.<br /> 30. The Respondents have filed Reply inter -alia questioning the<br /> maintainability of the Writ Petition. The case of the Respondents,<br /> in essence, is that the Writ Petition is barred by delay and laches;<br /> that the Petitioner had efficacious alternative remedy as per<br /> Section 44 of the MMRDA Act read with Rule 5 of the Rules of<br /> 1976; that the Writ Petition is liable to be dismissed on account of<br /> suppression of material facts; that the Writ Petition is a<br /> “camouflage” challenge to the policy decision of the State without<br /> challenging the corresponding statutory provision; that the<br /> extension of time for completion of construction can be granted<br /> only on payment of additional premium/penalty as per Articles<br /> 2(d) and 2(e) and, therefore, the Petitioner cannot claim<br /> extension of time without paying the premium; that the provision<br /> in the Supplementary Lease Deed would not override the<br /> Page 17 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> provisions of Article 2(d) of the original Lease Deed and,<br /> therefore, the same would be binding on the Petitioner; the<br /> construction of the basic built-up area should and ought to have<br /> proceeded independently and completed within a period of four<br /> years from the date of signing of the Lease Deed; Since the<br /> Petitioner had voluntarily requested for extension of time and had<br /> also given an undertaking to pay the additional premium, hence,<br /> the Petitioner cannot now question the action of the Respondent<br /> No. 1; that the “no time limit” clause in the Supplementary Lease<br /> Deed did not vary the terms and conditions of the original lease<br /> agreement.<br /> 31. This Writ Petition was analogously heard along with three<br /> other Writ Petitions being Writ Petition No. 864 of 2018, Writ<br /> Petition No. 242 of 2018 and Writ Petition No. 3209 of 2017,<br /> involving similar issues whereby, identical reliefs were sought by<br /> the Writ Petitioner(s). <br /> 32. Mr Vikram Nankani, learned Senior Counsel appearing for<br /> the Writ Petitioner has referred to the documents available on<br /> record to submit that the demand of additional premium for a<br /> sum of Rs.52.80 crores (approx) on account of alleged delay in<br /> Page 18 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> completing the construction is wholly arbitrary, illegal and, hence,<br /> unsustainable in the eyes of law in as much as such a demand is<br /> wholly untenable in view of Article 5 of the Supplementary Lease<br /> th<br /> Deed dated 5 November 2015. The learned Senior Counsel<br /> further submits that the Supplementary Lease Deed was executed<br /> by and in between the parties for incorporating the additional<br /> built-up area (BUA) by integrating the same in the same<br /> construction. He submits that Article 5 of the Supplementary<br /> Lease Deed unambiguously dispenses with the time limit for<br /> completing the construction as provided under Clause 2(d) of the<br /> th<br /> Original Lease Agreement dated 27 July 2006. Therefore, in view<br /> of Article 5, the Respondent No. 1 did not have any authority or<br /> right under the law to recover any amount as additional<br /> premium/ penalty for the delay in completion of the construction.<br /> 33. It is also submitted by Mr Nankani, learned Senior Counsel<br /> that the delay, if any, in completing the construction is due to<br /> factors such as undisclosed existence of old underground RCC<br /> piles in the site, delay in approving the building plans and<br /> issuance of Commencement Certificate as well as due to<br /> significant changes in the construction plan due to the allotment<br /> Page 19 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> of additional built-up area. Therefore, the Petitioner cannot be<br /> held responsible for the delay in completing the construction on<br /> any ground. <br /> 34. Mr Nankani, has further argued that the case of the<br /> Petitioner is squarely covered by the earlier decision of this Court<br /> rendered in the case of Raghuleela Builders Pvt. Limited and Anr.<br /> vs. The Mumbai Metropolitan Regional Development Authority &<br /> 1<br /> Ors. wherein, in identical fact situation and under similar<br /> circumstances, this Court, by interpreting similar clauses in the<br /> Lease Deed, has held that the demand for additional premium for<br /> time extension on account of delay in completing the construction<br /> was arbitrary and illegal and, accordingly, struck down such<br /> demand.<br /> 35. The learned Senior Counsel for the Petitioner has also<br /> submitted that in view of the leave granted by the Hon’ble<br /> th<br /> Supreme Court in order dated 27 July 2020 passed in Special<br /> Leave to Appeal (C) No(s) 6411/2020, it was open for the<br /> Petitioner to rely upon and refer to the decision in Raghuleela<br /> Builders Pvt. Ltd. & Anr . (Supra) to contend that the said decision<br /> <b>1</b><br /> (2020) (1) ABR 397: 2019 SCC OnLine Bom 4529.<br /> Page 20 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> of this Court, which has attained finality in the eyes of law, would<br /> be applicable to the facts and circumstances of this case as well.<br /> Therefore, the Writ Petition be allowed in terms of prayer clauses<br /> (a) and (b). <br /> 36. Responding to the above arguments, Mr Samdani, learned<br /> Senior Counsel appearing for the Respondents has questioned the<br /> maintainability of the Writ Petition by inter-alia contending that<br /> the Writ Petition involves disputed questions of facts. The same is<br /> also hit by delay and lache and barred under the law of<br /> limitations. According to Mr. Samdani the amount of additional<br /> premium, having been levied in terms of specific clause contained<br /> in the Lease Deed, read with the provisions of Mumbai<br /> Metropolitan Region Development Authority (Disposal of Land)<br /> Regulations, 1977 (hereinafter referred to as “Land Disposal<br /> Regulations”) as well as the Mumbai Metropolitan Region<br /> Development Authority Act, 1974 (hereinafter referred to as<br /> “MMRDA Act”), the same was not assailable by filing this Writ<br /> Petition. <br /> 37. It has been further argued by Mr Samdani that the demand<br /> made by the Respondent No.1 is statutory in nature and is in<br /> Page 21 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> terms of model form of lease, i.e. form ‘D’ to the Land Disposal<br /> Regulation. Therefore, the same cannot be challenged in a Writ<br /> Petition. He, has further argued that by filing the instant Writ<br /> Petition, the Petitioner is indirectly assailing the provisions of the<br /> MMRDA Act as well as the Regulations framed thereunder, in a<br /> manner which is impermissible in the eyes of law. <br /> 38. The learned Senior Counsel for the Respondents has further<br /> argued that the parties are bound by the terms of the Lease Deed<br /> as well as the Supplementary Lease Deed, the terms and<br /> conditions of which are, enforceable in the eyes of law. Therefore,<br /> the Petitioner cannot be permitted to seek relief which is contrary<br /> to the terms and conditions of the Lease Deed, so as to frustrate<br /> the claim of the Respondent No.1. Mr Samdani has summed up his<br /> arguments by contending that this is not a case where the<br /> fundamental rights of the Petitioner under Article 14 of the<br /> Constitution has been infringed in any manner. In the absence of<br /> any challenge to the specific provision of the Lease Deed, the<br /> Petitioner cannot be permitted to go behind the terms and<br /> conditions of the Deed and take a stand which is contrary to the<br /> express conditions of the Lease Deed.<br /> Page 22 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 39. In support of his above arguments, Mr Samdani, learned<br /> Senior Counsel, has relied upon he following decisions:-<br /> (a) Bank of Baroda, Mumbai & Anr vs. Mumbai<br /> 2<br /> Metropolitan Regional Development Authority & Ors.<br /> (b) Assistant Excise Commissioner & Ors. vs. Issac Peter &<br /> 3<br /> Ors.<br /> 4<br /> (c) State of UP & Ors. vs. Chaudhari Ran Beer Singh,<br /> (d) Goetze (India) Ltd. vs. Employees State Insurance<br /> 5<br /> Corporation<br /> (e) Transmission Corporation of Andhra Pradesh Ltd. &<br /> 6<br /> Anr. Vs. Sai Renewable Power Pvt. Ltd. & Ors.<br /> (f) Banda Development Authority, Banda vs. Motilal<br /> 7<br /> Agarwal & Ors.<br /> (g) Punjab Financial Corporation vs. Surya Auto<br /> 8<br /> Industires<br /> 9<br /> (h) Joshi Technologies International IBC vs. U.O.I. & Ors.<br /> (i) The Godhra Electricity Co. Ltd. & Anr. vs. The State of<br /> 10<br /> Gujrat & Anr<br /> 11<br /> (j) Dhanraj vs. Vikram Singh & Ors.<br /> 12<br /> (k) Dalip Singh vs. State of U.P & Ors.<br /> <b>2</b><br /> 2010 (3) Mh. L.J.<br /> <b>3</b><br /> (1994) 4 SCC 104.<br /> <b>4</b><br /> (2008) 5 SCC 550.<br /> <b>5</b><br /> (2008) 8 SCC 705.<br /> <b>6</b><br /> (2011) 11 SCC 34.<br /> <b>7</b><br /> (2011) 5 SCC 394.<br /> <b>8</b><br /> (2010) 1 SCC 297.<br /> <b>9</b> (2015) 7 SCC 728.<br /> <b>10</b><br /> (1975) 1 SCC 199.<br /> <b>11</b><br /> 2023 SCC OnLine SC 724.<br /> <b>12</b><br /> (2010) 2 SCC 114.<br /> Page 23 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Plea regarding Maintainability of the Writ Petition :-<br /> 40. Insofar as the plea regarding maintainability of the Writ<br /> Petition is concerned, at the very outset, it deserves to be<br /> mentioned herein that although the maintainability of the Writ<br /> Petition has been questioned inter-alia on the ground that several<br /> disputed questions of facts are involved there-in, yet, after<br /> examining the record, we find that the material assertions made in<br /> the Writ Petition are all based on documents annexed thereto,<br /> which are admitted documents. Moreover, in view of the plea<br /> raised by the Petitioner that the action of the Respondent No. 1 in<br /> levying additional premium/penalty for the delay in completion of<br /> construction is not only contrary to the terms and conditions of<br /> the Lease Deed, but also, arbitrary and illegal and hence, violative<br /> of the fundamental rights of the Petitioner under Article 14 of the<br /> Constitution, we are of the view that the issues raised in the Writ<br /> Petition have an element of public law character.