Adyaraj Developers Private Limited vs Airports Authority Of India & Ors.

Court
Delhi High Court

$~59
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: November 19 , 2026
# CNR No. DLHC010550872026
+ W.P.(C) 16940/2026, CM APPL. 79245/2026 & CM APPL.
79246/2026
ADYARAJ DEVELOPERS PRIVATE
LIMITED .....Petitioner
Through: Mr. Ashish Mohan, Sr. Adv.
with Mr. Rishabh Saxena, Mr.
Addtya Kapoor & Mr. Harsh
Ahuja, Advs.
versus
AIRPORTS AUTHORITY OF
INDIA & ORS. .....Respondents
Through: Mr. Digvijay Rai, SC &
Mr. Arohit Mishra, Adv. with
Mr. Gagan Kochar, AGM
(Law) & Ms. Kashish Singhal,
JE (Law) for AAI
CORAM:
HON'BLE MR. JUSTICE AMIT MAHAJAN
AMIT MAHAJAN, J. (Oral)
1. With the consent of the parties, the matter was heard finally.
2. By way of the present petition, the petitioner challenges the
notice dated 17.11.2026 issued by the Airports Authority of India
(AAI), directing forfeiture of its Earnest Money Deposit (EMD) of
₹1,05,42,000/-.
3. Briefly stated, the petitioner submitted a bid in a tender invited
by AAI for development and upgradation of Saharsa Airport at an
estimated cost of ₹35.14 crores.
Signature Not Verified
W.P.(C) 16940/2026 Page 1 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

4. It is the petitioner's case that it submitted its bid along with the
requisite EMD of ₹1,05,42,000/- through a Bank Guarantee dated
06.06.2026. However, owing to an inadvertent clerical error while
filling the BOQ, the quoted amount was reflected as ₹24.95 instead of
the intended amount of ₹24,95,00,000/-. Upon opening of the
financial bids on 14.07.2026, the petitioner was declared L-1.
5. Immediately upon noticing the error, the petitioner, vide letter
dated 21.07.2026, informed AAI of the inadvertent error, furnished a
detailed component-wise price assessment aggregating to
₹24,95,00,000/- and expressed its willingness to execute the work at
the said amount.
6. Thereafter, AAI issued a Show Cause Notice dated 03.09.2026,
alleging that the petitioner had denied execution of the work at the
quoted rates and calling upon it to show cause why its EMD should
not be forfeited. The petitioner submitted a detailed reply dated
08.09.2026, explaining the inadvertent nature of the error reiterating
that it had neither withdrawn nor sought to unilaterally modify its bid.
7. It is further the petitioner's case that, without affording any
hearing, AAI cancelled the tender on 14.10.2026 on administrative
grounds. However, vide the impugned notice dated 17.11.2026, AAI
rejected the petitioner's reply and directed forfeiture of the entire EMD
of ₹1,05,42,000/-, threatening encashment of the Bank Guarantee in
the event of non-payment within three days.
8. The learned counsel for the AAI submits that the amount
entered by a bidder on the CPP Portal is also automatically reflected in
words, leaving no scope for any inadvertent error. He submits that,
Signature Not Verified
W.P.(C) 16940/2026 Page 2 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

having emerged as the L-1 bidder, the petitioner, vide letter dated
21.07.2026, sought acceptance of a modified bid amount and, in the
alternative, requested withdrawal of its bid in the event the revised
amount was not acceptable to AAI.
9. He further submits that Clause 36 of the General Guidelines for
Bidders (GGB) prohibits withdrawal or modification of the bid during
its validity period and empowers AAI to forfeit the entire EMD in
such circumstances. He, therefore, submits that the AAI was well
within their rights to forfeit the EMD.
10. This Court is not persuaded by the stance taken by the AAI in
the present case.
11. In the opinion of this Court, the petitioner having quoted a price
of ₹24.95/-, does not require any debate as to whether the same was
entered inadvertently, since the figure itself is self-evident. A tender
invited for the development and upgradation of an airport, at an
estimated cost of ₹35.14 crores, could not possibly be executed for a
meagre amount of ₹24.95/-.
12. It is also pertinent to note that the petitioner, upon realising the
inadvertent error after opening of the financial bids on 14.07.2026,
promptly approached the AAI vide letter dated 21.07.2026, i.e. within
a period of one week, bringing the error to its notice and requesting
that its bid be considered at the intended amount of ₹24,95,00,000/-.
Thus, the conduct of the petitioner indicates that the same was a bona
fide mistake.
13. The respondents have contended that Clause 36 of the Tender
Document expressly provides that where a tenderer withdraws its
Signature Not Verified
W.P.(C) 16940/2026 Page 3 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

