Shree Naman Hotels Pvt. Ltd. vs Mumbai Metropolitan Region Development Authority And Anr
- Court
- Bombay High Court
- Case type
- WP
- Decided on
- 08-04-2026
<div> <b>2026:BHC-OS:8909-DB</b><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Shephali<br /> IN THE HIGH COURT OF JUDICATURE AT BOMBAY<br /> ORDINARY ORIGINAL CIVIL JURISDICTION<br /> WRIT PETITION NO. 3209 OF 2017<br /> Shree Naman Hotels Pvt. Ltd.,<br /> A company registered under the provisions <br /> of the Companies Act, 1956, having its <br /> registered office at 315, Parekh Market,<br /> 39, J.S.S. Road, Opera House, <br /> Mumbai 400 004. …Petitioner<br /> ~ versus ~<br /> 1. Mumbai Metropolitan Region<br /> Development Authority,<br /> a Body Corporate having its Head <br /> Office at MMRDA Office Building,<br /> Plot Nos. C-14 & C-15, ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051.<br /> SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Digitally signed<br /> by SHEPHALI<br /> SANJAY<br /> MORMARE<br /> Date: 2026.04.09<br /> 15:15:50 +0530<br /> 2. The Metropolitan Commissioner,<br /> being the Chief Executive Officer of <br /> the Mumbai Metropolitan Region <br /> Development Authority, having his <br /> office at MMRDA Office Building,<br /> Plot Nos. C-14 & C-15, ‘E’ Block, <br /> Bandra Kurla Complex, Bandra (East), <br /> Mumbai 400 051. …Respondents<br /> A PPEARANCES<br /> For the Petitioner Mr. Vikram Nankani, Senior<br /> Advocate, with Mr. Vaibhav Krishna<br /> & Mr. Tahir Pande, i/b Juris<br /> Consillis.<br /> For Respondents-MMRDA Mr. Pravin Samdani, Senior<br /> Advocate, with Mr. Nishant Chotani,<br /> Mr. Nivit Srivastava, Ms. Sneha<br /> Page 1 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Patil, Ms. Aditi Sinha, Mr.<br /> Hrishikesh Joshi & Ms. Isha Vyas,<br /> i/b Maniar Srivastava Associates.<br /> CORAM : SHREE CHANDRASHEKHAR, CJ &<br /> SUMAN SHYAM, J.<br /> nd<br /> RESERVED ON : 22 JANUARY 2026.<br /> th<br /> PRONOUNCED ON : 8 APRIL 2026.<br /> JUDGMENT ( Per Suman Shyam, J) :- <br /> 1. Rule, rule is made returnable forthwith.<br /> 2. By consent of the parties, the matter is taken up for final<br /> hearing.<br /> th<br /> 3. Assailing the Demand Notice dated 12 September 2017<br /> (Exhibit “P”) issued by Respondent No.1–Mumbai Metropolitan<br /> Region Development Authority (hereinafter referred to as<br /> “MMRDA”), whereby, the said Respondent had demanded payment<br /> of additional premium, together with interest, on account of alleged<br /> delay in completion of the construction, the Petitioner has<br /> approached this Court by filing the present Writ Petition inter alia<br /> contending that such demand pertaining to the construction of the<br /> basic built-up area of 18,600 sq. mtrs. in the building known as<br /> “Sofitel Hotel” on Plot Nos. C-57 and C-58 (combined) at Bandra-<br /> Page 2 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Kurla Complex (“BKC”) is contrary to the terms and conditions of<br /> th<br /> the Lease Deed dated 9 June 2006 and, therefore, is arbitrary,<br /> illegal, discriminatory and also is in violation of the fundamental<br /> rights guaranteed to the Petitioner under Article 14 of the<br /> Constitution of India. The facts and circumstances, giving rise to the<br /> filing of the present Writ Petition, shorn of unnecessary details, are<br /> as hereunder.<br /> 4. The Petitioner is a company incorporated under the<br /> provisions of the Companies Act, 1956 having its registered office at<br /> Opera House, Mumbai. It is a subsidiary of “Shree Naman<br /> Developers Ltd”. <br /> 5. The Respondent No.1, MMRDA is a statutory authority<br /> constituted under the Mumbai Metropolitan Region Development<br /> Authority Act, 1974 (hereinafter referred to as “the MMRDA Act”)<br /> and the Respondent No. 2 is the Metropolitan Commissioner of<br /> MMRDA.<br /> 6. The Respondent No.1, being the owner of the land, had<br /> th<br /> floated a Tender on 8 February 2005, for grant of 80-years lease in<br /> respect of Plot Nos. C-57 and C-58 (combined) admeasuring<br /> Page 3 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> approximately 8,092.40 sq. mtrs., situated in ‘G’ Block of Bandra-<br /> Kurla Complex, for construction of a Star Category Hotel with the<br /> maximum permissible built-up area of 18,600 sq. mtrs. The said<br /> tender was issued in terms of the provisions of the Mumbai<br /> Metropolitan Region Development Authority (Disposal of Land)<br /> Regulations, 1977. Although the bid process was initiated by<br /> th<br /> Respondent No. 1 on 8 February 2005, yet, the same was kept in<br /> abeyance. Thereafter, fresh bids were invited by the Respondent<br /> th<br /> No.1 on 18 November 2005 with revised terms including revised<br /> the reserve price.<br /> 7. In response to the above tender, the Petitioner’s parent<br /> company, viz., Shree Naman Developers Ltd. (“SNDL”), had<br /> th<br /> submitted its bid on 30 December 2005, offering premium of<br /> Rs.1,10,000/- per sq. mtrs., aggregating to Rs.204,60,00,000/- for<br /> the entire plot. The bid submitted by the SNDL came to be accepted<br /> th rd<br /> by Respondent No.1 in its 115 Meeting held on 3 February, 2006,<br /> under Resolution No.1072. Accordingly, Letter of Allotment dated<br /> th<br /> 14 February 2006 was issued in favour of SNDL.<br /> 8. SNDL, thereafter, paid the entire lease premium of<br /> Rs.204,60,00,000/- (Rupees Two hundred and four crores sixty<br /> Page 4 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> lakhs) to Respondent No.1 pursuant whereto, a Lease Deed dated<br /> th<br /> 9 June 2006 came to be executed by and in between the<br /> Respondent No.1 and SNDL, for granting leasehold rights in respect<br /> of the said plot of land for a period of 80 years for construction of a<br /> Star Category Hotel.<br /> th<br /> 9. Article 2(a) of the Lease Deed dated 9 June 2006 stipulates<br /> that building plans are to be submitted to the planning authority for<br /> approval. Article 2(d) provides that the lessee shall, within three<br /> months from receipt of approval of the plans, commence<br /> construction and within a period of four years from the date of the<br /> lease, complete and finish the building so as to render it “fit for<br /> occupation”. Article 2(e) lays down that in the event of failure to<br /> complete the construction within the stipulated period, the<br /> Metropolitan Commissioner may grant extension of time upon<br /> payment of additional premium at the prescribed rates.<br /> th<br /> 10. Possession of the said plot was handed over to SNDL on 13<br /> June 2006. Thereafter, with the permission of Respondent No.1,<br /> th<br /> granted on 14 July 2006, SNDL had assigned its right, title and<br /> interest under the Lease Deed, in favour of the present Petitioner,<br /> st<br /> by executing Deed of Assignment dated 1 August 2006.<br /> Page 5 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> 11. On 14 September 2006, a notification was issued by the<br /> Ministry of Environment and Forests (“MoEF”) requiring<br /> Environmental Impact Assessment (“EIA”) clearance for the project.<br /> th<br /> On 13 December 2006, the Petitioner had applied for permission<br /> from the Respondent No. 1 to commence excavation work pending<br /> th<br /> EIA clearance from the MoEF. By communication dated 13<br /> November 2006, the Respondent No.1 had, however, declined such<br /> permission and informed the Petitioner that excavation permission<br /> could be considered only after the Petitioner obtains the EIA<br /> clearance.<br /> 12. The Petitioner accordingly, applied for the EIA clearance on<br /> rd nd<br /> 23 November 2006 and the same came to be granted on 2 March<br /> 2007. Pursuant thereto, the Respondent No.1 had granted<br /> th<br /> excavation permission to the Petitioner on 8 March 2007.<br /> 13. In the meantime, the Petitioner had submitted building plans<br /> to Respondent No.1 and applied for Commencement Certificate.<br /> The first Commencement Certificate upto the plinth level was<br /> th <br /> issued only on 29 October 2007 i.e. after a delay of about 1 year 4<br /> months from the date of execution of the Lease Deed. <br /> Page 6 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 14. According to the Petitioner, considerable time was consumed<br /> in securing statutory approvals including EIA clearance from the<br /> Ministry of Environment and Forest (MoEF), height clearance from<br /> the Ministry of Civil Aviation. The Civil Aviation Ministry had<br /> granted permission for construction only up to a restricted height<br /> th<br /> vide communication dated 25 March 2008. Thereafter, Intimation<br /> of disapproval and further approvals were processed and ultimately,<br /> th<br /> Commencement Certificate dated 18 March 2009 was issued by<br /> the Respondent No.1 permitting construction of two basement<br /> levels, ground floor and 12 upper floors.<br /> st<br /> 15. In the meantime, on 31 December, 2008, the Respondent<br /> No.1 had permitted the Petitioner to utilize the area of staircase, lift<br /> and lobbies free of FSI against payment of premium of Rs.6.03<br /> crores, as a result of which, additional built up area of 11849.46 sq.<br /> mtrs. had become available to the Petitioner which resulted in<br /> th th th<br /> construction of the 12 and 13 floors. On 16 June, 2010, the<br /> Respondent No. 1 permitted further staircase area of 245 sq. mtrs.<br /> to be treated as free of FSI on payment of Premium. In the above<br /> process, there was substantial and unforeseen delay in<br /> commencement of the construction. The Petitioner could ultimately<br /> Page 7 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> commence construction of the two upper floors only after the<br /> month of July 2010.<br /> 16. In view of the above developments, the Respondent No.1<br /> th<br /> had issued two further Commencement Certificates dated 15<br /> th<br /> October 2009 and 7 July 2010. It is the case of the Petitioner that<br /> while permitting utilization of the additional built-up area, the<br /> Respondent No. 1 had not stipulated any time limit for completing<br /> the construction.