STATE PROJECT vs M/S KMV PROJECTS

Court
Karnataka High Court

- 1 -
COMAP No. 54 of 2025



ST
RESERVED ON 21 JULY 2026



















IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 18 DAY OF AUGUST, 2026
PRESENT
THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
AND
THE HON'BLE MRS. JUSTICE K.S. HEMALEKHA
COMMERCIAL APPEAL NO. 54 OF 2025


BETWEEN:
Digitally
signed by K
P SWETHA
Location:
High Court
of Karnataka

1. STATE PROJECT
DIRECTOR
RASHTRIYA MADHYAMIKA SHIKSHA ABHIYAN
NEW PUBLIC ANNEX BUILDING
N.T. ROAD, K.R. ROAD
BANGALURU - 560 001
...APPELLANT
(BY SRI KIRAN VASANTH RON, ADDITIONAL ADVOCATE GENERAL
A/W SRI K.S. HARISH, GOVERNMENT ADVOCATE)

AND:
1. M/S. KMV PROJECTS
REGIONAL OFFICE SITUATED
RD
AT NO. 302, 3 FLOOR
EAST PARK ROAD
KUMAR PARK (E)
BENGALURU - 560 020
REP. BY ITS VICE PRESIDENT AND
AUTHORISED SIGNATORY
SRI D. TARANATH DASARI

2. SRI JUSTICE K.N. KESHAVANARAYANA
SOLE ARBITRATOR, ARBITRATION

- 2 -
COMAP No. 54 of 2025



AND CONCILIATION CENTRE
BENGALURU (DOMESTIC AND INTERNATIONAL)
KANIJA BHAVANA
RACE COURSE ROAD
BENGALURU - 560 001
...RESPONDENTS
(BY SRI ZUFIKIR SHAFI, ADVOCATE FOR C/R-1)
THIS COMMERCIAL APPEAL IS FILED UNDER SECTION 13(1A)
OF THE COMMERCIAL COURTS ACT, 2015 READ WITH SECTION
37(1)(c) OF THE ARBITRATION AND CONCILIATION ACT, 1996
PRAYING TO SET ASIDE THE JUDGMENT DATED 30.11.2024,
PASSED IN COM.AP.NO.40/2024 ON THE FILE OF THE HON'BLE
LXXXVI ADDITIONAL CITY CIVIL AND SESSIONS JUDGE AT
BANGALORE AND CONSEQUENTLY.
THIS COMMERCIAL APPEAL HAVING BEEN HEARD AND
RESERVED FOR JUDGMENT, COMING ON FOR
PRONOUNCEMENT THIS DAY, JUDGMENT WAS PRONOUNCED
AS UNDER:
CORAM: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
and
HON'BLE MRS. JUSTICE K.S. HEMALEKHA

C.A.V. JUDGMENT
(PER: HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)
1. The appellant, the State Project Director, Rashtriya
Madhyamika Shikshana Abhiyana, has filed the present appeal
under Section 13(1A) of the Commercial Courts Act, 2015 [ CC Act ]
read with Section 37(1)(c) of the Arbitration and Conciliation Act,
1996 [ A&C Act ], impugning a judgment dated 30.11.2024

- 3 -
COMAP No. 54 of 2025



[ impugned order ] passed by the learned LXXXVI Additional City
Civil and Sessions Judge, Commercial Court, Bengaluru (CCH-87)
[ Commercial Court ] in Com.A.P.No.40/2024. The appellant had
filed the said petition under Section 34 of the A&C Act seeking
setting aside of an arbitral award dated 10.11.2023 [ impugned
award ] rendered by the learned Sole Arbitrator [ Arbitral Tribunal ].
The learned Commercial Court found no ground to interfere with
the impugned award and accordingly passed the impugned order
dismissing the petition.
2. Respondent No.1, M/s KMV Projects [ KMV ], was the claimant
before the Arbitral Tribunal and the appellant was the respondent.
In terms of the impugned award, the Arbitral Tribunal partly allowed
KMV's claims and directed the appellant to pay a total sum of
` 3,80,58,227/- (Rupees three crores eighty lakhs fifty-eight
thousand two hundred and twenty-seven only), comprising
`
1,94,43,288/- towards price adjustment (Claim No.1) together with
past and current interest of ` 1,04,99,375/-; ` 51,80,150/- towards
unproductive overhead charges, Claim No.6(a); and ` 29,35,414/-
towards loss of expected profit (Claim No.7); with future interest at
9% per annum on ` 2,75,58,852/- from the date of the award till
payment; and ` 3,00,000/- towards costs (Claim No.11).

