D R Singh vs South Delhi Municipal Corporation Of Delhi

Court
Central Administrative Tribunal

1 OA No.3754/2017

Central Administrative Tribunal
Principal Bench, New Delhi

OA No.3754/2017


Order reserved on: 03.11.2026
Order pronounced on: 26.11.2026


Hon’ble Dr. Chhabilendra Roul, Member (A)
Hon’ble Sh. Rajveer Singh Verma, Member (J)

Sh. D.R.Singh, AE (Civil),
(Aged about 56 years),
S/o Late Sh. R.K.Singh,
R/o B-226/1, Street No.11,
Bhajanpura,
Delhi-110053.
....Applicant

(By Advocate: Mr. M.K.Bhardwaj)

Versus

The Lt. Governor of Delhi & ors.
Through

1. The Chief Secretary,
Govt. of NCT of Delhi,
New Delhi.

2. The Commissioner,
SDMC,
th
26 floor, Civic Centre,
JLN Marg, Minto Road,
New Delhi-110002.

3. The Director of Inquiries,
Municipal Corporation of Delhi,
Civic Centre, Minto Road,
New Delhi-110002.
... Respondents

(By Advocate: Ms. Preksha Gaur with Ms. Cauveri Birbal )




SUNITA 2026.11.27
16:07:21+05'30'
DUTT

2 OA No.3754/2017

ORDER

By Dr. Chhabilendra Roul, Member (A)


The instant Original Application has been filed by the
applicant under Section 19 of the Administrative Tribunals
Act, 1985, seeking the following relief:
i) To quash and set aside the impugned order RDA
“
No.1/68/09, whereby the penalty of reduction in time
scale of pay by three stages for a period of three years with
cumulative effect was imposed upon the applicant, the
office order No.1/68/09/Vig./P/2015/81 dated
22.06.2015 (Annexure A-1), whereby the proposed penalty
was confirmed and the order No.1/68/2009 dated
03.08.2017 (Annexure A-1A) whereby his appeal is
rejected by the appellate authority, with all their effects.

ii) To restore the pay of the applicant, reeducated in
terms of the aforementioned impugned orders, with
arrears and interest thereon @18%.

iii) To allow the OA with cost.

iv) Any other orders may also be passed as this Hon’ble
Tribunal may deem fit and proper in the existing facts and
circumstances of the case.”

2. Factual Matrix

2.1 The present applicant worked as Assistant Engineer in
Building Department, West Zone, Municipal Corporation of
Delhi (MCD) and was in charge of Old Mahavir Nagar. It was
alleged that he allowed the owner/builder to carry out and
complete the unauthorised constructions at Ground Floor,
First Floor, and Second Floor in property No. S-4/85 and
Second and Third floors in property No. S-4/90, Old Mahavir
Nagar and failed to get it stopped/demolished at their initial
ongoing stage, under Section 332/461 and/or 466 -A of DMC
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

3 OA No.3754/2017

Act. He was issued a charge-sheet in terms of Rule 8 of MCD
Service (Control and Appeal) Rules, 1959 on 05.09.2009. The
unauthorised constructions were booked by one JE on
09.09.2008 and the seniors like the present applicant were
informed.
2.2 The Applicant submitted his reply on 17.08.2009 stating
that he has taken appropriate action and there was no lapse
on his part. He had further stated that no police force was
made available to demolish the unauthorised constructions.
After considering his reply, the Disciplinary Authority (DA)
ordered that a proper inquiry should be conducted in respect
of the charge-sheet. The Inquiry Officer (IO) submitted the
inquiry report on 22.09.2014 and proved the charges
contained in the charge-sheet. The IO concluded his inquiry
report in the following manner:
“In view of the aforesaid evidence produced by the
prosecution through inspection reports of Central Control
Room and JE/CTF, photographs of the impugned
properties and the testimony of PW-1 and PW-2 the
prosecution has succeeded in substantiating the charges
against both the COs i.e. Shri Dharmendra Kumar Meena,
JE (B) and Shri D.R.Singh, AE (B). On the other hand the
COs have not been able to rebut the charges effectively. It
is a fact that both the impugned properties were booked
by the CO Shri Dharmendra Kumar Meena, JE (B) but
only after the inspections of Central Control Room and
JE/CTF and as such the bookings do not come to their
rescue. In view of the aforesaid evidence I hold the charges
mentioned in their charge sheets as proved against both
the COs Shri Dharmendra Kumar Meena, JE (B) and Shri
D.R.Singh, AE (B).”

