Shri Krishan Baldev Bansal vs Balbir Singh Tyagi & Ors.
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment reserved on: 23.09.2026
Judgment pronounced on: 05.10.2026
Judgment uploaded on: 05.10.2026
# CNR No. DLHC010079682026
+ FAO(COMM) 64/2026 & CM APPL. 14176/2026
SHRI KRISHAN BALDEV BANSAL ......Appellant
Through: Mr. Satish Sahai and Ms.
Malaika Farhat, Advs.
versus
BALBIR SINGH TYAGI & ORS. .....Respondents
Through: Mr. Deepak R. Dahiya, Adv.
for R-1 and R-2.
CORAM:
HON'BLE MR. JUSTICE ANIL KSHETARPAL
HON'BLE MR. JUSTICE BHARAT PARASHAR
J U D G M E N T
ANIL KSHETARPAL, J.:
1. Through the present Appeal, the Appellant, who was
Respondent No.3 before the learned Sole Arbitrator, assails the order
dated 28.11.2025 [„Impugned Order‟] passed by the learned District
Judge in OMP (COMM.) No.25/2024 titled Balbir Singh Tyagi v.
Yogesh Bansal . By the Impugned Order, the learned District Judge
has set aside the arbitral award dated 23.12.2023 passed by the learned
Sole Arbitrator. The Appellant seeks setting aside of the Impugned
Order and restoration of the arbitral award insofar as it awards to him
the amount paid by him towards discharge of the liability of the
partnership firm to Union Bank of India, together with interest.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 1 of 28
2. The issue which arises for consideration in the present Appeal
is whether the learned District Judge was justified in setting aside the
arbitral award dated 23.12.2023 on the ground that the learned Sole
Arbitrator had adjudicated only the claim of the Appellant arising out
of the payment made by him towards the liability of the partnership
firm to Union Bank of India, notwithstanding the statement made by
the parties before the learned Arbitrator on 11.12.2023 that the award
may be passed only in respect of the said claim. A further question
which arises is whether the claim of the Appellant for reimbursement
of the amount paid by him towards the liability of the partnership firm
was beyond the scope of the arbitration agreement merely because the
Appellant had also stood as a guarantor for the cash-credit facility
availed by the firm.
FACTUAL MATRIX:
3. In order to appreciate the controversy involved in the present
Appeal, the relevant facts, in brief, are required to be noticed.
4. On 15.09.2004, Respondent No.3, Sh. Yogesh Bansal, and
Respondent No.1, Sh. Balbir Singh Tyagi, entered into a partnership
for carrying on the business of retailing electronic goods under the
name and style of M/s Nova Electro World (Respondent No.4 herein).
Respondent No.1 joined his wife, Respondent No.2, Smt. Mithlesh
Tyagi, as a sleeping partner, while Respondent No.3 joined his father,
the present Appellant, Sh. Krishan Baldev Bansal, as a partner. Under
the partnership arrangement, Respondent No.1 and Respondent No.2
together held 55% share, whereas Respondent No.3 and the Appellant
together held 45% share in the partnership firm.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 2 of 28
5. For carrying on the business of the partnership firm, the
partners took on rent premises bearing No.28-B, Block-A, Defence
Enclave, Madhu Vihar, opposite Hind Apartment, Sector-5, Dwarka,
New Delhi, at a monthly rent of Rs.10,000/-. The said premises were
jointly owned in equal shares by Respondent No.3 and Respondent
No.1. The partnership firm continued its business until September
2006. While Respondent No.3 subsequently asserted that the firm was
mutually decided to be dissolved in September 2006, disputes arose
between the parties concerning the dissolution of the firm, rendition of
accounts and settlement of the respective claims of the partners.
5. It is relevant to note that, during the subsistence of the
partnership, the firm availed a cash-credit facility of Rs.25,00,000/-
from the Union Bank of India, Janakpuri Branch. The present
Appellant, who was one of the partners of the firm, also stood as a
guarantor in respect of the said facility and, in that capacity, had
furnished security in respect of his property. According to the
Appellant, the liability arising from the said facility was a liability of
the partnership firm and not a personal liability incurred by him for his
own benefit.
6. The said cash-credit facility was not duly discharged by the
partnership firm. The material placed before the learned Sole
Arbitrator disclosed that an amount of approximately Rs.23.76 lakh
was outstanding towards the said facility. The Appellant received a
notice from the Bank in relation to the outstanding liability and,
thereafter, deposited a sum of Rs.23,90,000/- from his own funds
towards the settlement of the Bank‟s claim. The payment was made by
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 3 of 28
the Appellant in full and final settlement of the outstanding liability,
and a settlement certificate dated 28.04.2008 was also issued by the
Bank. The Appellant‟s case was that, having discharged a liability
which was otherwise that of the partnership firm, he was entitled to
recover from the other partners their respective shares in the amount
so paid by him.