tender or modifies its bid in terms and conditions which are not
acceptable to the Department, the AAI is entitled to forfeit the entire
EMD. The respondents have also placed reliance on the judgments of
the Supreme Court in Villayati Ram Mittal (P) Ltd. v. Union of India
: (2010) 10 SCC 532 , and Pooja Ceratech Private Limited v. Oil and
Natural Gas Corporation Ltd. : 2021 SCC OnLine SC 3504 .
14. In the opinion of this Court, the aforesaid judgments are not
applicable being distinguishable on facts. In Villayati Ram Mittal (P)
Ltd. (supra), the bidder, after the opening of the tender, sought to
correct a figure, on account of an alleged calculation mistake in its
bid, as a consequence of which the value of its offer increased from
₹32 crores to ₹41 crores. The Hon’ble Supreme Court found that the
bidder was not willing to stand by its original offer and was willing to
execute the work only at the revised bid amount. Similarly, in Pooja
Ceratech Private Limited (supra), the bidder had sought permission to
modify its price bid on the ground that a calculation mistake had been
committed while quoting the price, and the Hon’ble Supreme Court
upheld the action of the authority in forfeiting the security deposit in
terms of the relevant tender condition. The aforesaid decisions,
therefore, arose in circumstances where the bidders had sought to vary
their offers during the period of validity.
15. The facts of the present case, however, stand on a different
footing. As noticed hereinabove, the petitioner did not seek to
substitute one commercial offer with another. Rather, it promptly
brought to the notice of the AAI that the figure of ₹24.95 had been
entered inadvertently and explained that the intended bid amount was
Signature Not Verified
W.P.(C) 16940/2026 Page 4 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

₹24,95,00,000/-. Such as error is evidently a bona fide error as
evidently the petitioner could not have submitted an offer of ₹24.95
for the development and upgradation of an airport, which had been
floated at an estimated cost of ₹35.14 crores. The petitioner had also
expressed its willingness to execute the work at the intended price of
₹24,95,00,000/-. The alternative request for withdrawal was made
only in the event the AAI insisted upon treating the inadvertently
entered figure as the petitioner's actual bid.
16. There is no quarrel with the proposition that where a bidder
withdraws or modifies its bid during the period of validity, in breach
of the terms of the tender, the authority inviting the tender may be
entitled to forfeit the EMD in accordance with the applicable tender
conditions. However, the mere existence of such a clause cannot be
construed to mean that forfeiture must follow in every case,
irrespective of the nature and circumstances of the alleged withdrawal
or modification. Where the bidder has committed a bona fide and
apparent error, promptly brought the same to the notice of the
authority, the penalty imposed upon the bidder ought to also be
proportionate.
17. The legal position in this regard stands settled by the judgment
of the Supreme Court in ABCI Infrastructures (P) Ltd. v. Union of
India , (2025) 6 SCC 813 , wherein the Hon’ble Supreme Court
considered an almost identical situation involving an inadvertent
omission of zeros in a financial bid, resulting in the bid amount being
reflected as a grossly unrealistic figure. The Hon’ble Supreme Court
held that where the mistake in the bid is patent and self-evident, and
Signature Not Verified
W.P.(C) 16940/2026 Page 5 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

