Radiance Infracon And Developers Pvt Ltd vs Gls Infratech Pvt Ltd
- Court
- Delhi High Court
<div> <br /> $~ <br /> * <b>IN THE HIGH COURT OF DELHI AT NEW DELHI</b> <br /> <b> Judgment reserved on: 23.03.2026 </b><br /> <b> Judgment pronounced on: 13.04.2026 </b><br /> <br /> + FAO(OS) (COMM) 156/2024, CM APPL. 43047/2024 <br /> RADIANCE INFRACON AND <br /> DEVELOPERS PVT LTD .....Appellant <br /> Through: Mr. Jeevesh Nagrath, Sr. Adv. <br /> with Mr. Rupesh Gupta and Ms. Kritika <br /> Tuteja, Advs. <br /> <br /> versus <br /> <br /> GLS INFRATECH PVT LTD .....Respondent <br /> Through: Mr. Nakul Sachdeva, Mr. <br /> Shreyansh Rathi, Mr. Sagar Arora, Ms. <br /> Shrinkhala Tiwari and Mr. Abhinandan <br /> Sharma, Advs. <br /> <b>CORAM:</b> <br /> <b>HON'BLE MR. JUSTICE C. HARI SHANKAR</b> <br /> <b>HON'BLE MR. JUSTICE OM PRAKASH SHUKLA</b> <br /> <b>JUDGMENT</b> <br /> <b>% </b> <b> </b> <b> </b> <b> </b> <b> 13.04.2026 </b><br /> <br /> <b> </b><br /> <b>OM PRAKASH SHUKLA, J. </b><br /> <b> </b><br /> <b>Introduction </b><br /> <b> </b><br /> <b>1.</b> <b> </b> The Appellant has filed the present intra-court appeal under <br /> 1<br /> Section 37 of the Arbitration and Conciliation Act, 1996 , read with <br /> Section 13 of the Commercial Courts Act, 2015 and Section 151 of <br /> 2<br /> Civil Procedure Code, 1908, assailing the order dated 20.05.2024 <br /> passed by the learned Single Judge in O.M.P. (COMM) No. 223/2024. <br /> <br /> 1<br /> “the Act”, hereinafter <br /> 2<br /> “Impugned Order” hereinafter<br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>1</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> The said order arose from a petition filed by the Respondent under <br /> Section 34 of the Act seeking to set aside the arbitral award dated <br /> 3<br /> 27.11.2023 , as modified by the order dated 22.02.2024, to the limited <br /> extent of Rs. 15,90,00,000/- awarded as mesne profits from 01.07.2019 <br /> to 30.11.2023 and further till actual hand-over of possession of the land <br /> in dispute, in favour of the Appellant. <br /> <br /> <br /> <b>2.</b> <b> </b> In a nutshell, the present dispute arises out of a Collaboration <br /> 4<br /> Agreement dated 07.06.2016 between the Appellant (landowner), and <br /> the Respondent (Collaborator) for commercial development of the <br /> Appellant’s land in Gurugram. The Respondent was required to <br /> complete construction within the stipulated timelines and pay a non-<br /> refundable consideration of Rs. 5.50 crore. Due to delayed payments <br /> and failure to commence the project, the Appellant terminated the <br /> Agreement in June 2019, and subsequently invoked the arbitration <br /> clause. <br /> <br /> <b>3.</b> <b> </b> The learned Sole Arbitrator allowed Claim Nos. 1 and 2 of the <br /> Appellant, i.e., (i) handover of possession of the land in dispute and <br /> amount for actual loss of profits, (ii) costs of the proceedings, and <br /> consequently awarded a sum of Rs. 16,27,50,000 to the Appellant, <br /> while rejecting all Counter-Claims except Counter-Claim No. 4, which <br /> was partly allowed for Rs. 7,55,33,437/-. After adjustment, a net sum <br /> of Rs. 8,72,16,563/- was awarded in favour of the Appellant, along with <br /> mesne profits at the rate of Rs. 30,00,000/- per month till actual hand <br /> over of the possession of the land to the Appellant. <br /> <br /> <br /> 3<br /> “Arbitral Award” hereinafter <br /> 4<br /> “Agreement” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>2</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <br /> <b>4.</b> <b> </b> Aggrieved by the Arbitral Award, the Respondent herein filed a <br /> petition under Section 34 of the Act before this Court. <br /> <br /> <b>5.</b> <b> </b> By the Impugned Order, the learned Single Judge allowed the <br /> petition and set aside the Arbitral Award to the extent of Rs. <br /> 15,90,00,000/- towards mesne profits, holding that the quantification of <br /> loss of profit lacked evidentiary support, while granting liberty to the <br /> Appellant to pursue the Claim in accordance with law. <br /> <br /> <b>6.</b> <b> </b> The present appeal is confined to examining the correctness of <br /> the quantification of mesne profits by the learned Sole Arbitrator and <br /> the legality of the interference by the learned Single Judge. <br /> <br /> <br /> <br /> <br /> <b>Facts </b><br /> <b> </b><br /> <b> </b><br /> <b>7.