Nuclear Power Corporation Of India Ltd. vs M/S. Standard Corrosion Controls Pvt. Ltd.
- Court
- Bombay High Court
CNR No : HCBM020075862017
ARBP.639.2017.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
ARBITRATION PETITION NO. 639 OF 2017
WITH
ARBITRATION PETITION NO. 638 OF 2017
Nuclear Power Corporation of India Ltd.
…Petitioner
Versus
M/s. Standard Corrosion Controls Pvt. Ltd. …Respondent
Mr. Dhruva Gandhi a/w Ms. Kajal Gupta, Ms. Shweta Singh i/b M. V.
Kini & Co., for the Petitioner.
Mr. Prithviraj S. Gole a/w Mr. Siddhesh R. Pednekar, for the
Respondent.
CORAM : SOMASEKHAR SUNDARESAN, J.
RESERVED ON : APRIL 8, 2026
PRONOUNCED ON : OCTOBER 27, 2026
JUDGEMENT :
Context and Factual Background:
1. Nuclear Power Corporation of India Ltd. (“ NPCIL ”) has filed the
two captioned Petitions under Section 34 of the Arbitration and Conciliation
Act, 1996 (“ the Act ”). They challenge two arbitral awards, each dated
December 6, 2016 and each corrected by a corrigendum dated December 27,
2016 (collectively, “ Impugned Awards ”).
Page 1 of 30
October 27, 2026
Aarti Palkar
Digitally signed
by AARTI
GAJANAN
PALKAR
Date:
2026.10.27
16:54:38 +0530
AARTI
GAJANAN
PALKAR
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
2. Both the Impugned Awards are passed by a retired Chief Engineer
of NPCIL in favour of Standard Corrosion Controls Pvt. Ltd. (“ Standard
Corrosion ”).
3. The two underlying contracts and the two disputes are near-
identical. The two contracts are :
A) Work Order dated July 11, 2013 for internal and external painting
of residential quarters and a public building at Anusri Township,
Tarapur, Phase II (“ Anusri Contract ”). The contract value was Rs.
1,22,86,100. The contract period was twelve months from July 22, 2013,
with completion due on July 21, 2014.
B) Work Order dated June 13, 2013 for similar work at Anuvikas
Township, Tarapur (“ Anuvikas Contract ”). The contract value was Rs.
88,72,232. Work was to commence on July 15, 2013 and to be
completed on May 14, 2014.
4. Both contracts incorporate the same General Conditions of Contract
(“ GCC ”). Clause 17.8 of the GCC entails reference of disputes to a sole
arbitrator appointed by the Chairman and Managing Director of NPCIL, who
appointed the Learned Arbitral Tribunal on June 18, 2015.
5. The sequence of events is common to both contracts, unless stated
otherwise:
A) At the kick-off meeting on August 16, 2013, Kansai Nerolac
Page 2 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
was accepted as the source of internal paint. The parties
disagree on whether NPCIL insisted on Asian Paints or ICI
Dulux for external paint.
B) At the second Project Review Meeting (“ PRM ”) on
September 19, 2013, Standard Corrosion committed to
procuring internal paint by September 25, 2013. The
minutes record that the work orders would be cancelled
without intimation if painting did not begin by October 10,
2013.
C) Internal paint was delivered on October 5, 2013 and sent for
third-party testing on October 7, 2013. Painting began on
November 16, 2013.
D) NPCIL issued a first show cause notice on October 15, 2013.
Standard Corrosion replied on October 15 and October 25,
2013. NPCIL took no further action on that notice.
E) At the third PRM on November 28, 2013, Standard
Corrosion committed to deliver external paint by December
5, 2013. NPCIL issued a second show cause notice on
December 13, 2013. Standard Corrosion replied on
December 19 and December 20, 2013.
F) At the PRM on December 24, 2013, Standard Corrosion gave
a written undertaking on labour and paint. It agreed that if it
Page 3 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
failed to meet its commitments by January 10, 2014, the
contract would stand terminated and its security deposit and
the cost of work done would be forfeited.
G) External paint reached the site on January 9, 2014. The
third-party test report followed on February 15, 2014. By an
email of January 31, 2014, NPCIL recorded that labour
arrangements had improved and work was in progress, but
that the test certificate for external paint was awaited.
H) On February 17, 2014, NPCIL directed Standard Corrosion
to stop work, citing non-deployment of labour and non-
availability of painting material. A labour strike prevailed at
the plant site from February 24 to March 31, 2014. The
parties disagree on whether it extended to the township.
I) At the PRMs of March 26, 2014 and April 2, 2014, Standard
Corrosion gave fresh commitments. By its letter of April 2,
2014, it again accepted termination if it failed, and offered to
bear liquidated damages during the extended period.