<br /> 41. In the case of Joshi Technologies International IBC vs. U.O.I.<br /> & Ors. (Supra), relied upon by Mr Samdani, the Hon’ble Supreme<br /> Court has observed that there is no absolute bar to the<br /> Page 24 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> maintainability of a Writ Petition, even in contractual matters or<br /> where there are disputed questions of fact or even when monitory<br /> claim is raised, provided, the Court is called upon to examine the<br /> issue which has a public law character attached to it. Having<br /> regard to the core controversy involved in this proceeding and<br /> considering the fact that the issues involved in this Writ Petition<br /> would call for determination by this Court based on interpretation<br /> of the relevant Articles of the Lease Agreement as well as the<br /> documents exchanged by and between the parties so as to<br /> ascertain fairness in the action of the Respondent No 1, we are<br /> unable to agree with the stand of the Respondents that the Writ<br /> Petition ought to be dismissed on the ground that it raises<br /> disputed questions of facts. <br /> 42. Likewise, from a reading of Section 44 of the MMRDA, Act<br /> 1974, we find that the provision for Appeal provided thereunder,<br /> is available for disputes regarding recovery of money due to the<br /> authority as arrears of land revenue. Since the challenge made to<br /> the impugned demand notice is on the ground that the same is<br /> contrary to the terms of the Supplementary Lease Deed and hence,<br /> illegal and arbitrary as such, we are of the opinion that the said<br /> Page 25 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> controversy cannot be effectively adjudicated in an Appeal filed<br /> under Section 44. Therefore, we reject the contention of the<br /> Respondents that the Petitioner has an effective and efficacious<br /> alternative remedy.<br /> 43. We also find that all material facts necessary for<br /> appreciating the controversy have been disclosed in the Writ<br /> Petition. Therefore, we are of the view that the Writ Petition<br /> cannot also be dismissed on account of suppression of material<br /> facts as well.<br /> 44. In so far as the grounds of delay and laches as well as the<br /> plea of the claim being barred by the Law of Limitations is<br /> concerned, save and except making a bald assertion on such count<br /> the Respondents have failed to mention as to on which date the<br /> cause of action for the petitioner to institute the proceeding had<br /> ceased and on what count. There is also no oral argument<br /> advanced to that effect. <br /> 45. In Banda Development Authority, Banda vs. Motilal Agarwal<br /> & Ors. (Supra), relied upon by Mr Samdani, the Hon’ble Supreme<br /> Court has observed that no limitation has been prescribed for<br /> Page 26 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> filing a Writ Petition under Article 226 of the Constitution of India.<br /> However, the High Court will treat the delay in filing the Writ<br /> Petition as unreasonable, if the same is filed beyond the period of<br /> limitation prescribed for filing a Civil Suit for a similar cause.<br /> From the above, it would be apparent that although un-explained<br /> delay in instituting a Writ Petition could be a valid ground to<br /> decline relief to the Petitioner, yet, the law of Limitation would not<br /> have strict application in a Writ Petition. <br /> 46. There is no dispute in this case about the fact that the<br /> Respondent No. 1 is an instrumentality of the State and, therefore,<br /> would be “other authority” within the meaning of Article 12 of the<br /> Constitution of India. <br /> 47. Law is well settled that arbitrariness in the decision making<br /> process of the State or its instrumentality is a facet of Article 14 of<br /> 13<br /> the Constitution of India. In E.P..Royappa v State of Tamil Nadu ,<br /> it was pointed out that Article 14 would strike at arbitrariness in<br /> State action and ensure fairness and equality of treatment. <br /> 48. The present is not a proceeding simpliciter for enforcing a<br /> money claim but raises significant questions pertaining to the<br /> <b>13</b><br /> (1974) 4 SCC 3.<br /> Page 27 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> validity and fairness in the impugned action of the Respondent No<br /> 1, which are required to be adjudicated on the touch stone of<br /> Article 14. As such, we are of the considered opinion that such<br /> plea cannot be brushed aside merely on the ground of delay and<br /> laches, more so, since such delay has evidently not given rise to<br /> any parallel right of a third party. <br /> 49. In view of the foregoing discussions, we are of the view that<br /> the Writ Petition is maintainable in law as well as in the facts and<br /> circumstances of the case. <br /> 50. It would be further pertinent to note herein that in an<br /> earlier decision rendered by a co-ordinate Bench of this Court<br /> th<br /> dated 20 November 2019 in Raghuleela Builders Pvt. Limited<br /> and Anr. vs. The Mumbai Metropolitan Regional Development<br /> Authority & Ors. (Supra) wherein, identical issues were involved,<br /> this Court had entertained the Writ Petition. In that case also the<br /> th<br /> Petitioners had challenged a similar Demand Notice dated 12<br /> September, 2017 issued by the Respondent No.1, by invoking<br /> similar provisions of the Lease Deed as well as the Supplementary<br /> Lease Deed, demanding payment of a sum of Rs. 432 Crores as<br /> penalty for the delay in completion of construction of the building.<br /> Page 28 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> That was also a case wherein, although the initial built up area<br /> was 30550 sq. meters, which was to be consumed by constructing<br /> 9 (nine) floors in the building, yet, subsequently, due to the<br /> increase in the FSI, the Respondent No.1 had allotted additional<br /> built up area of 67000 sq. meters to the Petitioner resulting in<br /> construction of 11 additional floors in the same building. Due to<br /> the addition in the built up area, the construction of the building<br /> could not be completed within four years, as stipulated in Article<br /> 2(d) of the original Lease Deed, as a result of which, Demand<br /> th<br /> Notice dated 12 September, 2017 was served for recovery of<br /> penalty/additional premium along with interest calculated<br /> thereon. <br /> th<br /> 51. By the Judgment and Order dated 20 November 2019, in<br /> Raghuleela Builders Pvt. Ltd. & Anr. (Supra), the Division Bench<br /> th<br /> had set aside the impugned Demand Notice dated 12 September<br /> 2017 by holding that such a demand was not maintainable in the<br /> eyes of law. That apart, it was also observed that in view of the<br /> change in policy of the MMRDA increasing the time limit for<br /> completion of the building “Fit for occupation”, from four years to<br /> six years, the demand for penalty/additional premium for delay in<br /> Page 29 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> completion of construction within four years was ex-facie<br /> unreasonable, unjustified and discriminatory. <br /> 52. The Special Leave Petition (C) No. 6411 of 2020 preferred<br /> by the Respondent No.1 assailing the Judgment and Order dated<br /> th<br /> 20 November 2019 was dismissed by the Hon’ble Supreme Court<br /> th<br /> by the order dated 27 July 2020 after taking note of the findings<br /> recorded in paragraphs No. 38 and 40 of the Judgment and Order<br /> th<br /> dated 20 November 2019. However, it was clarified that since the<br /> judgment of the Division Bench of the Bombay High Court was<br /> rendered in the facts of that case, hence, it cannot influence any<br /> other matter in this behalf. With the above observation the Special<br /> Leave Petition was dismissed. <br /> th<br /> 53. In the order dated 27 July 2020 the Hon’ble Supreme<br /> Court, while dismissing the Special Leave to Appeal (C) No(s)<br /> 6411/2020, had observed as follows:-<br /> “We are not inclined to exercise our jurisdiction under Article<br /> 136 of the Constitution of India in the given facts of the case and<br /> more so as reflected from paragraphs 38 and 40 of the<br /> impugned judgment.<br /> Mr. K. K. Venugopal, learned Attorney General for India<br /> expresses some apprehension on account of there being other<br /> matters pending.<br /> Page 30 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> We clarify that the present matter is in the given facts of<br /> the case as stated aforesaid and thus, cannot be said to influence<br /> any other matter in this behalf. <br /> The special leave petition is dismissed in terms aforesaid.<br /> Pending applications shall also stand disposed of.”<br /> 54. It appears that the Respondent No. 1 had filed a Review<br /> th<br /> Petition seeking review of the order dated 27 July 2020, which<br /> was also dismissed by the Hon’ble Supreme Court vide order<br /> th<br /> dated 29 September 2020 passed in Review Petition (Civil) No.<br /> 1764 of 2020 arising out of SLP (C) No. 6411 of 2020.