7. The Appellant accordingly raised a claim before the learned
Sole Arbitrator in respect of the amount paid by him to the Bank.
While computing the amount recoverable from the other partners, the
Appellant deducted his own share of 10% from the amount of
Rs.23,90,000/- paid by him. The amount remaining thereafter was
Rs.21,51,000/-, which, according to the Appellant, was liable to be
contributed by the remaining partners in accordance with their
respective shares in the partnership.
8. The claim relating to the Bank liability was specifically
contested by Respondent Nos.1 and 2. However, in their written
statement, Respondent Nos.1 and 2 did not dispute that the partnership
firm had availed the loan/cash-credit facility from Union Bank of
India or that the Appellant, who had stood as guarantor, had made the
payment towards the outstanding liability. Their defence, as recorded
in the arbitral proceedings, was essentially that the payment made by
the Appellant was subject to the final settlement of the accounts of the
partnership firm and that the Appellant could not independently seek
recovery of the amount without an appropriate determination of the
accounts and liabilities of the firm.
9. During the arbitral proceedings, the Appellant was also cross-
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 4 of 28
examined in relation to the payment made by him to the Bank. He
stated, inter alia , that he had not consulted the other partners before
depositing the amount of Rs.23,90,000/- with the Bank and that he
had thereafter raised his claim for recovery of the amount from the
other partners. It was also brought out in his cross-examination that he
had not instituted separate proceedings for recovery of the said
amount.
10. Respondent No.1, Sh. Balbir Singh Tyagi, who entered the
witness box as RW-1, also admitted during cross-examination that the
firm had availed an overdraft/cash-credit facility of Rs.25,00,000/-
from Union Bank of India, that the Appellant had stood as guarantor
in respect thereof and that neither he nor his wife had made payment
towards the said liability. He was also questioned regarding the
payment stated to have been made by the Appellant towards discharge
of the Bank‟s claim. Thus, the question whether the partnership firm
had incurred the Bank liability and whether the Appellant had made
payment towards the same formed part of the evidence led before the
learned Sole Arbitrator.
11. The learned Sole Arbitrator considered the pleadings, affidavits
and the evidence, including the cross-examination of the parties, and
recorded a finding that the partnership firm had availed the cash-credit
facility, that the Bank had raised a demand in respect of the
outstanding amount, and that the Appellant had deposited the amount
from his own funds towards discharge of the said liability. The learned
Sole Arbitrator further found that the payment was not made for any
personal benefit of the Appellant and that no part of the amount paid
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 5 of 28
by him had thereafter been returned to him.
12. The maintainability of the Appellant‟s claim was, however,
questioned by Respondent No.1 at a later stage of the proceedings.
The objection was that, since the Appellant had made the payment in
his capacity as a guarantor, he ought to have instituted separate
proceedings for recovery of the amount and that the claim could not
be adjudicated in the arbitration proceedings. The learned Sole
Arbitrator rejected the said objection, principally noticing that no such
objection had been taken in the written statement filed by Respondent
No.1. The learned Sole Arbitrator also considered the judgment of the
Supreme Court in S.N. Prasad v. Monnet Finance Ltd. & Ors. , Civil
Appeal No.9224/2010, decided on 22.10.2020, and distinguished the
same on the ground that the factual situation in the present case
concerned a partner who had made payment towards the liability of
the partnership firm, whereas the decision relied upon by Respondent
No.1 arose in the context of a loan agreement containing an arbitration
clause.
13. It is significant for the controversy before this Court that, on
11.12.2023, the parties and their respective counsel made a statement
before the learned Sole Arbitrator that the award may be passed only
in respect of the claim raised by Respondent No.3, i.e. the present
Appellant, concerning the loan amount paid by him to the Bank as
guarantor. The learned Sole Arbitrator recorded the said statement and
proceeded on the basis that the other claims raised by the parties were
not required to be adjudicated in view of the said understanding.
14. The aforesaid course of proceedings assumes significance
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 6 of 28
because the arbitral proceedings had otherwise involved claims and
counterclaims relating to the dissolution of the partnership, rendition
of accounts, goodwill, the partnership premises and other alleged
liabilities between the parties. Respondent Nos.1 and 2 had, in their
pleadings, also raised a counterclaim seeking, inter alia, a declaration
regarding the dissolution of the firm, damages towards alleged loss of
goodwill, relief concerning the tenancy of the premises, and
production and settlement of the accounts of the partnership firm.
However, in view of the statement recorded on 11.12.2023, the
learned Sole Arbitrator proceeded to adjudicate only the claim of the
present Appellant concerning the amount paid by him towards the
Bank liability.
15. The learned Sole Arbitrator also noticed that no separate formal
issue had been framed in relation to the claim of the present Appellant
concerning the Bank payment. Nevertheless, the learned Sole
Arbitrator declined to defer the proceedings for framing such an issue.