</b> <b> </b> The Respondent herein claims to be a company engaged in the <br /> business of development and construction of commercial and <br /> residential properties in Gurugram, Haryana. On the other hand, the <br /> Appellant is the owner of the land located at Sector 16, Mehrauli Road, <br /> 5<br /> Gurugram . <br /> <br /> <b> </b><br /> <b>8.</b> Both the parties entered into a Collaboration Agreement dated <br /> 07.06.2016 for the commercial development of the subject land, under <br /> which the Respondent undertook to carry out construction and allied <br /> works and was obliged to pay a total consideration of Rs. 5.50 crore in <br /> instalments between June 2016 and December 2016. <br /> <br /> <b>9.</b> <b> </b> In addition to the said consideration, the Respondent was <br /> <br /> 5<br /> “subject land” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>3</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> obligated to develop and construct a building and consequently, upon <br /> completion of the project, the Respondent was entitled to a 54% share <br /> in the build-up area, along with a proportionate share in the land <br /> underneath, while the Appellant was to get 46% share. <br /> <br /> <b>10.</b> <b> </b> The scope of work and timelines are set out under Clause 11 of <br /> the Agreement. The same reads as follows: <br /> <br /></div><table><thead><tr><th>For preparation of building<br>plans for submission to<br>competent authority.</th><th>By or before the expiry of 30<br>days from the date of this<br>Agreement.</th></tr></thead><tbody><tr><td>Removal of overhead wire and<br>laying of underground wire<br>including approval from<br>competent authority.</td><td>By or before the expiry of 06<br>months from the date of this<br>Agreement.</td></tr><tr><td>Approval of building plan<br>from competent authority.</td><td>By or before the expiry of 02<br>months from the date of removal<br>of overheard wires.</td></tr><tr><td>Construction of building as<br>per approved plan and agreed<br>specifications.</td><td>By or before the expiry of 16<br>months from the date of sanction<br>of building plans or any other<br>extended period as mutually<br>agreed in writing.</td></tr><tr><td>Obtaining of completion<br>certificate & occupation<br>certificate.</td><td>By or before the expiry of 03<br>months of completion of<br>building.</td></tr></tbody></table><div><br /> <br /> 6<br /> <b>11.</b> <b> </b> It is made out from the record that a 66 kVA overhead <br /> electricity line was passing through the subject land. As per the <br /> Agreement, permission for the removal of overhead wire and laying of <br /> underground cable had already been issued by the Haryana Vidyut <br /> 7<br /> Prasaran Nigam Ltd. <i>vide</i> letter dated 31.01.2014. F or the proper <br /> construction and use of the proposed commercial building, it was <br /> <br /> 6<br /> Kilovolt-ampere <br /> 7<br /> “HVPNL” hereinafter<br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>4</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> necessary to remove the overhead wire and replace it with an <br /> underground cable. <br /> <br /> <b>12.</b> <b> </b> Adverting to the controversy, disputes arose between the parties <br /> regarding compliance with the agreed timelines. <br /> <br /> <b>13.</b> <b> </b> By October 2016, the Respondent had paid only about Rs. 1.15 <br /> crores, whereas, around Rs. 3.50 crores were due at that time as per the <br /> agreed schedule, out of the total consideration of Rs. 5.50 crores. <br /> <br /> <b>14.</b> <b> </b> According to the Appellant, this shortfall constituted a <br /> fundamental breach of the Agreement, especially since time was of the <br /> essence as per Clause 13 of the Agreement. It was further alleged that <br /> the construction schedule was not adhered to and key prerequisites for <br /> construction such as removal of the overhead transmission line and <br /> laying of the underground cable, were not completed within the <br /> stipulated timelines. Consequently, no construction activity took place <br /> on the subject land till 2017. <br /> <br /> <b>15.