2.3 After receiving the inquiry report, the applicant did not
furnish any reply or representation to this report. The DA vide
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

4 OA No.3754/2017

order dated 16.03.2015 proposed a penalty of “reduction of
scale of pay by three stages for a period of three years with
cumulative effect” upon the applicant. The applicant prefers
not to file any representation against the said proposed
penalty. The DA vide its order dated 08.06.2015 confirmed
the proposed penalty. The applicant submitted an appeal on
30.03.2017 against the penalty order communicated to him
on 17.05.2015. The Appellate Authority vide order dated
03.08.2017 rejected the said appeal by the applicant. Being
aggrieved the applicant has filed the present application
seeking the aforementioned relief.
3. Pursuant to the notices issued, the respondents entered
appearance and filed their reply, to which the applicant has
filed the rejoinder.

4. Submissions by learned counsel for the applicant


4.1 Relying on the grounds mentioned in the OA, the
learned counsel for the applicant submits that the applicant
challenges the penalty order dated 26.05.2015 and rejection
of his appeal by the Appellate Authority dated 03.08.2017 on
the following grounds:
I. The charge-sheet was initiated on 05.06.2009 and
concluded on 22.09.2014, nearly after five years. There was
inordinate delay in completing the inquiry. Under such
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

5 OA No.3754/2017

circumstances, the courts have taken a serious view and have
granted relief to the petitioners therein. In support of his
contention, the learned counsel for the applicant refers to the
judgment of the Apex Court in State of Andhra Pradesh Vs.
N. Radhakrishnan , 1988 (4) SCC 154 wherein it was held:
“In State of Punjab and others vs. Chaman Lal Goyal
(1995 (2) SCC 570), state of Punjab was aggrieved by the
order of the High Court of Punjab and Haryana quashing
memo of charges against Goyal and also the order
appointing Inquiry Officer to inquire into those charges.
In this case the incident, which was the subject-matter of
charge, happened in December, 1986 and in early
January, 1987, when Goyal was working as supdt. of
Nabha High Security Jail. It was only on July 9, 1992
that memo of charges was issued to Goyal. He submitted
his explanation of January 4, 1993 denying the charges.
Inquiry Officer was appointed on July 20, 1993 and soon
thereafter Goyal filed writ petition in the High Court on
august 24, 1993. The High Court quashed the memo of
charges on the principal ground of delay of five and a half
years in serving the memo of charges, for which there
was no acceptable explanation. This Court examined the
factual position as to how the delay occurred and if Goyal
had been prejudiced in any way on account of delay. This
Court relied on the Principles laid down in A.r. Antulay
vs. R.S. Nayak (1992 (1) SCC 225), and said, that though
that case pertained to criminal prosecution the principles
enunciated therein were broadly applicable to the pleas of
delay in taking the disciplinary proceedings as well.
Referring to decision in a.r. Antulay case this Court said:-
"In paragraph 86 of the judgment, this Court
mentioned the propositions emerging from the
several decisions considered therein and observed
that "ultimately the court has to balance and weigh
the several relevant factors - balancing test or
balancing process - and determine in each case
whether the right to speedy trial has been denied in
a given case." It has also been held that, ordinarily
speaking, where the court comes to the conclusion
that right to speedy trial of the accused has been
infringed, the charges, or the conviction, as the case
may be, will be quashed. At the same time, it has
been observed that that is not the only course open
to the court and that in a given case, the nature of
the offence and other circumstances may be such
that quashing the proceedings may not be in the
interest of justice. In such a case, it has been
observed, it is open to the court to make such other
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