<br /> 17. It is also the case of the Petitioner that construction of the<br /> entire building, comprising of two basements, ground floor and<br /> th<br /> thirteen floors was completed on 14 June 2011. Completion of the<br /> construction was, thereafter, certified by the Chief Town and<br /> th<br /> Country Planning Division of Respondent No. 1 on 17 June 2011.<br /> th<br /> 18. On 18 February, 2011, the Petitioner, through its architect,<br /> had applied for Occupation Certificate. By the communication<br /> rd<br /> dated 3 October 2011, the Respondent No.1 had informed the<br /> Petitioner that Occupation Certificate would be issued subject to the<br /> condition that “ The applicant shall provide 2 suits for 50 nights<br /> each per year and 1 meeting/conference room for atleast 20<br /> Page 8 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> persons to be accommodated on 20 occasions with all necessary<br /> technical equipment for presentations, per year free of any charge,<br /> fee or rent in the Hotel to MMRDA. Food, beverages and other<br /> services will be provided at a discount of 20% excluding taxes and<br /> service charges, if any.” Accordingly, the Petitioner was asked to<br /> convey its acceptance of the above condition within 7 days.<br /> th<br /> 19. On 29 September,2011 the Petitioner had once again<br /> requested for issuance of Occupation Certificate for the hotel but<br /> the same was declined. Instead, the Petitioner was asked to give an<br /> undertaking that it will not commence operation of the Hotel until<br /> payment of the additional premium. As such, the Petitioner was<br /> rd<br /> compelled to submit a Notarized undertaking dated 3<br /> October,2011 to such effect. <br /> th<br /> 20. On 11 October 2011, the Respondent No.1 had issued a<br /> conditional Occupation Certificate in respect of the said building.<br /> The Occupation Certificate so issued had also included the<br /> stipulation that the Petitioner shall provide two suits for 50 nights<br /> each per year and one meeting/conference room for atleast 20<br /> persons to be accommodated on 20 occasions, with all necessary<br /> technical support, to the MMRDA, free of charge, fee or rent. It was<br /> Page 9 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> also mentioned that the Petitioner shall not commence operation of<br /> the Hotel until the payment of the additional premium towards<br /> extension of time for completion of construction as per the Lease<br /> Deed and the undertaking dated 03/10/2011 is made.<br /> th<br /> 21. Thereafter, by letter dated 12 October 2011, the Respondent<br /> No.1 had demanded payment of additional premium amounting to<br /> Rs.25,42,74,636/- (Rupees Twenty Five crores Forty Two lakhs<br /> Seventy Four thousand Six hundred and Thirty Six), together with<br /> interest, for the alleged delay in completion of the construction<br /> beyond four years from the date of execution of the Lease Deed i.e.<br /> th<br /> beyond 9 June, 2010. <br /> 22. The Petitioner had submitted representations requesting for<br /> waiver of the demand for payment of additional premium/penalty<br /> but the said request came to be rejected by communication dated<br /> rd<br /> 3 January 2012 issued by the Respondent No.1. As such, in terms<br /> of the undertaking furnished to Respondent No.1, the Petitioner<br /> had paid two installments of Rs.4,39,37,781/-(Rupees Four Crores<br /> Thirty-Nine Lakhs Thirty-Seven Thousand Seven Hundred Eighty-<br /> One only) and Rs.4,54,54,537/- (Rupees Four Crores Fifty Four<br /> Lakhs Fifty Four Thousand Five Hundred and Thirty Seven only)<br /> Page 10 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> respectively, towards the demanded amount of additional<br /> premium/penalty The said amount was, however, paid under<br /> protest. <br /> st<br /> 23. Thereafter, further communications dated 1 September 2014<br /> rd<br /> and 23 April 2015 came to be issued by Respondent No.1 calling<br /> upon the Petitioner to pay the balance outstanding amount, which<br /> th<br /> had culminated in the impugned Demand Notice dated 12<br /> September 2017, by means of which, the Respondent No.1 had<br /> called upon the Petitioner to pay the entire outstanding dues failing<br /> which, the Respondents would recover the amount as arrears of<br /> Land Revenue and also determine the Lease.<br /> 24. It is the further case of the Petitioner that in its 131st Meeting<br /> nd <br /> held on 22 October 2012, the Respondent No.1 had considered<br /> granting extension of time for completion of construction from four<br /> years to six years in view of the extra time consumed in securing<br /> th<br /> various statutory approvals from different authorities. In its 138<br /> th<br /> Meeting held on 26 August 2015, the Respondent No.1 had<br /> resolved to amend Clause 2(d) of the standard form of the Lease<br /> Deed so as to provide six years time period for completion of the<br /> construction but made the said amendment applicable only to Lease<br /> Page 11 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> Deeds executed after 26 August 2015. According to the Petitioner,<br /> restricting the benefit of the said amendment only to Lease Deeds<br /> th<br /> executed after 26 August 2015 was highly arbitrary and<br /> discriminatory. <br /> 25. In the aforesaid circumstances, the Petitioner has instituted<br /> th<br /> the present Writ Petition challenging the Demand Notice dated 12<br /> th<br /> September 2017, as well as the earlier communications dated 12<br /> rd st rd<br /> October 2011, 3 January 2012, 1 September 2014, 23 April<br /> th<br /> 2015 and 25 June 2015, whereby the Respondent No.1 had<br /> demanded payment of additional premium, together with interest,<br /> on account of alleged delay in completion of the construction.<br /> 26. In the reply affidavit filed by the Respondents Nos.1 and 2, it<br /> has been inter- alia contended that the Writ Petition is not<br /> maintainable due to delay and laches on the part of the Petitioner<br /> in approaching this Court that the relief prayed for by the Petitioner<br /> relates to implementation of the terms and conditions of the Lease<br /> th<br /> Deed dated 9 June 2006 and, therefore, the same cannot be<br /> granted in a Writ Petition; that the Writ Petition having been<br /> instituted beyond the period of three years form the date of the<br /> demand, the same is bared by law of limitation; that the Petitioner<br /> Page 12 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> has an alternative, efficacious remedy in the form of a Civil Suit<br /> and, therefore, the Writ Petition is not maintainable on such count<br /> as well; that the Petitioner, having furnished a Notarized<br /> undertaking to pay the amount of additional premium/penalty and<br /> also agreeing not to commence the operation of the hotel till the<br /> amount is paid, is estopped from challenging the demand, more so,<br /> since part of the amount of additional premium/ penalty has<br /> already been deposited by the Petitioner; that a conjoint reading of<br /> Article 2(a) and 2(d) of the Lease Deed makes it clear that the<br /> construction of the building must be completed within four years<br /> from the date of the Lease Deed. Therefore, the demand made for<br /> additional premium/penalty due to delay in completion of<br /> construction is interim of Article 2(d) of the Lease Deed, which is<br /> on agreed conditions of the Lease Deed. As such, the same cannot<br /> be termed as arbitrary and illegal; that the resolution extending the<br /> period for completion of construction from four years to six years<br /> would apply prospectively and, therefore, the Petitioner would not<br /> be entitled to such benefit. It has, further, been contended that<br /> since most of the other parties have already complied with the<br /> demand of additional premium, hence, there can no justifiable<br /> ground for the Petitioner to dispute the claim; that the appointment<br /> Page 13 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> of one man committee is a matter of “internal management” of the<br /> MMRDA and the report submitted by the committee is only of<br /> persuasive value. <br /> 27. In the Rejoinder Affidavit, the Petitioner has reiterated its<br /> stand that the demand for penalty is arbitrary and has denied that<br /> there was any concluded contract to make payment of the penalty.<br /> It has also been contended that in the facts and circumstances of<br /> the case, it was not possible to complete the construction within<br /> four years from the date of execution of the Lease Deed in view of<br /> the additional built-up area allotted to the Petitioner permitting<br /> th th<br /> construction of the 12 and 13 floor and that there was no time<br /> limit for completion of the said construction. As such, the time line<br /> for completion of integrated composite structure of the building by<br /> using the additional built up area would not come within the ambit<br /> of Article 2(d) of the Lease Deed.<br /> 28. This Writ Petition was analogously heard along with three<br /> other similar Writ Petitions being Writ Petition No. 864 of 2018,<br /> Writ Petition No. 242 of 2018 and Writ Petition No. 2377 of 2018,<br /> wherein, identical reliefs were prayed for by the Writ Petitioner(s). <br /> Page 14 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 29. Mr. Vikram Nankani, learned Senior Counsel appearing for<br /> the Petitioner has referred to the documents available on record to<br /> submit that the demand for additional premium raised by<br /> Respondent No.1 on account of alleged delay in completion of<br /> construction of the building known as “Sofitel Hotel” on Plot Nos.<br /> C-57 and C-58 at Bandra-Kurla Complex is wholly arbitrary, illegal<br /> and unsustainable in the eyes of law. According to the learned<br /> Senior Counsel, such demand is also contrary to the terms and<br /> th <br /> conditions of the Lease Deed dated 9 June 2006 and, therefore,<br /> the Respondent No.1 had no authority to levy additional premium<br /> for the alleged delay in completion of the construction.