<br /> 55. From a plain reading of the decision rendered in Raghuleela<br /> Builders Pvt. Ltd. & Anr. (Supra) we are of the opinion that, even<br /> if the said decision is treated to have been rendered in different<br /> fact situation, even then, we can take note of the legal principles<br /> emanating therefrom. In that view of the matter we are unable to<br /> agree with the submission of the learned Counsel for the<br /> Respondents that the decision in the case of Raghuleela Builders<br /> Pvt. Ltd. & Anr. (Supra) cannot be looked into by this Court even<br /> for the purpose of deciding the question of maintainability of the<br /> Writ Petition. <br /> Page 31 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 56. It is to be noted herein that the question of maintainability<br /> of a Writ Petition is a mixed question of law and facts. Therefore,<br /> the question of maintainability of the Petition would obviously<br /> have to be considered having due regard to the peculiar facts and<br /> circumstances of each case. Having regard to the facts and<br /> circumstances of this case and considering the fact that a similar<br /> Writ Petition, raising similar issues in Raghuleela Builders Pvt. Ltd.<br /> & Anr. (Supra) had earlier been entertained by this Court, hence,<br /> for the sake of maintaining uniformity in judicial decision, we are<br /> not inclined to non-suit the Writ Petitioner merely on the plea of<br /> maintainability as raised by the Respondents. <br /> On Merits:-<br /> 57. During the Course of arguments, the learned Counsel for<br /> the Respondents has made it clear that the demand for additional<br /> penalty on account of delay in completing the construction had<br /> been raised by the Respondent No.1 in deference to Article 2(d) &<br /> th<br /> (e) of the Lease Deed dated 27 July 2006 which is as per Form<br /> ‘D’ of Regulation No 10 of the Mumbai Metropolitan Region<br /> Development Authority (Disposal of Land) Regulations, 1977.<br /> Therefore, the question as to whether such a claim /demand of<br /> Page 32 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> the Respondent No. 1 for payment of additional premium/ penalty<br /> on account of delay in completing the construction was<br /> maintainable in the eyes of law as well as in the facts and<br /> circumstances of the case would undoubtedly have to be answered<br /> by this court in the light of materials brought on record and by<br /> constructing the relevant clauses of the Lease Agreement. For the<br /> th<br /> above purpose Articles 2 (d) and (e) of the Lease Deed dated 27<br /> July 2006 would be relevant and therefore, the same are being<br /> reproduced herein-below for ready reference:-<br /> “2. The lessee hereby agrees to observe and perform the<br /> following conditions that is to say:<br /> (d) Time limits for commencement and completion of<br /> construction work: That the Lessee shall within three months<br /> from the receipt of approval of his plans and specifications of<br /> building or buildings intended to be erected on the land,<br /> commence and within a period of four years from the date of<br /> this lease at his own expense and in a substantial and<br /> workman-like manner and with the sound materials and in<br /> compliance with the said Development Control Regulations<br /> and Building Regulations and all Municipal Rules, bye-laws<br /> and Regulations applicable hereto and in strict accordance<br /> with the approved plans, elevations, sections, specifications<br /> and details, to the satisfactions of the Metropolitan<br /> Commissioner and confirming to the building lines marked on<br /> the plan hereto annexed, and the Development Control<br /> Regulations and Building Regulations, build and completely<br /> finish, fit for occupation a building to be used as building with<br /> all requisite drains and other proper convenience thereto.<br /> (e) Extension of time stipulated for construction of<br /> building or development of land: <br /> (i) If the Lessee shall not perform and observe the<br /> limitations of the time mentioned in clause 2(d) above for<br /> Page 33 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> construction of the intended building or otherwise<br /> development of land leased to him for reasons beyond his<br /> control, the Metropolitan Commissioner may permit extension<br /> of such time on payment of additional premium at the<br /> following rates:<br /> Up to 1 year ______ 25 percent of the premium<br /> Between 1 and 2 years ______ 35 percent of the premium<br /> Between 2 and 3 years ______ 40 percent of the premium<br /> (ii) If the Metropolitan Commissioner shall refuse to permit<br /> such extension of time or shall find the Lessee of having<br /> committed breach of any condition or covenant during<br /> limitation of time mentioned in clause 2(d) hereinbefore, the<br /> Metropolitan Commissioner may forfeit and determine the<br /> Lease; provided that in the event of such determination of<br /> lease 25 percent of the premium paid by the Lessee to the<br /> Lessor shall stand forfeited and the remaining 75 percent of<br /> such premium shall be refunded to him; provided further that<br /> the power to so determine the Lease shall not be exercised<br /> unless and until the Metropolitan Commissioner shall have<br /> given to the Lessee or left on some part of the demised<br /> premises a notice in writing of his intention to do so and of<br /> specific breach of the covenant or condition in respect of<br /> which forfeiture is intended and default shall have been made<br /> by the Lessee in remedying such breach within three months<br /> from the service of a notice on him on the notice being left on<br /> the demised premises.” <br /> 58. Although, time limit of four years for completion of the<br /> construction was imposed by clause 2(d) of the Lease Deed dated<br /> th<br /> 27 July 2006, yet, we find that after the allotment of the<br /> additional built-up area, the time limit for carrying out the<br /> construction by using such additional built up area had been done<br /> away with by inserting Article-5 in the Supplementary Lease Deed<br /> th<br /> dated 5 November 2015, which is reproduced herein-below for<br /> ready reference:-<br /> Page 34 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> st<br /> “5. The Lessee vide its letters dated 21 November,<br /> rd<br /> 2008 & 23 November, 2009 requested the Authority to<br /> allot additional built up area of 14100 sq. mtrs. & 14000<br /> sq. mtrs, respectively on the said land leased to them as<br /> stated hereinbefore and the Authority vide its letters dated<br /> th th<br /> 4 December 2008 & 25 November 2009 have offered<br /> 14100 sq. mtrs. & 14000 sq. mtrs. additional built up area<br /> respectively (hereinafter called as “the said additional built<br /> up area”), a copy whereof is annexed hereto as “Annexure-<br /> IV/A & IV/B”, for a premium of Rs. 92,07,30,000/-<br /> (Rupees Ninety Two Crore Seven Lakh Thirty Thousand<br /> Only) for additional built up area of 14100 sq. mtrs. &<br /> Rs.91,42,00,000/- (Rupees Ninety One Crore Forty Two<br /> Lakhs Only) for additional built up area of 14000 sq. mtrs.<br /> payable in one installment or 20% of the premium as First<br /> Installment and balance premium in four equal annual<br /> installment with simple interest @ 10% p.a. and delay in<br /> payment of installments shall attract penal interest at the<br /> prevailing Prime Lending Rate (PLR) decided by the<br /> Reserve Bank of India on the total amount due. Further<br /> there is no time limit for construction of the said additional<br /> built up area and the Lessee herein shall be at liberty to<br /> transfer the entire said allotted additional built up area<br /> subject to the provisions of the said lease deed, however<br /> there is no time limit for construction of the said additional<br /> built up area.”<br /> (emphasis supplied)<br /> 59. At the very out set it must be noted here-in that as per<br /> Article 2(d) the lessee is required to complete the construction<br /> within four years from the date of execution of the lease deed.<br /> However, Article 2 (c) of the Lease Deed makes it clear that no<br /> work shall commence or be carried out contrary to the<br /> Development Control Regulations and the Building Regulations<br /> applicable to the plot of land and until the plans, elevations,<br /> sections, specifications and details shall have been approved.<br /> Therefore, in view of Article 2(c), the construction cannot<br /> Page 35 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> commence until receipt of all statutory approvals including the<br /> approval of building plan etc. Article 2(a) of the Lease Deed<br /> mentions that the lessee shall within three months submit plans<br /> etc for approval. However, there is no condition in the Lease Deed<br /> laying down and time line for granting of such approval by the<br /> authority.<br /> 60. In a construction of this nature, permission of multiple<br /> statutory authorities including the Municipal Corporation, Fire<br /> department, Environment clearance, height clearance etc. will be<br /> necessary, without which the Commencement Certificate cannot<br /> be issued. Unless the Commencement Certificate is issued by the<br /> Authority, the construction work also cannot commence. These<br /> statutory authorities are not bound by the terms and conditions of<br /> the Lease Agreement. Notwithstanding the same, the Lease<br /> Agreement is completely silent as to who will be responsible in<br /> case of delay in granting approval by these statutory authorities<br /> coming in the way of early commencement and completion of the<br /> construction. <br /> 61. Not only that, the Lease Deed is also silent as to what would<br /> be the effect on the time line of four years for completion of the<br /> Page 36 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> construction as laid down in Article (d) in case, there is delay in<br /> granting of statutory approvals. If there is delay in granting<br /> permissions/ approval by the statutory authorities for any reason<br /> whatsoever, leading to delay in commencement of construction<br /> then in that event the Lessee will be left with no option to<br /> complete the construction within the stipulated time. Yet, as per<br /> Article 2(d), as interpreted by the Respondent No 1, the lessee<br /> would still be liable to pay penalty for the delay in completing the<br /> construction beyond the period of four years from the date of<br /> execution of the Lease Deed. Viewed from that perspective, Article<br /> 2(d) of the lease deed appears to be