6 OA No.3754/2017

appropriate order as it finds just and equitable in
the circumstance of the case."
In that case this Court said that it was more appropriate
and in interest of justice as well as in the interest of
administration that inquiry which has proceeded to a
large extent be allowed to be completed. At the same time
the Court directed that Goyal should be considered
forthwith for promotion without reference to and without
taking into consideration the charges or the pendency of
the inquiry, if he is found fit for promotion.
It is not possible to lay down any pre-determined
principles applicable to all cases and in all situations
where there is delay in concluding the disciplinary
proceedings. Whether on that ground the disciplinary
proceedings are to be terminated each case has to be
examined on the facts and circumstances in that case .
the essence of the matter is that the court has to take
into consideration all relevant factors and to balance and
weight them to determine if it is in the interest of clean
and honest administration that the disciplinary
proceedings should be allowed to terminate after delay
particularly when delay is abnormal and there is no
explanation for the delay. The delinquent employee has a
right that disciplinary proceedings against him are
concluded expeditiously and he s not made to undergo
mental agony and also monetary loss when these are
unnecessarily prolonged without any fault on his part in
delaying the proceedings. In considering whether delay
has vitiated the disciplinary proceedings the Court has to
consider the nature of charge, its complexity and on what
account the delay has occurred. If the delay is
unexplained prejudice to the delinquent employee is writ
large on the face of it. It could also be seen as to how
much disciplinary authority is serious in pursuing the
charges against its employee. It is the basic principle of
administrative justice that an officer entrusted with a
particular job has to perform his duties honestly,
efficiently and in accordance with the rules. If he deviates
from this path he is to suffer a penalty prescribed.
Normally, disciplinary proceedings should be allowed to
take its course as per relevant rules but then delay
defeats justice. Delay causes prejudice to the charged
officer unless it can be shown that he is to or when there
is proper explanation for the delay in conducting the
disciplinary proceedings. Ultimately, the court is to
balance these two diverse consideration.”

Referring to the aforementioned judgment, the learned
counsel contended that there was inordinate delay in
concluding the disciplinary inquiry against the applicant.
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

7 OA No.3754/2017

Accordingly, the penalty order as well as the rejection of the
applicant’s appeal should be quashed on this ground only.
II. The second ground emphasised by the learned counsel
for the applicant is that the charges attributed to the
applicant are not attributable to the applicant. The subject
matter was not his responsibility alone. It was the joint
responsibility of the applicant as SDE, the co-acceded JE and
his superior boss, the Executive Engineer. The Executive
Engineer was left out without imposing any punishment. The
applicant, who had taken appropriate action (passed the
demolition order) and brought to the notice of higher
authority about the unauthorised construction, has been
punished. It was the duty of the JE to carry out the
demolition of such an unauthorised construction, taking due
help from the police. Hence, both the Disciplinary Authority
and the Appellate Authority have not applied their judicious
mind in apportioning the responsibilities among the various
authorities in the hierarchy and singled out the applicant for
heavy punishment.
4.5 In support of his contention, the learned counsel for the
applicant refers to Annexure -A7 (page 94-95) wherein the
respondents themselves have issued detailed guidelines
regarding the responsibilities of the Assistant Engineer and
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

8 OA No.3754/2017

the Executive Engineer. Paragraph 7 of the said circular
dated 22.11.2000 states:
“7. Site inspection of unauthorised construction cases
shall be carried out to the following extent:

Assistant Engineer(B):-40% of total cases booked in his
jurisdiction.

Executive Engineer(B):-20% of total cases book in a
month.”