The reason recorded was that the claim had been raised before the
learned Sole Arbitrator, the parties and their counsel were fully aware
of the claim and had participated in the proceedings in relation thereto,
and no prejudice would be caused to any party by adjudication of the
said claim. The learned Sole Arbitrator also took note of the
considerable passage of time since the commencement of the arbitral
proceedings.
16. By the arbitral award dated 23.12.2023, the learned Sole
Arbitrator accordingly confined the adjudication to the Appellant‟s
claim arising from the payment made by him to Union Bank of India.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 7 of 28
Upon taking the amount of Rs.23,90,000/- paid by the Appellant as
the starting point and deducting the Appellant‟s own 10% share
amounting to Rs.2,39,000/-, the learned Sole Arbitrator determined
the amount recoverable from the other partners at Rs.21,51,000/-.
17. The learned Sole Arbitrator thereafter apportioned the said
amount amongst the remaining partners in accordance with the
respective shares attributed to them in the partnership. An amount of
Rs.2,39,000/- was determined against Respondent No.1, Sh. Balbir
Singh Tyagi, an amount of Rs.10,75,500/- against Respondent No.2,
Smt. Mithlesh Tyagi, and an amount of Rs.8,36,500/- against
Respondent No.3, Sh. Yogesh Bansal. The learned Sole Arbitrator
further awarded interest at the rate of 18% per annum on the said
amounts with effect from 28.04.2008, i.e. the date on which the
payment was made by the Appellant, until payment.
18. The aforesaid arbitral award was thereafter challenged under
Section 34 of the Arbitration and Conciliation Act, 1996 [„Arbitration
Act‟] by Respondent Nos.1 and 2, Balbir Singh Tyagi and Mithlesh
Tyagi, before the learned District Judge in OMP (COMM.)
No.25/2024. By the Impugned Order dated 28.11.2025, the learned
District Judge set aside the arbitral award, principally on the grounds
that the learned Sole Arbitrator had failed to adjudicate the other
reliefs forming part of the claim of the Appellant and that the claim
relating to the amount paid to Union Bank of India was beyond the
scope of the arbitration.
19. The Appellant, who was Respondent No.3 before the learned
Sole Arbitrator and in whose favour the monetary relief in respect of
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 8 of 28
the Bank payment had been granted, is aggrieved by the aforesaid
order and has accordingly preferred the present Appeal.
20. The challenge in the present Appeal is, therefore, required to be
examined against the specific backdrop in which the arbitral award
came to be rendered. The learned Sole Arbitrator did not adjudicate
upon the entirety of the disputes which had originally formed part of
the pleadings. Rather, the learned Sole Arbitrator proceeded to
adjudicate the Appellant‟s claim concerning the payment made to
Union Bank of India after recording the statement of the parties and
their counsel dated 11.12.2023 that the award may be passed only in
respect of that claim. The legality of that course, as well as the
character and arbitrability of the Appellant‟s claim, constitute the
central questions arising in the present Appeal.
CONTENTIONS OF THE PARTIES:
21. Contentions on behalf of the Appellant:
21.1 It was submitted that the learned District Judge erred in
proceeding on the premise that the learned Sole Arbitrator was
required to adjudicate all the reliefs originally forming part of the
Appellant‟s counterclaim. It was submitted that, on 11.12.2023, the
parties, in the presence of their respective counsel, submitted before
the learned Sole Arbitrator that the award may be passed only on the
claim made by Respondent No.3, i.e. the present Appellant. The said
submission was duly recorded in the contemporaneous order-sheet and
was not thereafter withdrawn or modified.
21.2 It was submitted that paragraph 55 of the arbitral award merely
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 9 of 28
recorded the understanding arrived at on 11.12.2023, namely, that the
award would be confined to the Appellant‟s claim concerning the
amount paid by him to the Bank, and that the other claims were not
required to be adjudicated. It was contended that the learned District
Judge erred in giving the expression “claim made by respondent
No.3” a meaning wider than that intended by the parties and recorded
by the learned Sole Arbitrator.
21.3 It was further submitted that the reliance placed upon Order
XIV Rule 2 of the Code of Civil Procedure, 1908, was misplaced,
since the present case arose in arbitration and the scope of
adjudication had been specifically narrowed by the parties themselves
during the arbitral proceedings. Once the parties agreed to confine the
award to the claim which remained pressed, the mere fact that the
original counterclaim contained other reliefs could not invalidate the
award.
21.4 On the question of arbitrability, it was submitted that the claim
of Rs.21,51,000/- was not a personal claim arising out of the
Appellant‟s relationship with the Bank, but represented the amount
paid by him towards the liability of the partnership firm. Reliance was
placed on the Settlement Certificate dated 28.04.2008, which records
that the account was in the name of M/s Nova Electro World and that
the Appellant, described as a partner and guarantor, had paid
Rs.23,90,000/- towards full and final settlement of the dues of the
firm.
