Mrs. Shrikrishan Teli Communication Through Its Proprietor Krishandas Dandotiya vs The State Of Madhya Pradesh

Court
Madhya Pradesh High Court
Decided on
13-03-2026

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
1 WP-19988-2020
IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR

BEFORE
HON'BLE SHRI JUSTICE AMIT SETH
WRIT PETITION No. 19988 of 2020
MRS. SHRIKRISHAN TELI COMMUNICATION THROUGH ITS
PROPRIETOR KRISHANDAS DANDOTIYA
Versus
THE STATE OF MADHYA PRADESH AND OTHERS
Appearance:
Shri G.S.Sharma - Advocate for the petitioner.
Shri G.K.Agarwal - Govt. Advocate for respondents/State.
Reserved on : 09/03/2026
Delivered on : 13/03/2026
ORDER
The instant writ petition filed under Article 226/227 of the
Constitution of India takes exception to the order dated 20.02.2020
(Annexure-P/1) passed by the Civil Surgeon cum Chief Hospital
Superintendent, District Morena, (M.P.), whereby alleging breach of Clause
8 of the NIT, the earnest money deposited by the petitioner has been
forfeited and the petitioner-firm has been blacklisted on the ground that in
spite of being declared L-1 in the bidding process, the petitioner has failed to
get the agreement executed and make supply of food items on the approved
rates.
2. Brief facts leading to filing of the present writ petition are as under:
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
2 WP-19988-2020
2.1For procurement and supply of food and other items for patients in

the hospital at Morena in the year 2019-20, NIT was issued by the
respondents. The petitioner participated in the said NIT and apart from the
rates of other supplies, quoted the rates of Moong Dal at Rs.80/- per quintal
and Tuar Dal at Rs.90/- per quintal. The rates submitted by the petitioner
were approved by the committee headed by the Collector in its meeting
dated 27.12.2019.
2.2The petitioner realizing that there has been error in submission of
rates, as the petitioner intended to supply the pulses at the rate of Rs.80/- and
Rs.90/- per kg, i.e., Rs.8,000/- per quintal and Rs.9,000/- per quintal,
submitted an application dated 02.01.2020 to respondent No.5 seeking
acceptance of his rates at Rs.80 and 90 per kg as against Rs.80/- and 90/- per
quintal submitted in his bid. The purchase order dated 10.01.2020
(Annexure-P/4) was issued to the petitioner directing the petitioner to supply
the pulses and other items in terms of the rate submitted in bid and as
approved, including Moong Dal at Rs.80/- per quintal and Tuar Dal at
Rs.90/- per quintal, and the petitioner was also called upon to execute the
agreement on approval/sanction of the rates submitted by him in the bid
proceedings. Vide order dated 21.02.2020 (Annexure-P/6), the application
dated 02.01.2020 submitted by the petitioner was rejected on the ground that
the bid submitted by the petitioner stood accepted on 27.12.2019 itself.
2.3It appears that the petitioner finding the bid submitted by him to be
difficult to perform, did not comply with the supply order and, therefore,
after issuance of notice to the petitioner, the impugned order dated
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
3 WP-19988-2020
20.02.2020 was passed.

2.4The petitioner preferred an appeal against the said order before the
Commissioner, Chambal Division, Morena, which has been rejected on the
ground of maintainability vide order dated 25.08.2020 (Annexure-P/2).
3. Learned counsel appearing for the petitioner submits that there was
inadvertent typographical error in the matter of submission of rates of pulses.
He submits that supply of Moong and Tuar pulse at the rate of Rs.80/- and
90/- per quintal is impossible, as the same is the rate of per kg of the pulse.
He further submits that even prior to issuance of the first purchase order, the
application was submitted by the petitioner seeking correction of his bid and
without deciding the same, the purchase order was issued in his favor. He
submits that there was no concluded contract entered into between the
petitioner and respondents inasmuch as no contract agreement was executed
in compliance of the communication dated 10.01.2020 (Annexure-P/4), and
therefore, it was not lawful on the part of the respondent authorities to forfeit
the earnest money deposited by the petitioner on the ground of non-
performance of the contract or for non-compliance of the purchase order. He
further submits that no notice prior to passing the order of blacklisting was
also served on the petitioner.
4. In support of his contentions, counsel for the petitioner places
reliance upon the judgment of this Court in the case of Amit Mishra v.
General Manager (Transport), M.P. State Civil Supplies Corporation Ltd.,
Bhopal and others, reported in 2008 (4) MPLJ 542, to contend that prior
opportunity of hearing/notice is necessary before passing an order of
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
4 WP-19988-2020
blacklisting. He further places reliance upon the judgment in the case