4.6 He also referred to the circular dated 05.02.2008
(Annexure A-12), which has reiterated the same. Further the
learned counsel for the applicant has cited the judgment of
the Apex Court in Man Singh vs. State of Haryana , Civil
Appeal No. 3186/2008, decided on 01.05.2008 as well as the
judgment of Apex Court in Rajendra Yadav vs. State of M.P.
in Civil Appeal No. 2070/2012 decided on 13.02.2013,
wherein the Apex Court had taken serious view when the
there was no action taken by the administrative authorities
against the supervisory officers. It amounts to meting out
discriminatory treatment to the applicant vis-a-vis the
Executive Engineer.

4.7 The learned counsel for the applicant further contends
that the respondents have imposed the penalty based on an
inquiry report which has allegedly held that the charges
against the applicant were proved. But there was lack of
evidence against the applicant in view of his claim of
apportionment of responsibilities in the matter of taking
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

9 OA No.3754/2017

action against unauthorised constructions. The IO has based
his conclusion only on the prosecution evidence and did not
take into account the defences forwarded by the applicant
during the inquiry proceedings. The applicant has taken
appropriate action as admitted by PW-1. He referred to the
same as it has been mentioned in the inquiry report dated
22.09.2015. Particularly the IO has reported:
“During cross examination by the COs PW-1 stated that it
is correct that sealing action was initiated by the COs in
r/o both the properties but at a later stage which is matter
of record. PW-1 further stated that it is also a matter of
record whether the Cos had written letters to Water &
Electricity Deptt. To get the Water/Electricity connection
disconnected. PW-1 mentioned in his report that these
actions were taken at a later stage. PW-1 further stated
that the matter relating to fixation of demolition
programme and procuring police force and its availability
is also to be seen by the Bldg. Department. PW-1 further
stated that both the properties were residential in nature
as per appearance from outside and at the time of
inspection by the JE/CTF the u/c was found in progress
in both the properties. However, PW-1 admitted that at
the time of inspection by the Vig. Deptt. No construction
was found in progress and the u/c was booked in r/o both
the properties on complaint as per Ex.S-4.”


4.8 The learned counsel for the applicant further states that
the Appellate Authority has, without evidence, stated that:
“10) Evidently, the appellant had failed to take any
proactive action against the unauthorized construction in
both the properties at the initial stages, allowing the
owner/builder to raise the building, in utter disregard of the
provisions of the building byelaws. Therefore, the records
beyond any reasonable doubt reflect that the appellant had
been grossly lackadaisical in discharge of his duties and
responsibilities. Such attitude amongst the Municipal
employees has been the cause of mushrooming unauthorized
construction. Hence such misconduct cannot go unpunished
and in fact merits to be meted out commensurate punitive
action, so as to be an adequate deterrent for others.”

SUNITA 2026.11.27
16:07:21+05'30'
DUTT

10 OA No.3754/2017

4.9 Referring to the above, the learned counsel for the
applicant states that this conclusion is based on conjectures.
The applicant has taken appropriate action after the matter
was brought to his notice, and a notice for demolition of an
unauthorised construction was issued by him. Hence, he has
taken proactive steps to prevent an unauthorised
construction. In support of his averment the learned counsel
for the applicant refers to order dated 09.02.2015 in OA No.
314/2015, wherein the applicant has been given relief under
similar grounds and on account of delay in completing the
inquiry, which had caused prejudice to the employee.
5. Submission by the learned counsel for the
Respondents


5.1 The learned counsel for the respondents averred that
depending upon the nature of the case and facts and
circumstances during the inquiry proceedings, delay in
completing the inquiry would attract prejudice as enacted by
the respondents. In support of his averment, he cites the
judgment of the Apex Court in Government of Andhra
Pradesh Vs. Appala Swamy , (2009) 1 SCC (L&S) wherein
Paragraph 12 of the judgment it was held:
“12. So far as the question of delay in concluding the
departmental proceedings as against a delinquent officer
is concerned, in our opinion, no hard and fast rule can be
laid down therefor. Each case must be determined on its
our facts. The principles upon which a proceeding can be
directed to be quashed on the ground of delay are:
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

11 OA No.3754/2017

(1) Where by reason of the delay, the employer condoned
the lapsee on the part of the employee;
(2) where the delay caused prejudice to the employee.
Such a case of prejudice, however, is to be made out by
the employee before the Inquiry officer.”