- 4 -
COMAP No. 54 of 2025



3. The present appeal is one of a batch of nine appeals,
(COMAP Nos.53/2025 to 61/2025), filed by the appellant against
orders passed by the learned Commercial Court dismissing the
appellant's petitions under Section 34 of the A&C Act,
(Com.A.P.Nos.39/2024 to 47/2024) assailing separate Arbitral
Awards rendered by the Arbitral Tribunal constituted of Sole
Arbitrator in respect of the contract of nine packages awarded to
M/s. KMV. The arbitral awards rendered are substantially in similar
terms and the issues involved in the said nine appeals are also
materially similar.
PREFATORY FACTS
4. Rashtriya Madhyamika Shikshana Abhiyana [ RMSA ] is a
centrally sponsored scheme launched in the year 2009-10 by the
Ministry of Human Resource Development, Government of India,
for enhancing access to, and the quality of, secondary education.
The Government of Karnataka [ GoK ] implemented the scheme
through the appellant and took up 2,024 civil works under 77
packages between 2009-10 and 2013-14. The said civil works
involved construction of new school buildings, Adarsha Vidyalayas
[ model schools ] and girls' hostels, and strengthening and
upgradation of existing schools at an aggregate cost of ` 1,645.70

- 5 -
COMAP No. 54 of 2025



crores. The scheme has since been integrated with Samagra
Shikshana Karnataka (2018-19).
5. On 24.09.2012, tenders were invited on a package basis
through the e-procurement portal in respect of works spread over
thirty districts of the State. KMV emerged the successful bidder in
respect of nine packages comprising 406 scattered work sites. The
present dispute pertains to Package A-4 — Construction of
Adarsha Vidyalayas at Bidar and Aurad Blocks and Girls' Hostels
at Bidar, Aurad, Basavakalyan and Humnabad Blocks of Bidar
District [ the subject package ] – comprising six works. After KMV
was declared as the lowest bidder (L1), the parties entered into
negotiations, and pursuant to said negotiations, KMV reduced its
quoted rates.
6. By its letter dated 13.02.2013 (Ex.C2), which bears an
acknowledgement of service at the appellant's office, KMV offered
a revised price of ` 17,61,88,838/-, being 19.55% above the
updated estimate. It is material to note that KMV concluded the
said letter by stating that it was "ready to execute the above project
considering the inclusion of 'Price Adjustment Clause' at the said
price. Thereafter, by Letter of Acceptance dated 18.03.2013

- 6 -
COMAP No. 54 of 2025



(Ex.C3), the appellant accepted the revised offer for a contract
price of ` 1,761.89 lakhs.
7. The parties executed a Construction Agreement [ the
Agreement ] dated 15.05.2013 (Ex.C4). Clause 4 of the Agreement
stipulates that the Letter of Acceptance, the Contract Data, the
Conditions of Contract, and the Special Conditions of Contract,
among other documents, formed an integral part of the Agreement.
8. Notice to proceed with the work was issued on 17.05.2013
(Ex.C5) and the stipulated period of completion was twenty months
therefrom, which expired on 16.02.2015. During execution,
1
additional quantities and EIRL items were required to be executed.
Upon approval of the competent authority, the parties entered into
a Supplementary Agreement dated 17.03.2017, which forms part of
`
Ex.C4, for 374.89 lakhs taking the revised contract value to
` 2,136.78 lakhs.
9. Clause 4(i) of the Supplementary Agreement stipulates that all
conditions of the original agreement (the Agreement) are applicable
"except for the price adjustment clause, for which a decision will be
taken after the completion of enquiry ordered by the Government".

1
Extra Items Rate List: unbudgeted items

- 7 -
COMAP No. 54 of 2025



10. There was delay in execution of the works it was not
completed within the stipulated period. During the period between
2013 and 2019, KMV addressed several letters to the appellant,
inter alia , alleging (i) delay in handing over sites; (ii) delay in supply
of drawings; (iii) delay in approval of work slips and EIRL items; (iv)
delay in release of payments; (v) non availability of water and
power; and (vi) scarcity of sand. KMV invoked Clause 39 of the
Conditions of Agreement and raised the price adjustment. None of
the said bills were paid.
11. In the meantime, under Government Order No. ED 49 MCD
2016 dated 16.11.2016, the GoK, while granting administrative
approval to a revised project cost of ` 1,717.24 crores excluding
price adjustment, the GoK directed (i) an audit by the Karnataka
Institute of Public Auditors [ KIPA ] into the causes of and
responsibility for the delay; and (ii) an enquiry into the issue of price
adjustment by a committee headed by an officer of the rank of
Additional Chief Secretary. The committee reported that the price
adjustment clause incorporated in the tender documents for the
RMSA civil works of 2009-10 and 2010-11 was not duly approved
and was not binding on the GoK. By a communication dated
17.07.2018, the State Project Director informed the contractors that

