Bvm Engineering Industries Limited vs Imperia Heights Private Limited & Anr.
- Court
- Delhi High Court
$~6
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: 13 July, 2026
+ CONT.CAS(C) 1430/2025
BVM ENGINEERING INDUSTRIES LIMITED .....Petitioner
Through: Mr. Samar Bansal, Sr. Adv. with Mr.
Vedant Kapur and Ms. Anshika
Saxena, Advs.
Mob: 8377944021
versus
IMPERIA HEIGHTS PRIVATE LIMITED & ANR. .....Respondents
Through: Mr. P.S. Bindra, Sr. Adv. with Mr.
Tushar Sharma, Mr. Sachin Jain and
Mr. Ram Pawar, Advs. for R-1 & 2
Mob: 9354124731
Email: [email protected]
CORAM:
HON'BLE MS. JUSTICE MINI PUSHKARNA
MINI PUSHKARNA, J (ORAL):
1. The present contempt petition has been filed alleging wilful
th
disobedience of the order dated 24 June, 2025, passed by the learned Sole
Arbitrator in an application filed under Section 17 of the Arbitration and
Conciliation Act, 1996 (“Arbitration Act”), in the matter bearing Case No.
DIAC/9857/12-24, titled as BVM Engineering Industries Limited Versus
Imperia Heights Private Limited & Anr.
th
2. The relevant portions of the order dated 24 June, 2025, as passed by
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 1 of 7
the learned Sole Arbitrator, read as under:
“xxx xxx xxx
3. Thus, by way of the aforesaid order, the respondents herein were
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 2 of 7
directed to resume the re-development and construction work at the site in
question, in terms of the Principal Collaboration Agreement and subsequent
Supplementary Agreements.
4. Learned Senior Counsel appearing for the petitioner submits that the
aforesaid order passed by the learned Arbitrator has attained finality, as the
appeals against the said order already stand rejected.
th
5. Attention of this Court has been drawn to the order dated 25
February, 2026, wherein, certain timelines with regard to the work to be
th
undertaken were noted. The order dated 25 February, 2026, passed by this
Court, reads as under:
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 3 of 7
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 4 of 7
xxx xxx xxx”
6. Today, learned Senior Counsel appearing for the petitioner submits
th
that despite the aforesaid timelines, being noted by this Court on 25
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 5 of 7
February, 2026, the respondents have failed to comply with the same.
7. Per contra , learned Senior Counsel appearing for the respondents has
handed over to this Court, a copy of the Affidavit filed on behalf of the
th th
respondent on 11 July, 2026 in terms of order dated 07 May, 2026.
8. The said affidavit is taken on record.
9. By referring to the aforesaid Affidavit, learned Senior Counsel
appearing for the petitioner submits that admittedly, the timelines have not
been met by the respondents.
10. In response, learned Senior Counsel appearing for the respondents
submits that the structure of the building in question is complete. Further,
the re-development and construction work at the site in question, shall be
st
completed by 31 March, 2027.
11. At this stage, learned Senior Counsel appearing for the petitioner
submits that the petitioner is not being granted access to the site, though he
is the co-owner of the property.
12. In response, learned Senior Counsel appearing for the respondents
submits that the petitioner was interfering in the construction work being
carried out at the site. However, the access of the petitioner to the site in
question, has never been denied.
13. Accordingly, considering the submissions made before this Court, the
undertaking on behalf of the respondents that the work shall be completed in
th
terms of the Collaboration Agreement dated 10 July, 2013 and subsequent
st
Supplementary Agreements, executed between the parties, by 31 March,
2027, is taken note of.
14. The respondents are held bound by the aforesaid undertaking.
15. It is further directed that the petitioner shall be granted access to the
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 6 of 7
premises, i.e., A-20, Mohan Cooperative Industrial Estate, Mathura Road,
New Delhi-110044 .
16. Further, it is directed that the petitioner shall not interfere in the re-
development and construction work being carried out by the respondents, in
terms of the Collaboration Agreement and subsequent Supplementary
th
Agreement dated 26 May, 2022.
17. With the aforesaid directions, the present contempt petition is
accordingly disposed of.
MINI PUSHKARNA, J
JULY 13, 2026 /SK
Signature Not Verified
Digitally Signed
By:HARIOM SHARMA
Signing Date:16.07.2026
16:41:50
CONT.CAS(C) 1430/2025 Page 7 of 7