J) By a notice for final action dated April 19, 2014, NPCIL
terminated both contracts under Clause 13.2, 13.2.2 (a) & (b)
of the GCC. Standard Corrosion says it received the notice
on April 21, 2014. It protested on April 25 and April 28,
2014 and offered to still complete the work. NPCIL’s notice
Page 4 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
recorded that about 70% of the contract time had elapsed
against about 6% of the work executed. However, NPCIL’s
case before the Learned Arbitral Tribunal was that progress
was 2.78% under the Anusri Contract and 5.10% under the
Anuvikas Contract.
K) NPCIL got the balance work executed through Samadhan
Enterprises, under a work order dated February 9, 2015, at
the risk and cost of Standard Corrosion. To recover its risk
and cost, NPCIL encashed the performance bank guarantee,
retained the value of the unutilised paint, and withheld Rs.
6,63,491 due to Standard Corrosion under yet another work
order.
6. Three provisions of the GCC frame the controversy. Clauses 4.10.1
and 6.4.1, which deal with materials, read thus:
“ 4.10.1 The Contractor shall place purchase order well in time for
supply of goods as deemed necessary as per the contract. He shall arrange to
give notice sufficient in advance for necessary quality assurance at the place
of manufacturing. The contractor shall submit an un-priced copy of Purchase
order to Engineer-in-charge in order to ensure that all the requirements of
technical specifications have been met.
6.4.1 The Contractor shall, at his own expense, provide all materials
required for the works, other than the material, which are to be issued by the
Corporation.”
[Emphasis Supplied]
Page 5 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
7. Clause 7.1.1 deals with time. It reads thus:
“7.1.1 The execution of the works shall commence from the date of
commencement as mentioned in the work order and the completion period for
the work shall also be reckoned from the said date. The time allowed for
execution of the works or the extended time in accordance with these
conditions shall be the essence of the Contract.”
[Emphasis Supplied]
8. Clause 13.2.1, which deals with termination, reads thus:
“13.2.1 If the Contractor:
(a) At any time makes default in proceeding with the works with due
diligence and continues to do so after 7 days notice in writing from the
Engineer-in-Charge; or
(b) Commits default in complying with any of the terms and conditions of
the Contract and does not remedy it or take effective steps to remedy it within
7 days after a notice in writing is given to him in that behalf by the Engineer-
in-Charge; or
*(c) to (k)
The Engineer-in-charge may, upon giving 7 days’ notice to the Contractor,
terminate the Contract and expel the Contractor from the Site. The
Corporation’s election to terminate the Contract shall not prejudice any other
rights of the Corporation, under the Contract or otherwise.”
[Emphasis Supplied]
9. Standard Corrosion invoked arbitration on January 14, 2015. It
made nine claims. NPCIL made no counter-claim. NPCIL raised three
preliminary objections but did not insist on them at the hearing on February
25, 2016. Both sides relied on documents. No oral evidence was led. The
Page 6 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
Learned Arbitral Tribunal heard the parties on February 25, 2016, March 11,
2016 and March 21, 2016 and received written arguments. He dealt with three
issues:
A) Whether the slow progress of the work was due to reasons solely
attributable to Standard Corrosion;
B) Whether NPCIL’s termination of the contract was lawful; and
C) Whether NPCIL was entitled to withhold any dues of Standard
Corrosion towards risk and cost.
10. The Learned Arbitral Tribunal decided all three issues in favour of
Standard Corrosion:
A) Delay: The slow progress was held not to be solely attributable to
Standard Corrosion. He treated the monsoon, the delivery time for
paint, the third-party testing requirement, NPCIL’s alleged instruction
on the external paint brand and delay in finalising the shade card, and
the labour strike as outside its reasonable control;
B) Termination: The termination was held to be unlawful. The
second show cause notice had become redundant once NPCIL accepted
the reply and allowed the work to continue. A fresh seven-day notice
under Clause 13.2.1 was required and was not given. NPCIL had been
inclined to terminate from the outset. Time was not made the essence of
the contract; and
Page 7 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
C) Risk and cost: NPCIL could not withhold dues towards risk and
cost. This is a consequence of the termination being unlawful.
Separately, NPCIL took about nine months to award the balance work,
did not prove its actual expenditure and did not mitigate its losses.
11. Five heads of claims were allowed. On quantification, loss of profit
was limited to 10% of the value of the unexecuted work. Claims 3, 4 and 9, for
tools and tackles, statutory and administrative expenses and costs, were
rejected. The sums awarded are as follows:
Head Anusri
Award (Rs.)
Anuvikas Award
(Rs.)