- 8 -
COMAP No. 54 of 2025



price adjustment would not be paid and that extension of time
would be considered only upon giving up their contractual claims in
that behalf.
12. The said Government Order and communication were
impugned by three other contractors namely, M/s Jampana
Constructions Pvt. Ltd., M/s NCC Ltd., and M/s KBR Infratech Pvt.
Ltd. in W.P. Nos.38613/2018, 35594/2018 and 34990/2018
respectively. By orders dated 25.02.2019 (Ex.R2), a learned Single
Judge of this Court quashed the Government Order dated
16.11.2016 and restrained the State from acting upon KIPA's
reports and suggestions. The court observed that whether Clause
39 was incorporated with approval or inserted unauthorisedly is a
disputed question of fact, and relegated the petitioners to
arbitration. The intra-court appeals – W.A. Nos.958/2019, 996/2019
and 1031/2019 by the contractors, and W.A. No.2791/2019 by the
State – were disposed of by a Division Bench of this Court on
20.10.2020, observing that "the parties would be governed by the
terms of the contract entered into by them in respect of various
packages awarded by the State".
13. By its letter dated 12.03.2019 (Ex.C68), KMV set out the
causes of delay and its claims; and by legal notice dated

- 9 -
COMAP No. 54 of 2025



08.05.2019 (Ex.C69), it invoked the arbitration agreement under
Clause 24 of the Conditions of Contract read with Clause 4 of the
Special Conditions of Contract.
14. The appellant responded by letter dated 11.06.2019 (Ex.C70),
stating that the claims were rejected in its office letter No.146 dated
06.05.2019 and that the reference was premature in view of the
pendency of the writ appeals.
15. KMV filed an application under Section 11 of the A&C Act
(C.M.P.No.251/2019) seeking appointment of an Arbitrator. This
Court allowed the same by an order dated 05.11.2020 and
appointed a Sole Arbitrator to adjudicate the disputes between the
parties.
16. In the meanwhile, by Government Order No.EP 89 YYK 2020
dated 30.09.2020 (Ex.R1), the GoK, adopted the recommendations
of the Technical Advisory Committee in supersession of the KIPA
report, ordered that (i) for computing extension of time and penalty,
each work site in a package be treated as a separate unit; (ii) the
administration be held responsible for delays occasioned by
causes beyond the contractor's control; and (iii) price adjustment
be allowed in respect of the 25 packages whose tender conditions

- 10 -
COMAP No. 54 of 2025



contained the price adjustment clause. Admittedly, the sums due to
KMV were released only thereafter and were received in full before
29.03.2021. By an order dated 13.01.2021, extension of time was
ARBITRAL PROCEEDINGS
17. KMV filed its statement of claims before the Arbitral Tribunal
claiming an amount of ` 34,55,75,317/- (Rupees Thirty-four crores
Fifty-five lakhs Seventy-five thousand Three hundred and
Seventeen) under eleven heads. The summary of claims as set
out in the statement of claims is reproduced below.
Claim amount
Claims Particulars
(Amt. in Rs.)
Claim No.1 Payment of Price 2,06,35,903
Adjustment/Escalation Bill
Claim No.2 Payment of equitable enhanced
rates executed beyond tender
completion period
Claim No.3 Payment of equitable enhanced
rates executed beyond Tender
Completion Period for extra Items
1,39,37,227
Claim No.4 Payment of equitable enhanced
rates executed beyond Tender
Completion Period for quantities
more than 125%
Claim No.5 Payment towards idle labour 3,17,95,861
charges
Claim No.6(a) Payment of unproductive overhead 51,80,143
charges
Claim No.6(b) Payment of additional overhead 78,22,820
charges
Claim No.7 Payment towards loss of expected 51,80,143
profit on the balance work as on

- 11 -
COMAP No. 54 of 2025



original tender completion date
2,59,00,715
Claim No.8(a) Loss of expected profit due to non-
receipt of profit by tender
completion period
2,49,61,334
Claim No.8(b) Loss of expected profit due to non-
receipt of profit by actual
completion period
15,38,13,311
Claim No.9 Payment towards interest on claim
amount calculated up to
31.12.2020 at the rate of 24%
3,99,288
Claim No.10 Payment towards additional Bank
Guarantee charges beyond original
agreement period
Claim No.11 Payment of Rs.12,00,000/-
(Rupees Twelve Lakhs only)
towards Cost of Litigation
12,00,000
Total 34,55,75,317