o f S.R.S. Infra Project Pvt. Ltd., Gwalior vs Gwalior Development
Authority, reported in 2010 (2) MPLJ 142, to contend that in the absence of
any concluded contract entered into between the petitioner and the
respondents, the respondents had no authority to forfeit the earnest money
deposited by the petitioner, as no contract agreement was executed between
the petitioner and the respondent. Accordingly, he submits that the petition
deserves to be allowed.
5. On the other hand, counsel appearing for the State, by placing
reliance on the terms and conditions of the NIT, filed as Annexure-R/1 to the
return, submits that clause 8 of the NIT is specific and unambiguous. The
petitioner was bound to make good the supply within a period of seven days
from the date of issuance of the purchase order. In the event of failure to
supply in terms of the purchase order issued, the earnest money deposited by
the petitioner is liable to be forfeited, and the petitioner firm was liable to be
blacklisted. He submits that despite issuance of purchase order dated
10.01.2020 and the notices dated 27.01.2020 and 30.01.2020 even affixed at
the office of the petitioner, the petitioner did not comply with the supply
order and therefore, the action has been taken against the petitioner in terms
of clause 8 as well as clause 10 of the conditions enumerated in the NIT
itself.
6. He further submits that subsequent alteration of bid by the petitioner
via communication dated 02.01.2020 is of no consequence, as the financial
bid of the petitioner was accepted on 27.12.2019 as is evident from the
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
5 WP-19988-2020
communication dated 21.01.2020 (Annexure-P/6), whereby while rejecting

the application submitted by the petitioner, the petitioner was specifically
informed that at the time of opening of financial bid of the petitioner in the
presence of the representative of the petitioner, namely Jitendra Singh, no
objection was raised and therefore, at this stage, the petitioner cannot be
permitted to resile from his bid offered once the same stands accepted. He
further submits that the technical bid of the petitioner was opened in the
presence of the representative of the petitioner on 19.12.2019. At that stage
also, the petitioner did not object to the bid submitted by him and allowed the
bid proceedings to proceed further. Accordingly, he submits that the petition
deserves dismissal.
7. No other point has been pressed by learned counsel for the parties.
8. Heard learned counsel appearing for the parties and perused the
record.
9. In the given facts and circumstances of the case and the arguments
advanced by learned counsels appearing for rival parties, the issue calling for
consideration is whether the respondents were justified in forfeiting the
earnest money deposit made by the petitioner for non-execution of the
purchase and supply orders of food and other items and not executing the
contract in spite of being declared the successful bidder (L-1), and also
whether the order of blacklisting the petitioner has been passed by following
due process of law?
10.It is an undisputed fact that NIT (Annexure-R/1) was issued by the
respondents for procurement and supply of food and other items for the
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
6 WP-19988-2020
patients admitted in District Hospital Morena for the year 2019-20. The last