<br /> 30. It is further submitted by Mr. Nankani that the delay, if any, in<br /> completion of construction occurred due to circumstances beyond<br /> the control of the Petitioner which included the extra time<br /> consumed in obtaining statutory approvals such as Environmental<br /> Clearance from the Ministry of Environment and Forests , height<br /> clearance from the Civil Aviation authorities as well as other<br /> permissions required for development of the project. According to<br /> the learned senior counsel, the Petitioner could not have<br /> commenced or continued with the construction without obtaining<br /> Page 15 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> such statutory approvals and therefore, the time consumed in<br /> securing such approvals ought to be excluded while computing the<br /> period stipulated under Article2(d) of the Lease Deed for<br /> completing the construction.<br /> 31. The learned Senior Counsel has also submitted that the<br /> Respondent No.1 had itself permitted the Petitioner to utilize the<br /> additional built-up area in the same building by excluding certain<br /> areas from the FSI, upon payment of additional premium and by<br /> issuing revised commencement certificates. According to him, once<br /> such additional development was permitted and incorporated in the<br /> building, the project had to be executed as a composite<br /> development plan and therefore, the original time limit<br /> contemplated under Article 2(d) of the Lease Deed could not have<br /> been applied in such a rigid manner for the purpose of levying<br /> additional premium.<br /> 32. The learned Senior Counsel has further submitted that the<br /> issues raised in the present Writ Petition are squarely covered by<br /> the decision of this Court in Raghuleela Builders Pvt. Limited and<br /> Anr. vs. Mumbai Metropolitan Region Development Authority &<br /> Page 16 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 1<br /> Ors. wherein, under similar facts and circumstances, this Court has<br /> held that the demand of additional premium/ penalty for alleged<br /> delay in completion of construction was arbitrary and unsustainable<br /> in law. He further submits that the aforesaid judgment has attained<br /> finality in the eyes of law inasmuch as the Special Leave Petition<br /> preferred by the Respondent No.1 against the said judgement also<br /> came to be dismissed by the Hon’ble Supreme Court by order dated<br /> th<br /> 27 July 2020 passed in Special Leave to Appeal (C) No.6411 of<br /> 2020. According to the learned Senior Counsel, the principle laid<br /> down in the said decision would apply to the facts of the present<br /> case and therefore, the same would lay down a binding precedent<br /> for this court to follow. As such,submits Mr. Nankani, the<br /> impugned demand of penalty raised by Respondent No.1 deserves<br /> to be set aside and a direction is required to be issued by this Court<br /> to refund the amount of penalty already deposited by the Petitioner<br /> under protest.<br /> 33. Responding to the above submissions, Mr. Pravin Samdani,<br /> learned Senior Counsel appearing for Respondents has questioned<br /> the maintainability of the Writ Petition on the grounds that the<br /> <b>1</b><br /> (2020) (1) ABR 397: 2019 SCC OnLine Bom 4529.<br /> Page 17 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> same involves disputed issues of facts and that, it is hit by delay and<br /> laches in as much as, the relief claimed there-in is also barred by<br /> the law of Limitation. Contending that the demand raised by<br /> Respondent No.1 is in terms of the provisions of the Mumbai<br /> Metropolitan Region Development Authority Act, 1974 and the<br /> Mumbai Metropolitan Region Development Authority (Disposal of<br /> Land) Regulations, 1977 (hereinafter referred to as “Land Disposal<br /> Regulations”) Mr. Samdani has argued that the additional premium<br /> has been levied in accordance with the terms of the Lease Deed<br /> executed between the parties, which is in the statutory form<br /> prescribed under the said Regulations. As such, the same cannot be<br /> waived.<br /> 34. The learned Senior Counsel for Respondents further submits<br /> that, by filing the present Writ Petition, the Petitioner is in effect<br /> seeking to challenge the contractual stipulations contained in the<br /> Lease Deed without challenging the statutory provisions governing<br /> the same, which is impermissible in law. It is submitted that once<br /> the Petitioner has entered into the Lease Deed with full knowledge<br /> and understanding of the terms and conditions contained therein, it<br /> would be bound by the conditions contained in the Lease Deed.<br /> Page 18 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Therefore, the Petitioner cannot now resile from its contractual<br /> obligations. <br /> 35. The learned Senior Counsel further submits that, under the<br /> terms of the Lease Deed, extension of time for completion of<br /> construction can be granted, only upon payment of additional<br /> premium at the prescribed rates and therefore the demand raised<br /> by Respondent No.1 cannot be said to be arbitrary or illegal. To sum<br /> up his arguments, the learned senior counsel has submitted that it<br /> is not a case of violation of the fundamental rights of the Petitioner<br /> and therefore, it is not entitled to any relief in exercise of<br /> discretionary jurisdiction of this Court under Article 226 of the<br /> Constitution of India. As such, the Writ Petition deserves to be<br /> dismissed.<br /> 36. In support of his above arguments, Mr Samdani has relied<br /> upon he following decisions:-<br /> (a) Bank of Baroda, Mumbai & Anr vs. Mumbai<br /> 2<br /> Metropolitan Regional Development Authority & Ors.<br /> (b) Assistant Excise Commissioner & Ors. vs. Issac Peter &<br /> 3<br /> Ors.<br /> <b>2</b><br /> 2010 (3) Mh. L.J.<br /> <b>3</b><br /> (1994) 4 SCC 104.<br /> Page 19 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 4<br /> (c) State of UP & Ors. vs. Chaudhari Ran Beer Singh,<br /> (d) Goetze (India) Ltd. vs. Employees State Insurance<br /> 5<br /> Corporation<br /> (e) Transmission Corporation of Andhra Pradesh Ltd. &<br /> 6<br /> Anr. Vs. Sai Renewable Power Pvt. Ltd. & Ors.<br /> (f) Banda Development Authority, Banda vs. Motilal<br /> 7<br /> Agarwal & Ors.<br /> (g) Punjab Financial Corporation vs. Surya Auto<br /> 8<br /> Industires<br /> 9<br /> (h) Joshi Technologies International IBC vs. U.O.I. & Ors.<br /> (i) The Godhra Electricity Co. Ltd. & Anr. vs. The State of<br /> 10<br /> Gujrat & Anr<br /> 11<br /> (j) Dhanraj vs. Vikram Singh & Ors.<br /> 12<br /> (k) Dalip Singh vs. State of U.P & Ors.<br /> Plea regarding Maintainability of the Writ Petition :-<br /> 37. Insofar as the plea of the maintainability of the Writ Petition<br /> is concerned, at the very outset, it deserves to be mentioned herein<br /> that although the maintainability of the Writ Petition has been<br /> questioned inter-alia on the ground that several disputed questions<br /> <b>4</b><br /> (2008) 5 SCC 550.<br /> <b>5</b><br /> (2008) 8 SCC 705.<br /> <b>6</b><br /> (2011) 11 SCC 34.<br /> <b>7</b><br /> (2011) 5 SCC 394.<br /> <b>8</b><br /> (2010) 1 SCC 297.<br /> <b>9</b><br /> (2015) 7 SCC 728.<br /> <b>10</b><br /> (1975) 1 SCC 199.<br /> <b>11</b><br /> 2023 SCC OnLine SC 724.<br /> <b>12</b><br /> (2010) 2 SCC 114.<br /> Page 20 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> of facts are involved there-in, yet, after examining the record, we<br /> find that the material assertions made in the Writ Petition are all<br /> based on documents annexed thereto, which are admitted<br /> documents. Moreover, in view of the plea raised by the Petitioner<br /> that the action of the Respondent No. 1 in levying additional<br /> premium/penalty for the delay in completion of construction is<br /> arbitrary and illegal and hence, violative of the fundamental rights<br /> of the Petitioner guaranteed under Article 14 of the Constitution of<br /> India, we are of the view that the issues raised in the Writ Petition<br /> have an element of public law character.<br /> 38. In case of Joshi Technologies International IBC vs. U.O.I. &<br /> Ors. (Supra), relied upon by Mr Samdani, the Hon’ble Supreme<br /> Court has observed that there is no absolute bar to the<br /> maintainability of a Writ Petition, even in contractual matters or<br /> where there are disputed questions of fact or even when monitory<br /> claim is raised, provided, the Court is called upon to examine the<br /> issue which has a public law character attached to it. Having regard<br /> to the core controversy involved in this proceeding and considering<br /> the fact that the issues involved in this Writ Petition would call for<br /> determination by this Court based on interpretation of the relevant<br /> Page 21 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Articles of the Lease Agreement as well as the documents<br /> exchanged by and between the parties so as to ascertain fairness in<br /> the action of the Respondent No 1, we are unable to agree with the<br /> stand of the Respondents that the Writ Petition ought to be<br /> dismissed on the ground that it raises disputed questions of facts. <br /> 39. Likewise, from a reading of Section 44 of the MMRDA, Act<br /> 1974, we find that the provision for Appeal provided thereunder, is<br /> available for resolving disputes pertaining to recovery of money due<br /> to the authority as arrears of land revenue. Since the challenge<br /> made to the impugned demand notice is on the ground that the<br /> same is contrary to the terms of the Lease Deed, hence, we are of<br /> the opinion that the said controversy cannot be effectively<br /> adjudicated in an Appeal filed under Section 44. Therefore, we<br /> reject the contention of the Respondents that the Petitioner has an<br /> effective and efficacious alternative remedy.<br /> 40. We also find that all material facts necessary for dealing with<br /> the controversy have been stated in the Writ Petition. Therefore, the<br /> Writ Petition cannot also be dismissed on account of suppression of<br /> material facts.