18. It was the KMV's case that after it was declared a successful
bidder, it had reduced its rates by factoring in the price escalation
clause and the economies of scale. KMV claimed that the appellant
did not hand over the sites within the stipulated period despite
various requests. Thus, KMV was effectively prevented from
completing the contract within time, and the execution of the works
was prolonged. KMV alleged that the appellant also withheld
amounts due to KMV, which compelled KMV to seek reference of
disputes to arbitration.
19. The respondent contended that the price variation clause
(clause 39) of the conditions of contract was not applicable as the
notice inviting tenders uploaded expressly provided that the said

- 12 -
COMAP No. 54 of 2025



clause be read as deleted. It is contended that this clause was
unauthorisedly included in the Agreement. Thus, the appellant was
not bound by the said price variation clause.
20. On the basis of the pleadings between the parties, the
Arbitral Tribunal framed the following issues.
"1. Whether Claimant proves that non completion of the
works under the contract within the stipulated period
was for the reasons solely attributable to Respondent,
resulting in breach of contract by Respondent, as such,
the delay in completion of the works was solely
attributable to Respondent?

2. Whether for the reasons set out in SOC which were
beyond the control of Claimant, he was prevented from
completing the entire scope of work within the
scheduled contract period?

3. Whether Respondent proves that the delay in completion
of the works under the contract within the original period
stipulated under the contract was solely attributable to
Claimant?

4. Whether Respondent proves that as the requirements of
Clause 37.3 of Conditions of Contract have not been
complied with by Claimant, none of the claims put-forth
in SOC is tenable?

5. Whether the Claimant is entitled for payment of amounts
claimed under various heads as put-forth under claim
Nos.1 to 8 of SOC?

6. Whether the Claimant is entitled for payment towards
past interest on the amounts claimed up to 31-12-2021
at 24% PA as claimed under claim No.9 of SOC?

7. Whether Claimant is entitled for current and future
interest at 24%PA on the amount claimed?

- 13 -
COMAP No. 54 of 2025



8. Whether Claimant is entitled for cost of this arbitral
proceeding?

9. To what order and award the parties are entitled to?"

21. The Arbitral Tribunal, after examining the evidence and
materials placed on record, found that non-completion of the
contract within the stipulated period was for the reasons
attributable to the appellant. The Arbitral Tribunal also partly found
that some of the actions had prevented KMV from completing the
contract.
22. The Arbitral Tribunal partly allowed claims No. 1, 6(a), and 7.
The Arbitral Tribunal also awarded future interest and costs but
rejected the remaining claims.
23. The dispositive part of the impugned award is set out below:
"The claims of Claimant as put forth in Statement of
Claim are allowed in part as under:

(1) Claim No.1 is allowed in part in a sum of
Rs.1,94,43,288/- only as against the claim of
Rs.2,06,35,903/- together with Rs.1,04,99,375/- towards
past and current interest calculated up to 10.11.2023,
totalling to Rs.2,99,42,663/;

(2) Claim No.6(a) is allowed in a sum of Rs.51,80,150/-;

(3) Claim No.7 is allowed in part in a sum of Rs.29,35,414/-
only, as against the claim of Rs.51,80,143/-;

(4) Respondent is directed to pay to Claimant a total sum of
Rs.3,80,58,227/-as per Sl.No.(1) to (3) above together

- 14 -
COMAP No. 54 of 2025



with future interest at the rate of 9% per annum from the
date of this Award till the date of payment on-
Rs.02,75,58,852/-;

(5) Claim No.11 is allowed in part in a sum of Rs.3,00,000/-
only as against claim of Rs.12,00,000/-. Respondent is
directed to pay to Claimant, this amount within a period
of 3 months from the date of this award failing which the
said amount shall carry interest at the rate of 9% per
annum from the date of award till the date of payment;

(6) Claim Nos.2 to 5, 6(b); 8(a); 8(b), 9 and 10 are rejected
in their entirety;

(7) Claimant shall pay requisite stamp duty on this award
payable as per Karnataka Stamp Act,

With the pronouncement and publication of Award, this
Arbitral Proceeding stand terminated as per Section 32(1) of
the Act.

