Kripa Nand Jha vs The Union of India

Court
Patna High Court

IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.2339 of 2025
CNR No. BRHC010088512025
======================================================
Kripa Nand Jha Son of Jata Shankar Jha, Resident of Sunita Sadan Mohalla
Mithila Colony, Nasariganj, East of Jagdamba Mandir, Mahaveer Path, Road
No. 03, Patna-801503
... ... Petitioner/s
Versus
1. The Union of India through the Secretary, Ministry of Housing and Urban
Affairs, Nirman Bhawan, C-Wing, Central Secretariat, New Delhi-110011
2. Union Bank of India through its Managing Director cum Chief Executive
Officer, having its Head Office at Union Bank Bhavan, 239, Vidhan Bhavan
Marg, Nariman Point, Mumbai- 400 021, Maharashtra.
3. The Regional Manager, Union Bank of India, having Regional Office at
Nasheman Bhawan, 1st Floor, Mazharool Haque Path, Frazer Road, Patna-
800001
4. The Chief Manager, Union Bank of India, ULP Patna Branch, 1st Floor,
Aditya Arcade, Exhibition Road, Patna- 800001.
5. The Branch Manager, Union Bank of India, Indira Bhawan Branch, Patna-
800001.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s : Mr. Purushottam Kumar Jha, Advocate
Mr. Narendra Kumar, Advocate
For the Res. Nos. 2 to 5 : Mr. Prashant Kumar, Advocate
Ms. Kritika Upadhyay, Advocate
Mr. Shashank Shekhar, Advocate
For the UoI : Mr. Arun Kumar Satyamurti, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE HARISH KUMAR
ORAL JUDGMENT
Date : 23-11-2026
Heard Mr. Purushottam Kumar Jha, learned Advocate
for the petitioner, Ms. Kritika Upadhyay, learned Advocate for
the Union Bank of India, and Mr. Arun Kumar Satyamurti,
learned Advocate representing the Union of India.
2. The petitioner, a practicing Advocate of this Court,
having requirement of his house and official chamber,

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
2/16
approached the respondent Bank for a loan under the Credit
Linked Subsidy Scheme for MIG under the Pradhan Mantri
Awas Yojana-Urban ( hereinafter referred to as PMAY-U) to the
tune of Rs. 15 lakhs for construction of his residential building
over his purchased land. The respondent Bank, after scrutiny of
the documents and upon completion of the necessary
formalities, sanctioned a housing loan to the tune of Rs. 15
lakhs jointly in the name of the petitioner and his wife vide
sanction Letter dated 03.12.2020, subject to repayment thereof
in 165 equal monthly installments of Rs. 14,059/-. The scheme
under which the loan account was opened and the amount was
disbursed in phases, as also the sanction letter, contemplated
that the petitioner was entitled to subsidy against the said
housing loan, the scheme being operational till 21.07.2021. The
respondent Bank was also obligated under the scheme to claim
subsidy against the petitioner's housing loan.
3. The petitioner, accordingly, upon completion of the
structure of his building, that is, G+1, measuring about 1680 sq.
ft. (156 sq. metres / FAR 123 sq. metres), with financial
assistance from the respondent Bank, submitted the completion
certificate to the respondent Bank vide Certificate No. UBI-
1706-2022 dated 17.06.2022 and started paying the EMIs to the

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
3/16
respondent Bank.
4. Notwithstanding the aforesaid facts, the petitioner,
claiming eligibility under the Credit Linked Subsidy Scheme for
MIG-II under PMAY-U, upon being deprived of the subsidy
against the said housing loan, enquired about its status from the
respondent Bank, whereupon he was informed that an ID for
subsidy had already been generated in his name and that the
subsidy would shortly be credited to his loan account. The
petitioner kept waiting for the subsidy amount to be credited,
but, save and except for the assurances extended by the
respondent Bank, the subsidy amount was never credited to his
loan account.
5. The petitioner also sought information under the
Right to Information Act, 2005, with regard to the status of his
entitlement to the subsidy amount. The Regional Branch of the
Bank seemingly informed him that the applicant's ID had been
generated, but further claim submission had not been made by
the branch and, therefore, the claim had not been lodged.
6. Aggrieved by the action of the respondent Bank,
whereby the petitioner claims to have been deprived of his legal
right, resulting in monetary loss on account of payment of
interest on the loan amount, the petitioner has approached this