<br /> Page 22 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 41. In so far as the grounds of delay and laches as well as the<br /> plea of the claim being barred by the Law of Limitations is<br /> concerned, save and except making a bald assertion on such count<br /> the Respondents have failed to mention as to on which date the<br /> cause of action for the petitioner to institute the proceeding had<br /> ceased and on what count. <br /> 42. In Banda Development Authority, Banda vs. Motilal Agarwal<br /> & Ors. (Supra), relied upon by Mr Samdani, the Hon’ble Supreme<br /> Court has observed that no limitation has been prescribed for filing<br /> a Writ Petition under Article 226 of the Constitution of India.<br /> However, the High Court will treat the delay in filing the Writ<br /> Petition as unreasonable, if the Writ Petition is filed beyond the<br /> period of limitation prescribed for filing a Civil Suit for similar<br /> cause. From the above, it would be apparent that although<br /> unexplained delay in instituting a Writ Petition could be a valid<br /> ground to decline relief, yet, the law of Limitation would not have<br /> strict application in a Writ Petition. <br /> 43. There is no dispute in this case about the fact that the<br /> Respondent No. 1 is an instrumentality of the State and, therefore,<br /> would be an “other authority” within the meaning of Article 12 of<br /> Page 23 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> the Constitution of India. Law is well settled that arbitrariness in<br /> the decision making process of the State or its instrumentality is a<br /> facet of Article 14 of the Constitution of India. In E.P..Royappa v<br /> 13<br /> State of Tamil Nadu , it was pointed out that Article 14 would<br /> strike at arbitrariness in State action and ensure fairness and<br /> equality of treatment. <br /> 44. The present is not a proceeding simpliciter for enforcing a<br /> money claim but raises significant questions pertaining to the<br /> validity and fairness in the impugned action of the Respondent No<br /> 1, which are required to be adjudicated on the touch stone of<br /> Article 14 of the Constitution. As such, we are of the considered<br /> opinion that such pleas cannot be brushed aside merely on the<br /> ground of delay, more so, since such delay has evidently not given<br /> rise to any parallel right of a third party. <br /> 45. In view of the fore going discussions, we are of the view that<br /> the Writ Petition is maintainable in law as well as in the facts and<br /> circumstances of the case. <br /> <b>13</b><br /> (1974) 4 SCC 3.<br /> Page 24 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 46. It would be further pertinent to note herein that in an earlier<br /> th<br /> decision rendered by a co-ordinate Bench of this Court dated 20<br /> November 2019 in Raghuleela Builders Pvt. Limited and Anr. vs.<br /> The Mumbai Metropolitan Regional Development Authority & Ors.<br /> (Supra) wherein, identical issues were involved, this Court had<br /> entertained the Writ Petition. In that case also the Petitioners had<br /> th<br /> challenged a similar Demand Notice dated 12 September, 2017<br /> issued by the Respondent No.1 by invoking similar provisions of the<br /> Lease Deed demanding payment of a sum of Rs. 432 Crores as<br /> penalty for the delay in completion of construction of the building.<br /> That was also a case wherein, although the initial built up area was<br /> 30550 sq. meters, which was to be consumed by constructing 9<br /> (nine) floors in the building, yet, subsequently, due to the increase<br /> in the FSI, the Respondent No.1 had allotted additional built up<br /> area of 67000 sq. meters to the Petitioner resulting in construction<br /> of 11 additional floors in the same building. Due to the addition of<br /> the built up area, the construction of the building could not be<br /> completed within four years, as stipulated in Article 2(d) of the<br /> th<br /> original Lease Deed, as a result of which, Demand Notice dated 12<br /> September, 2017 was served for recovery of penalty/additional<br /> premium along with interest calculated thereon. <br /> Page 25 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:19 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> 47. By the Judgment and Order dated 20 November 2019, in<br /> Raghuleela Builders Pvt. Ltd. & Anr. (Supra), a Division Bench of<br /> th<br /> this court had set aside the impugned Demand Notice dated 12<br /> September 2017 by holding that such a demand was not<br /> maintainable in the eyes of law. That apart, it was also observed<br /> that in view of the change in policy of the MMRDA increasing the<br /> time limit for completion of the building “Fit for occupation”, from<br /> four years to six years, the demand for penalty/additional premium<br /> for delay in completion of construction within four years was ex-<br /> facie unreasonable, unjustified and discriminatory. <br /> 48. The Special Leave Petition (C) No. 6411 of 2020 preferred by<br /> th<br /> the Respondent No.1 assailing the Judgment and Order dated 20<br /> November 2019 was dismissed by the Hon’ble Supreme Court by<br /> th<br /> the order dated 27 July 2020 by taking note of the findings<br /> recorded in paragraphs No. 38 and 40 of the Judgment and Order<br /> th<br /> dated 20 November 2019. However, it was clarified that since the<br /> judgment of the Division Bench of the Bombay High Court was<br /> rendered in the facts of that case, hence, it cannot influence any<br /> other matter in this behalf. With the above observation the Special<br /> Leave Petition was dismissed. <br /> Page 26 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> 49. In the order dated 27 July 2020 the Hon’ble Supreme Court,<br /> while dismissing the Special Leave to Appeal (C) No(s) 6411/2020,<br /> had observed as follows:-<br /> “We are not inclined to exercise our jurisdiction under Article 136<br /> of the Constitution of India in the given facts of the case and more<br /> so as reflected from paragraphs 38 and 40 of the impugned<br /> judgment.<br /> Mr. K. K. Venugopal, learned Attorney General for India<br /> expresses some apprehension on account of there being other<br /> matters pending.<br /> We clarify that the present matter is in the given facts of<br /> the case as stated aforesaid and thus, cannot be said to influence<br /> any other matter in this behalf. <br /> The special leave petition is dismissed in terms aforesaid.<br /> Pending applications shall also stand disposed of.”<br /> 50. It appears that the Respondent No. 1 had filed a Review<br /> th<br /> Petition seeking review of the order dated 27 July 2020, which<br /> was also dismissed by the Hon’ble Supreme Court vide order dated<br /> th<br /> 29 September 2020 passed in Review Petition (Civil) No. 1764 of<br /> 2020 arising out of SLP (C) No. 6411 of 2020.<br /> th<br /> 51. In the order dated 27 July 2020, the Hon’ble Supreme<br /> Court had no doubt observed that the decision in Raghuleela<br /> Builders Pvt. Ltd. & Anr. (Supra) was in the facts of that case.<br /> However, we are of the view that we can take note of the legal<br /> principles, if any, emanating from the said decision. In Raghuleela<br /> Page 27 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Builders Pvt. Ltd. & Anr this court has entertained a similar Writ<br /> Petition seeking identical reliefs. <br /> 52. The the question of maintainability of a Writ Petition is a<br /> mixed question of law and facts. Therefore, such question would<br /> obviously have to be considered having due regard to the peculiar<br /> facts and circumstances of each case. Having regard to the facts and<br /> circumstances of this case and considering the fact that a similar<br /> Writ Petition, raising similar issues in Raghuleela Builders Pvt. Ltd.<br /> & Anr. (Supra) had earlier been entertained by this Court, hence,<br /> for the sake of maintaining uniformity in judicial decision, we are<br /> not inclined to non-suit the Petitioner merely on the plea of<br /> maintainability as raised by the Respondents. <br /> On Merit :-<br /> 53. At the very out set it must be noted here-in that as per Article<br /> 2(d) of the Lease Deed, the lessee is required to complete the<br /> construction within four years from the date of execution of the<br /> Lease deed. However, Article 2 (c) of the Lease Deed makes it clear<br /> that no work shall commence or be carried out contrary to the<br /> Development Control Regulations and the Building Regulations<br /> Page 28 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> applicable to the plot of land and until the plans, elevations,<br /> sections, specifications and details shall have been approved.<br /> Therefore, in view of Article 2(c), the construction of the building<br /> cannot commence until the receipt of all statutory approvals<br /> including the approval of building plan etc. Article 2(a) of the Lease<br /> Deed mentions that the lessee shall within three months submit<br /> plans etc for approval. However, there is no condition in the Lease<br /> Deed laying down and time line for granting of such approval by<br /> the authority.