5.2 In the instant case, the inquiry was completed on
22.09.2014, nearly five years after issuance of the charge-
sheet on 05.06.2009. However, due to the complexity of the
inquiry and the disciplinary case, the applicant cannot invoke
the principle of prejudice, without any substantial evidence to
that effect. And, there is no hard and fast rule for each and
every disciplinary case to be completed within a stipulated
period. If any time line is mentioned, it is advisory only; not
mandatory.
5.3 As regards allegation that there was lack of evidence to
prove the charges against the applicant, the learned counsel
for the applicant states that the IO has detailed the evidences
based on which he has proved the charges. On the contrary,
the applicant preferred not to bring any defence witnesses nor
documents in support of his assertions during the inquiry
proceedings as well as on subsequent stages of appeal. Even,
he preferred not to reply to the report of the IO and to the
notice issued by the DA for imposing the proposed penalty.
Moreover, the disciplinary cases are decided by the competent
DA and AA based on preponderance of evidences. The
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

12 OA No.3754/2017

exactitude expected in criminal cases is not strictly applied to
disciplinary cases. The IO in his report has given details of
the evidence based on which the IO proved the charges
against the applicant. He referred to the relevant part of
“Analysis of Evidence & Findings” of the inquiry report which
states the following:
“A careful perusal of the prosecution documents
exhibited as Ex.S-1 to S-6, the testimony of PW-1 and
PW-2, the defence documents and the written arguments
of the PO as well as the COs reveal the following vital
facts which would be useful in deciding the culpability of
the COs in so far as the charges in the present inquiry
are concerned.
(i) The complaint (Ex.S-1) of Sh. D. Sehgal received in the
Vig. Deptt. on 21.8.2008, clearly mentions that u/c is
going on in properties Nos. S-4/90 and S-4/85, Mahavir
Nagar.
(ii) The report dated 25.8.2008 (Ex.S-2) submitted by the
Supervisor, Central Control Room alongwith photographs
as per the directions of CVO/MCD clearly reveals that
u/c was going on in properties Nos. S-4/85 and S-4/90,
Mahavir Nagar.
(iii) The specific report dated 28.8.2008 (Ex.S-2 page
10/c) of JE/CTF in respect of property No. S-4/90
alongwith the colour photograph clearly mentions that
new additional SF and half portion of TF constructed at
old and occupied building. The report further mentions
that structure work completed and finishing work is
going on at the time of inspection. The report further
concludes that the construction work on SF and TF is
totally unauthorized. The side portion of the aforesaid
building as shown in the photograph clearly shows fresh
construction.
(iv) The specific report dated 30.8.2008 (Ex.S-2 page 7/c)
of JE/CTF in respect of property No. S-4/85 alongwith
the colour photograph clearly mentions that construction
work is going on at the GF. The report further mentions
that roof casting work found in the said property but no
any permission seen at the site.
(v) During examination PW-1 and PW-2 stated that at the
time of inspection of Vigilance team u/c was found going
on in properties No. S-4/85 and S-4/90, Old Mahavir
Nagar which corroborate the contents of the complaint
(Ex.S-1) and the inspection report (Ex.S-2) of JE/CTF.
(vi) PW-1 further stated that the owner/builder of P. No.
S-4/85 had carried out u/c at GF, FF & SF. The u/c at
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