</b> <b> </b> In view of the continuing defaults, the Appellant issued a Notice <br /> of Breach dated 13.02.2017 alleging breach of the Agreement. The <br /> Respondent, in its reply, denied any breach and attributed delays to the <br /> Appellant’s lack of cooperation. The Appellant refuted these allegations <br /> <i>vide</i> reply dated 10.04.2017, but still granted a further grace period of <br /> 15 days to the Respondent to pay the outstanding sum of Rs. 4.35 crore. <br /> The Respondent, however, by its subsequent communication dated <br /> 29.05.2017, reiterated its earlier stand and disputed the Appellant’s <br /> entitlement to unilaterally enforce the payment schedule. <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>5</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <br /> <b>16.</b> <b> </b> Despite the earlier disputes, the parties executed an Addendum <br /> 8<br /> Agreement dated 15.11.2017 , extending the timeline for payment of <br /> Rs. 4.35 crores till 10.02.2018. So far as the schedule of construction <br /> was concerned, the substantive obligations remained the same, but the <br /> timelines for completion of those obligations were extended till <br /> 15.02.2020. <br /> <br /> <br /> <b>17.</b> <b> </b> It is not in dispute that the Respondent eventually paid the entire <br /> balance consideration of Rs. 4.35 crores, albeit belatedly, with the last <br /> payment made on 15.06.2018. <br /> <br /> <b>18.</b> <b> </b> According to the Appellant, despite payment, construction did <br /> not commence. The Respondent attributed delays to factors beyond its <br /> control, particularly the requirement for fresh approvals for the <br /> overhead transmission wire as the earlier permission dated 31.01.2014 <br /> obtained from HVPNL had become ineffective due to a change in the <br /> concerned authorities. <br /> <br /> <b>19.</b> <b> </b> As no progress was made, the Appellant repeatedly raised <br /> concerns with the Respondent. Due to lack of satisfactory response and <br /> the project remaining inchoate, the Appellant issued a Termination <br /> Notice dated 15.06.2019 and called upon the Respondent to hand over <br /> vacant and peaceful possession of the subject land. The Respondent, in <br /> its reply, disputed the validity of the termination, and refused to hand <br /> over possession. <br /> <br /> <br /> 8<br /> “Addendum Agreement” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>6</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>20.</b> <b> </b> Thus, it could be understood that the <i>lis</i> between the parties <br /> centred around the alleged breaches of the Agreement by the <br /> Respondent, particularly its failure to follow the agreed payment <br /> schedule and complete construction within the stipulated timelines. It <br /> also involved the validity of the termination of the Agreement by the <br /> Appellant and the consequences arising from it including the recovery <br /> of possession of the subject land and loss of profits. <br /> <br /> <b>21.</b> <b> </b> In view of the Respondent’s non-compliance with the <br /> Termination Notice, the Appellant invoked arbitration under Clause <br /> 21(f) of the Agreement by notice dated 04.07.2019. <br /> <br /> <b>22.</b> <b> </b> Pursuant thereto, by order dated 27.02.2020, this Court appointed <br /> Justice A.K. Sikri, Supreme Court (Retd.), as the learned Sole <br /> Arbitrator. Before the learned Arbitrator, the Appellant sought <br /> possession of the subject land along with damages for loss of profits on <br /> account of the Respondent's continued possesion. The Respondent <br /> resisted the Claims and filed a Counter-Claims seeking specific <br /> performance of the Agreement, asserting its readiness and willingness <br /> to perform, and in the alternative, sought reimbursement of expenses <br /> allegedly incurred. <br /> <b>Proceedings before the Arbitral Tribunal and Arbitral Award </b><br /> <b>23.</b> <b> </b> The Appellant raised two Claims before the learned Arbitral <br /> 9<br /> Tribunal and the Respondent raised five Counter-Claims. Upon <br /> consideration of the pleadings, evidence, and submissions, the learned <br /> <br /> 9<br /> “Tribunal” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>7</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> Tribunal allowed the Appellant’s Claims with certain modifications and <br /> rejected the Respondent’s Counter-Claims, save and except Counter-<br /> Claim No. 4, which was partly allowed. A tabulation of the same is thus: <br /> <br /></div><table><thead><tr><th>Sr. No.