ex-facie unfair, unreasonable<br /> and hence, unconscionable. However, since the Articles of the<br /> Lease Deed are not under challenge, hence, the said aspect of the<br /> matter need not detain this Court. <br /> 62. From the facts alluded to above, it is clear that as per Article<br /> th<br /> 2(d) of the Lease Deed dated 27 July 2006, there was an<br /> obligation on the Petitioner to commence and complete the<br /> construction within a period of four years form the date of the<br /> Lease. However, according to the Petitioner, there was delay in<br /> commencement of construction for various reasons, including non-<br /> Page 37 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> disclosure by the Respondent No. 1 that there were pre-existing<br /> underground piling on the plot of land due to a previous<br /> construction, as a result of which, the Petitioner had to abandon<br /> the underground piling work and, thereafter, raise open<br /> foundational piles, which had resulted not only in substantial<br /> change in the construction plan but the same had also consumed<br /> extra time for which the Petitioner was not responsible. The<br /> assertion made by the Petitioner on the above count have not been<br /> denied by the Respondents in their counter Affidavit. <br /> 63. It must further be noted herein that the commencement and<br /> completion of construction work, as per Article 2(d) of the Lease<br /> th<br /> Deed dated 27 July 2006, would be possible only when the<br /> Respondent No. 1 provides the plot of land, which is ready in all<br /> respect for commencement of construction to be followed by<br /> approval of the building plans etc by the Respondent No 1. As a<br /> matter of fact, as mentioned above, Article 2(c) of the Lease Deed<br /> itself stipulates that no work shall be commenced or carried on in<br /> contravention of any of the Development Control Regulation and<br /> Building Regulation or until the plans, elevations, sections,<br /> specifications and details have been approved. To the above<br /> Page 38 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> extent, it cannot be denied that there was a reciprocal obligation<br /> on the Respondent No. 1 not only to provide the plot of land, in a<br /> condition which was ready for commencement of construction but<br /> the building plan is also sanctioned expeditiously. <br /> 64. The Respondent No. 1 was also under an obligation to<br /> disclose the fact as regards pre-existing underground pile which<br /> would have a material bearing on the timeline of the construction.<br /> However, it is not in dispute that the Respondent No. 1 had failed<br /> to disclose the same to the Petitioner at the time of execution of<br /> the Lease Deed. It is the pleaded case of the Petitioner that<br /> because of the pre-existing underground pile, it had become<br /> impossible for the Petitioner to commence the construction as per<br /> the original timeline stipulated in Article 2(d) since the<br /> construction could not move forward without either removing the<br /> underground piles or a change in the plan. The first question that<br /> would, therefore, arise for consideration of this Court is, as to<br /> whether, having failed to discharge its reciprocal obligation in<br /> providing the plot in a condition which was ready for<br /> commencement of construction, can the Respondent No. 1 seek<br /> refuge under Article 2(d) and (e) of the Lease Deed to demand<br /> Page 39 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> penalty from the Petitioner for the delay in completing the<br /> construction?<br /> 65. In order to answer the said question, it would be significant<br /> th<br /> to note herein that the Lease Agreement dated 27 July 2006 is<br /> not merely an Agreements for construction of a building but is a<br /> Deed of Lease within the meaning of Section 105 of the Transfer<br /> of Property Act 1882, thus creating right and interest of the Lessee<br /> over the demised property. The relationship between the parties<br /> under the Lease Deed would be that of landlord and a tenant.<br /> Therefore, as long as the Lessee pays the lease rent and/or<br /> premium, as the case may be, and does not violate any of the<br /> terms and conditions of the Lease Deed, the right of the Lessee to<br /> enjoy the property shall stand protected under Section 108 of the<br /> Transfer of Property Act, 1882.<br /> 66. Section 108(a) of the Transfer of the Property Act, 1882<br /> dealing with the rights and liabilities of Lessor and Lessee reads as<br /> follows:-<br /> “108. Rights and liabilities of lessor and lessee.— In the absence<br /> of a contract or local usage to the contrary, the lessor and the<br /> lessee of immoveable property, as against one another,<br /> respectively, possess the rights and are subject to the liabilities<br /> Page 40 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> mentioned in the rules next following, or such of them as are<br /> applicable to the property leased:—<br /> (A) Rights and liabilities of the lessor<br /> (a) the lessor is bound to disclose to the lessee any<br /> material defect in the property, with reference to its intended<br /> use, of which the former is and the latter is not aware, and<br /> which the latter could not with ordinary care discover.”<br /> 67. From the language employed in Section 108(a) of the<br /> Transfer of Property Act, 1882 it is apparent that the Respondent<br /> No. 1 was duty-bound to disclose to the Petitioner that there were<br /> pre-existing underground piling in the land, which fact was not<br /> within the knowledge of the Petitioner at the time of submitting<br /> the bids or executing the Lease Agreement. The aforesaid fact was<br /> discovered by the Petitioner at a much later stage, i.e., only when<br /> the excavation work had commenced. Therefore, it is established<br /> beyond doubt that the Respondent No. 1 had failed to discharge<br /> its obligation under Section 108(a) of the Transfer of Property Act,<br /> 1882. If that be so, consequences under the law would<br /> undoubtedly ensue.<br /> 68. Law is settled that a party, which is responsible for causing<br /> the delay leading to breach of a condition in the contract cannot<br /> invoke the penalty clause or terminate the contract on such count.<br /> The aforesaid rule is based on the legal maxim “Nullus<br /> Page 41 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> commodum capere potest de injuria sua propria”, which means no<br /> man can take advantage of its own wrong [see Ashok Kapil vs<br /> Sanaulla (dead) & Ors., reported in (1996) 6 SCC 342]. The said<br /> doctrine does not permit a party to the contract responsible for the<br /> breach to invoke the penalty clause or to claim liquidated damage<br /> against the other party.<br /> 69. Under the “doctrine of prevention”, if the performance of<br /> condition of a contract by one party is unduly prevented by the<br /> other, the condition would be deemed to have either been satisfied<br /> or waived.<br /> 70. Dealing with the question as to whether a promisee would<br /> be entitled to liquidated damages, if by his own act or omission,<br /> he has prevented the promisor for completing the work within the<br /> date of completion, the Hon’ble Supreme Court has made the<br /> following observations in paragraph 34 in Welspun Specialty<br /> Solutions Ltd. (formerly known as Remi Metals Gujarat Limited)<br /> 14<br /> vs Oil and Natural Gas Corporation Limited :-<br /> “34. In order to consider the relevancy of time conditioned<br /> obligations, we may observe some basic principles: <br /> <b>14</b><br /> (2022) 2 SCC 382.<br /> Page 42 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> (a) Subject to the nature of contract, general<br /> rule is that promisor is bound to complete the obligation<br /> by the date for completion stated in the contract. [Refer<br /> to Percy Bilton Ltd. v. Greater London Council, [1982] 1<br /> WLR 794(HL)].<br /> (b) That is subject to the exception that the<br /> promisee is not entitled to liquidated damages, if by his<br /> act or omissions he has prevented the promisor from<br /> completing the work by the completion date. [Refer<br /> Holme v. Guppy, (1838) 3 M & W 387]<br /> (c) These general principles may be amended by<br /> the express terms of the contract as stipulated in this<br /> case.”<br /> 71. Section 53 of the Indian Contract Act, 1872 provides that in<br /> a contract containing reciprocal obligation, when one party<br /> prevents the other from performing the same, the contract would<br /> become voidable at the option of the party so prevented. The<br /> preventing party is also liable to make compensation for any loss.<br /> 72. What follows from the above is that even if it is held that<br /> demand of additional premium/ penalty for delay in completing<br /> the construction beyond fours from the date of execution of the<br /> Lease Deed is treated as a component of liquidate damage under<br /> Article 2 (d) yet, the Respondent No. 1 would not be entitled to<br /> recover the same, if it had, in any manner contributed to the delay.<br /> 73. It is no doubt correct that accepting the responsibility on<br /> account of failure on the part of the Respondent No 1 to disclose<br /> about the pre-existing underground piles affecting the excavation<br /> Page 43 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> work and upon consideration of the issues represented by the<br /> Petitioner on such count, the Metropolitan Commissioner, by the<br /> th<br /> Notice dated 9 September 2014, had condoned the delay in<br /> th<br /> completing the construction for 11 months i.e. upto 26 June<br /> 2011, without levying any penalty. However, the communication<br /> dated 09/09/2014 indicates that for granting extension of time for<br /> th th<br /> completing the construction from 27 June 2011 to 6 June 2014<br /> additional premium @ 10% of the lease premium had been levied<br /> upon the Petitioner. <br /> 74. In the above context, it would be significant to note here-in<br /> th<br /> that as per the Certificate dated 18 February,2014 (Exhibit- “O”)<br /> issued by the Architect engaged by the Petitioner, the construction<br /> of 2 basements + stilt+ podium+ service floor+ 7 upper floors<br /> th<br /> were completed on 18 February,2014. Such construction was<br /> evidently carried out by utilizing the initial built up area of 14,100<br /> sq mtrs. In the reply affidavit, the Respondents have denied that<br /> th<br /> the construction of initial BUA was completed on 18<br /> February,2014 and has further denied the receipt of the said letter<br /> th<br /> 18 February,2014. However, there is no specific averment in the<br /> th<br /> reply affidavit stating as to, if not on 18 February,2014, on which<br /> Page 44 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> date had the Petitioner completed the construction of the initial<br /> Built up Area.