21.5 It was submitted that the Appellant had claimed only the
amount attributable to the other partners after deducting his own 10%
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 10 of 28
share of Rs.2,39,000/-, and that the learned Sole Arbitrator had
apportioned the balance amongst the other partners in accordance with
their respective partnership shares. The claim, therefore, according to
the Appellant, concerned the inter se adjustment of the firm‟s liability
and fell within the disputes contemplated by Clause 15 of the
Partnership Deed.
21.6 It was further submitted that the learned Sole Arbitrator had
considered the evidence on record, including the fact that the firm had
availed the cash-credit facility and that the Appellant had made the
payment from his own funds. It was pointed out that Respondent No.1
had also admitted the relevant facts in cross-examination. The learned
District Judge, it was contended, could not substitute his own
appreciation of the evidence for the findings recorded by the learned
Sole Arbitrator.
21.7 It was lastly submitted that the learned Sole Arbitrator had in
fact considered the objection regarding arbitrability, noticed that the
objection had not been raised in the written statement, and considered
and distinguished Monnet Finance (supra). The Appellant
accordingly submitted that neither of the grounds relied upon in the
Impugned Order warranted interference with the arbitral award.
22. Contentions on behalf of the Respondent Nos. 1 and 2:
22.1 Per contra , it was submitted that the proceeding sheet dated
11.12.2023 merely recorded that the award may be passed on the
“ claim made by respondent No.3 ” and did not record any agreement to
adjudicate only the claim relating to the Bank payment.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 11 of 28
22.2 It was submitted that the Appellant‟s counterclaim comprised
several reliefs, including dissolution of the partnership, rendition of
accounts and monetary claims under different heads. According to the
respondents, once the proceedings were confined to the Appellant‟s
claim, the learned Sole Arbitrator was required to adjudicate the
entirety of the claim and could not select one monetary component
while leaving the remaining reliefs unanswered.
22.3 It was contended that paragraph 55 of the arbitral award could
not enlarge or modify the contemporaneous order-sheet and that, if the
remaining reliefs were intended to be abandoned or not pressed, an
appropriate statement or application ought to have been placed on
record.
22.4 On arbitrability, it was submitted that the claim of
Rs.21,51,000/- arose from the Appellant‟s independent relationship
with the Bank as guarantor and was not a dispute contemplated by the
arbitration clause in the Partnership Deed. It was pointed out that the
Appellant had admitted that he had not consulted the other partners
before making the payment and that there was no document
evidencing authorisation by the firm for such payment.
22.5 It was further submitted that the learned Sole Arbitrator had not
properly adjudicated the objection regarding arbitrability and that the
objection could not have been rejected merely because it was not
raised in the written statement. According to the respondents, the
learned Sole Arbitrator had thus adjudicated a claim outside the scope
of the arbitration while leaving the principal disputes concerning
dissolution and accounts undecided.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 12 of 28
ANALYSIS & FINDINGS:
23. This Court has carefully considered the submissions advanced
on behalf of the parties and perused the material on record.
24. The controversy before this Court essentially has two distinct
facets. The first concerns the scope of the adjudication which
remained before the learned Sole Arbitrator after the statement
recorded on 11.12.2023. The second concerns the nature of the claim
relating to the payment made by the Appellant to Union Bank of India
and whether such claim could be adjudicated in the arbitration
between the partners. The two questions need to be examined
separately.
A. Scope of adjudication after the proceedings dated 11.12.2023:
25. The starting point for examining the first issue must necessarily
be the order-sheet dated 11.12.2023, which is reproduced as under:
“ORDER
11.12.2023
Present:- Sh. Satish Sahay Ld. Counsel for claimant alongwith sh.
Yogesh Bansal claimant in person
Sh. Deepak Dahiya Ld Counsel for Respondent No. I & 2 alongwith
Sh. B. S. Tyagi, respondent No. 1 in person.
Arguments heard again from both Ld. counsels. It is submitted
by parties that award may be passed only on the claim made by
respondent No. 3.
To come on 23.12.2023 for passing award.”
26. The learned District Judge has also noticed the aforesaid order-
sheet. The disagreement essentially arises with respect to the meaning
to be attributed to the expression “ claim made by respondent No.3 ”.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 13 of 28
According to the learned District Judge, the expression necessarily
encompassed all the reliefs forming part of the Appellant‟s
counterclaim. According to the Appellant, the parties intended that
only the particular claim concerning the amount paid by him to the
Bank should be adjudicated.
27. At this stage, it would be useful to notice the manner in which
the learned Sole Arbitrator understood the aforesaid statement. In
paragraph 55 of the arbitral award, the learned Sole Arbitrator
recorded that, on 11.12.2023, the parties as well as their learned
counsel had submitted that the award may be passed only on the claim
made by Respondent No.3 “ regarding loan amount paid by him to
bank being its guarantor ”. The learned Sole Arbitrator further
recorded that the other claims made by the parties need not be
discussed and decided in view of the statement made by all the parties.