Claim 1 – payment for work done 3,14,543 4,62,226
Claim 2 – value of unused paint 7,01,133 6,32,601
material
Claim 5 – refund of performance 6,14,400 4,44,000
bank guarantee
Claim 6 – loss of profit (10% of 11,27,042 7,77,740
unexecuted work)
Claim 7 – 50% of amount withheld 3,31,745 3,31,745
under another work order
Sub-total 30,88,863 26,48,312
Claim 8 – interest at 12.25% p.a. 7,42,668 6,53,688
(simple)
Total awarded 38,31,531 33,02,000
12. The corrigenda, issued under Section 33 of the Act, corrected the
computation of pendente lite interest in both awards. The Anuvikas
corrigendum also substituted the summary table and reduced the total payable
Page 8 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
from Rs. 39,13,832 to Rs. 33,02,000. If unpaid within 90 days, each sum
carries simple interest at 15% per annum from the date of the award until
payment. The parties were left to bear their own costs.
13. The Petitions were admitted on January 17, 2018 and have been on
the docket of this Court since then. The Impugned Awards were stayed on
condition that NPCIL deposit 75% of the awarded sum with interest within six
weeks. Standard Corrosion was permitted to withdraw the deposit against a
bank guarantee of a nationalised bank. On February 6, 2026, the parties were
directed to file short Notes on Submissions and the hearing was time-bound.
NPCIL concluded its submissions on April 2, 2026. Both sides filed Notes on
Submissions dated April 8, 2026.
Grounds of Challenge and Contentions:
14. NPCIL primarily contends that the Impugned Awards conflict with
the Public Policy of India. It says they contravene the fundamental policy of
Indian law and the most basic notions of morality or justice, and that they are
perverse and patently illegal. It says the findings are unsupported by evidence
or ignore vital material on record. While a number of grounds have been
pleaded, including levelling allegations about the lack of impartiality of the
Learned Arbitral Tribunal, the aforesaid grounds alone were pressed in the
submissions.
15. NPCIL’s contentions may be summarised thus:
Page 9 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
A) The finding that the slow progress was not solely
attributable to Standard Corrosion is said to be perverse and
ignores material on record, because:
I) The work orders and agreements were executed in the
monsoon. Standard Corrosion committed to the
completion dates, knowing the commencement dates and
the monsoon season. No contemporaneous letter
complained of the monsoon, other than a letter of October
15, 2013, which was withdrawn by a letter of October 17,
2013;
II) Clauses 4.10.1 and 6.4.1 made paint procurement,
Standard Corrosion’s obligation. The tender was issued on
March 14, 2013. In its letter of October 25, 2013, Standard
Corrosion itself stated that “[d]ue to some financial
problems, paint material was not procured in time”. The
Learned Arbitral Tribunal did not consider this letter;
III) At the PRMs of November 28, 2013 and December 24,
2013, Standard Corrosion committed to procure and
deliver external paint. It cited no circumstance beyond its
control. The finding that these commitments were beyond
its reasonable control is ex facie perverse;
IV) No letter shows that NPCIL insisted on Asian Paints or
Page 10 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
ICI Dulux. NPCIL’s letter of October 21, 2013 only shared
shades. Third-party certification was a contractual
requirement. The Learned Arbitral Tribunal could not
hold that work should have begun without it;
V) The finding that a second lot of internal paint was not
required is irrational when only 5-6% of the work was
done. Standard Corrosion admitted a shortage of labour,
yet the Learned Arbitral Tribunal held that NPCIL had
furnished no proof. This wrongly shifted the burden of
proof. The email of February 7, 2014 and the letter of
February 15, 2014 were not considered; and
VI) The Statement of Claim does not plead that the strike
hampered the work. It mentions the strike only while
referring to the letter of April 28, 2014. The Learned
Arbitral Tribunal recorded that there was no conclusive
proof on the strike, yet held that it affected the work.
NPCIL adds that the strike was confined to the plant site
and not the township;
B) The finding that the termination was unlawful is said to be
perverse because:
I) The second show cause notice of December 13, 2013
was never withdrawn. The default continued well
Page 11 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
beyond seven days. Clause 13.2.1 does not require a
fresh notice for a continuing default. The finding that
“no such notice” was given ignores the notice, the
later correspondence and the Clause itself;
II) The Learned Arbitral Tribunal did not consider
Standard Corrosion’s letter of April 2, 2014, in which
it accepted termination if it failed to meet its
commitments. He relied on the letter of January 31,
2014 without considering the later communications
of February 2014. He did not doubt the figures in the
termination notice, yet held the termination illegal;
and
III) Time was of the essence under Clause 7.1 and by the
conduct of the parties. In any event, NPCIL
terminated the contract under Clause 13 and not
under Clause 7.1, so the Learned Arbitral Tribunal
did not need to examine this question;
C) If the termination was lawful, NPCIL was entitled to recover
its risk and cost, as set out in its Written Statement. NPCIL
contends that claims 1, 2, 5, 6 and 7 must then be reversed
as a necessary consequence;
D) The award of loss of profit is bad in law. No evidence was
Page 12 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
led. Once the termination is lawful, Standard Corrosion
cannot be placed as if the contract had been performed. The
Learned Arbitral Tribunal did not consider the costs
Standard Corrosion would have incurred, or NPCIL’s
entitlement to compensation for delay. NPCIL relies on the
1
Supreme Court ruling in Unibros and the decision of a
Learned Single Judge of this Court in CFM Asset
2
Reconstruction on the need for evidence of loss of profit
3
and on Ramesh Kumar Jain for what amounts to perversity
and patent illegality.