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
4/16
Court invoking its extraordinary jurisdiction, seeking issuance
of a writ in the nature of mandamus directing the respondent
Bank to reimburse and pay the subsidy amount under PMAY-U
against his housing loan, in consonance with the provisions and
guidelines issued by the Union of India, Ministry of Housing
and Urban Affairs. Besides, a further prayer has been made to
compensate the petitioner by paying interest on the subsidy
amount which, according to him, has accrued under the
aforesaid scheme.
7. Mr. Purushottam Kumar Jha, learned Advocate for
the petitioner, while pressing the application, emphatically
submitted that the petitioner is entitled to the subsidy amount,
which is his legal right under the Credit Linked Subsidy Scheme
(CLSS) for Middle Income Group (MIG) under PMAY-U, and
which was to be disbursed by the respondent Bank through its
nodal agency. The Bank was only required to claim the subsidy
and, thus, was merely a forwarding agency to the National
Housing Bank. Only thereafter was the Union of India required
to approve and release the subsidy amount into the petitioner's
loan account. Nonetheless, the Bank has not processed the
petitioner's loan application and has acted contrary to the public
policy framed by the Government of India, thereby depriving

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
5/16
the petitioner of his legal rights.
8. Referring to the scheme and the sanction letter, Mr.
Jha, further submitted that the respondent Bank was not
authorized to scrutinize the claim application; rather, its duty
was only to forward the application to the National Housing
Bank, which was the competent authority to approve or
disapprove the same.
9. Referring to the stand taken by the Bank in its
counter affidavit, learned Advocate for the petitioner
vehemently contended that the pleadings must be supported by
documents and that, once it has been admitted by the Regional
Branch of the respondent Bank that the claim submission was
not forwarded to the National Housing Bank, as a result of
which the subsidy against the petitioner's housing loan was not
extended, the laches on the part of the respondent Bank
becomes evident. However, taking a U-turn, the Bank has made
a false and misleading statement that its role is primarily that of
a facilitating institution, which forwards eligible cases to the
designated Central Nodal Agency for consideration and release
of subsidy. The legal right of the petitioner to receive the
subsidy has been negated solely on the ground that the
constructed area of the building is beyond the permissible limit,

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
6/16
which is nothing but a mala fide action on the part of the
respondent Bank, more so when the construction of the
petitioner's house is within the prescribed limit.
10. Drawing attention to a decision rendered by the
Hon'ble Supreme Court in the case of A.K. Lakshmipathy
(Dead) & Ors. Vs. Rai Saheb Pannalal H. Lahoti Charitable
Trust & Ors., 2010 (1) SCC 287 , it is further argued that no one
should be punished for a mistake committed by others and no
one can be allowed to take advantage of their own mistake. The
apparent arbitrary action of the Bank is writ large and, as such,
the petitioner is not only entitled to receive the subsidy against
his housing loan but is also entitled to be compensated for the
loss and injury suffered by him, besides the mental agony
caused to him.
11. Placing reliance upon a decision rendered in the
case of Whirlpool Corporation Vs. Trade Marks, Mumbai &
Ors., (1998) 8 SCC 1 , it is submitted that the facts of the present
case clearly demonstrate that the respondent Bank has arbitrarily
usurped the power and jurisdiction of the National Housing
Bank and, thus, notwithstanding the availability of a statutory
alternative remedy, the writ petition is maintainable in such
circumstances, particularly where the authority has acted

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
7/16
without jurisdiction or usurped the jurisdiction of another
authority. It is further submitted that the ratio propounded in the
aforesaid case has recently been reiterated in the case of Godrej
Sara Lee Ltd. Vs. Excise and Taxation Officer-cum-Assessing
Authority & Ors., (2025) 11 SCC 808 .
12. Per contra , Ms. Kritika Upadhyay, learned
Advocate for the Bank, has raised a preliminary objection with
regard to the maintainability of the writ petition and submitted,
inter alia , that before invoking the extraordinary jurisdiction of
this Court for issuance of a writ of mandamus, the petitioner
must first establish that a specific demand or representation was
made before the competent authority and that such demand was
either rejected or remained unattended. Admittedly, no
representation, application or request was ever submitted by the
petitioner before the respondent Bank seeking processing of his
alleged claim under PMAY-U (Credit Linked Subsidy Scheme).
13. Adverting to the relief sought for and the facts
enumerated hereinabove, it is further contended that the
grievance of the petitioner is that the respondent Bank failed to
process or upload his PMAY-U subsidy claim. Even if such
allegation is assumed to be correct, it relates to the manner in
which banking services were rendered and, at best, pertains to