<br /> 75. It is to be noted here-in that Article 2(d) of the Lease Deed<br /> th<br /> dated 27 July 2006 was incorporated keeping the initial built up<br /> area of 14,100 sq. mtrs in mind and not the additional built up<br /> area allotted subsequently for which the Supplementary Lease<br /> Deed was executed. As such, the said article can at best have<br /> relevance with regard to the period for completion of construction<br /> of the initial built up area and no further. Therefore, in view of<br /> th<br /> Article 5 of the Supplementary Lease Deed dated 5 November,<br /> 2015, no time restriction could be enforced by the Respondent No<br /> 1 on completion of the construction by using the additional built<br /> up area. For the said reason, it was incumbent upon the<br /> Metropolitan Commissioner to deal with the issue of delay in the<br /> light of Article 5 before imposing any penalty upon the Petitioner.<br /> However, there is no reference to Article 5 in the communication<br /> th<br /> dated 9 September 2014 nor is there any mention as to the basis<br /> on which relaxation of time was granted only for 11 months<br /> without levying any penalty.<br /> Page 45 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> th<br /> 76. From the Commencement Certificate dated 29 July,2011<br /> (Exhibit-”J”) we find that commencement of construction of 2<br /> level basement+ stilt+ podium+ service floor + 15 upper floors<br /> pertaining to total built up area of 28,332.04 sq mtrs as against<br /> the total permissible built up area of 42,200 sq mtrs was issued<br /> only in the month of July,2011 after considering the 12 amended<br /> drawing submitted by the Petitioner. The Commencement<br /> Certificate dated 29th July,2011, which was issued beyond the<br /> period of four years from the date of execution of the Lease Deed,<br /> was evidently for carrying out construction of composite nature on<br /> the same building. If that be so, it is not clear as to on what basis,<br /> relaxation of time without imposing penalty was granted only for<br /> th<br /> 11 months i.e. till 26 June 2011. In a construction of this nature<br /> involving multiple Commencement Certificates issued at different<br /> stages due to allotment of additional built up area, it would be<br /> wholly impracticable and irrational to expect the Petitioner to<br /> th<br /> complete the construction of the entire building within 26 June<br /> 2011 when the Commencement Certificate itself was issued on<br /> th<br /> 29 July 2011.<br /> Page 46 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 77. That apart, there is also no determination as to the effect<br /> that the pre-existing foundational piles would have on the over-all<br /> time -line for competition of the construction, which in our view,<br /> ought to have been considered by the Respondent No 1 and<br /> reasons recorded in support of the decision to confine the<br /> relaxation of time only to 11 months. <br /> 78. It would be further significant to note that the Respondent<br /> No 1 had demanded and realized the additional premium as a<br /> penalty for breach of Article 2(d) of the Lease Deed on account of<br /> alleged failure on the part of the Petitioner to complete the<br /> construction with-in four years. However, no prior notice was ever<br /> served upon the Petitioner before realizing the amount. Not only<br /> that, there was also no default notice or notice of termination of<br /> the lease deed ever served by the Respondent No 1 as a result of<br /> which the Petitioner was denied of a reasonable opportunity to<br /> put forth its version before the amount of penalty was realized<br /> and/or adjusted. The arbitrary and high handed approach of the<br /> Respondents is further evident from the mere fact that the amount<br /> of additional premium was not only demanded but even adjusted/<br /> realized from the Petitioner even before issuance of the<br /> Page 47 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> th<br /> communication dated 9 September 2014 by means of which, the<br /> decision of the Respondent No.1 on the request for extension of<br /> time, without levy of penalty, was formally communicated to the<br /> Petitioner.<br /> 79. From the materials available on record, it is apparent that<br /> the petitioner had never accepted the demand for payment of<br /> additional premium made by the Respondent No.1 for the alleged<br /> delay in completing the construction but had all along objected to<br /> the same by contending that the delay was on account of factors<br /> beyond its control. Such plea, in the opinion of this court,<br /> deserved due consideration and proper answer by the Respondent<br /> No.1 before realizing the amount of penalty.<br /> 80. Demand for recovery of penalty on the ground of breach of<br /> terms of the lease agreement, which involves legal disputes,<br /> cannot be based on mere ipse dixit of one of the parties to the<br /> contract but such claim can be enforced only upon determination<br /> of the controversy in accordance with law. However, in the present<br /> case, there was no such determination. Therefore, the recovery/<br /> adjustment of the penalty by the Respondent No 1, in our view,<br /> Page 48 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> was in clear violation of the principles of natural justice and<br /> administrative fair play. <br /> 81. It is also to be noted herein that although the Respondent<br /> No. 1 had allotted the additional plots of land being R-1.1 and R-<br /> 1.4 for carrying out conjoint development of the plots as a<br /> singular plot along with Plot No. R-1.2 and R-1.3, yet, the<br /> th<br /> Supplementary Lease Deed dated 5 November 2015 facilitating<br /> the construction thereon by dispensing with the time restriction,<br /> th<br /> was executed only on 5 November 2015. From the projections<br /> th<br /> made in the communication dated 9 September 2014, it appears<br /> th<br /> that the construction was completed on 6 June 2014. However,<br /> curiously enough, the Supplementary Lease Deed containing<br /> Article 5, which removes the time limit for completing the<br /> construction, was signed on a date which was subsequent not only<br /> to the deposit of the additional premium/penalty by the Petitioner<br /> th<br /> but also to the issuance of the communication/notice dated 9<br /> September 2014, by means of which, such penalty was adjusted,<br /> thereby leaving no scope for the Petitioner to avail the benefit<br /> under Article 5 of the Supplementary Lease Deed. Therefore, the<br /> manner in which the amount of penalty had been recovered from<br /> Page 49 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> the Petitioner by circumventing the provisions of Article 5 of the<br /> Supplementary Lease Deed raises a serious doubt as to the<br /> bonafide of the Respondent No.1 in raising such demand. <br /> 82. Since the construction of the entire 42,200 sq. mtrs. was<br /> required to be carried out on a singular plot and in the same<br /> building, therefore, it is evidently a case of composite<br /> construction. Article 5 of the Supplementary Lease Deed makes it<br /> clear that after the allotment of the additional Built up Area, it<br /> was not the intention of the parties to continue with the original<br /> time line as contemplated under Article 2 (d) in as much as Article<br /> 5 is a specific stipulation completely dispensing with the time<br /> restriction for completing the construction of the building. As<br /> such, time was no longer the essence of the contract. <br /> 83. A Supplementary Contract reflects the subsequent intent of<br /> the parties. Therefore, if it was the intention of the parties to still<br /> continue with the same time restriction clause for completion of<br /> the construction of the building even after allotment of the<br /> additional built up area, then in that event, there was nothing<br /> preventing the Respondent No. 1 from clarifying the matter by<br /> inserting suitable stipulation in the Supplementary Lease Deed.<br /> Page 50 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> However, there was no such indication in the Supplementary<br /> Lease Deed. Had it been the intention to continue with the<br /> original stipulation under Article 2 (d) in that case, the<br /> Respondent No 1 would have invariably issued default notice<br /> upon the Petitioner immediately on expiry of the period of four<br /> years from the date of execution of the Lease Deed. The failure to<br /> do so without any just explanation, unequivocally goes to show<br /> that even the Respondent No. 1 was conscious of the fact that in<br /> view of Article 5 of the Supplementary Lease Deed the time<br /> restriction clause envisaged by Article 2 (d) would no longer be<br /> enforceable against the Petitioner. Under such circumstances, we<br /> are unable to agree with the stand of the Respondents that<br /> notwithstanding Article 5 of the Supplementary Lease Deed, the<br /> Petitioner was still under an obligation to complete the entire<br /> construction including the additional built up area within the time<br /> restriction clause envisaged under Article 2 (d) of the Lease Deed.