date for submission of bid was 17.12.2019 up to 5:30 PM and the date of
opening of the technical bid was 19.12.2019 at 1 PM. A pre-bid meeting was
also scheduled on 07.12.2019 at 1 PM. It is also undisputed that financial
bids so received were opened on 27.12.2019.
​ 11.Clause 8 of the terms of NIT provided that the successful bidder
was required to make the supply of the items within a period of seven days
from the date of issuance of the purchase order. In the event of delay in
supply of purchase order, penal deduction of 5% was provided with a
condition that the purchase shall be made from the next lowest bidder by
forfeiting the earnest money deposited by the L-1 bidder and he shall be
blacklisted.
​ 12.Clause 10 of the NIT further stipulated that the sanctioned rates of
the bid shall be applicable up to 13.03.2020 and no alteration in the same
would be accepted during the said period.
​ 13.The chart appended with the NIT (Annexure-R/1) indicates that in
all, the bids were required to be submitted for supply of approximately 74
items which included food, vegetable, fruits and other items meant for the
patients. The rates were required to be quoted for each item separately and
for the pulses, i.e., Moong and Tuar Dal, the rates were required to be quoted
on per quintal basis. The said document indicates that in all four bidders
including the petitioner submitted their rates. The bids for the pulses,
i.e., Moong and Tuar dal was submitted by the petitioner at Rs.80/- and
Rs.90/- respectively. After consideration of the financial bid on 27.12.2016
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
7 WP-19988-2020
by the committee, the petitioner was declared L-1 and the rates quoted by the

petitioner were also approved by the Collector, Morena.
​ 14.An application dated 02.01.2020 (Annexure-P/3) was submitted by
the petitioner to the Civil Surgeon cum Hospital Superintendent stating that
by mistake, the rates of pulses, i.e., moong and tuar dal have been quoted by
the petitioner on per kg basis at Rs.80/- and Rs.90/-, respectively, the same
may be accepted at the rate of Rs.8,000/- and Rs.9,000/- per quintal,
respectively. Thus, the petitioner after opening of financial bid and he being
declared L-1, submitted an application seeking alteration of his bids only in
respect of two items on the ground that he had committed mistake in quoting
rates.
​ 15.A purchase order dated 10.01.2020 was issued to the petitioner
calling upon him to make supplies of the items as mentioned therein
including moong and tuar dal as per the rates submitted and accepted within
the prescribed time frame and also get an agreement executed. As per the
own pleadings of the petitioner, the petitioner did not made any supply in
response to the purchase order dated 10.01.2020 nor got the agreement
executed. Another representation was submitted by the petitioner on
22.01.2020 seeking disposal of his request for alteration of his bids in respect
of moong and tuar dal. The application made by the petitioner came to be
rejected by the respondents vide order dated 21.01.2020 (Annexure-P/6) on
the ground that the financial bids quoted by the petitioner was accepted in
presence of the representative of the petitioner, Shri Jitendra Singh, on
27.12.2019 by the committee and the said rates have also been approved by
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
8 WP-19988-2020
the Collector. Therefore, the request of the petitioner seeking alteration in the

bids is not permissible. Another communication dated 17.01.2020
(Annexure-P/7) was issued to the petitioner calling upon him to make good
the supplies. However, as per the handwritten endorsement made on the
same, the petitioner refused to accept the purchase order on the ground that
he has not executed any agreement for supply.
​ 16.It appears that notices dated 27.01.2020 and 30.01.2020 were tried
to be served on the petitioner, but the petitioner refused to accept the same
and therefore the same were affixed on the residence of the petitioner. The
same was also sent through registered post on the known address of the
petitioner, yet the petitioner refused to accept the said notices/supply orders,
and it is thereafter, the respondents have passed the impugned order dated
20.02.2020, whereby for not making the supplies on the sanctioned rates and
not executing the agreement in spite of being declared L-1, the earnest
money deposit of the petitioner in terms of Clause 8 of the NIT has been
forfeited and he has been blacklisted.
​ 17.It has been strenuously argued by counsel appearing for the
petitioner that unless there is a concluded contract/agreement executed
between the petitioner and the respondents, it is not lawful on the part of the
respondents to forfeit the earnest money deposited by the petitioner by
placing reliance on the Division Bench judgment of this Court in the case of
S.R.S. Infra Project Pvt. Ltd. (supra). In the case of S.R.S. Infra Project Pvt.
Ltd. (supra), the petitioner was lacking in eligibility to participate in the
tender process, yet his bid was considered and the earnest money was
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
9 WP-19988-2020
forfeited, and it is in those facts and circumstances, the Division Bench of