the bidder promptly brings the same to the notice of the concerned
authority upon its discovery, equitable relief may be granted. The
Court further emphasised that the doctrine of proportionality would
apply even in contractual matters where the error is writ large and the
circumstances merit equitable intervention. The relevant extract of the
aforesaid judgment is reproduced hereinbelow:
“15. The short question before us is whether BRO was justified in
accepting the bid of Rs 1569, and on the failure of the appellant to
execute the agreement asking for forfeiture vide encashment of
bank guarantee of Rs 15,04,64,000.
16. A mistake may be unilateral or mutual, but it is always
unintentional. If it is intentional, it ceases to be a mistake. Mistakes
or errors, though avoidable, are committed inadvertently. They
have varied consequences in law. As per Section 20 of the Contract
Act, 1872 (hereinafter “the Contract Act”) whereby both parties to
an agreement are under a mistake as to matter of fact essential to
an agreement, the agreement is void. The Explanation to Section
20 says that an erroneous opinion as to the value of the thing
which forms the subject-matter of an agreement is not deemed to
be a mistake as a matter of fact.
17. This will not be a case covered by Section 20 of the Contract
Act. However, this is not the first time that this question has arisen
either before this Court or courts outside of India. In W.B. SEB v.
Patel Engg. Co. Ltd. [W.B. SEB v. Patel Engg. Co. Ltd., (2001) 2
SCC 451] , this Court referred to para 84 of American
Jurisprudence (2nd Edn., Vol. 64 at p. 944), which reads: (SCC p.
468, para 26)
“26. … ‘As a general rule, equitable relief will be granted to
a bidder for a public contract where he has made a material
mistake of fact in the bid which he submitted, and where,
upon the discovery of that mistake, he acts promptly in
informing the public authorities and requesting withdrawal of
his bid or opportunity to rectify his mistake particularly when
he does so before any formal contract is entered into.’ ”
18. Thereafter, reference was made to two decisions of the
Supreme Court of the United States in Moffett Hodgkins Clarke
Co. v. City of Rochester [Moffett Hodgkins Clarke Co. v. City of
Rochester, 1900 SCC OnLine US SC 154 : 44 L Ed 1108 : 178 US
Signature Not Verified
W.P.(C) 16940/2026 Page 6 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

373 (1900)] and Hearne v. Marine Insurance Co. [Hearne v.
Marine Insurance Co., 22 LEd 395 : 87 US 488 (1874)] wherein it
is observed that where the mistake is apparent and the party
promptly informs the other as soon as it is discovered but before
entering into a contract, equitable orders may be passed. However,
the mistake should be clear, explicit, and undisputed. Further, a
mistake on one side may be a ground for rescinding but not for
reforming a contract where the minds of the parties have not met,
yet there is no contract and hence none to be rectified. Relief may
not be granted where it is inequitable.
19. While accepting this legal position, this Court in W.B. SEB
[W.B. SEB v. Patel Engg. Co. Ltd., (2001) 2 SCC 451] has
propounded the following exceptions to the general principle on a
person seeking relief in equity on account of mistake: (SCC p. 469,
para 27)
“27. … (1) Where the mistake might have been avoided by
the exercise of ordinary care and diligence on the part of the
bidder; but where the offeree of the bid has or is deemed to
have knowledge of the mistake, he cannot be permitted to
take advantage of such a mistake.
(2) Where the bidder on discovery of the mistake fails to act
promptly in informing to the authority concerned and request
for rectification, withdrawal or cancellation of bid on the
ground of clerical mistake is not made before opening of all
the bids.
(3) Where the bidder fails to follow the rules and regulations
set forth in the advertisement for bids as to the time when
bidders may withdraw their offer; however where the mistake
is discovered after opening of bids, the bidder may be
permitted to withdraw the bid.”
20. This judgment also refers to a decision of the Superior Court of
New Jersey in Spina Asphalt Paving Excavating Contractors Inc.
v. Borough of Fairview [Spina Asphalt Paving Excavating
Contractors Inc. v. Borough of Fairview, 304 NJ Super 425 (App
Div 1997)] . The said case is related to the rectification of mistakes
in the bid specifications. Relief granted in the said case was upheld
by the Superior Court with the caution that generally an error in
the statement of a price would not be treated as immaterial and it
is only when the case of error was patent and the true intent of the
bidder obvious that such an error might be disregarded.
21. In W.B. SEB [W.B. SEB v. Patel Engg. Co. Ltd., (2001) 2 SCC
Signature Not Verified
W.P.(C) 16940/2026 Page 7 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