16. Standard Corrosion’s contentions may be summarised thus:
A) The delay was beyond its reasonable control because:
I) The work orders were issued in the monsoon. The
paint shade was finalised late, third-party testing was
mandatory and the external paint maker was changed
at NPCIL’s instance. Painting began after about three
months and 24 days. About 33% of the Anusri
Contract period and 40% of the Anuvikas Contract
period were lost by then;
1 Unibros v. All India Radio, 2023 SCC OnLine SC 1366 (paragraphs 15 to 19).
2 CFM Asset Reconstruction Pvt. Ltd. & Anr. v. M/s. SAR Parivahan Pvt. Ltd. & Ors.,
Judgment dated 13th June 2024 in I.A. (L) NO. 6246 / 2024 in Commercial Arbitration
Petition (L) No.5565 / 2024 (paragraphs 11, 12 and 15).
3 Ramesh Kumar Jain vs. Bharat Aluminium Company Limited, 2025 SCC OnLine SC 2857
(paragraphs 32 to 35).
Page 13 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
II) The first show cause notice of October 15, 2013 was
premature, since third-party testing results were
awaited. NPCIL took no further action on it;
III) Standard Corrosion attributes to NPCIL a delay of
about seven months in arranging external paint,
which reached the site on January 9, 2014; and
IV)NPCIL stopped the work on February 17, 2014 on a
labour condition not found in the contract. The
labour strike from February 24 to March 31, 2014 was
not specifically denied in NPCIL’s Statement of
Defence;
B) The termination was unlawful because:
I) NPCIL accepted Standard Corrosion’s replies to the
second show cause notice, let the work continue and
acknowledged improvement by its email of January
31, 2014. Clause 13.2.1 required seven days’ notice,
and none was given;
II) NPCIL was inclined to terminate the contract from
the second PRM of September 19, 2013; and
III) Time was not of the essence, since Clauses 7.6 and
7.7 provide for extension and for compensation for
Page 14 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
delay. Standard Corrosion offered to complete the
work and bear liquidated damages, at which time, the
contract period was yet to run out under both work
orders;
C) Risk and cost could not be recovered after an unlawful
termination. NPCIL awarded the balance work only after
about nine months, which is almost the entire contract
period. It did not supply the replacement contractor’s
expenditure;
D) The Learned Arbitral Tribunal did not accept the claims
blindly. He awarded loss of profit at 10% against 15%
claimed, and interest at the contractual rate of 12.25%
against 18% claimed. He rejected three heads of claim; and
E) The Impugned Awards are reasoned and founded on the
documentary record. NPCIL did not press its preliminary
objections. The Learned Arbitral Tribunal considered each
contention. There is no error on the face of the Impugned
Awards, and this Court must not re-appreciate evidence
under Section 34 of the Act.
Points for Determination:
17. In light of these contentions, and keeping in mind the narrow
Page 15 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
confines of the jurisdiction under Section 34 of the Act, the following core
issues arise for determination:
A) Whether the findings that the slow progress was not solely
attributable to Standard Corrosion can be said to be perverse, patently
illegal or in conflict with the fundamental policy of Indian law.
B) Whether the finding that NPCIL’s termination was unlawful
warrants interference. This includes the findings that no fresh seven-day
notice was given under Clause 13.2.1 and that time was not of the
essence.
C) Whether the rejection of NPCIL’s risk and cost recoveries, and the
allowance of claims 1, 2, 5, 6 and 7, stand or fall with the finding on
termination. The Learned Arbitral Tribunal also recorded a separate
finding on risk and cost in paragraph 28.4.2; and
D) Whether the award of loss of profit can stand on this record.
Analysis and Findings:
18. I have heard at length Mr. Dhruva Gandhi, Learned Advocate on
behalf of NPCIL and Mr. Prithviraj Gole, Learned Advocate on behalf of
Standard Corrosion, and with their assistance, and written notes on
arguments, I have examined the material on record.
19. At the threshold, it may be mentioned that arbitration was invoked
in January 2015 i.e., well prior to the amendments to the Act that took effect
Page 16 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
on October 23, 2015, but the captioned Petitions were filed after the
amendments took effect. Therefore, the post-amendment standard of review
under Section 34 of the Act would apply to the instant case. Yet, even applying
4
the pre-amendment standard and the law declared in Associate Builders , the
Impugned Awards, for the reasons set out below, do not merit interference.
20. Having said that, I have examined the contentions of the parties
and the contents of the Impugned Awards. While preliminary objections were
taken by NPCIL, they were not jurisdictional in nature but were based on
questions of fact and also not pressed in the arbitral proceedings. The issues
then boiled down to analysing the causes of delay, the validity of termination
and the consequence of whether the risk apportionment would lead to
Standard Corrosion having to bear the burden of completion of the work with
the use of another contractor.