28. Thus, there is no dispute that the learned Sole Arbitrator did not
adjudicate the entirety of the claims originally pleaded by the parties.
The question is whether, in the circumstances in which the
proceedings stood on 11.12.2023, such non-adjudication constituted a
failure on the part of the learned Sole Arbitrator to exercise the
jurisdiction vested in him.
29. In this Court‟s view, the answer to this question has to be
determined from the proceedings as they actually unfolded before the
learned Sole Arbitrator. The order-sheet dated 11.12.2023 is a
contemporaneous record of the proceedings. It records a submission
made by the parties after arguments had been heard. Significantly, the
order-sheet does not record that the award was to be passed on all the
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 14 of 28
reliefs contained in the counterclaim of Respondent No.3. It records
only that the award may be passed on the claim made by Respondent
No.3.
30. The subsequent description contained in paragraph 55 of the
arbitral award assumes significance in this context. The learned Sole
Arbitrator did not merely state that he was unilaterally choosing to
adjudicate one component of the Appellant‟s counterclaim. He
recorded that the parties and their counsel had made a submission on
11.12.2023 and identified the claim to be adjudicated as the claim
concerning the amount paid by Respondent No.3 to the Bank as
guarantor. The Impugned Order does not identify any
contemporaneous statement, application or other material placed
before the learned Sole Arbitrator which demonstrates that this
understanding recorded in the award was contrary to the position
taken by the parties on 11.12.2023.
31. The learned District Judge has principally faulted the learned
Sole Arbitrator for not obtaining a separate application or statement on
oath from the parties recording that only one particular relief was to be
adjudicated. In this Court‟s view, the absence of such a separate
document cannot, by itself, efface the statement actually recorded in
the contemporaneous proceedings dated 11.12.2023. The arbitration
proceedings are to be examined on the basis of the record of the
proceedings and the conduct of the parties before the Tribunal. The
order-sheet records the submission of the parties; paragraph 55 of the
award explains the understanding of that submission; and the award
thereafter confines itself to the claim so identified.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 15 of 28
32. The learned District Judge has also relied upon the general
principle underlying Order XIV Rule 2 of the Code of Civil
Procedure, 1908, and has observed that, although the provision may
not have direct application, a Court is required to pronounce judgment
upon the issues arising before it. There can be no quarrel with the
general proposition that an adjudicating authority ordinarily ought to
decide the disputes which remain for its determination. However, the
present case has to be considered in the context of the specific course
adopted by the parties themselves at the conclusion of the arbitral
proceedings.
33. The material question, therefore, is not whether an arbitrator
can ordinarily leave a relief unanswered. The material question is
whether the reliefs which were not adjudicated continued to remain
for determination after the parties made the statement recorded on
11.12.2023. If, pursuant to the statement of the parties, the scope of
adjudication stood confined to the claim of Respondent No.3
concerning the amount paid towards the Bank liability, the learned
Sole Arbitrator could not be faulted merely because the original
pleadings contained additional reliefs which were no longer required
to be adjudicated.
34. In this regard, it is also relevant that the arbitral proceedings
had continued for a considerable period and that the learned Sole
Arbitrator had already recorded evidence in relation to the Bank
payment. The learned Sole Arbitrator, in the award, also noted that the
other claims made by the parties were not required to be discussed and
decided in view of the statement made on 11.12.2023. Thus, the
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 16 of 28
course adopted by the learned Sole Arbitrator was not one of declining
to exercise jurisdiction over a live claim; rather, it was based upon the
understanding that the parties had confined the adjudication to a
particular claim.
35. The reliance placed in the Impugned Order upon the principle
that all issues arising before an adjudicating authority ought to be
decided, therefore, does not address the precise controversy. The
question whether an issue was required to be decided necessarily
depends upon whether it remained a live issue for adjudication at the
stage when the award was rendered. In the present case, the
contemporaneous order-sheet dated 11.12.2023 and the corresponding
finding recorded by the learned Sole Arbitrator in paragraph 55 of the
award show that the parties had agreed to proceed only with the claim
of Respondent No.3 which was ultimately adjudicated.
36. This Court is, therefore, unable to sustain the finding of the
learned District Judge that the learned Sole Arbitrator committed a
jurisdictional error merely by not adjudicating the other reliefs
forming part of the Appellant‟s original counterclaim. The Impugned
Order proceeds on the assumption that the statement dated 11.12.2023
required adjudication of every relief claimed by Respondent No.3.
Such an assumption does not sufficiently account for the
contemporaneous record of the proceedings and, in particular, the
manner in which the learned Sole Arbitrator understood and acted
upon the statement of the parties.