451] , the private party, the bidder did not succeed for several
reasons, including the factum that the error was not obvious and
self-evident. Further, the correction of such mistakes after one-
and-a-half months after the opening of the bids would have
violated the express clauses relating to the computation of the bid
amount. Thus, waiver of the rule or conditions in favour of the one
bidder would have created unjustifiable doubts in the minds of
others impairing the rule of transparency and fairness and
providing room for manipulation for awarding contracts.
22. The decision in W.B. SEB [W.B. SEB v. Patel Engg. Co. Ltd.,
(2001) 2 SCC 451] was referred to and followed where a relief to
the bidder was apparent before this Court in Omsairam Steels &
Alloys (P) Ltd. v. State of Odisha [Omsairam Steels & Alloys (P)
Ltd. v. State of Odisha, (2024) 9 SCC 697 : (2024) 4 SCC (Civ)
279 : 2024 INSC 520] . This decision observes that while the Court
must exercise a lot of restraint in exercising the power of judicial
review in contractual commercial matters, the doctrine of
proportionality nevertheless applies when the error or mistake is
writ large and equity merits the grant of some relief.
23. Reference was made to the decision in Coimbatore District
Central Coop. Bank v. Employees Assn. [Coimbatore District
Central Coop. Bank v. Employees Assn., (2007) 4 SCC 669 :
(2007) 2 SCC (L&S) 68] where discussing the question of
proportionality or punishment imposed on the striking workmen it
is observed: (SCC pp. 678-79, paras 18-20)
“18. “Proportionality” is a principle where the court is
concerned with the process, method or manner in which the
decision-maker has ordered his priorities, reached a
conclusion or arrived at a decision. The very essence of
decision-making consists in the attribution of relative
importance to the factors and considerations in the case. The
doctrine of proportionality thus steps in focus true nature of
exercise—the elaboration of a rule of permissible priorities.
19. de Smith states that “proportionality” involves
“balancing test” and “necessity test”. Whereas the former
(balancing test) permits scrutiny of excessive onerous
penalties or infringement of rights or interests and a manifest
imbalance of relevant considerations, the latter (necessity
test) requires infringement of human rights to the least
restrictive alternative. [Judicial Review of Administrative
Action (1995), pp. 601-05, para 13.085; see also Wade &
Forsyth: Administrative Law (2005), p. 366.]
Signature Not Verified
W.P.(C) 16940/2026 Page 8 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

20. In Halsbury's Laws of England (4th Edn.), Reissue, Vol.
1(1), pp. 144-45, para 78, it is stated:
‘The court will quash exercise of discretionary powers in
which there is no reasonable relationship between the
objective which is sought to be achieved and the means used
to that end, or where punishments imposed by administrative
bodies or inferior courts are wholly out of proportion to the
relevant misconduct. The principle of proportionality is well
established in European law, and will be applied by English
courts where European law is enforceable in the domestic
courts. The principle of proportionality is still at a stage of
development in English law; lack of proportionality is not
usually treated as a separate ground for review in English
law, but is regarded as one indication of manifest
unreasonableness.’ ”
Accordingly, in the said case the appellant was directed to make a
payment of Rs 3 crores within the stipulated period and on the said
payment the security deposit in the form of a bank guarantee of
over Rs 9 crores was directed to be refunded.
24. The present case does not fall under any exception, for the
error or mistake in quoting a price of Rs 1569, does not require
any argument and cannot be debated as it is self-evident. A
contract of this nature for an estimated value of more than Rs 1500
crores spread over 48 months requiring construction of roads and
tunnels of the length of more than 4 km in a hilly terrain can never
be executed for a mere Rs 1569.
25. At the same time, we agree with BRO, that the appellant was at
fault and had made the mistake, of having failed to add the
required zeros in the financial bid. The plea of a system glitch
should not be accepted, as others had successfully uploaded their
bids without a problem.
26. BRO justified encashing the bank guarantee by citing delays
caused by issuing a second notice inviting bids. This claim is
baseless, as BRO was aware of the Rs 1569 error. Instead of
declaring the bid non est due to the clear mistake, BRO asked the
appellant to justify the bid, cancelled the notice, declared the
appellant a defaulter, invoked the bank guarantee, and issued a
fresh notice inviting bids.
27. Thus, BRO's claim that the delay was entirely due to the
appellant's mistake is flawed, ignoring BRO's own lapses.
Mistakes, including by authorities, should be resolved through
Signature Not Verified
W.P.(C) 16940/2026 Page 9 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