this Court held that once the petitioner therein was lacking eligibility to
participate in the tender process, his bid was required to be rejected, and in
the absence of there being any concluded contract between the parties
therein, the earnest money could not have been forfeited.
​ 18.However, in the case in hand, the petitioner was fully eligible to
participate in the tender proceedings and on the basis of the rates quoted by
him in his bid, he was declared L-1 on 27.01.2019 by the committee and the
rates quoted by him were approved by the Collector. Clause 8 of the NIT in
question provides that the supplies are required to be made on the accepted
rates within a period of seven days, failing which apart from monetary penal
action, the contractor is liable for forfeiture of earnest money and
blacklisting. Clause 10 of the NIT further provides that once the quoted rates
are approved, then no alteration therein shall be permitted. The conditions of
the NIT nowhere provide that a concluded contract would come into play
only after execution of a formal agreement.
19.In view whereof, once the petitioner was declared L-1 and the rates
submitted by him were accepted and approved, it was incumbent upon him to
make good the supplies in terms of the purchase orders issued. The alteration
of rates quoted in the bid was specifically barred in terms of Clause 10 of the
NIT, and therefore, the request made by the petitioner seeking alteration of
quoted rates in his bid for Moong and Tuar pulses was not legally
sustainable, and therefore, the judgment in the case of S.R.S. Infra Project
Pvt. Ltd. (supra) relied upon by the petitioner is of no assistance to him.
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
10 WP-19988-2020
​ 20.The issue as to whether in contract matters, after opening of the

financial bids, the alteration in the rates quoted in the bid is permitted or not
recently came up for consideration before the Apex Court in the case of
Prakash Asphaltings and Toll Highways (India) Ltd. vs. Mandeepa
Enterprises and Others, Civil Appeal No.11418/2025, decided on
12.09.2025, and in paragraphs 32, 33, and 36 of the said judgment, the Apex
Court has held as under:
“32. Therefore, though the contention of respondent No.
1 is that it had made an inadvertent mistake in quoting
the BOQ rate of per day figure instead of the total
contract period of 1095 days, a closer scrutiny would
however belie such contention. In columns 5, 6 and 7,
respondent No. 1 filled up the amount in figures and
words as Rs. 9,72,999.00 and Rupees nine lakhs
seventy two thousand nine hundred and ninety nine
respectively for 1095 days. In such circumstances, it
cannot be said to be an inadvertent or unintentional
mistake, as is being contended on behalf of respondent
No. 1. Therefore, allowing respondent No. 1 to rectify
such mistakes after finalization of the financial bid
would be highly improper as it would have the effect of
unsettling the entire tender process.

33. In Patel Engineering Company Limited (supra), this
Court had rejected a similar contention that the mistakes
were unintentional and had occurred due to fault of the
computer in the following manner:
23. The mistakes/errors in question, it is
stated, are unintentional and occurred due to
the fault of computer termed as “a repetitive
systematic computer typographical
transmission failure”. It is difficult to accept
this contention. A mistake may be unilateral
or mutual but it is always unintentional. If it
is intentional it ceases to be a mistake. Here
the mistakes may be unintentional but it was
not beyond the control of Respondents 1 to 4
to correct the same before submission of the
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
11 WP-19988-2020
bid. Had they been vigilant in checking the
bid documents before their submission, the
mistakes would have been avoided. Further,
correction of such mistakes after one-and-a-
half months of opening of the bids will also
be violative of clauses 24.1, 24.3 and 29.1 of
the ITB.