13 OA No.3754/2017

GF and FF was booked by the CO Sh. D.K. Meena, JE on
9.9.08 vide u/c file No.B/UC/WZ/08/302 (Ex.S-4) and
u/c at SF on 3.11.08 vide file no. B/UC/WZ/08/582.
PW-1 further stated that similarly, the owner/builder of
P.No. 4/90, Old Mahavir Nagar had carried out u/c at SF
& TF which was booked by Sh. D.K. Meena, JE on 9.9.08
vide file No. B/UC/WZ/08/300 (Ex.S-4).
(vii) u/c in both the impugned properties i.e., at GF and
FF in property No.S-4/85, Old Mahavir Nagar and at SF
and TF in property No.S-4/90, Old Mahavir Nagar had
been booked by the CO Shri D.K.Meena, JE (B) on
9.9.2008 i.e. after the surprise inspection of both the
properties by the Supervisor, Central Control Room on
25.8.2008 and by JE/CTF on 28.8.2008 and 30.8.2008
as mentioned above.
(viii) The COs could not stop the O/B from carrying out
further u/c at SF of property No.S-4/85 even after
booking of u/c at GF and FF of the said property on
9.9.2008 and the u/c at SF of the said property had to be
booked on 3.11.2008.”

5.4 In view of the above, the learned counsel for the
respondent states that the assertion that the IO held the
charges as proved without evidence is contrary to the facts of
the case as reported above. Moreover, in the inquiry report,
the cross examination of the PW-1 has been mentioned
wherein the said PW has categorically stated that whatever
action taken by the applicant was only after it was pointed
out to him and after the unauthorised construction was
brought to his notice. It was the bounden duty of the
applicant as SDE to prevent the unauthorised construction
when such construction was initiated. It has been rightly
mentioned by the DA in Para 10 of the proposed penalty
notified to the applicant that he had failed to take proactive
timely steps to prevent the unauthorised constructions.

SUNITA 2026.11.27
16:07:21+05'30'
DUTT

14 OA No.3754/2017

6. Analysis

6.1 The applicant has not brought out any malice on the
part of the respondents to adduce prejudice on account of
delay in completing the enquiry. By merely stating the fact
that the enquiry took five years to complete does not attract
the principle of prejudice on account of delayed completion of
the enquiry. As it has been rightly pointed out by the learned
counsel for the respondents citing Paragraph 12 of the
Appala Swamy (supra) case, there is no gold standard
statutorily fixed for completion of any disciplinary
proceedings. The applicant has failed to bring anything on
record to substantiate that based on the facts and
circumstances of the disciplinary proceedings, there is
deliberate delay in completing the disciplinary inquiry by the
IO. The judgment in N. Radhakrishnan (supra) by the Apex
Court does not come to the rescue of the applicant due to the
distinguishable facts and circumstances of the case at hand
in comparison to that case.

6.2 The learned counsel for the applicant tried to impress
upon that there was lack of evidence to prove the charges
against the applicant. As it has been rightly pointed out by
the learned counsel for the respondents, the IO has detailed
the evidence against the applicant (documents and statement
of PW-1) to prove the charges. The DA in Paragraph 10 of the
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

15 OA No.3754/2017

proposed penalty also has relied on 7 points as to how the IO
has proved the charges against the applicant. We have
perused the inquiry report and the penalty order/proposal
and are of the opinion that the assertion by the applicant in
the OA and the submissions by his counsel have failed to
substantiate such assertion. By mere verbal assertion that
there was no evidence does not convince this Tribunal that
there was no evidence. On the contrary, as pointed out above,
there was sufficient evidence to hold the charges proved
against the applicant.
6.3 Moreover, the exactitude of gold standard of evidence in
criminal proceedings is not warranted in disciplinary
proceedings. We agree with the contention of the learned
counsel for the respondents that in disciplinary cases
preponderance of evidence is applied to prove the charges
against the Charged Officer (CO). In this context, it would not
be out of place to refer the judgment of the Apex Court in B.C
Chaturvedi vs. Union of India , (1995) 6 SCC 749 wherein it
was held:
“Judicial review is not an appeal from a decision but a
review of the manner in which the decision is made.
Power of judicial review is meant to ensure that the
individual receives fair treatment and not to ensure that
the conclusion which the authority reaches is necessarily
correct in the eye of the court. When an inquiry is
conducted on charges of misconduct by a public servant,
the Court/Tribunal is concerned to determine whether
the inquiry was held by a competent officer or whether
rules of natural justice are complied with. Whether the
findings or conclusions are based on some evidence, the
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