corrective steps. A practical approach could have avoided the
delay, which was caused by BRO's refusal to acknowledge the
appellant's genuine error and the unwarranted cancellation of the
bid.
28. The alleged two-month delay by the appellant is incorrect. The
error, submitted on 3-6-2023, became apparent only when
financial bids were opened on 24-8-2023. The appellant promptly
acknowledged the mistake on 25-8-2023.
29. A fresh tender was issued, and financial bids opened on 9-1-
2024 revealed the lowest bid of Rs 1290 crores, lower than the
earlier Rs 1351 crores. Thus, while delayed, the contract was
awarded at a lower cost.
30. In view of the aforesaid discussion, we direct the appellant to
pay Rs 1 crore to BRO, as a consequence of their error. Upon
receiving this payment, BRO shall return the appellant's original
bank guarantee or demand draft of Rs 15.04 crores within one
week.
31. The impugned judgment [ABCI Infrastructure (P) Ltd. v. Union
of India, 2023 SCC OnLine HP 1871] is set aside, and the appeal
is allowed in the aforesaid terms. There would be no order as to
costs.”
18. Applying the aforesaid principles to the facts of the present
case, this Court is conscious of the fact that the petitioner is also at
fault in having failed to enter the correct amount in the financial bid.
However, such an error, by itself, cannot be a sufficient ground for
forfeiture of the entire EMD, particularly when the mistake was
apparent on the face of the bid and was promptly brought to the notice
of the AAI within a week of opening of the financial bids.
19. It is also pertinent to note that the AAI itself cancelled the
tender on 14.10.2026, citing administrative reasons. The cancellation
was not attributed to any default on the part of the petitioner, nor did
the cancellation notice record that the petitioner had withdrawn its bid
or otherwise impeded the tender process. Further, the AAI has not
Signature Not Verified
W.P.(C) 16940/2026 Page 10 of 11
Signed By:HARMINDER
KAUR
Signing Date:23.11.2026
20:51:54

demonstrated that the petitioner’s inadvertent error resulted in any
actual financial loss or other prejudice to the respondents. The tender
was cancelled on administrative grounds, independently of the
proceedings initiated against the petitioner.
20. Thus, applying the doctrine of proportionality to the facts of the
present case, this Court is of the opinion that the petitioner made a
bona fide mistake which, in the totality of the circumstances, did not
result in any financial loss or prejudice to the AAI, particularly when
the tender itself was subsequently cancelled by the AAI on
administrative grounds. In such circumstances, forfeiture of the entire
EMD would be wholly disproportionate. This Court, therefore, does
not find any justification for encashment of the petitioner's EMD or
for imposition of any penalty upon it.
21. In view of the above, the present petition is allowed and the
impugned notice dated 17.11.2026 is set aside.
22. The AAI is directed to return the petitioner’s bank guarantee
within a period of 3 weeks.
AMIT MAHAJAN, J
NOVEMBER 19, 2026
“SS”