<br /> 84. After a careful reading of Article 5 of the Supplementary<br /> Lease Deed, we are also of the considered opinion that the<br /> construction of the building was not severable in nature so as to<br /> apply a different time line to the original allotment and the<br /> Page 51 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> additional built up area for the purpose of completing the<br /> construction of the entire building in a state which is “fit for<br /> occupation”. Therefore, we are of the view that Article 5 of the<br /> th<br /> Supplementary Lease Deed dated 5 November, 2015 would<br /> obliterate the restriction of time for completion of construction of<br /> the building. <br /> 85. There is no controversy in this case about the fact that the<br /> th<br /> Lease Deed dated 27 July , 2006 as well as the Supplementary<br /> th<br /> Lease Deed dated 5 November,2015 are contract agreements<br /> within the meaning of section 10 of the Indian Contract Act, 1872.<br /> Law says that the onus to remove ambiguity in a contract would<br /> always be on the party drafting the contract. The legal maxim<br /> “Contra Proferentum” means, ambiguity to be resolved against the<br /> party which had drafted the contract. While dealing with the<br /> maxim “Contra Proferentum” , the Hon’ble Supreme Court, in case<br /> of Industrial Promotion and Investments Corporation of Orissa<br /> 15<br /> Ltd., vs New India Assurance Co. Ltd. & Anr. has made the<br /> following observations:-<br /> “We proceed to deal with the submission made by the counsel<br /> for the appellant regarding the rule of contra proferentem . The<br /> <b>15</b><br /> (2016) 15 SCC 315 <br /> Page 52 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:21 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Common Law rule of construction “verba chartarum fortius<br /> accipiuntur contra proferentem” means that ambiguity in the<br /> wording of the policy is to be resolved against the party who<br /> prepared it. MacGillivray on Insurance Law deals with the rule<br /> of contra proferentem as follows:<br /> “The contra proferentem rule of construction<br /> arises only where there is a wording employed<br /> by those drafting the clause which leaves the<br /> court unable to decide by ordinary principles<br /> of interpretation which of two meanings is the<br /> right one. ‘One must not use the rule to create<br /> the ambiguity—one must find the ambiguity<br /> first.’ The words should receive their ordinary<br /> and natural meaning unless that is displaced<br /> by a real ambiguity either appearing on the<br /> face of the policy or, possibly, by extrinsic<br /> evidence of surrounding circumstances.”<br /> 86. Law is also well settled that while constructing the terms of<br /> a contract, the document must be read as a whole so as to<br /> ascertain the true intent of the parties. In Bank of India & Anr. Vs<br /> 16<br /> K. Mohandas , the Hon’ble Supreme Court has held that it is well<br /> recognized principle of construction of a contract that it must be<br /> read as a whole in order to ascertain the true meaning of its<br /> several clauses and the words of each clause should be interpreted<br /> so as to bring them into harmony with the other provisions if that<br /> interpretation does no violence to the meaning of which they are<br /> entirely susceptible. The observations made in paragraph 28 of the<br /> said decision would be relevant in the present case and, therefore,<br /> are being reproduced herein-below for ready reference:-<br /> <b>16</b><br /> (2009) 5 SCC 313.<br /> Page 53 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> “28. The true construction of a contract must depend upon the<br /> import of the words used and not upon what the parties choose<br /> to say afterwards. Nor does subsequent conduct of the parties in<br /> the performance of the contract affect the true effect of the clear<br /> and unambiguous words used in the contract. The intention of<br /> the parties must be ascertained from the language they have<br /> used, considered in the light of the surrounding circumstances<br /> and the object of the contract. The nature and purpose of the<br /> contract is an important guide in ascertaining the intention of the<br /> parties.”<br /> 87. In contra distinction to novation of contract as<br /> contemplated by Section 62 of the Indian contract Act wherein,<br /> the original contract is substituted by a new contract such that the<br /> original contract need not be performed, in case of a<br /> Supplementary Contract, the original contract as well as the<br /> Supplementary Contract would both govern the rights and interest<br /> of the parties and the clauses of both the contracts would be<br /> enforceable in law to the extent those are not in conflict with one<br /> another.<br /> 88. Article 2(d) of original Lease Deed read with Article 5 of the<br /> Supplementary Lase Deed clearly denotes that the time restriction<br /> contemplated by the original Lease Deed had been subsequently<br /> relaxed. That apart, a conjoint reading of both the Articles projects<br /> a scenario which is reasonably susceptible to the conclusion that<br /> more than one interpretation of the time restriction clause in<br /> plausible, thus giving rise to ambiguity in the contract which is not<br /> Page 54 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> only latent but also patent in nature. We, therefore, find force in<br /> the submission of the learned counsel for the Petitioner that,<br /> having regard to the facts and circumstances of this case, it would<br /> be impossible to implement Article 2(d) on a composite project<br /> built with with additional built up area. <br /> 89. We have taken note of the stand of the Respondents that<br /> th<br /> Clause 2(d) of the Lease Deed dated 27 July 2006 puts in place a<br /> policy decision of the authority and, therefore, the same is not<br /> amenable to challenge by one of the contracting parties by<br /> invoking the jurisdiction of the Writ Court under Article 226 of the<br /> Constitution of India. However, we are of the view that such<br /> argument of the Respondents cannot be countenanced in view of<br /> the law laid down in the case of Industrial Promotion and<br /> Investments Corporation of Orissa Ltd., vs New India Assurance<br /> Co. Ltd. & Anr. (Supra), which categorically holds that the<br /> principle of “Contra Proferentum” would apply even in a case<br /> where there is ambiguity in the wording of the policy.<br /> 90. In so far as the undertaking given by the Petitioner to pay<br /> the additional premium and the consequent deposit of the amount<br /> of Rs.52,80,98,641/- is concerned, it must be noted herein that<br /> Page 55 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> the Writ Petitioner had not only objected to the demand for<br /> payment of additional premium/penalty for the alleged delay in<br /> completing the construction but had also deposited the amount<br /> under protest, thereby categorically conveying that the deposit<br /> was not made voluntarily or in discharge of its contractual<br /> obligation. Such protest was not only raised contemporaneously<br /> but the same was also in writing and unambiguous in nature,<br /> thus, putting the Respondent No. 1 on clear notice that the<br /> Petitioner has not accepted the decision in principle.<br /> 91. It also appears from the materials on record that apparently<br /> due to the pressure mounted by the Respondent No. 1 demanding<br /> payment of additional premium/penalty, the Petitioner was<br /> compelled to deposit the penalty as otherwise the Petitioner would<br /> not only be prevented from obtaining the Occupancy Certificate<br /> thus, causing serious economical prejudice to its interest but the<br /> same would also expose the Petitioner to the risk of termination<br /> of the Lease. Since the Petitioner had evidently made the deposit<br /> of penalty under duress and under compelling circumstances,<br /> hence, the principles of waiver, estoppel and acquiescence would<br /> not operate against the Petitioner in this case. From the protest<br /> Page 56 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> raised by the Petitioner, it was apparent that the Petitioner had<br /> reserved its right to agitate the matter at an appropriate time,<br /> thus, keeping the cause alive. Therefore, we hold that the claim<br /> for refund of the amount made by the Petitioner would not be<br /> barred under the law merely on account of the undertaking given<br /> by it.<br /> 92. Section 72 of the Indian Contract Act provides that a person<br /> who receives payment made by the payee under coercion must<br /> repay or return the same. <br /> 93. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury<br /> (1868) 12 Moo Ind App 65, the Privy Council has held that<br /> payment made not voluntarily but under species of compulsion<br /> would be liable to be returned.<br /> 94. In Valpy vs Manley (1845) 1 CP 594, the Court of England<br /> & Wales has held that money paid under the constraint of threats<br /> to interfere with the legal right is sufficient to make it recoverable.<br /> 95. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before<br /> the Privy Council, it was held that if a person pays money to save<br /> Page 57 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> his property which has been wrongly attached in execution, he is<br /> entitled to recover it.<br /> 96. Relying upon the case of Ram Kishen Singh (Supra), the<br /> Privy Council in the case of Kanhaya Lal vs The National Bank of<br /> 17<br /> India Limited has held that if a payment is made under protest<br /> and involuntarily, under coercion, the party making such payment<br /> would be entitled to claim refund of the same.