21. It is noteworthy that the first “kick off” meeting was held on August
16, 2013, while the contracts had been awarded in June-July 2013. In other
words, two to three months had already gone by. The Learned Arbitral
Tribunal found that Standard Corrosion had tied down supplies from Kansai
Nerolac for internal and external paint, even before bidding. This
manufacturer being on the list of four permissible manufacturers, it was
found, there was no reason for the kick-off meeting leading to approval of this
supplier only for internal paint and deferring the decision on the supplier of
4 Associate Builders Vs. Delhi Development Authority – (2015) 3 SCC 49
Page 17 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
the external paint. Samples had been sent to the approved laboratory only on
October 7, 2013, by which time, the monsoon season had ended, during which
it was found that work would not have been possible. While tools, tackles,
scaffolding were ready, the Learned Arbitral Tribunal found that NPCIL could
have permitted work to commence subject to approval by the laboratory,
considering that Kansai Nerolac was a reputed supplier whose standing as a
supplier had been approved by NPCIL.
22. I am not inclined to interfere with logical and reasonable findings of
fact by the Learned Arbitral Tribunal. I must remember that the Section 34
jurisdiction is not an appellate jurisdiction. The reasoning of the Learned
Arbitral Tribunal in the Impugned Awards in support of the findings of factors
being outside the reasonable control of Standard Corrosion are logical findings
based on assessment of evidence by the master of the evidence, who is the best
judge of the quality and quantity of evidence. The Learned Arbitral Tribunal
has studied and analysed the minutes of each PRM and examined the timeline
of activities to arrive at his conclusions.
23. The Learned Arbitral Tribunal found that the first show cause
notice was issued on October 15, 2013 which falls within about a week of
provision of samples to the laboratory. The paint material had reached the site
on October 5, 2013 and sent for laboratory testing two days later and within
few days the show cause notice was issued. It is difficult to get into whether
the Learned Arbitral Tribunal was meant to look for documentary evidence of
Page 18 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
Asian Paints having been brought in for supply of external paint only at the
request of NPCIL, when the Learned Arbitral Tribunal was reasonably well
placed to arrive at the finding that the intention was to get competitively
priced supplies from Kansai Nerolac even before bidding. The Learned
Arbitral Tribunal has also found delay in approving the shade by NPCIL.
24. Even while such activity was carried on in parallel, a second show
cause notice was issued on December 13, 2013 and a PRM being held on
December 24, 2013. Various commitments with new variables of conditions
including deployment of more labour with police verification were reduced to
writing in the minutes of this PRM. There was also a delay in supply of paint
by Asian Paints. In this context, the Learned Arbitral Tribunal has weighed an
email dated January 31, 2014 from NPCIL to Standard Corrosion
acknowledging improvement in labour arrangements and that work was
progressing smoothly. However, third party laboratory testing certification of
the external paint had not been received as yet.
25. Yet, in about two weeks, NPCIL stopped work on February 17, 2014
on the premise that 20 workers each for internal and external painting had not
been deployed. It is not disputed that there was a labour strike but there is a
dispute about whether it led to disruption of access issues to just the plant or
also the township, between February 24, 2014 and March 31, 2014. The next
PRM was held on March 26, 2014 towards the end of the strike period and
commitments to deploy 20 workers per site for internal painting and 25 for
Page 19 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
external painting per site, was recorded in the minutes with an initial
deployment of 12 workers on each site from March 27, 2014. Another PRM
held on April 2, 2014 recorded further commitments and on the same date, a
letter from Standard Corrosion to NPCIL indicating that they would be bound
by the terms and also liable to liquidated damages and termination for breach
of commitments, was recorded. On April 21, 2014, a termination notice dated
April 19, 2014 was served by NPCIL.
26. Taking a holistic view of the events, the Learned Arbitral Tribunal
has found the approach of NPCIL of repeatedly and persistently threatening
termination even while making progress and agreeing to terms in PRM
minutes, to be unreasonable. In this context, the Learned Arbitral Tribunal
has arrived at a view that NPCIL appears to have had a predetermined
approach of terminating the work orders granted to Standard Corrosion. I do
find that the conduct of NPCIL appears to have been one of blowing hot and
cold, as found by the Learned Arbitral Tribunal. I am not satisfied that the
findings by the Learned Arbitral Tribunal are so implausible and unreasonable
that the standard of perversity or patent illegality has been met for the Section
34 Court to interfere with the Impugned Awards.
27. The Learned Arbitral Tribunal has also found that the award of
contract to another contractor at the risk and cost of Standard Corrosion was
undertaken well after the originally scheduled contract period for performance
by Standard Corrosion. The actual details of the costs and expenditure
Page 20 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
incurred in completing the work have not been brought on record by NPCIL.