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
8/16
an allegation of deficiency in service. The petitioner, therefore,
has an efficacious statutory remedy available for adjudication of
such disputes before the competent Consumer Commission.
14. In response to the submissions advanced by
learned Advocate for the petitioner, pertaining to the merit of the
case, the learned Advocate for the respondent Bank submits that
it acts only as the Primary Lending Institution under the PMAY-
CLSS scheme. The subsidy is neither sanctioned nor released by
the respondent Bank from its own funds. Eligible claims are
processed in accordance with the scheme and are thereafter dealt
with by the designated Central Nodal Agency in terms of the
applicable Government guidelines. Therefore, no writ can be
issued directing the respondent Bank to grant subsidy beyond
the scope of the scheme or contrary to the applicable procedure.
15. The relevant chronology of events clearly depicts
that the scheme remained operational only up to 21.07.2021,
whereas the petitioner furnished the building completion
certificate and relevant documents only on 17.06.2022, i.e,
subsequent to the closure of the scheme, and the PMAY
application ID was generated on 22.06.2022. Thus, according to
learned Advocate for the Bank, there was no laches or lapse on
the part of the respondent Bank. The petitioner's own admission

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
9/16
clearly reflects that the building completion certificate and
relevant documents were furnished more than one year after the
closure of the scheme. It is specifically contended that the date
of sanction of the loan cannot be the sole relevant consideration,
ignoring the subsequent events, since the present case concerns
a construction loan where the petitioner admittedly completed
the formalities and furnished the relevant documents only after
the scheme had already ceased to operate.
16. In the aforesaid circumstances and in view of the
position emerging from the scheme, the petitioner cannot claim
an automatic right to subsidy merely because the loan had been
sanctioned during the currency of the scheme. The respondent
Bank has acted strictly in accordance with the applicable
procedure and, moreover, the petitioner has failed to establish
any statutory provision or binding guideline imposing an
absolute duty upon the respondent Bank to ensure the grant of
subsidy merely because a housing loan had been sanctioned.
17. This Court has given careful consideration to the
submissions advanced by learned Advocates for the respective
parties and has also perused the materials available on record.
18. Before adverting to the facts of the case, in order
to answer the preliminary objection raised by learned Advocate

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
10/16
for the respondent Bank regarding the maintainability of the
writ petition and issuance of a writ of mandamus, it would be
relevant to observe that certain pre conditions are sine qua non
for issuance of a writ of mandamus. The petitioner must have a
legally enforceable right to demand performance of the act, and,
conversely, the respondent, being a public authority or agency,
must be under a positive statutory or constitutional obligation to
perform a specific act. Besides the aforesaid right and
corresponding duty, there must be a specific demand made by
the petitioner calling upon the authority to perform its duty,
followed by a wrongful refusal, failure or neglect on the part of
the authority to discharge such duty. It also needs to be observed
that, since a writ of mandamus is an extraordinary remedy, it
ought to be granted only when there is no other specific, equally
efficacious, beneficial and effective legal remedy available.
19. From the facts adverted to and discussed
hereinabove, it is undisputed that, before invoking the
extraordinary jurisdiction of this Court, the petitioner failed to
call upon either the respondent Bank or the Central Nodal
Agency, i.e., the National Housing Bank, to consider or decide
his claim.
20. Coming to the subsequent chain of facts, the

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
11/16
petitioner had sought information under the Right to
Information Act, 2005. Upon perusal thereof, it is evident that
the petitioner was asked to furnish a copy of the application, if
any, submitted by him earlier, as the Central Public Information
Officer, Regional Head of the respondent Bank, had informed
that no such application for subsidy under PMAY-U against his
housing loan had been submitted. The petitioner neither
furnished a copy of the application nor the application ID
generated by the respondent Bank.
21. Notwithstanding the aforesaid factual position, in
order to give quietus to the litigation exercising the
extraordinary jurisdiction of this Court, when, this Court
perused the Credit Linked Subsidy Scheme for Middle Income
Group (CLSS for MIG), it is evident that an obligation was cast
upon the Bank that the branch would process the proposal as per
the guidelines and sanction the loan after proper credit appraisal
and due diligence of the applicant's property, whenever a
customer directly approached the branch and submitted an
application along with all the required documents. The branch
was further obligated to submit account-wise claim data in the
Excel sheet provided by the National Housing Bank to the
Regional Offices, which would consolidate the data received