33.1. xxxx xxxx xxxx
34. xxxx xxxx xxxx
35. xxxx xxxx xxxx

36. In the recent case of M/s. ABCI Infrastructures
Private Limited (supra), this Court has dealt with a
similar issue as in the present case. In that case,
appellant was ranked as L-1 bidder with the bid price of
Rs. 1,569.00 (rupees one thousand five hundred and
sixty nine only). According to the appellant, they had
quoted a bid price of Rs. 1,569 crores but due to system
error, the quoted amount appeared just as 1,569.00.
After the financial bids were opened and announced,
appellant stated that it had discovered the mistake and
accordingly the mistake was informed to the respondent
authority stating that its actual bid was Rs. 1,569 crores
and not Rs. 1,569.00. Though the mistake was bald-
faced, Border Roads Organization, the respondent
authority, insisted on accepting the bid inspite of the
letters from the appellant seeking to withdraw from the
tender. Ultimately Border Roads Organization declared
the appellant as a defaulter and decided to forfeit its bid
security. Consequently, the bank guarantee was sought
to be encashed. It was in that context, this Court though
observed that the mistake was self evident, nonetheless
it agreed with the Border Roads Organization that the
appellant was at fault and had made the mistake of
having failed to add the required zeroes in the financial
bid. The plea of system glitch put forth by the appellant
was not acceptable as the others had successfully
uploaded their bids without any problem. In the facts of
that case, this Court noted that there were subsequent
developments leading to fresh tender and award of
contract though at a lower price. In the circumstances,
this Court directed the appellant to pay Rs. 1 crore to

Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
12 WP-19988-2020
the Border Roads Organization as a consequence of its
error and upon receipt of the same, Border Roads
Organization was directed to return appellant’s original
bank guarantee.”

21.The perusal of the judgment rendered by the Apex Court in the case
o f Prakash Asphaltings and Toll Highways (India) Ltd. (supra) would
indicate that even if the ground of alleged mistake in the submission of bid is
raised, then also after the opening of the financial bid, the request for
alteration in the bid is not permissible. The petitioner herein, since was
participating in the tender for supply to the Government functionary and was
competing with other contractors, it was incumbent upon him to be vigilant
and careful in quoting the rates while submitting his bid. The entire tender
process on account of default on the part of the petitioner was rendered
unworkable, ultimately adversely affecting the general public at large, i.e.,
the patients admitted in the Government Hospital at Morena. The petitioner,
in spite of receipt of series of notices, did not respond nor made any supplies
and therefore, the action of forfeiture of earnest money was taken by the
respondents in terms of Clause 8 of the NIT which cannot be said to be
arbitrary, illegal or unjustified. No interference is therefore called for insofar
as challenge made by the petitioner to the action/order of forfeiture of earnest
money is concerned.
22.The issue of blacklisting of the petitioner for unlimited period is
now taken up for consideration. Though Clause 8 of the NIT also empowers
the authority to blacklist the contractor apart from forfeiture of the earnest
money in case of default in the supplies in response to the purchase order
issued, however, it has been consistently held by this Court as well as the
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
13 WP-19988-2020
Apex Court that prior to passing an order of blacklisting, a notice calling

upon the contractor to show cause as to why he should not be blacklisted is
necessary. The purchase orders dated 10.01.2020 and 17.01.2020 placed on
record with the petition do not indicate that the petitioner was noticed on the
issue of blacklisting. Learned counsel appearing for the State was unable to
point out either from the return or from the documents filed along with the
return that any specific notice on the question of blacklisting was issued to
the petitioner.
23.The Apex Court in the case of Gorkha Security Services vs.
Government of NCT of New Delhi; (2014) 9 SCC 105, considered and
reiterated that a show cause notice prior to passing an order of blacklisting is
necessary. The relevant part of the judgment in the case of Gorkha Security
Services (supra) reads as under:-
“........Necessity of serving show-cause notice as a
requisite of the principles of natural justice

16. It is a common case of the parties that the
blacklisting has to be preceded by a show-cause notice.
Law in this regard is firmly grounded and does not even
demand much amplification. The necessity of
compliance with the principles of natural justice by
giving the opportunity to the person against whom
action of blacklisting is sought to be taken has a valid
and solid rationale behind it. With blacklisting, many
civil and/or evil consequences follow. It is described as
"civil death" of a person who is foisted with the order of
blacklisting. Such an order is stigmatic in nature and
debars such a person from participating in government
tenders which means precluding him from the award of
government contracts.
xxxx xxxx xxxx
19. Recently, in Patel Engg. Ltd. v. Union of India
[Patel Engg. Ltd. v. Union of India, (2012) 11 SCC 257
(2013) 1 SCC (Civ) 445] speaking through one of us
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
14 WP-19988-2020
(Jasti Chelameswar, J.) this Court emphatically
reiterated the principle by explaining the same in the
following manner: (SCC pp. 262-63, paras 13-15)