<br /> 54. In a construction of this nature, permission of multiple<br /> statutory authorities including the Municipal Corporation, Fire<br /> department, Environment clearance, height clearance etc. will be<br /> necessary, without which the Commencement Certificate cannot be<br /> issued. Unless the Commencement Certificate is issued by the<br /> Authority, the construction work also cannot commence. These<br /> statutory authorities are not bound by the terms and conditions of<br /> the Lease Agreement. Notwithstanding the same, the Lease<br /> Agreement is completely silent as to who will be responsible in case<br /> of delay in granting approval by these statutory authorities coming<br /> Page 29 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> in the way of early commencement and completion of the<br /> construction. <br /> 55. Not only that, the Lease Deed is also silent as to what would<br /> be the effect on the time line of four years for completion of the<br /> construction as laid down in Article (d), in case, there is delay in<br /> granting of statutory approvals. If there is delay in granting<br /> permissions/ approval by the statutory authorities for any reason<br /> whatsoever, leading to delay in commencement of construction,<br /> then in that event, the Lessee will be left with no option to<br /> complete the construction within the stipulated time. Yet, as per<br /> Article 2(d), as interpreted by the Respondent No 1, the lessee<br /> would still be liable to pay penalty for the delay in completing the<br /> construction beyond the period of four years from the date of<br /> execution of the Lease Deed. Viewed from that perspective, Article<br /> 2(d) of the lease deed appears to be ex-facie unfair, unreasonable<br /> and hence, unconscionable. However, since the Articles of the Lease<br /> Deed are not under challenge, hence, the said aspect of the matter<br /> need not detain this Court. <br /> 56. After hearing the arguments of both the sides and on<br /> examining the materials brought on record, we are of the<br /> Page 30 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> considered opinion that the core controversy involved in this<br /> proceeding would be pertaining to the issue as to whether or not,<br /> the insistence/demand for additional premium/penalty made by<br /> the Respondent No. 1 on the ground of delay in completing the<br /> construction of the building beyond the period of four years from<br /> the date of execution of the Lease Deed was in accordance with law<br /> ? To answer the said question, it would be necessary for this Court<br /> th<br /> to refer to Articles 2(d) and 2(e) of the Lease Deed dated 9 June<br /> 2006, which are reproduced hereinbelow for ready reference:-<br /> “2. The Lessee hereby agrees to observe and perform the<br /> following conditions that is to say:<br /> (d) Time limits for commencement and completion of<br /> construction work: That the Lessee shall within three months<br /> from the receipt of approval of his plans and specifications of<br /> building or buildings intended to be erected on the land,<br /> commence and within a period of four years from the date of<br /> this lease at his own expense and in a substantial and workman-<br /> like manner and with the sound materials and in compliance<br /> with the said Development Control Regulations and Building<br /> Regulations and all Municipal Rules, bye-laws and Regulations<br /> applicable hereto and in strict accordance with the approved<br /> plans, elevations, sections, specifications and details, to the<br /> satisfactions of the Metropolitan Commissioner and confirming<br /> to the building lines marked on the plan hereto annexed, and<br /> the Development Control Regulations and Building Regulations,<br /> build and completely finish, fit for occupation a building to be<br /> used as building with all requisite drains and other proper<br /> convenience thereto.<br /> (e) Extension of time stipulated for construction of building<br /> or development of land: <br /> Page 31 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> (i) If the Lessee shall not perform and observe the<br /> limitations of the time mentioned in clause 2(d) above<br /> for construction of the intended building or otherwise<br /> development of land leased to him for reasons beyond<br /> his control, the Metropolitan Commissioner may permit<br /> extension of such time on payment of additional<br /> premium at the following rates:<br /> Up to 1 year ______ 25 percent of the premium<br /> Between 1 and 2 years ______ 35 percent of the premium<br /> Between 2 and 3 years ______ 40 percent of the premium<br /> (ii) If the Metropolitan Commissioner shall refuse to permit<br /> such extension of time or shall find the Lessee of having<br /> committed breach of any condition or covenant during<br /> limitation of time mentioned in clause 2(d)<br /> hereinbefore, the Metropolitan Commissioner may<br /> forfeit and determine the Lease; provided that in the<br /> event of such determination of lease 25 percent of the<br /> premium paid by the Lessee to the Lessor shall stand<br /> forfeited and the remaining 75 percent of such premium<br /> shall be refunded to him; provided further that the<br /> power to so determine the Lease shall not be exercised<br /> unless and until the Metropolitan Commissioner shall<br /> have given to the Lessee or left on some part of the<br /> demised premises a notice in writing of his intention to<br /> do so and of specific breach of the covenant or condition<br /> in respect of which forfeiture is intended and default<br /> shall have been made by the Lessee in remedying such<br /> breach within three months from the service of a notice<br /> on him on the notice being left on the demised<br /> premises.”<br /> 57. As has been noted hereinabove, after the execution of the<br /> th<br /> Lease Deed on 9 June,2006, physical possession of the plot of land<br /> th<br /> was handed over by the Respondent No. 1 to SNDL on 13 June<br /> st<br /> 2006. On 1 August, 2006, SNDL had assigned its rights over the<br /> th<br /> plot in favour of the Petitioner. On 25 August,2006, the Petitioner<br /> had applied for height clearance from the Ministry of Civil<br /> Aviation , requesting for increase in the height of the building from<br /> Page 32 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 56.27 mtrs. to 90 mtrs. so as to consume the full FSI. In the<br /> th<br /> meantime notification dated 14 September,2006 came to be issued<br /> by the Ministry of Environment and Forest laying down that<br /> Environment Impact Assessment (EIA) would be required for such<br /> rd<br /> projects. On 3 October,2010, the Petitioner had applied for<br /> permission to start excavation but the same was declined on the<br /> ground that Environment Clearance will be necessary. Accordingly,<br /> rd<br /> the Petitioner had applied for EIA which was received on 3<br /> February 2007. Thereafter, the Petitioner had applied for<br /> permission to start excavation and shoring work which was granted<br /> th th<br /> by the Respondent No. 1 on 8 March 2007. Therefore, until 8<br /> March, 2007, there was no scope for the Petitioner to commence<br /> even the excavation work. <br /> th<br /> 58. It would be significant to note herein that on 20 March<br /> 2007, additional FSI was granted to the Petitioner on payment of<br /> sum of Rs. 1,99,56,035/-. Thereafter, Commencement Certificate<br /> th<br /> for the work up to the plinth level was issued on 29 October 2007.<br /> th<br /> While the aforesaid process was underway, on 18 November 2008,<br /> the Respondent No. 1 had offered additional built-up area to the<br /> Page 33 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Petitioner. However, no time limit was laid down for completing the<br /> construction with the additional FSI.<br /> st<br /> 59. On 31 December 2008, the Petitioner paid a sum of Rs.<br /> 6,22,34,818/- for 1,849.46 sq. mtrs of additional BUA (lobby/stair<br /> th<br /> case free of FSI) and on 18 March 2009, Commencement<br /> Certificate (CC) for two level basement+ground+12 upper floors<br /> was received.<br /> 60. From the above facts, it would be evident that although the<br /> th<br /> Lease Deed was executed on 9 June 2006 containing the<br /> stipulation in the form of Article 2(d) making it mandatory for the<br /> Lessee to complete the construction of the building within four<br /> th<br /> years from execution of the Lease Deed, i.e., 9 June 2006, yet, the<br /> th<br /> CC for the entire building was issued only on 18 March 2009, i.e.,<br /> nearly after two years and nine months since the date of execution<br /> of the Lease Deed thereby, leaving a period of barely one year and<br /> three months for the Petitioner to complete the construction. In a<br /> construction of a high rise building of this nature containing 13<br /> floors, it would be wholly inconceivable for any Lessee to<br /> commence and complete the construction of the building within a<br /> period of one year and three months. <br /> Page 34 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 61. In the above context, it would be further pertinent to note<br /> st<br /> herein that on 1 July 2010, the Petitioner had paid a sum of<br /> Rs.5,96,61,133/- as premium for the additional lobby and passage<br /> area free from FSI. Thereafter, the final CC for two level<br /> basement+ground+13 floors, as per the amended plan, was<br /> th th<br /> received by the Petitioner on 15 October 2009 and 7 July 2010.<br /> 62. It is the undisputed position of fact that the Petitioner had<br /> th<br /> completed the construction of the building upto the 13 floors on<br /> th<br /> 14 June 2011, which fact has also been duly acknowledged in the<br /> th<br /> Completion Certificate dated 17 June 2011 issued by the Chief<br /> Town and Country Planning Division of Respondent No. 1.<br /> Notwithstanding the same, the formal request made by the<br /> th<br /> Petitioner by the letter dated 29 September 2011 for issuance of<br /> Occupation Certificate was not acted upon apparently on the<br /> ground that the Petitioner had failed to pay the proposed penalty<br /> due to the delay in completion of construction of the building. <br /> 63. At this stage, it would be significant to note herein that<br /> although the Respondents had demanded additional<br /> premium/penalty due to the alleged delay in completing the<br /> construction of the building within four years from the date of<br /> Page 35 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> execution of the Lease Deed i.e. within 8 June, 2010, yet, until<br /> th<br /> 12 October 2011,no formal demand for payment of the additional<br /> premium/penalty was raised by the Respondent No. 1. <br /> 64. In the above context, it would be further pertinent to<br /> mention herein that apparently on being demand by the<br /> rd<br /> Respondent No. 1, on 3 October 2011, the Petitioner had<br /> submitted a Notarized undertaking to the Respondent No. 1 not to<br /> commence operation of the hotel until the payment of additional<br /> premium is made. Upon receipt of the said undertaking, the Chief<br /> of the Town & Country Planning Division of the Respondent No. 1,<br /> th<br /> had addressed a letter on 11 October 2011 informing the<br /> Petitioner about the issuance of the Occupation Certificate for two<br /> level basement+ground+13 upper floors for the Five Star category<br /> hotel on land bearing No. C-57 and C-58 (combined) in ‘G’ Block in<br /> BKC. The Occupation Certificate had, however, clearly mentioned in<br /> Clause-11 that the Applicant, i.e., the Petitioner shall not commence<br /> operation of the hotel until the payment of additional premium<br /> towards extension of time for completion of construction, as per the<br /> provisions of the lease Deed, is made to the MMRDA, as assured by<br /> rd<br /> the communication dated 3 October, 2011.