This, coupled with the delay would indicate that mitigation efforts were not
undertaken. This again, is a finding that is not implausible. I am not inclined
to disturb the Learned Arbitral Tribunal’s findings on this facet of the matter –
the very absence of what expenditure was occasioned by having to engage
someone else to complete the work should be fatal to the element of risk and
cost of such completion being to the account of Standard Corrosion.
28. I am not persuaded that NPCIL has made out a case for me to
interfere with the Impugned Awards. The Section 34 Court would need to
second-guess the assessment of evidence by the Learned Arbitral Tribunal to
accept NPCIL’s contentions. Whether the work orders having been awarded
during the monsoon making it improbable for the view on circumstances
outside the control of Standard Corrosion; whether the withdrawal of the
monsoon complaint in the correspondence should turn the needle; whether
the introduction of Asian Paints through a particular dealer matters; and
whether the timelines for testing, police verification and supply were within
the reasonable control of Standard Corrosion, are not matters for this Court to
re-examine.
29. What is apparent is that the work orders were terminated before the
scheduled dates of completion and even the new contractor was not appointed
within that period, and worse, no evidence was led about the expenditure
incurred in completing the work. On the strength of these facts, for bank
Page 21 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
guarantees to be invoked, amounts available in other work orders to be
extracted, and the severe steps taken in the matter before the scheduled dates
of completion, even while the very first “kick off” PRM was held well into the
timeline, I believe the best judgement of what has transpired has to be left to
the Learned Arbitral Tribunal, who is none other than a former senior official
of NPCIL.
30. I also must state that I do not find the contents of the Impugned
Awards to be such that no reasonable or rational person would have arrived at
such findings. Likewise, this is not a case where one can hold that there has
been a whimsical, arbitrary or unreasonable approach adopted by the Learned
Arbitral Tribunal. I have kept in mind the following passage from Associate
Builders when considering this challenge to the Impugned Awards ( the
footnote in the judgement, to the extracted paragraph is also set out below the
extract ):
33 . It must clearly be understood that when a court is applying the “public
policy” test to an arbitration award, it does not act as a court of appeal and
consequently errors of fact cannot be corrected. A possible view by the arbitrator on
facts has necessarily to pass muster as the arbitrator is the ultimate master of the
quantity and quality of evidence to be relied upon when he delivers his arbitral
award. Thus an award based on little evidence or on evidence which does not
measure up in quality to a trained legal mind would not be held to be invalid on this
score. Once it is found that the arbitrators approach is not arbitrary or capricious,
then he is the last word on facts. In P.R. Shah, Shares & Stock Brokers (P)
Ltd. v. B.H.H. Securities (P) Ltd. [(2012) 1 SCC 594 : (2012) 1 SCC (Civ) 342] , this
Court held : (SCC pp. 601-02, para 21)
Page 22 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
“21. A court does not sit in appeal over the award of an Arbitral Tribunal by
reassessing or reappreciating the evidence. An award can be challenged only
under the grounds mentioned in Section 34(2) of the Act. The Arbitral
Tribunal has examined the facts and held that both the second respondent and
the appellant are liable. The case as put forward by the first respondent has
been accepted. Even the minority view was that the second respondent was
liable as claimed by the first respondent, but the appellant was not liable only
on the ground that the arbitrators appointed by the Stock Exchange under
Bye-law 248, in a claim against a non-member, had no jurisdiction to decide a
claim against another member. The finding of the majority is that the
appellant did the transaction in the name of the second respondent and is
therefore, liable along with the second respondent. Therefore, in the absence
of any ground under Section 34(2) of the Act, it is not possible to re-examine
the facts to find out whether a different decision can be arrived at.”
[Inserted Footnote – extracted below:]
Very often an arbitrator is a lay person not necessarily trained in law.
Lord Mansfield, a famous English Judge, once advised a high military
officer in Jamaica who needed to act as a Judge as follows:
" General, you have a sound head, and a good heart; take courage and
you will do very well, in your occupation, in a court of equity. My
advice is, to make your decrees as your head and your heart dictate, to
hear both sides patiently, to decide with firmness in the best manner
you can; but be careful not to assign your reasons, since your
determination may be substantially right, although your reasons may
be very bad, or essentially wrong".
34. It is with this very important caveat that the two fundamental principles which
form part of the fundamental policy of Indian law (that the arbitrator must have a
judicial approach and that he must not act perversely) are to be understood.
[Emphasis Supplied]
Case Law Cited by NPCIL:
Page 23 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
5
31. NPCIL has relied on Ramesh Kumar Jain for what amounts to
perversity and patent illegality but the portion cited essentially invokes
Associate Builders and therefore, to avoid prolixity, having dealt with
Associate Builders , in my opinion, it is not necessary to add further to the
analysis.