<br /> 97. Materials on record unequivocally go to show that the<br /> deposit of penalty was dehors any proper demand raised in<br /> writing but was forced under the circumstances created by the<br /> Respondent No. 1, as noted above. Hence, by any stretch of<br /> reasonable reckoning, the deposit of the penalty as well as the<br /> undertaking, cannot be treated as voluntarily so as to prevent the<br /> Petitioner to seek refund of the amount in accordance with law. <br /> 98. In view of the foregoing discussion, we are of the un-<br /> hesitant opinion that the demand for payment of the<br /> penalty/additional premium for alleged delay in completing the<br /> construction was not maintainable under Article 2(d) & (e) of the<br /> Lease Deed. Moreover, such amount was realized by the<br /> <b>17</b><br /> 1913 SCC Online PC 4.<br /> Page 58 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> Respondent No. 1 from the Petitioner in a most arbitrary, high<br /> handed, unfair, and unreasonable manner by subjecting the<br /> Petitioner to undue pressure and threat of termination of the<br /> lease, thus putting its business interest in peril. The Petitioner was<br /> made to deposit the amount of penalty under coercion. The<br /> recovery of the penalty was also not preceded by any Show Cause<br /> Notice thus, acting in clear contravention of the principle of<br /> natural justice. Therefore, consequences under the law on such<br /> counts must follow.<br /> 99. Mr Samdani has vociferously argued that the Lease<br /> Agreement is in the prescribed Form-D of the regulations and,<br /> therefore, the same would have the force of a statute. As such,<br /> without challenging the statutory provisions, the Petitioner cannot<br /> refuse to comply with the terms of the Lease Deed. We are afraid,<br /> such argument of the learned Senior Counsel does not commend<br /> for acceptance by this Court. This we say so firstly, because the<br /> Petitioner has not assailed Article 2(d) of the Lease Deed dated<br /> th<br /> 27 July 2006 but has merely taken a stand that in view of the<br /> allotment of additional built-up area, additional time was required<br /> to complete the construction of the building. That is the reason<br /> Page 59 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> why Article 5 was inserted in the Supplementary Lease Deed<br /> th<br /> dated 5 November 2015, as a result of which Article 2(d) of the<br /> original Lease Deed stood automatically displaced. We find<br /> sufficient force in such argument of the Petitioner’s counsel.<br /> 100. Secondly, it is not a case where the construction was<br /> delayed due to negligence of the Lessee. On the contrary, it<br /> appears from the materials on record that the construction was<br /> delayed due to delay in issuance of statutory approvals including<br /> environment clearance . Since even as per the terms and<br /> conditions of the Lease Deed, the construction cannot commence<br /> without the approval of the plan and issuance of the<br /> Commencement Certificate, hence, by a reasonable and<br /> harmonious construction of the Articles of the Lease Deed, we<br /> hold that, the time line of four years for completing the<br /> construction under Article 2(d) ought to be computed from the<br /> date of issuance of Commencement Certificate and not from any<br /> prior date. Therefore, having regard to the facts and circumstances<br /> of this case, we find that even the condition precedent for<br /> th<br /> invoking the Article 2(d) of the Lease Deed dated 27 July 2006<br /> was not met in as much as the construction of the original built-up<br /> Page 60 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> area was evidently completed by the Petitioner within the period<br /> of four years from the date of issuance of the Commencement<br /> Certificate by the Respondent No. 1. As such, viewed from that<br /> angle also, in our opinion, there was no legal justification for the<br /> Respondent No.1 to insist on additional premium/penalty from<br /> the Petitioner even under Article 2(d) on account of alleged delay<br /> in completing of the construction beyond the period of four years.<br /> 101. In the case of Bank of Baroda, Mumbai & Anr (Supra),<br /> relied upon by Mr Samdani, the primary issue was as to whether<br /> the Respondent No. 1 (MMRDA) was bound to charge premium as<br /> per the provisions of the regulation as applicable during the<br /> relevant period because of the fact that the amendment to the<br /> regulations did not show that it had any retrospective effect. In<br /> Assistant Excise Commissioner & Ors. (Supra), it was held that<br /> even in a contract between the parties which is governed by<br /> statutory provisions, the terms and conditions of the contract<br /> would be binding both upon the Government and the Licensee<br /> and neither of them can depart therefrom. It was also not be open<br /> to any officer of the Government either to modify, amend or alter<br /> the terms and conditions. In Chaudhari Ran Beer Singh (Supra),<br /> Page 61 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> the Hon’ble Supreme Court has held that in matters of policy<br /> decision, the scope of interference by the Court is extremely<br /> limited. In Goetze (India) Ltd. (Supra), the Hon’ble Supreme<br /> Court has held that when the liability to pay the interest is<br /> statutory, there is no power of waiver of the same; in Transmission<br /> Corporation of Andhra Pradesh Ltd. (Supra), the Hon’ble Supreme<br /> Court has held that when the parties have entered into the field of<br /> contract simpliciter, their rights are controlled by the terms and<br /> conditions of the contracts executed by them. Therefore, in the<br /> absence of challenge to the contract, it would not be permissible<br /> for the Court to go behind the contact and permit questioning of<br /> the statutory jurisdiction vested in the regulatory commission.<br /> However, as would be apparent from the facts alluded to herein<br /> above, it is apparent that the issues involved in the Writ petition<br /> do not involve any challenge to a particular Clause/Article in the<br /> Lease Deed or to any statutory provision. On the contrary, the core<br /> controversy in this petition is pertaining to the question of<br /> application of the terms and conditions of the Lease Deed to the<br /> facts and circumstances of this case. Therefore, we are of the<br /> opinion that the ratio laid down in the abovenoted decisions relied<br /> Page 62 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> upon by Mr Samdani would not be of any assistance to the<br /> Respondents in the facts and circumstances of the present case.<br /> 102. Having held as above, we deem it appropriate to record<br /> here-in that although the learned Counsel for the Petitioner has<br /> argued that this case is squarely covered by the decision rendered<br /> in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said<br /> assertion has been strongly contested by the Respondent’s Counsel<br /> by submitting that in view of the observations made by the<br /> th<br /> Hon’ble Supreme Court in the order dated 27 July 2020, no<br /> reliance can be placed on the said judgment on any count for the<br /> purpose of deciding the present Writ Petition. On a careful<br /> examination of the decision in Raghuleela Builders Pvt. Ltd. &<br /> Anr . (Supra) we also find that the said decision was rendered in<br /> the facts of that case. However, it is important to note here-in that<br /> one of the question raised in the said proceedings was pertaining<br /> to the question as to whether, the decision of the MMRDA to apply<br /> the extension of time from 4 years to 6 years for completing the<br /> construction only to the post August 2015 was valid in the eyes of<br /> law, is also a question raised in the present proceeding. While<br /> Page 63 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> answering the said question, it was held in Raghuleela Builders<br /> Pvt. Ltd. & Anr . (Supra), as follows:-<br /> “38. The MMRDA constituted a single member committee of<br /> retired Judge of the Supreme Court to decide whether the<br /> MMRDA should give concession in recovery of premium<br /> considering the time required for plot owner to obtain<br /> permissions from various authorities for construction of building<br /> thereon. It is contended that one member committee has<br /> concluded that the charging of premium for extension of time<br /> for completing construction in Bandra-Kurla Complex area,<br /> specifically in case where additional built up area has been<br /> allotted by the MMRDA, was illegal. In its 138th meeting held<br /> on 26th August 2015, the MMRDA had acknowledged the<br /> difficulties faced by the lessees and that the condition of<br /> completion of construction within 4 years of the execution of the<br /> lease was adversely affecting the tendering process. The<br /> MMRDA had appointed an expert one man committee of retired<br /> Supreme Court Judge in that regard. The single member<br /> committee has advised that the period of 6 to 7 years be granted<br /> for completion of construction.<br /> 39. The lease deed entered into by the MMRDA with the<br /> lessees are as per form D, prescribed under the MMRDA<br /> (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease<br /> deed provides that for building plans to be submitted to country<br /> and town planing division for approval within 3 months from<br /> the date of lease. Clause 2(c) of the lease deed provides that no<br /> work is to be carried out until all plans, elevations, specifications<br /> are approved by the concerned authorities. Clause 2(d) provides<br /> that within 3 months of the approval of plans, the lessee is to<br /> commence construction which is to be completed within four<br /> years of the lease. Clause 2(e) provided for extension of time.