<br /> Page 36 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 65. As has been noted herein above, the formal request for<br /> payment of additional premium/penalty was made by the<br /> Respondent No. 1 for the first time, by addressing the letter dated<br /> th<br /> 12 October 2011 to the director of Shree Naman Hotels Pvt. Ltd.<br /> th<br /> The letter dated 12 October 2011 was followed up by the<br /> st rd<br /> communications dated 1 September 2014 and 23 April 2015<br /> thus, renewing the demand for payment of outstanding dues along<br /> with interest, on the additional premium/penalty. Such demand<br /> th<br /> had culminated in the Notice dated 12 September 2017,the<br /> contents whereof are reproduced herein below for ready<br /> reference:-<br /> EXHIBIT = ‘P’<br /> MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY<br /> _________________________________________________________ <br /> th<br /> No.LEC/BKC (G)/SNDL(C-57 & 58)/179/2017 Date: 12 September 2017<br /> NOTICE<br /> WHEREAS the Mumbai Metropolitan Region Development<br /> Authority issued a Show Cause Notice dated 22/08/2014 for non-<br /> payment of requisite dues and non-performance of the Lease Deed<br /> conditions as stated therein.<br /> WHEREAS you have submitted your say along with<br /> explanation vide your letter dated 19/09/2014 & 22/09/2014. <br /> WHEREAS your representation/explanation is examined<br /> thoroughly and no merit was found in the submission/ explanation<br /> given by you.<br /> AND WHEREAS the explanation submitted vide your letter<br /> 19/09/2014 & 22/09/2014 dated with reference to the Show<br /> Cause Notice is unsatisfactory and hence was summarily rejected<br /> vide our letter dated 23/12/2014.<br /> Page 37 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> WHEREAS you were instructed to pay the outstanding dues<br /> as stated in the Notice under reference within a period of 30 days.<br /> However, till date you did not pay the requisite dues to MMRDA<br /> and thus failed to comply with your obligations.<br /> AND WHEREAS the amount due to the Authority along<br /> with the interest due thereon is as shown in the statement annexed<br /> hereto as Annexure. An amount due to Authority is un-paid till<br /> date & thus you have therefore committed breach of the terms and<br /> conditions of the said Deed of Lease and therefore, the Authority<br /> has power to recover the said due amount as stated hereinbefore<br /> as arrears of land revenue and also resume the said land as per the<br /> Article 5 and 6 of the said Deed of Lease.<br /> NOW THEREFORE, in exercise of the powers conferred by<br /> Articles 5 and 6 of the said Deed of Lease, I, the Dy. Metropolitan<br /> Commissioner for and on behalf of the Metropolitan Commissioner<br /> of the Authority hereby call upon you to remedy or cause to be<br /> remedied within 30 days from the date of this notice. Please take<br /> further notice that in the event of the default to comply with this<br /> requisition, the Authority will have the right to determine the<br /> Lease and enter upon the premises and proceed further to recover<br /> the due amount stated hereinbefore as arrears of land revenue.”<br /> Sd/-<br /> (A.R. Wankhade) <br /> Dy. Metropolitan Commissioner,<br /> M.M.R.D.A.<br /> To,<br /> The Director,<br /> Shree Naman Hotels Pvt. Ltdl, <br /> Naman Centre, Plot No. C-31-32,<br /> G-Block, Bandra-Kurla Complex, <br /> Bandra (East), Mumbai – 400 051.<br /> 66. From the facts alluded to hereinabove, it is evident that after<br /> the allotment of the additional built-up area, two additional floors<br /> th th<br /> in the form of 12 and 13 floors, besides other common area<br /> spaces, were added to the built-up area originally sanctioned by the<br /> Respondent No. 1. Such addition in the built-up area did not come<br /> Page 38 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> with any time limit for completing the construction nor was it a<br /> th<br /> part of the original Lease Deed dated 9 June,2006. <br /> 67. It is axiomatic that with the allotment of additional built up<br /> area, there would be fundamental changes in the drawings and<br /> building plan, which would require fresh approval followed by<br /> issuance of Commencement Certificate. Therefore, even as per the<br /> terms of the Lease Agreement, it would not permissible for the<br /> lessee to commence construction of the building without obtaining<br /> such approvals. Under such circumstances, it is apparent that due<br /> to allotment of additional built up area, it would no longer be<br /> feasible for the Lessee to stick to the original time line for<br /> completion of the construction as contemplated by Article 2(d) of<br /> th<br /> the Lease Deed dated 9 June 2006. Notwithstanding the same, the<br /> Respondent No.1 had applied pressure on the Petitioner to extract<br /> additional monetary benefits from the Petitioner by relying upon<br /> Article 2(d) on the ground of delay in completing the construction.<br /> 68. Be that as it may, it is the case of the Petitioner is that there<br /> was no delay in completing the construction beyond the period of<br /> four years. However, even if it is assumed that there was any delay,<br /> th<br /> the construction was evidently and admittedly completed on 14<br /> Page 39 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> June, 2011 i.e. within the period of six years from the date of<br /> execution of the Lease Deed. Therefore, since the MMRDA has<br /> already taken a policy decision to extend the time period for<br /> completing the construction from four years to six years, as such,<br /> in any view of the matter, no penalty would be payable by the<br /> Petitioner on account of delay in completing the construction.<br /> 69. It would be significant to note here-in at the cost of repetition<br /> th<br /> that as per Article 2(a) of the Lease Deed dated 9 June 2006, no<br /> work can begin until plans are approved and the requirement of<br /> Development Control Regulations and Building Regulations are<br /> met. As per the Development Regulations, Commencement<br /> Certificate can be issued only after all the statutory approvals<br /> including approval of building plan is obtained. Unless<br /> Commencement Certificate is issued, it would not be permissible to<br /> commence construction. <br /> 70. In the present case, the first Commencement Certificate upto<br /> th<br /> to the plinth level was issued only on 29 October, 2007 i.e. after a<br /> delay of more than 1 year four month from the date of execution of<br /> the Lease Deed. Thereafter, another Commencement Certificate was<br /> th<br /> issued on 18 March,2009 i.e. after a delay of more than 2 years<br /> Page 40 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> and 9 months. There is nothing on record to show that the<br /> Petitioner was, in any way, responsible for such delay. <br /> 71. In a construction of this nature involving issuance of multiple<br /> Commencement Certificates preceded by changes in design lay out<br /> pursuant to allotment of additional built up area allotted by the<br /> Respondent No 1 itself by realizing adequate premium, it would be<br /> highly unfair for the MMRDA to insist on a time line for completion<br /> of the construction based on a clause in the original Lease Deed<br /> which did not contemplate such subsequent developments.<br /> Therefore, demanding payment of penalty for delay in completion<br /> of the construction, without making adequate adjustment in the<br /> time frame, in our opinion, would be wholly arbitrary, irrational,<br /> unreasonable and hence, liable to be declared so by this court. <br /> 72. As has been noted above, there is nothing on record to<br /> suggest that there was any delay in completing the construction<br /> due to the negligence on the part of the Lessee i.e. the Petitioner.<br /> On the contrary, it appears that the construction was delayed due to<br /> the delay in issuance of statutory approvals/ permissions including<br /> environmental clearance. As per the terms and conditions of the<br /> Lease Deed, the construction cannot commence without the<br /> Page 41 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> approval of the building plan and issuance of the Commencement<br /> Certificate, which are beyond the control of the lessee. As such, by a<br /> reasonable and harmonious construction of the Articles of the Lease<br /> Deed, we are of the opinion that, save and except in a case where<br /> there is willful negligence on the part of the lessee, the time line of<br /> four years for completing the construction ought to be computed<br /> from the date of issuance of the Commencement Certificate and not<br /> from any prior date. Since the Commencement Certificate in this<br /> th<br /> case was issued on 29 October, 2007, hence, we are of the opinion<br /> that even under Article 2(d) of the Lease Deed, the period of four<br /> years would, at best, run from the date of issuance of the first<br /> Commencement Certificate, in which case, the Petitioner would be<br /> th<br /> entitled to time till 28 October,2011 for completing the<br /> construction. <br /> 73. In present case, the construction was admittedly completed<br /> th<br /> by the Petitioner on 14 June, 2011. Therefore, having regard to<br /> the facts and circumstances of the case, we are of the view that the<br /> condition precedent for invoking the Article 2(d) of the Lease Deed<br /> was not met in this case. As such, viewed from that angle also, in<br /> our opinion, there was no legal justification for the Respondent<br /> Page 42 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> No.1 to insist on additional premium/penalty from the Petitioner<br /> even under Article 2(d) on account of alleged delay in completing<br /> the construction beyond the period of four years.