REASONS AND CONCLUSION
24. The appellant has assailed the impugned award on several
grounds. First, the appellant submitted that the price adjustment
clause was not part of the contract between the parties. It was
contended that the tender documents state that clause 39 of the
conditions of contract was deleted. Thus, the Arbitral Tribunal has
erred in ordering an award on the basis of the said clause. Second,
it is submitted that the Arbitral Tribunal awarded claims without any
evidence or material to substantiate them.
25. The Arbitral Tribunal rejected the contention that clause 39 of
the conditions of contract is not a part of the Agreement. The

- 15 -
COMAP No. 54 of 2025



Arbitral Tribunal set out elaborate reasons in support of the
conclusion that the said clause forms part of the Agreement. First,
the Agreement expressly included the Conditions of Contract as
part of the contract, and the signed Agreement did not contain any
notation excluding Clause 39. The Contract Data – which also
forms a part of the Agreement – sets out the formulae for
computing the price variation. It also includes a notation N/A for
some clauses, but the same is not applicable for the formulae set
out for computing price variation under clause 39 of the Conditions
of Contract
26. The Arbitral Tribunal examined the nature of the Agreement
and found that the Agreement specifically sets out the documents,
which would form and be read as part of the Agreement. The
Arbitral Tribunal also noted that the contract between the parties
was an item rate contract and not a lump sum contract. The term
“initial contract price” was defined as the contract price listed in the
letter of acceptance. The Arbitral Tribunal reasoned that the said
contract price (critical contract price) was subject to adjustment on
account of variations in quantities, as well as increase or decrease
in the prices of various components.

- 16 -
COMAP No. 54 of 2025



27. The Arbitral Tribunal accepted KMV’s contention that it had
negotiated the reduced price on the basis that the contract would
include a price variation clause, which would cover it for any
escalation. Additionally, the Arbitral Tribunal noted that KMV had
raised several bills and various communications referring to the
price variation clause, which were not refuted at the material time.
28. Admittedly, the price variation clause formed part of the
Agreement that was finally executed between the parties. In view
of the above, the Arbitral Tribunal's conclusion to the effect that the
price variation clause formed part of the Agreement is a matter that
relates to interpretation of the Agreement between the parties and
is well within its jurisdiction. The conclusion is also informed by
reasons. In this view, the said conclusion would warrant no
interference under Sections 34 or 37 of the A&C Act.
29. Mr. Ron, the learned AAG fairly did not press the aforesaid
challenge. He focused his submissions primarily on the ground that
the amounts awarded against claim Nos.1, 6(a) and 7 were without
any material evidence and were inconsistent with the findings of
the learned Arbitral Tribunal to the aforesaid effect.

- 17 -
COMAP No. 54 of 2025



30. At this stage, it would be relevant to refer to the Claim
Statement, which sets out the basis for the said claims (Claim
Nos.1, 6(a) and 7). KMV had set out various issues that had
plagued the execution of the works. It claimed that there was, (i)
delay in supply of agreement copies and signing of the condition of
contract; (ii) delay in handing over site; (iii) delay in performance of
pooja; iv) delay in supply of drawings; (v) non-availability of water
and power source; (vi) scarcity of sand; (vii) increase in quantities
to be executed; (viii) delay in payments; (ix) delay in approval of
work slips/EIRL; (x) increase in cost of material due to shortage;
(xi) posting of technical staff; xii) loss of working season; and xiii)
extension of bank guarantees.
31. KMV claimed that the delay was beyond its control and the
reasons for the delay were attributable to the appellant. It claimed
that the appellant had committed a breach of the contract resulting
in the execution period being prolonged. On the basis of the
aforesaid narration, KMV claimed: "payment of price
adjustment/escalation bill as claim No.1 and quantify the said
amount as ` 2,06,35,903/-".
32. It is material to note that the Claim Statement did not provide
any calculation or the break-up of the said amount. The legal notice

- 18 -
COMAP No. 54 of 2025



(Exhibit-C69) also did not set out the details of claim No.1.
Similarly, the Claim Statement did not set out any break up or
provide any details as to the other claims including claim Nos.6(a)
and 7 (payment of additional overhead charges and payment
towards loss of expected profits on the balanced work order as on
the original tender completion date).
33. In the context of claim no.1, the Arbitral Tribunal observed
as under:
"233. However, Claimant has not produced either a
calculation sheet indicating all the relevant factors for
deriving the amounts payable for each of the
permitted components supported by required
documents or produced any documentary evidence
to substantiate the total claim of Rs.2,06,35,903/-
towards price adjustment. Claimant has also not
placed any evidence to show as to how he has
arrived at the figure of Rs.2,06,35,903/-towards price
adjustment claim."