<br /> Clause 2(e) contemplates a situation when the time for<br /> completion of construction can be extended, parties to the<br /> contract contemplated that certain uncertainties or situations<br /> may arise which may require more time for completion of the<br /> construction. In view of this, time is not essence of the contract<br /> between the parties and rightly so since construction of any<br /> building in Bandra Kurla Complex, several permissions are<br /> required from the various authorities and not only from the<br /> MMRDA who is planning authority for the Bandra Kurla area,<br /> namely,<br /> (1) The environmental clearance under the<br /> Environmental Impact Notification from the Ministry of<br /> Environment and Forest.<br /> Page 64 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> (2) Building height clearance from the Ministry of<br /> Civil Aviation because of the close proximity to Airport.<br /> (3) Clearance from the high rise committee.<br /> (4) Permission from the the MCGM.<br /> (5) Permission from the traffic police.<br /> Each of these authorities is required to be approached<br /> separately since there is no single window clearance / nodal<br /> agency which would co-ordinate with the aforesaid authorities<br /> for granting of all necessary permissions. In view of the delay in<br /> obtaining permissions which are beyond the control of lessee, no<br /> work could be carried out as per clause 2(d) of the lease deed.<br /> 40. The MMRDA had issued a letter of allotment dated 20th<br /> March 2012 allotting additional 67,000 sq. meters at<br /> consideration of 984 crore. Part payment of Rs.196 crore was<br /> received on 20th March 2012. The supplementary lease deed<br /> was executed for additional built up area of 67,000 sq. meters.<br /> The letter of allotment dated 20th March 2012, the acceptance<br /> of part payment of consideration for additional built up area<br /> allotted, diluted the time period of four years and there was no<br /> question of application of condition of occupation certificate for<br /> built up area within 4 years when additional built up area was<br /> allotted for raising additional 11 floors on the same building.<br /> 41. The resolution passed by MMRDA for extending the time<br /> period for completing construction from 4 years to 6 years only<br /> for leases executed after 26th August 2015 also appears to be<br /> arbitrary, discriminatory, without basis and justification. The said<br /> set of circumstances are prevailing for the construction being<br /> carried out under the leases executed prior to 26th August 2015.<br /> Therefore, not extending this benefit of this extension of time<br /> from 4 years to 6 years to the prior leases in respect of other<br /> plots in the BKC, is completely arbitrary, discriminatory,<br /> capricious and violative of Article 14 of the Constitution of<br /> India. There is no reasonable basis or justification for this<br /> decision. The classification sought to be made between the<br /> leases prior and subsequent to 26th August 2015 is not founded<br /> on intelligible differentia and neither does this differentia has<br /> any logic, rational, nexus to the object sought to be achieved.<br /> The MMRDA has sought to treat equals as unequal. The lessees<br /> of plots are being discriminated on the basis of their date of<br /> execution of their leases. The lessees who are placed in similar<br /> circumstances prevailing for construction in Bandra Kurla area<br /> are entitled to equal treatment guaranteed under Article 14 of<br /> the Constitution of India.”<br /> Page 65 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 103. It is not in dispute that the Lease Deed involved in<br /> Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was also in Form ‘D’<br /> of the Regulations of 1977 wherein the same Articles 2 (d) and (e)<br /> were involved. The Writ Petitioner there-in was also a similarly<br /> situated lessee, from whom, penalty for delay in completing the<br /> construction beyond the period of 4 years was raised by the<br /> Respondent No 1. The Petitioner in that case had also raised<br /> identical plea as regards the applicability of the time extension<br /> th<br /> Clause. The Lease Deed in that case was also executed prior to 26<br /> August, 2015. If that be so there can be no doubt about the fact<br /> that the legal principles discussed and the findings & observations<br /> recorded in paragraphs 38 and 41 of Raghuleela Builders, in so<br /> far as uniform applicability of the 6 years time extension clause is<br /> concerned, would be applicable to the facts of the present case as<br /> well. Therefore, we hold that by applying the principles parity, the<br /> Respondent No. 1 would be duty-bound to extend the same<br /> benefit of extension of time for completion of construction to six<br /> years to the present Petitioner as well. <br /> 104. In the facts and circumstances of this case, we are also of<br /> the opinion that there is no legal justification for the Respondent<br /> Page 66 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> No. 1 to confine the benefit of the time extension clause only to<br /> th<br /> those Lease Agreements which were executed after 26 August<br /> 2015 as such an approach would be highly arbitrary and<br /> discriminatory in nature. Therefore, having regard to the peculiar<br /> facts and circumstances of this case, we do not find any justifiable<br /> ground to take a different view on the aforesaid issue. <br /> 105. Law is well settled that for maintaining judicial discipline<br /> and propriety, a decision rendered by a Coordinate Bench on the<br /> same issue must be respected and followed by a Coordinate<br /> Bench. In the case of Mary Pushpam vs. Televi Curusumary &<br /> 18<br /> Ors. the Hon’ble Supreme Court has observed that when a<br /> decision of a Coordinate Bench of the same High Court is brought<br /> to the notice of the Bench, it is to be respected and would be<br /> binding, subject to the right of the Bench of such co-equal forum<br /> to take a different view and refer the question to a larger Bench.<br /> In other words, any decision of a Coordinate Bench would be<br /> binding on a Bench of equal strength subject to the condition that<br /> if a different view is sought to be taken in the matter, then the<br /> issue would have to be referred to a larger Bench.<br /> <b>18</b><br /> (2024) 1 SCR 11.<br /> Page 67 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 106. The above legal principle has taken a firm footing in the<br /> Indian Jurisprudence by a long line of judicial pronouncements.<br /> We do not deem it necessary to burden this judgment by referring<br /> to all those decisions. However, suffice it to mention here-in that<br /> unless there are justifiable grounds to take a different view in the<br /> matter warranting reference to a larger Bench, the previous<br /> decision of a coordinate Bench would be binding on a Bench of<br /> equal strength.<br /> 107. Consequently, it is held that even as per Article 2(d) & (e) of<br /> th<br /> the Lease Deed dated 27 July 2006, the Writ Petitioner would be<br /> entitled to six years time for completion of the construction with<br /> th<br /> effect from 11 July 2009, i.e., the date of issuance of the<br /> amended Commencement Certificate. Since, the construction of<br /> the initial built-up area was completed in February, 2014, i.e.,<br /> th<br /> within six years from 11 June 2009, hence, Articles 2(d) & (e) of<br /> th<br /> the Lease Deed dated 27 July 2006 could not have been invoked<br /> by the Respondent No. 1 in the facts and circumstances of the<br /> present case.<br /> 108. In the above context, it would be further pertinent to note<br /> herein that the Writ Petitioner, being aggrieved by the order dated<br /> Page 68 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> th<br /> 20 October, 2022 passed by this Court in the present proceeding<br /> granting adjournment, had earlier approached the Hon’ble<br /> Supreme Court by filing SLP (C) Diary No.(s) 15384/2023, inter<br /> alia contending that the case of the Writ Petitioner was covered by<br /> the judgment of Raghuleela Builders Pvt. Ltd. & Anr. (Supra) and,<br /> therefore, there was no justification for the High Court to adjourn<br /> the Writ Petition, thus keeping the Writ Petition pending as the<br /> same could have been disposed of in terms of the judgment<br /> rendered in the case of Raghuleela Builders Pvt. Ltd. & Anr.<br /> (Supra). The aforesaid Special Leave Petition was disposed of by<br /> th<br /> the Hon’ble Supreme Court by order dated 28 April 2023, by<br /> making a request to this High Court to finally decide the Writ<br /> Petition expeditiously, on its own merit, preferably within a period<br /> of two months. In the said order it was also observed that it would<br /> be open to the Writ Petitioner to demonstrate, whether their case<br /> is also covered by the observations contained in the Judgment and<br /> th<br /> Order dated 20 November 2019 rendered in the case of<br /> Raghuleela Builders Pvt. Ltd. & Anr. (Supra). <br /> 109. For the reasons stated above, this Writ Petition succeeds and<br /> the same is hereby allowed in terms of payer clauses (a) and (b).<br /> Page 69 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b><br /><br /> Sunteck-oswp-2377-2018-J-R.doc<br /> <br /> 110. Consequently, we hold that the Petitioner is entitled for the<br /> refund of the amount of Rs.52,80,98,641/- (Rupees Fifty Two<br /> Crores Eighty Lakhs Ninety Eight Thousand Six Hundred and Forty<br /> One only) deposited with the Respondent No.1. The Respondent<br /> No 1 is, therefore, directed to refund the aforesaid amount to the<br /> Writ Petitioner within a period of 90 (ninety) days from the date<br /> of receipt of the Certified Copy of this order, failing which, the<br /> amount would carry interest at the rate of 14% per annum, i.e. the<br /> same rate which was payable by the Petitioner under the Lease<br /> Agreement due to delay in paying premium, to be calculated from<br /> the date of this order till the date of the refund. <br /> 111. With the above observations, the Rule is made absolute.<br /> 112. The Writ Petition stands disposed of.<br /> 113. Parties to bear their own costs.<br /> (SUMAN SHYAM, J) (CHIEF JUSTICE) <br /> Page 70 of 70<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:22 :::</i></b></div>