37. This, however, does not conclude the matter. Even if the parties
had confined the adjudication to the Appellant‟s claim concerning the
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 17 of 28
Bank payment, it would still be necessary to examine whether the said
claim was within the scope of the arbitration agreement and could
validly have been adjudicated by the learned Sole Arbitrator. It is this
question which falls for consideration next.
B. Whether the claim relating to the amount paid to Union Bank of
India was within the scope of the arbitration?
38. The second issue concerns the nature of the claim which was
ultimately adjudicated by the learned Sole Arbitrator. The learned
District Judge proceeded on the basis that the claim of Rs.21,51,000/-
was a personal claim of the Appellant arising out of his independent
relationship with Union Bank of India as a guarantor and, therefore,
fell outside the scope of the arbitration agreement contained in the
Partnership Deed. The learned District Judge further observed that the
payment had been made by the Appellant to protect the property
furnished by him as security and that there was no document showing
that the partnership firm had authorised him to make the payment on
its behalf.
39. in order to examine the aforesaid conclusion, it is necessary to
keep in view the nature of the underlying liability as well as the nature
of the relief actually granted by the learned Sole Arbitrator. The
Settlement Certificate dated 28.04.2008 issued by Union Bank of
India records that the account in question was in the name of M/s
Nova Electro World and that the Bank had initiated recovery
proceedings under Section 13(2) of the Securitisation and
Reconstruction of Financial Assets and Enforcement of Security
Interest Act, 2002 against the borrower and the guarantors. The
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 18 of 28
certificate thereafter specifically records that the Appellant, described
as “ one of the partners and guarantors of the account ”, had paid
Rs.23,90,000/- towards “full and final settlement of the dues of the
above firm”.
40. The description contained in the Settlement Certificate is of
considerable significance. The document does not describe the
payment as being towards a personal borrowing of the Appellant. On
the contrary, the account was that of M/s Nova Electro World and the
payment was made towards settlement of the dues of the said firm.
The fact that the Appellant was also a guarantor explains the capacity
in which the Bank was entitled to proceed against him. It does not, by
itself, determine the character of the subsequent claim raised by the
Appellant against his co-partners.
41. The distinction between the two relationships is material. The
relationship between the Bank and the Appellant arose from the
guarantee furnished by the Appellant in respect of the cash-credit
facility. The claim which came to be adjudicated by the learned Sole
Arbitrator, however, was not a claim by the Appellant against the
Bank, nor was it a claim for any relief concerning the guarantee itself.
The claim was made by one partner against the other partners in
respect of the amount which he asserted had been paid by him towards
discharge of the liability of the partnership firm.
42. The manner in which the learned Sole Arbitrator quantified the
claim further demonstrates the nature in which it was presented and
adjudicated. The Appellant had paid Rs.23,90,000/- to the Bank. He
did not seek recovery of the entire amount from the other partners. His
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 19 of 28
own 10% share, amounting to Rs.2,39,000/-, was first deducted. The
balance amount of Rs.21,51,000/- was thereafter apportioned amongst
the remaining partners in accordance with their respective shares in
the partnership.
43. Thus, the learned Sole Arbitrator did not proceed on the basis
that the Appellant had acquired an independent debt against the other
partners merely because the Bank had recovered money from him as a
guarantor. The adjudication proceeded on the basis that the amount
paid by the Appellant represented discharge of a liability of the
partnership firm and that, after accounting for the Appellant‟s own
share, the remaining partners were liable to bear the balance in
accordance with their respective interests in the partnership.
44. This aspect assumes further significance in view of the
Partnership Deed dated 15.09.2004. Clause 15 thereof provides that
disputes “ in regard to the clause of this partnership deed or books of
accounts ” shall be referred to arbitration, with the award being final,
conclusive and binding upon the parties. The present claim arose in
the context of the liability of the partnership firm, the payment made
towards such liability by one of the partners and the consequential
adjustment of the respective shares of the partners. The claim was thus
placed before the learned Sole Arbitrator as part of the inter se dispute
concerning the financial liabilities of the partnership.
45. The learned District Judge has principally proceeded on the
footing that since the Appellant had not consulted the other partners
before making the payment and since there was no document showing
that the firm had authorised him to deposit the amount on its behalf,
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 20 of 28
the payment was necessarily personal to the Appellant. In our view,
the two questions cannot be conflated.
46. The fact that the Appellant did not consult the other partners
before making the payment may have a bearing upon the merits of the
claim, if otherwise relevant. It does not, by itself, answer the anterior
question as to the nature of the claim brought before the learned Sole
Arbitrator. The question for the Tribunal was whether the amount paid
by the Appellant was towards a liability of the partnership firm and, if
so, whether the Appellant was entitled to claim contribution from the
other partners in accordance with the arrangement between them.
These were matters which arose from the relationship between the
partners and the financial affairs of the partnership.