32. As regards the assault on the Impugned Awards in reliance upon
Unibros , I find that it turns on its own facts. It is apparent that Unibros
involved consideration of loss of opportunity (i.e. profitability, rather than loss
of profits) in a terminated construction contract. The following extracts are
noteworthy:
16. To support a claim for loss of profit arising from a delayed contract or missed
opportunities from other available contracts that the appellant could have earned
elsewhere by taking up any, it becomes imperative for the claimant to substantiate the
presence of a viable opportunity through compelling evidence. This evidence should
convincingly demonstrate that had the contract been executed promptly, the
contractor could have secured supplementary profits utilizing its existing resources
elsewhere.
17. One might ask, what would be the nature and quality of such evidence? In our
opinion, it will be contingent upon the facts and circumstances of each case.
However, it may generally include independent contemporaneous evidence such as
other potential projects that the contractor had in the pipeline that could have been
undertaken if not for the delays, the total number of tendering opportunities that the
contractor received and declined owing to the prolongation of the contract, financial
statements, or any clauses in the contract related to delays, extensions of time, and
compensation for loss of profit. While this list is not exhaustive and may include any
5 Ramesh Kumar Jain vs. Bharat Aluminium Company Limited, 2025 SCC OnLine SC 2857
(paragraphs 32 to 35).
Page 24 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
other piece of evidence that the court may find relevant, what is cut and dried is that
in adjudging a claim towards loss of profits, the court may not make a guess in the
dark; the credibility of the evidence, therefore, is the evidence of the credibility of
such claim.
[Emphasis Supplied]
33. CFM Asset Reconstruction was a case of a sale of property by lender
and the absence of a valuation report to assess the contention that the sale was
undervalued. That has no relevance to the facts of this case.
34. In the matter in hand, in sharp contrast, Claim No. 6 is not at all
about loss of profits had Standard Corrosion worked elsewhere, and instead, it
is a claim about loss of profit in the two works contracts that was denied by the
wrongful termination. The two concepts i.e. loss of profits and loss of
opportunity (from deployment elsewhere) are distinct although often
confused.
35. Loss of profit in a wrongly terminated contract is a function of
assessing what profits may have been made had the contract not been
terminated. Implicit in any commercially sensible party executing a contract
is an acknowledgement that the other party had something to profit from by
6
agreeing to the contract . This has been adopted by the Supreme Court in
7
MSK Projects as a “reimbursement” and restoration. The following extracts
are noteworthy:
6 A.T. Brij Paul Singh & Ors. v. State of Gujarat, (1984) 4 SCC 59
7 MSK Projects India (JV) Ltd. v. State of Rajasthan, (2011) 10 SCC 573
Page 25 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
38. In common parlance, “reimbursement” means and implies restoration of an
equivalent for something paid or expended. Similarly, “compensation” means
anything given to make the equivalent. (See State of Gujarat v. Shantilal
Mangaldas [(1969) 1 SCC 509 : AIR 1969 SC 634] , Tisco Ltd. v. Union of
India [(2001) 2 SCC 41 : AIR 2000 SC 3706] , GDA [(2004) 5 SCC 65 : AIR 2004 SC
2141] and HUDA v. Raj Singh Rana [(2009) 17 SCC 199 : (2011) 2 SCC (Civ) 136 :
AIR 2008 SC 3035] .) However, in Dwaraka Das v. State of M.P. [(1999) 3 SCC 500 :
AIR 1999 SC 1031] it was held that a claim by a contractor for recovery of amount as
damages as expected profit out of contract cannot be disallowed on ground that there
was no proof that he suffered actual loss to the extent of amount claimed on account
of breach of contract.
39. A.T. Brij Paul Singh In v. State of Gujarat [(1984) 4 SCC 59 : AIR 1984 SC
1703], while interpreting the provisions of Section 73 of the Contract Act, 1972, this
Court held that damages can be claimed by a contractor where the Government
is proved to have committed breach by improperly rescinding the contract and for
estimating the amount of damages, the court should make a broad evaluation instead
of going into minute details. It was specifically held that where in the works contract,
the party entrusting the work committed breach of contract, the contractor is entitled
to claim the damages for loss of profit which he expected to earn by undertaking the
works contract. Claim of expected profits is legally admissible on proof of the breach
of contract by the erring party. It was further observed that : (SCC pp. 64-65, para
10)
“10. … What would be the measure of profit would depend upon the facts and
circumstances of each case. But that there shall be a reasonable expectation
of profit is implicit in a works contract and its loss has to be compensated by
way of damages if the other party to the contract is guilty of breach of
contract cannot be gainsaid .”
[Emphasis Supplied]
36. This again leads to an intersection with Associate Builders
Page 26 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
(paragraphs 52 to 54) where interference with awards which allowed the
claims for loss of profitability purely based on formula was disapproved by the
Supreme Court. Therefore, in my view, one must differentiate between where
loss of profit is awarded in cases of illegally terminated contracts based on a
percentage of the unexecuted portion, without always requiring detailed
evidentiary proof, and loss of profitability where one has to assess what other
opportunities may have arisen and what overheads would have been and what
profitability analysis would need to be brought to bear.