<br /> 74. In so far as the undertaking given by the Petitioner to pay the<br /> additional premium/ penalty is concerned, it must be noted herein<br /> that the Writ Petitioner had not only objected to the demand for<br /> payment of additional premium/penalty for the alleged delay in<br /> completing the construction but had also deposited the amount<br /> under protest, thereby categorically conveying that the deposit was<br /> not made voluntarily or in discharge of its contractual obligation.<br /> Such protest was not only raised contemporaneously but the same<br /> was also in writing and unambiguous in nature, thus, putting the<br /> Respondent No. 1 on clear notice that the Petitioner has not<br /> accepted the decision in principle.<br /> 75. It also appears from the materials on record that apparently<br /> due to the pressure mounted by the Respondent No. 1 demanding<br /> payment of additional premium/penalty, the Petitioner was<br /> compelled to deposit the penalty as otherwise the Petitioner would<br /> not only be prevented from obtaining the Occupation Certificate<br /> thus, causing serious economical prejudice to its interest but the<br /> Page 43 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> same would also expose the Petitioner to the risk of termination of<br /> the Lease. Since the Petitioner had evidently made the deposit of<br /> penalty under duress and under compelling circumstances, hence,<br /> the principles of waiver, estoppel and acquiescence would not<br /> operate against it in this case. From the protest raised by the<br /> Petitioner, it was apparent that the Petitioner had reserved its right<br /> to agitate the matter at an appropriate time, thus, keeping the<br /> cause alive. Therefore, we hold that Petitioner would be entitled to<br /> claim refund / seek waiver of additional premium/ penalty on<br /> account of alleged delay, if any, in completing the construction. <br /> 76. Section 72 of the Indian Contract Act provides that a person<br /> who receives payment made by the payee under coercion must<br /> repay or return the same. <br /> 77. In Fatima Khatoon Chowdrain vs. Mahmoed Jan Chowdhury<br /> (1868) 12 Moo Ind App 65, the Privy Council has held that<br /> payment made not voluntarily but under species of compulsion<br /> would be liable to be returned.<br /> Page 44 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 78. In Valpy vs Manley (1845) 1 CP 594, the Court of England &<br /> Wales has held that money paid under the constraint of threats to<br /> interfere with the legal right is sufficient to make it recoverable.<br /> 79. In Ram Kishen Singh vs. Dooli Chand (1881) 8 IA 93 before<br /> the Privy Council, it was held that if a person pays money to save<br /> his property which has been wrongly attached in execution, he is<br /> entitled to recover it.<br /> 80. Relying upon the case of Ram Kishen Singh (Supra), the<br /> Privy Council in the case of Kanhaya Lal vs The National Bank of<br /> 14<br /> India Limited has held that if a payment is made under protest<br /> and involuntarily, under coercion, the party making such payment<br /> would be entitled to claim refund of the same.<br /> 81. In the present case, the Petitioner was forced to give an<br /> undertaking to pay the additional premium under the<br /> circumstances, as noted above, created by the Respondent No. 1.<br /> The arbitrary and high handed action of the Respondent No 1 is<br /> further apparent from the fact that although there was no such<br /> th<br /> condition in the Lease Deed dated 9 June,2006, yet, as has been<br /> <b>14</b><br /> 1913 SCC Online PC 4.<br /> Page 45 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> mentioned above, the Respondents had demanded 2 suits for 50<br /> nights and conference facility for 20 persons on 20 occasions free of<br /> charge, fee or rent as a condition for issuing the Occupancy<br /> Certificate to the Petitioner. On a pointed query made by this court<br /> as to under what authority, such demand was made by the<br /> Respondents, the learned Senior Counsel for the Respondents could<br /> not give any convincing reply. <br /> 82. In view of the foregoing discussion, we are of the considered<br /> opinion that the demand for payment of the penalty/additional<br /> premium was not maintainable under Article 2(d) of the Lease<br /> Deed. Moreover, such amount was demanded/realized by the<br /> Respondent No. 1 without serving any prior Show Cause Notice<br /> upon the Petitioner thus, acting in clear contravention of the<br /> principle of natural justice. Even a proper Demand Notice was not<br /> served upon the Petitioner before realizing the amount. As such, we<br /> hold that not only the demand for additional premium/ penalty, but<br /> even the retention of any part thereof, as might have been<br /> deposited by the Petitioner under protest, was without the<br /> authority under the law. <br /> Page 46 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 83. In the case of Bank of Baroda, Mumbai & Anr (Supra), relied<br /> upon by Mr Samdani, the primary issue was as to whether the<br /> Respondent No. 1 (MMRDA) was bound to charge premium as per<br /> the provisions of the regulation as applicable during the relevant<br /> period because of the fact that the amendment to the regulations<br /> did not show that it had any retrospective effect. In Assistant Excise<br /> Commissioner & Ors. (Supra), it was held that even in a contract<br /> between the parties which is governed by statutory provisions, the<br /> terms and conditions of the contract would be binding both upon<br /> the Government and the Licensee and neither of them can depart<br /> therefrom. It was also not be open to any officer of the Government<br /> either to modify, amend or alter the terms and conditions. In<br /> Chaudhari Ran Beer Singh (Supra), the Hon’ble Supreme Court has<br /> held that in matters of policy decision, the scope of interference by<br /> the Court is extremely limited. In Goetze (India) Ltd. (Supra), the<br /> Hon’ble Supreme Court has held that when the liability to pay the<br /> interest is statutory, there is no power of waiver of the same; in<br /> Transmission Corporation of Andhra Pradesh Ltd. (Supra), the<br /> Hon’ble Supreme Court has held that when the parties have entered<br /> into the field of contract simpliciter, their rights are controlled by<br /> the contracts executed between them. Therefore, in the absence of<br /> Page 47 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> challenge to the contract, it would not be permissible for the Court<br /> to go behind the contact and permit questioning of the statutory<br /> jurisdiction vested in the regulatory commission. However, as<br /> would be apparent from the facts alluded to herein above, it is<br /> apparent that the issues involved in the Writ petition do not involve<br /> any challenge to a particular Clause/Article in the Lease Deed or to<br /> any statutory provision. On the contrary, the core controversy in<br /> this petition is pertaining to the question of application of the terms<br /> and conditions of the Lease Deed to the facts and circumstances of<br /> this case. Therefore, we are of the opinion that the ratio laid down<br /> in the abovenoted decisions relied upon by Mr Samdani would not<br /> be of any assistance to the Respondents in the facts and<br /> circumstances of the present case.<br /> 84. Having held as above, we deem it appropriate to reiterate<br /> herein that the learned Counsel for the Petitioner has argued that<br /> the case of the Writ Petitioner is squarely covered by the decision of<br /> this Court in the case of Raghuleela Builders Pvt. Ltd. & Anr .<br /> (Supra). The said assertion has, however, been strongly resisted by<br /> the Respondent’s Counsel by submitting that in view of the<br /> observations made by the Hon’ble Supreme Court in the order<br /> Page 48 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> th<br /> dated 27 July 2020, no reliance can be placed on the said<br /> judgment for any purpose for deciding the present Writ Petition. On<br /> a careful examination of the Judgment rendered in Raghuleela<br /> Builders Pvt. Ltd. & Anr . (Supra) we also find that the said decision<br /> was rendered in the facts of that case. However, one of the issues<br /> raised in the said proceedings was pertaining to the question as to<br /> whether, the decision of the MMRDA to apply the extension of time<br /> from 4 years to 6 years for completing the construction only to the<br /> post August 2015 was valid in the eyes of law, is also an issue raised<br /> in the present proceeding. While answering the said question, it<br /> was held in Raghuleela Builders Pvt. Ltd. & Anr . (Supra), as<br /> follows:-<br /> “38. The MMRDA constituted a single member committee of<br /> retired Judge of the Supreme Court to decide whether the<br /> MMRDA should give concession in recovery of premium<br /> considering the time required for plot owner to obtain<br /> permissions from various authorities for construction of building<br /> thereon. It is contended that one member committee has<br /> concluded that the charging of premium for extension of time for<br /> completing construction in Bandra-Kurla Complex area,<br /> specifically in case where additional built up area has been<br /> allotted by the MMRDA, was illegal. In its 138th meeting held on<br /> 26th August 2015, the MMRDA had acknowledged the difficulties<br /> faced by the lessees and that the condition of completion of<br /> construction within 4 years of the execution of the lease was<br /> adversely affecting the tendering process. The MMRDA had<br /> appointed an expert one man committee of retired Supreme Court<br /> Judge in that regard. The single member committee has advised<br /> that the period of 6 to 7 years be granted for completion of<br /> construction.