34. Notwithstanding the finding that the KMV has neither
produced any calculation sheet nor any documentary evidence to
substantiate its claim, the Arbitral Tribunal proceeded to award an
amount of ` 1,94,43,288/- towards price adjustment under claim
No.1. The only reason for awarding the said amount was that a
letter dated 20.09.2017 (Exhibit-C63) set by KMV mentioned that it
had submitted a bill for ` 1,94,43,288/- and the appellant had not

- 19 -
COMAP No. 54 of 2025



responded to the said letter. The Arbitral Tribunal reasoned that it
was obligatory on the appellant to respond to the same. Since the
appellant had not done so; it presumed that the said bill was not
disputed. Plainly, the said reasoning is unsustainable. There is no
dispute that the onus to establish the claim for variation in price
rested on the KMV. The appellant's Statement of Objections
indicates that the appellant has denied the claim in its entirety.
Thus, KMV had to not only establish that it was entitled to price as
adjusted but also prove the quantum of such variation.
35. Merely producing a letter which mentions a bill is clearly no
evidence to establish a claim of escalation. According to KMV,
escalation was payable in terms of the price adjustment clause 39
of the Conditions of Contract. Clause 39 is set out below:
"39. Price Adjustment :
39.1 Contract Price shall be adjusted for increase or
decrease in rates and Prices of Labour, Materials,
Fuels and Lubricants in accordance with the
following Principles and Procedures and as per the
Formulae given in the Contract Data.
a) The Price Adjustment shall apply for the Work
done from the Date of Commencement upto the End
of Original Period of Completion or Extensions
granted by the Employer and shall not apply to Work
carried out beyond the Stipulated Period of
Completion for Reasons attributable to the
Contractor.

- 20 -
COMAP No. 54 of 2025



b) Price Adjustment shall be admissible from the
Date of Opening of Tenders (Original or Extended).
c) The Price Adjustment shall be determined during
each quarter from the Formulae given in Contract
Data.
d) Following Expressions and Meanings are
assigned to the Work done during the quarter:
R= Total Value of Work done during the quarter. It
will exclude Value for Works executed under
Variations for which Price Adjustment (if any) will be
worked out separately based on the Terms mutually
agreed.
39.2 To the extent that full compensation for any rise
or fall in costs to the contractor is not covered by the
Provisions of this or other Clauses in the Contract,
the Unit Rates included in the Contract shall be
deemed to include Amounts to cover the
Contingency of such other rise or fall in costs."

36. As apparent from the above, clause 39 of Conditions of
Contract refers to the formulae in the Contract Data. The Contract
Data sets out formulae on the basis of which the contract price was
to be adjusted for labour component, cement component, steel
component, fuel and lubricant component, plant and machinery
spares component, and for other materials. The variables as set
out in the formulae required to be establish for the quantum of price
variation to be computed according to the formulae. However, as
stated above, KMV had not produced any material to show as to
how the amount as claimed by it was computed.

- 21 -
COMAP No. 54 of 2025



37. There is no evidence or material to establish the quantum of
compensation/escalation as claimed. Therefore, an arbitral award
for the said sum is unsustainable. An arbitral award, which is not
based on any relevant material, is vitiated by patent illegality.
38. The claimant had claimed a sum of ` 51,80,143/- towards
unproductive overhead charges under claim No.6(a) and
` 78,22,820/- towards additional overhead charges under claim
No.6(b). In regard to the said claim, the Arbitral Tribunal noted as
under:
"257. In SOC, there is no averments made in support
of these claims to indicate the basis and the
methodology under which the amounts have been
arrived at. Even PW1 in his affidavit evidence has
not stated anything in this regard."

39. Although, the Arbitral Tribunal found that there was neither
any evidence nor any averments to support the claims, it awarded
the claim of additional overhead charges on the basis of the
Hudson formula as referred to by the Supreme Court in a decision
2
in McDermott International Inc. v. Burn Standard Ltd. and Ors .
40. KMV had submitted a spreadsheet (Exhibit-C71) claiming
10% of the contract price as overhead charges. Apparently, it had

2
(2006) 11 SCC 181

- 22 -
COMAP No. 54 of 2025



computed the amount of extra overhead charges by multiplying the
value of work less the value of the amount paid after the tender
completion date by 10%. This is noted by the Arbitral Tribunal in
the impugned award as under:
"265. As indicated in the spreadsheet submitted as
per Ex.C71 and the spreadsheet submitted along
with the written arguments, Claimant has claimed
overhead and establishment charges at 10% of the
contract price. In these spreadsheets, the
methodology for working out the quantum has been
shown as UPOH Value = 70% of BOQ value X
percentage of overhead and establishment charges.
With regard to unproductive overhead and
establishment charges, the methodology indicated in
the spreadsheets is: Value of Extra and Additional
Overhead = (Value of revised estimate minus
amount paid up to tender completion) X 10%. On this
basis, the Claimant has worked out actual figures
towards each of the two heads in respect of five
working locations."