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
12/16
from the branches and submit the same to RBMD, CO, for
onward submission to NHB. The subsidy, as stipulated, was to
be credited to the loan account. The circular dated 29.06.2017
also contemplates the eligibility criteria, besides the area of
construction, disbursement of loan and interest subsidy, etc.
22. The operational guidelines for sanction and
claiming of subsidy further stipulate that the branch would
conduct inspections of each project on a regular basis and
prepare progress/end-use reports. The progress details would be
required for claiming subsidy. Upon completion of the
construction, the branch would prepare a completion certificate.
These progress reports and utilisation certificates were required
to be maintained on record, and a consolidated certificate was to
be sent to RBD, CO, through the concerned Regional Offices
for onward submission to NHB. The branch was also required to
link the Aadhaar details of the beneficiary family to avoid
duplication before submitting the claim to NHB. The subsidy
amount received by RBMD/CO was thereafter to be forwarded
to the respective Regional Office for direct credit to the
borrower's account upon receipt of the subsidy from NHB, by
deducting the same from the principal loan amount of the
borrower.

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
13/16
23. Even if, in the interest of justice, the claim of the
petitioner is considered on merits, what remains undisputed is
that the housing loan was sanctioned on 31.12.2020, whereas
the petitioner furnished the building completion certificate and
relevant documents only on 17.06.2022, and the application ID
was generated on 22.06.2022. In the meantime, the PMAY-
CLSS (MIG) scheme, which was effective from 01.01.2017,
became non-operational with effect from 31.03.2021.
Thereafter, the scheme continued only in respect of cases where
claims had been successfully lodged but the subsidy amount had
not yet been released by NHB in the MIG category. Subsequent
thereto, no funds under CLSS for MIG were released by the
Ministry of Housing and Urban Affairs after the financial year
2020-21.
24. The response to the customer grievance regarding
PMAY subsidy, a copy whereof has also been marked as
Annexure R/3 to the counter affidavit filed on behalf of the
respondent Bank, fortifies the aforesaid facts. It, inter alia, states
that no further claims are being uploaded since the scheme for
CLSS for MIG was operational up to 21.07.2021, whereas
CLSS for EWS/LIG was operational up to 15.06.2022, and that
no claim can be processed where the claim has not been lodged

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
14/16
by the branch/Regional Office within the stipulated timeline or
where the applicant ID was generated but the claim was not
submitted by the branch.
25. The PMAY-CLSS scheme introduced by the
Ministry of Housing and Urban Affairs contemplated that the
subsidy against a sanctioned housing loan was to be processed
by the Primary Lending Institution in accordance with the
scheme and thereafter dealt with by NHB in terms of the
applicable Government guidelines. The sanction of a housing
loan and eligibility under the PMAY-CLSS scheme for grant of
subsidy obviously operate in different fields. A borrower may
satisfy the requirements for sanction of a housing loan, yet
entitlement to subsidy is dependent upon the provisions of the
Government scheme and fulfillment of all applicable conditions.
26. Generation of the subsidy ID on 22.06.2022 was
merely an initiation of the process at the level of the Bank,
which was required to be examined by the nodal agency in the
light of the scheme and the guidelines issued in this behalf,
subject to fulfillment of all other requisite criteria, including the
prescribed area of construction.
27. Even if, this Court accepted the contention that
upon sanction of the housing loan by the Bank under PMAY-U

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
15/16
(CLSS), the petitioner became entitled to the Credit Linked
Subsidy Scheme for Middle Income Group and that,
immediately thereafter, all the requisite documents and account-
wise claim data in the prescribed Excel sheet were required to
be submitted to NHB, no effective and positive direction can
now be issued directing the respondent Union of India or the
Ministry of Housing and Urban Affairs to consider the
petitioner's claim for subsidy against his housing loan, since the
Credit Linked Subsidy Scheme for Middle Income Group has
become non-operational with effect from 31.03.2021.
Admittedly, the present writ petition came to be filed on
10.02.2023.
28. In view of the aforesaid facts, circumstances and
the discussions made, hereinabove, this Court finds that the
present writ petition is devoid of any merit.
29. However, the dismissal of the writ petition shall
not come in the way of the petitioner approaching the competent
Consumer Commission, if he is of the opinion that there has
been a deficiency in service on the part of the respondent Bank.
It is pertinent to observe that the remedy under the Consumer
Protection Act, 2019, is in addition to, and not in derogation of,
the provisions of any other law for the time being in force.

Patna High Court CWJC No.2339 of 2025 dt.23-11-2026
16/16
30. With the aforesaid liberty, the present writ petition
stands dismissed.

(Harish Kumar, J)
sumit/-
AFR/NAFR
NAFR
CAV DATE
NA
Date of pronouncement
23.11.2026
Uploading Date
25.11.2026
Transmission Date
NA