<br /> Page 49 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> 39. The lease deed entered into by the MMRDA with the<br /> lessees are as per form D, prescribed under the MMRDA (Disposal<br /> of Lands) Regulations 1977. Clause 2(a) of the lease deed<br /> provides that for building plans to be submitted to country and<br /> town planing division for approval within 3 months from the date<br /> of lease. Clause 2(c) of the lease deed provides that no work is to<br /> be carried out until all plans, elevations, specifications are<br /> approved by the concerned authorities. Clause 2(d) provides that<br /> within 3 months of the approval of plans, the lessee is to<br /> commence construction which is to be completed within four<br /> years of the lease. Clause 2(e) provided for extension of time.<br /> Clause 2(e) contemplates a situation when the time for<br /> completion of construction can be extended, parties to the<br /> contract contemplated that certain uncertainties or situations may<br /> arise which may require more time for completion of the<br /> construction. In view of this, time is not essence of the contract<br /> between the parties and rightly so since construction of any<br /> building in Bandra Kurla Complex, several permissions are<br /> required from the various authorities and not only from the<br /> MMRDA who is planning authority for the Bandra Kurla area,<br /> namely,<br /> (1) The environmental clearance under the Environmental<br /> Impact Notification from the Ministry of Environment and Forest.<br /> (2) Building height clearance from the Ministry of Civil<br /> Aviation because of the close proximity to Airport.<br /> (3) Clearance from the high rise committee.<br /> (4) Permission from the the MCGM.<br /> (5) Permission from the traffic police.<br /> Each of these authorities is required to be approached<br /> separately since there is no single window clearance / nodal<br /> agency which would co-ordinate with the aforesaid authorities for<br /> granting of all necessary permissions. In view of the delay in<br /> obtaining permissions which are beyond the control of lessee, no<br /> work could be carried out as per clause 2(d) of the lease deed.<br /> 40. The MMRDA had issued a letter of allotment dated 20th<br /> March 2012 allotting additional 67,000 sq. meters at<br /> consideration of 984 crore. Part payment of Rs.196 crore was<br /> received on 20th March 2012. The supplementary lease deed was<br /> executed for additional built up area of 67,000 sq. meters. The<br /> letter of allotment dated 20th March 2012, the acceptance of part<br /> payment of consideration for additional built up area allotted,<br /> diluted the time period of four years and there was no question of<br /> application of condition of occupation certificate for built up area<br /> Page 50 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> within 4 years when additional built up area was allotted for<br /> raising additional 11 floors on the same building.<br /> 41. The resolution passed by MMRDA for extending the time<br /> period for completing construction from 4 years to 6 years only<br /> for leases executed after 26th August 2015 also appears to be<br /> arbitrary, discriminatory, without basis and justification. The said<br /> set of circumstances are prevailing for the construction being<br /> carried out under the leases executed prior to 26th August 2015.<br /> Therefore, not extending this benefit of this extension of time<br /> from 4 years to 6 years to the prior leases in respect of other plots<br /> in the BKC, is completely arbitrary, discriminatory, capricious and<br /> violative of Article 14 of the Constitution of India. There is no<br /> reasonable basis or justification for this decision. The<br /> classification sought to be made between the leases prior and<br /> subsequent to 26th August 2015 is not founded on intelligible<br /> differentia and neither does this differentia has any logic, rational,<br /> nexus to the object sought to be achieved. The MMRDA has<br /> sought to treat equals as unequal. The lessees of plots are being<br /> discriminated on the basis of their date of execution of their<br /> leases. The lessees who are placed in similar circumstances<br /> prevailing for construction in Bandra Kurla area are entitled to<br /> equal treatment guaranteed under Article 14 of the Constitution<br /> of India.”<br /> 85. It is not in dispute that the Lease Deed involved in<br /> Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was also in Form ‘D’ of<br /> the Regulations of 1977 wherein the same Articles 2 (d) and (e)<br /> were involved. The Writ Petitioner there-in was also a similarly<br /> situated lessee from whom penalty for delay in completing the<br /> construction beyond the period of 4 years was raised by the<br /> Respondent No 1. The Petitioner in that case had also raised<br /> identical plea as regards the applicability of the time extension<br /> th<br /> Clause. The Lease Deed in that case was also executed prior to 26<br /> August, 2015. If that be so there can be no doubt about the fact<br /> Page 51 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> that the legal principles discussed and the findings & observations<br /> recorded in paragraphs 38 and 41 of Raghuleela Builders, in so far<br /> as applicability of the 6 years time extension clause is concerned,<br /> would be squarely applicable to the facts of the present case.<br /> Therefore, the Respondent No. 1 would be duty-bound to extend<br /> the benefit of extension of time for completion of construction upto<br /> six years to the present Petitioner as well. <br /> 86. In the facts and circumstances of this case, we are also of the<br /> opinion that there is no legal justification for the Respondent No. 1<br /> to confine the benefit of the time extension clause only to those<br /> th<br /> Lease Agreements which were executed after 26 August 2015 as<br /> such an approach would be highly arbitrary and discriminatory in<br /> nature. Therefore, having regard to the peculiar facts and<br /> circumstances of this case, we do not find any justifiable ground to<br /> take a different view on the aforesaid issue. <br /> 87. Law is well settled that for maintaining judicial discipline and<br /> propriety, a decision rendered by a Coordinate Bench on the same<br /> issue must be respected and followed by a Coordinate Bench. In the<br /> 15<br /> case of Mary Pushpam vs. Televi Curusumary & Ors. the Hon’ble<br /> <b>15</b><br /> (2024) 1 SCR 11.<br /> Page 52 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> Supreme Court has observed that when a decision of a Coordinate<br /> Bench of the same High Court is brought to the notice of the Bench,<br /> it is to be respected and would be binding, subject to the right of<br /> the Bench of such co-equal forum to take a different view and refer<br /> the question to a larger Bench. In other words, any decision of a<br /> Coordinate Bench would be binding on a Bench of equal strength<br /> subject to the condition that if a different view is sought to be<br /> adopted then the matter would have to be referred to a larger<br /> Bench.<br /> 88. The above legal principle has taken a firm footing in the<br /> Indian Jurisprudence by a long line of judicial pronouncements. We<br /> do not deem it necessary to burden this judgment by referring to all<br /> those decisions. However, suffice it to mention that unless there are<br /> justifiable grounds to take a different view in the matter warranting<br /> reference to a larger Bench, the previous decision of a coordinate<br /> Bench would be binding on a Bench of equal strength.<br /> 89. Consequently, it is held that even as per Article 2(d) of the<br /> th<br /> Lease Deed dated 9 June 2006, the Writ Petitioner would be<br /> entitled to six years time for completion of the construction with<br /> th<br /> effect from the date of execution of the Lease Deed, i.e., upto 8<br /> Page 53 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> June 2012. Since the construction of the Hotel building was<br /> th<br /> admittedly completed on 14 June 2011, i.e. within six years<br /> hence, even as per Article 2(d) no penalty would be payable by the<br /> Petitioner on account of delay in completing the construction. <br /> 90. For the reasons stated above, we hold that the Demand<br /> th<br /> Notice dated 12 September 2017, demanding additional<br /> premium/ penalty from the Petitioner, is illegal and without the<br /> authority of law. The same is accordingly set aside. <br /> 91. This Writ Petition, therefore, succeeds and the same is hereby<br /> allowed in terms of payer clause (A). <br /> 92. It appears from the statement annexed to the Demand Notice<br /> th<br /> dated 12 September 2017 that the Petitioner has already<br /> deposited a total amount of Rs.8,93,92,318/- together with<br /> interest, as additional premium/penalty due to delay in completion<br /> of the construction. The Respondent No. 1 is, therefore, directed to<br /> verify and refund the entire amount deposited by the Petitioner, as<br /> additional premium/penalty, within a period of 90 (ninety) days<br /> from the date of receipt of the Certified Copy of this order, failing<br /> which, the amount would carry interest at the same rate at which<br /> Page 54 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b><br /><br /> Shree Naman Hotels-oswp-3209-2017-J-R.doc<br /> <br /> interest was payable by the Petitioner under the Lease Agreement<br /> due to delay in paying premium, to be calculated on the above<br /> amount from the date of this order till the date of the refund. <br /> 93. With the above observations, the Rule is made absolute.<br /> 94. The Writ Petition stands disposed of.<br /> 95. Parties to bear their own costs.<br /> (SUMAN SHYAM, J) (CHIEF JUSTICE) <br /> Page 55 of 55<br /> <b><i>::: Uploaded on - 09/04/2026</i></b> <b><i>::: Downloaded on - 09/04/2026 15:32:20 :::</i></b></div>