“13. The concept of 'blacklisting' is explained
by this Court in Erusian Equipment &
Chemicals Ltd. v. State of W.B. [Erusian
Equipment & Chemicals Ltd. v. State of
W.B., (1975) 1 SCC 70] as under: (SCC p.
75, para 20)
20. Blacklisting has the effect of
preventing a person from the
privilege and advantage of entering
into lawful relationship with the
Government for purposes of gains.
14. The nature of the authority of the State to
blacklist the persons was considered by this
Court in the abovementioned case and took
note of the constitutional provision (Article
298), which authorises both the Union of
India and the States to make contracts for any
purpose and to carry on any trade or
business. It also authorises the acquisition,
holding and disposal of property. This Court
also took note of the fact that the right to
make a contract includes the right not to
make a contract. By definition, the said right
is inherent in every person capable of
entering into a contract. However, such a
right either to enter or not to enter into a
contract with any person is subject to a
constitutional obligation to obey the
command of Article 14. Though nobody has
any right to compel the State to enter into a
contract, everybody has a right to be treated
equally when the State seeks to establish
contractual relationships. The effect of
excluding a person from entering into a
contractual relationship with the State would
be to deprive such person to be treated
equally with those, who are also engaged in
similar activity.

15. It follows from the above judgment in
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
15 WP-19988-2020
Erusian Equipment case [Erusian Equipment
& Chemicals Ltd. v. State of W.B., (1975) 1
SCC 70] that the decision of the State or its
instrumentalities not to deal with certain
persons or class of persons on account of the
undesirability of entering into the contractual
relationship with such persons is called
blacklisting. The State can decline to enter
into a contractual relationship with a person
or a class of persons for a legitimate purpose.
The authority of the State to blacklist a
person is a necessary concomitant to the
executive power of the State to carry on the
trade or the business and making of contracts
for any purpose, etc. There need not be any
statutory grant of such power. wer. The only
legal limitation upon the exercise of such an
authority is that the State is to act fairly and
rationally without in any way being arbitrary-
thereby such a decision can be taken for
some legitimate purpose. What is the
legitimate purpose that is sought to be
achieved by the State in a given case can vary
depending upon various factors.”
20. Thus, there is no dispute about the requirement of
serving show-cause notice. We may also hasten to add
that once the show-cause notice is given and
opportunity to reply to the show-cause notice is
afforded, it is not even necessary to give an oral
hearing. The High Court has rightly repudiated the
appellant's attempt in finding foul with the impugned
order on this ground. Such a contention was specifically
repelled in Patel Engg. [Patel Engg. Ltd. v. Union of
India, (2012). 11 SCC 257: (2013) 1 SCC (Civ) 445]
[Emphasis Supplied]

24.When the facts of the present case are examined in the light of the
proposition of law laid down by the Apex Court, it is seen that prior to
passing of the order of blacklisting dated 20.02.2020, no notice was issued to
the petitioner calling upon him to show cause as to why he should not be
blacklisted. That apart, the order of blacklisting does not indicates the time
Signature Not Verified
Signed by: ADNAN HUSAIN
ANSARI
Signing time: 3/14/2026
3:37:12 PM

NEUTRAL CITATION NO. 2026:MPHC-GWL:9096
16 WP-19988-2020
period for which the petitioner is sought to be blacklisted and is, therefore,

unsustainable on this count as well, accordingly the order dated 20.02.2020
(Annexure-P/1) passed by the respondents, to the extent it directs for
blacklisting of petitioner, is hereby quashed.
25.In view of the above considerations and discussions, the writ
petition filed by the petitioner to the extent it challenges the forfeiture of
earnest money, stands dismissed. However, the challenge put forth by the
petitioner to the extent it directs for blacklisting of the petitioner is hereby
allowed.
26.For blacklisting, liberty is reserved in favour of the respondents to
take action against the petitioner in accordance with law, if so desired.
27.With the aforesaid, the writ petition stands partly allowed and
disposed of.
28.Pending application(s), if any, shall stand closed.
(AMIT SETH)