16 OA No.3754/2017

authority entrusted with the power to hold inquiry has
jurisdiction, power and authority to reach a finding of
fact or conclusion. But that finding must be based on
some evidence. Neither the technical rules of Evidence
Act nor of proof of fact or evidence as defined therein,
apply to disciplinary proceeding. When the authority
accepts that evidence and conclusion receives support
therefrom, the disciplinary authority is entitled to hold
that the delinquent officer is guilty of the charge. The
Court/Tribunal in its power of judicial review does not
act as appellate authority to re- appreciate the evidence
and to arrive at its own independent findings on the
evidence. The Court/Tribunal may interfere where the
authority held the proceedings against the delinquent
officer in a manner inconsistent with the rules of natural
justice or in violation of statutory rules prescribing the
mode of inquiry or where the conclusion or finding
reached by the disciplinary authority is based on no
evidence. If the conclusion or finding be such as no
reasonable person would have ever reached, the
Court/Tribunal may interfere with the conclusion or the
finding, and mould the relief so as to make it appropriate
to the facts of each case.
The disciplinary authority is the sole judge of facts.
Where appeal is presented. The appellate authority has
co- extensive power to reappreciate the evidence or the
nature of punishment. In a disciplinary inquiry the strict
proof of legal evidence and findings on that evidence are
not relevant. Adequacy of evidence or reliability of
evidence cannot be permitted to be canvassed before the
Court/Tribunal. In Union of India v. H.C. Goel [(1964) 4
SCR 781], this Court held at page 728 that if the
conclusion, upon consideration of the evidence, reached
by the disciplinary authority, is perverse or suffers from
patent error on the face of the record or based on no
evidence at all, a writ of certiorari could be issued.”

6.2 As regards the assertion by the applicant in the OA and
his counsel during final submissions that the respondents
have discriminated against the applicant in punishing him
and leaving out the supervisory office like the Executive
Engineer, this Tribunal is of the view that it is indirect way of
admitting his charges. Whether a co-accused was equally
punished or not punished at all would not determine the
culpability of any accused in disciplinary proceedings. If
SUNITA 2026.11.27
16:07:21+05'30'
DUTT

17 OA No.3754/2017

charges are proved against any individual employee, it is
sufficient and the penalty that has to be imposed is
independent of any decision to be taken by the respondents
against other COs or non-COs like the Executive Engineer
based on the facts and circumstances of the case. Demanding
equal punishment against others is no defence at all.
6.3 Moreover, the respondents have punished the other CO,
i.e. the Junior Engineer who was equally held responsible for
the unauthorised constructions. Hence, it is contrary to the
assertion by the applicant and his counsel during the final
hearing. In the hierarchy of administration and shouldering
responsibilities, disproportionate culpability assigned for any
breach in discipline. An Executive Engineer has a broader
responsibility that a JE or DSE. For each unauthorised
construction, there are primary responsibilities. And for each
violation on the spot, demanding equal punishment for the
Executive Engineer at par with the DSE is not acceptable by
any cogent principle. An Executive Engineer may have more
than one DSE and more broad responsibilities than a DSE.
Moreover, proved charges against the DSE cannot absolve
him of the onus of being punished invoking that no
punishment or lesser punishment imposed against others in
the hierarchy of responsibilities.

SUNITA 2026.11.27
16:07:21+05'30'
DUTT

18 OA No.3754/2017

7. Conclusion

7.1 In view of the above, this Tribunal comes to the
conclusion that the present OA lacks merit and hence it is
dismissed.
8. No order as to costs.

9. All pending MAs, if any, are disposed of accordingly.


(Rajveer Singh Verma) (Dr. Chhabilendra Roul)
Member (J) Member (A)

‘SD’