47. Similarly, the absence of any document evidencing prior
authorisation by the other partners does not, by itself, establish that the
claim adjudicated by the learned Sole Arbitrator was a dispute
confined to the Appellant‟s relationship with the Bank. The amount
paid by the Appellant was towards the outstanding liability arising
from the loan facility availed by the partnership firm. The Appellant,
being one of the partners, was not required, merely for discharging an
existing liability of the partnership firm, to obtain prior permission of
the other partners before making such payment. Significantly, the
Respondents have not led any evidence to establish that the amount so
paid by the Appellant was not recoverable on account of the
partnership firm. On the contrary, the Bank had treated the account as
that of M/s Nova Electro World and had accepted the payment
towards full and final settlement of the dues of the said firm. The
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 21 of 28
dispute which thereafter remained between the Appellant and the
other partners was, therefore, with respect to the inter se incidence of
the payment so made.
48. It is also relevant that the learned Sole Arbitrator did not
mechanically accept the Appellant‟s claim for the entire amount paid
by him. The Appellant‟s own 10% share was excluded and only the
balance was directed to be borne by the other partners in accordance
with their respective shares. The award, therefore, proceeded upon the
partnership arrangement itself while determining the extent of the
liability of each of the partners.
49. The objection raised by Respondent Nos.1 and 2 was, no doubt,
that the Appellant had made the payment in his capacity as a guarantor
and that he had not obtained the consent of the other partners.
However, the mere description of the Appellant as a guarantor cannot,
in the facts of the present case, conclude the question of arbitrability.
The same person was simultaneously a partner of the firm and a
guarantor of the firm‟s cash-credit facility. The Settlement Certificate
itself identifies him in both capacities. The relevant inquiry, therefore,
is the substance of the claim which he brought before the Tribunal and
not merely the capacity in which the Bank proceeded against him.
50. In this context, the observation in the Impugned Order that the
Bank‟s recovery against the Appellant was a bipartite transaction
between the Bank and the Appellant does not, by itself, answer the
question arising in the present Appeal. The Bank‟s right to recover the
outstanding amount from the Appellant as a guarantor is one aspect of
the matter. The Appellant‟s claim against the other partners, after
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 22 of 28
making such payment, is a distinct aspect. The latter claim has to be
examined with reference to the partnership relationship and the
arbitration agreement governing disputes between the partners.
51. The learned District Judge also observed that the learned Sole
Arbitrator had not properly decided the objection concerning
arbitrability and had “ simply refused to entertain ” the same on the
ground that the objection had not been taken in the written statement.
On examination of the arbitral award, this description does not appear
to be entirely accurate.
52. The learned Sole Arbitrator did notice the objection concerning
the maintainability of the Appellant‟s claim. The award records the
objection that the Appellant‟s claim was not maintainable in the
arbitration and further records the reliance placed upon the judgment
in Monnet Finance (supra) . The learned Sole Arbitrator thereafter
distinguished the said decision in the context of the facts of the present
case. The learned Sole Arbitrator also noticed that no such objection
had been taken in the written statement.
53. It is true that the mere fact that an objection was not taken in the
written statement may not, by itself, furnish an answer to every
question concerning the scope of an arbitration agreement. However,
that is not the same as saying that the learned Sole Arbitrator failed to
consider the objection altogether. The record demonstrates that the
objection was noticed and a view was taken thereon. Whether that
view was sustainable had to be examined within the parameters of the
jurisdiction available under Section 34 of the Arbitration Act.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 23 of 28
54. More importantly, the learned District Judge, while holding that
the claim was beyond the scope of the arbitration, has not sufficiently
addressed the distinction between the original relationship of the Bank
with the Appellant and the subsequent claim of the Appellant against
his co-partners. The Settlement Certificate, which formed part of the
material before the learned Sole Arbitrator, records that the underlying
account was that of the partnership firm and that the amount of
Rs.23,90,000/- was paid towards full and final settlement of the dues
of that firm.
55. The nature of the relief granted by the learned Sole Arbitrator
also cannot be overlooked. The award did not direct the Bank to do
anything, nor did it adjudicate upon the validity of the guarantee
furnished by the Appellant. It determined the liability of the other
partners towards the Appellant after giving effect to the respective
partnership shares. The dispute, therefore, as adjudicated, was one
between the partners concerning the financial consequence of a
payment made towards the firm‟s liability.
56. This Court is, therefore, unable to agree with the conclusion in
the Impugned Order that the claim of the Appellant was, merely by
reason of his status as a guarantor, a personal claim lying wholly
outside the scope of the arbitration. The capacity in which the Bank
proceeded against the Appellant cannot, by itself, determine the nature
of the inter se claim which the Appellant subsequently raised against
the other partners.