41. There is no evidence or material to suggest that the
overhead charges are of 10% value of work done. Nonetheless, the
Arbitral Tribunal had accepted the same on the ground that a
suggestion had been put to KMV's witness, PW1, that the item
rates mentioned covered 10% overhead charges and 10% as
contractor's profit. It is relevant to extract the relevant extract of
PW1's statement which is set out below:

- 23 -
COMAP No. 54 of 2025



"17. It is true that the tender price awarded to the
claimant was over and above the PWD SR prevailing
at the relevant point of time. However, it is not
correct to suggest that it was 20% above the PWD
SR. According to me, it was 19% above the PWD
SR. I do not know if it is suggested that the
percentage over and above the PWD SR covers
10% towards the overhead charges and 10%
towards contractors’ profit. It is not correct to suggest
that since the tender price includes 10% of
contractors’ profit, claimant has not suffered any
loss."

42. It was necessary for the KMV to produce some material or
evidence to establish its overhead charges. The denial by a
witness to a suggestion to the effect that the overhead charges
were included in the contract price cannot be construed as an
admission on the part of the appellant that the KMV's overhead
charges are 10% of the total contract value.
43. In our view, the amount awarded against claim No.6(a) is
unsupported by any evidence or material.
44. Insofar as the loss of profits (claim No.7) is concerned, the
Arbitral Tribunal expressly noted that there were no averments to
support the claim.The relevant extract of impugned award is set out
below:
"274. Under this claim, Claimant has sought payment
of Rs.51,80,143/- towards loss of expected profit on

- 24 -
COMAP No. 54 of 2025



the balance work as on the original tender
completion date.
275. In SOC, there is no averments made in support
of this claim to indicate the basis and the
methodology under which the amount has been
arrived at. Even PWI in his affidavit evidence has not
stated anything in this regard."

45. Notwithstanding the aforesaid finding, the Arbitral Tribunal
found that it was just and proper to grant compensation at the rate
of 10% of the expected profit of 10% of the balance work that was
executed after the contract completion date. The Arbitral Tribunal
held that the work of a value of ` 5,18,01,427/- was executed after
the contract completion date. Notwithstanding, that there was
material to establish the expected profit, the Arbitral Tribunal
assumed that the expected profit on the said amount of
` 51,80,143/- would be 10% of that amount (computed at
` 51,80,143/-) and the Arbitral Tribunal awarded 10% of that
amount per annum from the date of expiry of the completion period
up to the date of actual payment. Since the execution of the
contract was delayed by 68 months (5 years and 8 months), the
Arbitral Tribunal computed the amount payable against claim No.7
as ` 29,35,414/- along with interest. We also note that there is an
inconsistency in the impugned award to the extent that the Arbitral
Tribunal has awarded future interest at the rate of 6% per annum

- 25 -
COMAP No. 54 of 2025



on the said claim in paragraph 292 of the impugned award. But in
paragraph 293 of the impugned award, the Arbitral Tribunal has
awarded a future interest at the rate of 9% per annum against the
said amount.
46. The Arbitral Tribunal referred to the decision in case of
3
A.T. Brij Paul Singh and others v. State of Gujarat and MSK
4
Projects India (JV) Limited v. State of Rajasthan . And, on the
strength of the said decisions held that the claim for loss of profits
by a contractor would be maintainable if the employer had
breached the terms.
47. There is no cavil that if the employer breaches the terms of
the contract, then the contractor would be entitled to loss of profits
for the unexecuted works. However, in the present case, KMV had
completed the works. Thus, it had received the element of profit,
which was included in the contract price. Although KMV had not
articulated in so many words, it is obvious that its claim for loss of
profits could only be on account of prolongation of works. This is on
the assumption that if the work had been completed within the
stipulated period, KMV could be free to take up other works which

3
(1984) 4 SCC 59

4
(2011) 10 SCC 573

- 26 -
COMAP No. 54 of 2025



would yield profit. However, there was neither any pleadings nor
any evidence to establish this claim.
5
48. In Bharat Coking Coal Ltd. v L.K. Ahuja , the Supreme
Court had, in the context of claim for loss of profit and prolongation
of works, observed as under:
“24 . Here when claim for escalation of wage bills and
price for materials compensation has been paid and
compensation for delay in the payment of the amount
payable under the contract or for other extra works is to
be paid with interest thereon, it is rather difficult for us to
accept the proposition that in addition 15% of the total
profit should be computed under the heading “Loss or
Profit”. It is not unusual for the contractors to claim loss of
profit arising out of diminution in turnover on account of
delay in the matter of completion of the work. What he
should establish in such a situation is that had he
received the amount due under the contract, he could
have utilised the same for some other business in which
he could have earned profit. Unless such a plea is raised
and established, claim for loss of profits could not have
been granted. In this case, no such material is available
on record. In the absence of any evidence, the arbitrator
could not have awarded the same. This aspect was very
well settled in Sunley (B) & Co. Ltd. v. Cunard White Star
Ltd. [(1940) 1 KB 740 : (1940) 2 All ER 97 (CA)] by the
Court of Appeal in England. Therefore, we have no
hesitation in deleting a sum of Rs 6,00,000 awarded to
the claimant.”