37. In the matter in hand, Claim No. 6 is purely a claim for a reasonable
profit margin that may have been earned had the two work orders not been
cancelled even before their scheduled expiry dates, and the Learned Arbitral
Tribunal was entitled to make a reasonable estimate, which he exercised by
truncating the profit margin to 10% from the 15% claimed.
38. It is now trite law that the Supreme Court has repeatedly iterated
that Courts must not lightly interfere with arbitral awards. The scope of
review by the Section 34 Court is also well covered in multiple judgements of
the Supreme Court in judgements apart from Associate Builders , including
8 9 10 11
Dyna Technologies , Ssangyong , Konkan Railway and OPG Power . Even
implied reasons that are discernible may be inferred to support the just and
8 Dyna Technologies Private Limited v. Crompton Greaves Ltd – (2019) 20 SCC 1
9 Ssangyong Engineering & Construction Co. Ltd. v. National Highways Authority of India –
(2019) 15 SCC 131
10 Konkan Railways Co. Ltd. v. Chenab Bridge Project Undertaking – 2023 INSC 742
11 OPG Power Generation Pvt. Ltd. v. Enexio Power Cooling Solutions India Pvt. Ltd &
Anr.– (2025) 2 SCC 417
Page 27 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
fair outcome arrived at in arbitral awards. To avoid prolixity, I do not think it
necessary to burden this judgement with quotations from these judgements.
Suffice it to say (to extract from just one of the foregoing), in Dyna
Technologies , the Supreme Court held thus:
“24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an
award only on the grounds provided therein or as interpreted by various courts. We
need to be cognizant of the fact that arbitral awards should not be interfered with in a
casual and cavalier manner, unless the court comes to a conclusion that the
perversity of the award goes to the root of the matter without there being a possibility
of alternative interpretation which may sustain the arbitral award. Section 34 is
different in its approach and cannot be equated with a normal appellate jurisdiction.
The mandate under Section 34 is to respect the finality of the arbitral award and the
party autonomy to get their dispute adjudicated by an alternative forum as provided
under the law. If the courts were to interfere with the arbitral award in the usual
course on factual aspects, then the commercial wisdom behind opting for alternate
dispute resolution would stand frustrated.
25. Moreover, umpteen number of judgments of this Court have categorically held
that the courts should not interfere with an award merely because an alternative view
on facts and interpretation of contract exists. The courts need to be cautious and
should defer to the view taken by the Arbitral Tribunal even if the reasoning provided
in the award is implied unless such award portrays perversity unpardonable
under Section 34 of the Arbitration Act .”
[Emphasis Supplied]
Summary of Conclusions:
39. To conclude, I am not persuaded that the Impugned Awards
contravene the fundamental policy of Indian law or the most basic notions of
Page 28 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
morality or justice, or that they are perverse and patently illegal. It is hard to
hold that the reasons set out are incapable of being given by a rational and
reasonable mind, or that the findings are unsupported by evidence or ignore
vital material on record. Individual elements of what more could have been
dealt with or how differently it could have been dealt with, do not lend
themselves for acceptance in the facts of this case.
40. Therefore, I see no reason to disturb the finding that the pace of
work was not solely attributable to Standard Corrosion. Likewise the reasons
for which termination was held to be unlawful do not warrant interference.
The interpretation of evidence such as the email of January 31, 2014 is a
plausible one, and considering the language in the contract and the conduct of
the parties, it would be hard to displace the finding that time was not of the
essence. The termination having been validly held as unlawful, it would follow
that there was no case for visiting upon Standard Corrosion, the consequences
of termination. That apart, no evidence was led to indicate the expenditure
incurred, for it to be visited upon Standard Corrosion and for the further steps
such as invocation of bank guarantees and extraction of amounts lying in other
works contracts, to be effected. Finally, in the matrix of this case, the
reasonable estimation of loss of profit from the two works contracts (as
opposed to loss of opportunity) does not merit interference by the Section 34
Court.
41. In the result, the captioned Petitions are dismissed and the
Page 29 of 30
October 27, 2026
Aarti Palkar
Uploaded on - 27/10/2026 Downloaded on - 27/10/2026 16:59:08
ARBP.639.2017.doc
Impugned Awards are upheld.
42. Within a period of four weeks from the upload of this Order on the
Court’s website, the security, if any, given by Standard Corrosion for release of
amounts deposited in Court shall stand discharged and released along with the
balance amounts lying with the Registry of this Court. All amounts to be
released shall be paid along with earnings thereon.
43. All actions required to be taken pursuant to this order shall be taken
upon receipt of a downloaded copy as available on this Court’s website.
[ SOMASEKHAR SUNDARESAN, J.]
Page 30 of 30