57. At the same time, it is necessary to emphasise that the
conclusion reached herein is confined to the claim which was actually
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 24 of 28
adjudicated by the learned Sole Arbitrator. We are not examining, nor
is it necessary for the disposal of the present Appeal to examine, the
other claims originally pleaded by the parties concerning dissolution,
rendition of accounts, goodwill, tenancy or any other relief which,
pursuant to the proceedings dated 11.12.2023, was not adjudicated by
the learned Sole Arbitrator.
58. The next question is the extent to which the learned District
Judge could have interfered with the findings of the learned Sole
Arbitrator on the factual aspects of the payment. The learned Sole
Arbitrator considered the Settlement Certificate, the evidence of the
parties and the admissions made during cross-examination. The
finding that the firm had availed the cash-credit facility and that the
Appellant had made the payment towards the outstanding liability is
supported by the material which was before the Tribunal.
59. The learned District Judge, while exercising jurisdiction under
Section 34 of the Arbitration Act, was certainly entitled to examine
whether the award suffered from a ground contemplated under Section
34. However, the mere fact that the learned District Judge viewed the
payment differently from the manner in which it was viewed by the
learned Sole Arbitrator could not, by itself, justify setting aside the
award. In the present case, the learned Sole Arbitrator‟s finding was
not founded upon an isolated assertion of the Appellant. The existence
of the firm‟s cash-credit facility, the Appellant‟s status as a guarantor
and partner, and the payment of Rs.23,90,000/- towards settlement of
the firm‟s dues are reflected in the material placed before the Tribunal.
60. The Respondents‟ contention that the Appellant had not
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 25 of 28
consulted the other partners before making the payment also does not,
in the facts of the present case, demonstrate that the learned Sole
Arbitrator lacked jurisdiction to adjudicate the claim. The payment
was made towards an outstanding liability of the partnership firm and
not towards any personal borrowing or liability of the Appellant. The
Appellant, being a partner of the firm, was entitled to take steps in the
interest of the partnership, including for the discharge of an
outstanding liability of the firm. In any event, the Respondents have
not led any evidence to establish that the amount paid by the
Appellant was not a liability of the partnership firm or that the same
was not recoverable in the inter se accounts of the partners. The
absence of prior consultation, therefore, does not convert a claim
concerning the financial liability of the partnership into a dispute
wholly unrelated to the partnership.
61. The learned District Judge, therefore, in this Court‟s view, fell
into error on both counts which formed the foundation of the
Impugned Order. First, the learned District Judge treated the other
reliefs contained in the Appellant‟s original counterclaim as
continuing to require adjudication notwithstanding the statement
recorded on 11.12.2023 and the understanding recorded by the learned
Sole Arbitrator in paragraph 55 of the award. Secondly, the learned
District Judge treated the Appellant‟s claim concerning the amount
paid towards the firm‟s Bank liability as a personal claim arising
exclusively from the guarantee, without sufficiently considering the
character of the claim as one arising inter se the partners from the
discharge of the firm‟s liability.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 26 of 28
62. The two conclusions in the Impugned Order are interlinked.
Once it is accepted that, on 11.12.2023, the parties confined the
adjudication to the Appellant‟s claim concerning the amount paid to
the Bank, the only question which remained for adjudication was
whether that particular claim could validly be decided in the
arbitration. As noticed hereinabove, the underlying liability was that
of the partnership firm; the Settlement Certificate expressly records
payment towards the dues of the firm; the Appellant was himself a
partner; the Partnership Deed contained an arbitration clause
concerning disputes relating to the partnership deed and books of
accounts; and the amount awarded was calculated by giving effect to
the respective partnership shares.
63. In these circumstances, the learned Sole Arbitrator‟s
adjudication of the said claim cannot be characterised as an
adjudication of a dispute wholly outside the scope of the arbitration
merely because the Appellant had also furnished a guarantee to the
Bank.
64. Consequently, the principal grounds on which the learned
District Judge set aside the arbitral award cannot be sustained. The
finding that the learned Sole Arbitrator was required to adjudicate the
other reliefs originally forming part of the Appellant‟s counterclaim
does not accord with the contemporaneous proceedings dated
11.12.2023. Equally, the conclusion that the Bank-payment claim was
non-arbitrable merely because the Appellant was a guarantor is not
borne out by the nature of the claim actually adjudicated and the
material on record.
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 27 of 28
CONCLUSION:
65. For the foregoing reasons, the Appeal is allowed. The order
dated 28.11.2025 passed by the learned District Judge in OMP
(COMM.) No.25/2024 is set aside.
66. Consequently, the arbitral award dated 23.12.2023 passed by
the learned Sole Arbitrator is restored.
67. The pending application also stands disposed of.
ANIL KSHETARPAL, J.
BHARAT PARASHAR, J.
OCTOBER 05, 2026
jai/pal
Signature Not Verified
Signed By:JAI
NARAYAN
Signing Date:05.10.2026
11:04:36
FAO(COMM) 64/2026 Page 28 of 28