Hindustan Petroleum Corporation Ltd vs M/S. Nandi Cylinder Pvt. Ltd.
- Court
- Bombay High Court
sns 211-osapp-699-2011.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
APPEAL NO.699 OF 2011
IN
ARBITRATION PETITION NO.105 OF 2011
M/s. Hindustan Petroleum Corporation Ltd. ]
A company incorporated and registered ]
under the Indian Companies Act, 1956, ]
having its registered office at ]
17, Jamshedji Tata Road, ]
Mumbai – 400 020. ] … Appellant
V/s.
M/s. Nandi Cylinder Private Limited ]
A company incorporated and registered ]
under the Indian Companies Act, 1956, ]
th
having its office at 402, 4 Floor, Maltinaik ]
Plaza, Hanuman Tekdi, Abids, ]
Hyderabad – 500 001. ] … Respondent
Mr. S. A. Bhalwal a/w. Adv. Anupam Surve, Adv. Usha Singh i/by M/s. Vyas
& Bhalwal for the Appellant.
CORAM : A. S. GADKARI AND
KAMAL KHATA, JJ.
th
DATE : 8 June 2026
Judgment (Per : A. S. Gadkari, J) :-
1) By this Appeal, the Appellant (Orig. Respondent) impugns the
th
Order dated 30 June, 2011, whereby the Petition filed by the Respondent’s
(Orig. Petitioner) under Section 34 of the Arbitration Act was allowed. By
1/4
Digitally
signed by
SUMEDH
NAMDEO
SONAWANE
Date:
2026.07.08
11:00:53
+0530
SUMEDH
NAMDEO
SONAWANE
sns 211-osapp-699-2011.doc
th
the said order, the Award dated 30 August, 2010, passed in favour of the
Appellant, allowing its counter-claim and rejecting the Respondent’s claim,
came to be set aside.
2) Heard Mr. Bhalwal, learned counsel appearing for the
Appellant. We have also Perused the entire record.
3) The record indicates that, the Respondent had entered into a
contract with the Petitioner for supply of LPG cylinders for the period from
th th
7 June, 2004 until 6 June, 2005. According to the Respondent, though it
was entitled to receive an amount of Rs.5,48,478/- towards supply of the
cylinders, the said amount was not paid on the ground that the Appellant
was entitled to recover from the Respondent an amount of approximately
Rs.52,00,000/- towards liquidated damages.
4) The learned Arbitrator allowed the counter-claim of the
Appellant. While doing so, the learned Arbitrator computed limitation from
th
14 February, 2006, being the date of the last correspondence addressed by
the Appellant, instead of computing limitation from the date on which the
th
cause of action had accrued being 6 June, 2005. This date arose during the
th
pendency of the contract which ended on 6 June, 2005. Additionally, the
learned Arbitrator also took into account the fact that, the Respondent had
th
not filed its claim until 5 June, 2005 and that the Appellant thereafter filed
th
its counter-claim by 8 September, 2008. On that basis, the learned
Arbitrator held that the counter-claim was within limitation.
2/4
sns 211-osapp-699-2011.doc
5) The impugned Order holds that, the reasons given by the
learned Arbitrator disclose complete non-application of mind to the relevant
law. The learned Single Judge held that, the alleged short supply of
cylinders would have occurred during the currency of the contract, which
th
came to an end on 6 June, 2005. Consequently, any claim for liquidated
damages was required to be made within a period of three years from the
accrual of the cause of action.
6) Mr. Bhalwal, learned counsel appearing for the Appellant
submitted that, the learned Arbitrator had rightly passed the Award in
th
favour of the Appellant. He submitted that, the letter dated 14 February,
2006, along with the earlier correspondence collectively marked as Exhibit
R-4 before the learned Arbitrator, constituted the date of cause of action, as
the Petitioner had demanded its legitimate dues from the Respondent on
that date.
6.1) According to him, therefore, the limitation for filing counter-
th
claim commenced from 14 February, 2006. He submitted that, the counter-
th
claim filed on 8 September, 2008 was, therefore within the period of
limitation. He further submitted that, the learned Single Judge committed a
serious error in not appreciating this vital aspect and in holding that the
counter-claim was barred by limitation.
7) We are unable to accept the said submission. In our view, the
alleged liability towards liquidated damages arose, if at all, during the
3/4
sns 211-osapp-699-2011.doc
th
subsistence of the contract, which ended on 6 June, 2005. The period for
filing a claim for recovery of the said amount of approximately
Rs.52,00,000/- towards liquidated damages would, therefore, expire on or
th th
before 5 June, 2008. The counter-claim filed by the Appellant on 8
September, 2008 was clearly beyond the prescribed period of limitation.
8) In substance, Mr Bhalwal seeks a re-appreciation the facts and
evidence on record. Such an exercise is not permissible either under Section
34 or Section 37 of the Arbitration Act, 1996.
9) In our view, the counter-claim filed by the Appellant was
barred by limitation. The learned Single Judge was, therefore, right in
allowing the Petition filed by the Respondent and setting aside the Award.
The impugned Order does not suffer from any error either in law or on facts
warranting interference in appeal.
10) We find no merit in the Appeal. The Appeal is accordingly
dismissed.
(KAMAL KHATA, J.) (A.S. GADKARI, J.)
4/4