49. We also consider it apposite to refer to the following
observations made by the Supreme Court in UNIBROS v All India
6
Radio :

5
(2004) 5 SCC 109

- 27 -
COMAP No. 54 of 2025



“16. To support a claim for loss of profit arising from
a delayed contract or missed opportunities from other
available contracts that the appellant could have earned
elsewhere by taking up any, it becomes imperative for the
claimant to substantiate the presence of a viable
opportunity through compelling evidence. This evidence
should convincingly demonstrate that had the contract
been executed promptly, the contractor could have
secured supplementary profits utilizing its existing
resources elsewhere.

17. One might ask, what would be the nature and quality
of such evidence? In our opinion, it will be contingent
upon the facts and circumstances of each case.
However, it may generally include independent
contemporaneous evidence such as other potential
projects that the contractor had in the pipeline that could
have been undertaken if not for the delays, the total
number of tendering opportunities that the contractor
received and declined owing to the prolongation of the
contract, financial statements, or any clauses in the
contract related to delays, extensions of time, and
compensation for loss of profit. While this list is not
exhaustive and may include any other piece of evidence
that the court may find relevant, what is cut and dried is
that in adjudging a claim towards loss of profits, the court
may not make a guess in the dark; the credibility of the
evidence, therefore, is the evidence of the credibility of
such claim.

18. Hudson's formula, while attained acceptability and is
well understood in trade, does not, however, apply in a
vacuum. Hudson's formula, as well as other methods
used to calculate claims for loss of off-site overheads and
profit, do not directly measure the contractor's exact
costs. Instead, they provide an estimate of the losses the
contractor may have suffered. While these formulae are
helpful when needed, they alone cannot prove the
contractor's loss of profit. They are useful in assessing
losses, but only if the contractor has shown with evidence
the loss of profits and opportunities it suffered owing to
the prolongation.


6
2023 SCC OnLine SC 1366

- 28 -
COMAP No. 54 of 2025



19. The law, as it should stand thus, is that for claims
related to loss of profit, profitability or opportunities to
succeed, one would be required to establish the following
conditions : first, there was a delay in the completion of
the contract; second, such delay is not attributable to the
claimant; third, the claimant's status as an established
contractor, handling substantial projects; and fourth,
credible evidence to substantiate the claim of loss of
profitability. On perusal of the records, we are satisfied
that the fourth condition, namely, the evidence to
substantiate the claim of loss of profitability remains
unfulfilled in the present case.

20. The First Award was interfered with by the High Court
for the reasons noted above. The Arbitrator, in view of
such previous determination made by the High Court,
could have granted damages to the appellant based on
the evidence on record. There was, so to say, none
which on proof could have translated into an award for
damages towards loss of profit. A claim for damages,
whether general or special, cannot as a matter of course
result in an award without proof of the claimant having
suffered injury. The arbitral award in question, in our
opinion, is patently illegal in that it is based on no
evidence and is, thus, outrightly perverse; therefore,
again, it is in conflict with the “public policy of India” as
contemplated by section 34(2)(b) of the Act.”

50. In the present case, there are no averments that would
support the award of the claim as computed by the Arbitral
Tribunal. There is no basis for awarding 10% of the assumed
profits, calculated as 10% of the contract value executed after the
stipulated completion date. In view of the above, to that extent, the
impugned award is vitiated by patent illegality.
51. It is also relevant to note that the Arbitral Tribunal had
rejected certain claims on the ground that the claims were not

- 29 -
COMAP No. 54 of 2025



supported by any averments or any evidence. Having recorded
similar findings in respect to claim Nos.1, 6(a) and 7, the said
claims were required to suffer the same fate.
52. The impugned award to the extent that it awards claim
Nos.1, 6(a) and 7 in favour of the KMV is unsustainable and is
accordingly set aside. Consequently, the interest awarded on the
said sums would not survive. The costs (claim No.11) have been
awarded on the basis of the KMV's success in the aforementioned
claims. Thus, the same is also liable to be set aside.
53. Accordingly, the impugned award to the extent of sums
awarded against claim Nos.1, 6(a), 7 and 11 is set aside. The
appeal is allowed in the aforesaid terms.

Sd/-
(VIBHU BAKHRU)
CHIEF JUSTICE


Sd/-
(K.S. HEMALEKHA)
JUDGE
KMV/KPS