</th><th>Particulars</th><th>Claimed Amount<br>(Rs.)</th><th>Awarded<br>Amount<br>(Rs.)</th></tr></thead><tbody><tr><td>Claim<br>No.1</td><td>Relief for possession and<br>damages for actual loss<br>suffered by the Appellant</td><td>75.27 crore</td><td>15,90,00,000<br>along with<br>possession</td></tr><tr><td>Claim<br>No.2</td><td>Cost of proceedings</td><td></td><td>37,50,000/-</td></tr><tr><td>Counter<br>Claim<br>No.1</td><td>Claim for Specific<br>Performance and direction<br>to Appellant for<br>registration of documents</td><td></td><td>Rejected</td></tr><tr><td>Counter<br>Claim<br>No.2</td><td>Claim for loss of profits<br>suffered by the<br>Respondent during the<br>delayed period</td><td>15,40,88,479/-</td><td>Rejected</td></tr><tr><td>Counter<br>Claim<br>No.3</td><td>Cost of Arbitration</td><td></td><td>Rejected</td></tr><tr><td>Counter<br>Claim<br>No.4</td><td>Claim for Damages</td><td>9,89,85,929/-</td><td>7,55,33,437/-</td></tr><tr><td>Counter<br>Claim<br>No.5</td><td>Claim for Loss of Profit</td><td>42,80,23,552</td><td>Rejected</td></tr></tbody></table><div><br /> <br /> <b>24.</b> <b> </b> Through Claim No. 1, the Appellant sought (i) peaceful and <br /> vacant possession of the subject land, and (ii) a sum of <br /> Rs. 75,27,00,000/- towards loss of profits for four years, alleging that <br /> the Respondent induced the Appellant to execute the Agreement and <br /> the Addendum Agreement by assurances of timely payment and <br /> construction, but failed to perform its obligations, undertook no <br /> effective construction, retained possession of the land, and thereby, <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>8</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <br /> caused financial loss to the Appellant. <br /> <br /> <b>25.</b> <b> </b> Upon consideration of the material on record, the learned <br /> Tribunal noted that removal of the 66 kVA overhead transmission line <br /> was a necessary precondition for development. The learned Tribunal <br /> recorded that under Clause 11, the Respondent was obligated to <br /> complete specified developmental activities within the stipulated <br /> timelines, including preparation of building plans, removal of the <br /> overhead wire, and execution of construction. It was found that none of <br /> these milestones were achieved within the agreed timelines and that <br /> only Rs. 1.15 crore had been paid by December 2016 which is in <br /> contravention of Clause 12. <br /> <br /> <b>26.</b> <b> </b> Thereafter, the learned Tribunal examined the effect of the <br /> Addendum Agreement, whereby revised timelines were agreed. While <br /> noting that the Appellant had accepted delayed payments, it held that <br /> even the revised timelines were not adhered to. The removal of the <br /> overhead wire, which was to be completed by 15.05.2018, was in fact <br /> achieved only in 2019, and the building plans were not prepared even <br /> till the date of termination on 15.06.2019. The explanations advanced <br /> by the Respondent, including delays in regulatory approvals, were not <br /> accepted, in view of the fact that the obligation to obtain such approvals <br /> formed part of the Respondent’s contractual responsibilities, and the <br /> <br /> Respondent failed to adhere to it.<br /> <br /> <b>27.</b> <b> </b> On a cumulative assessment, the learned Tribunal held that the <br /> Respondent had failed to perform its obligations within the stipulated <br /> or even a reasonable time, with no realistic possibility of completion <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>9</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> within the extended period, i.e., by 15.02.2020. It was found that the <br /> Respondent lacked readiness and willingness to perform, and <br /> accordingly, the Termination Notice dated 15.06.2019 was upheld as <br /> valid. Therefore, the Appellant was held entitled to the recovery of <br /> possession. <br /> <br /> <b>28.</b> <b> </b> Insofar as the Claim for damages is concerned, the learned <br /> Tribunal distinguished between the pre-termination and post-<br /> termination periods. The claim for loss of profits up to the date of <br /> termination was rejected since the project had not reached a stage where <br /> profits could have been realised. Therefore, the claim for loss of profits <br /> up to 15.06.2019 was rejected. <br /> <br /> <br /> <b> </b><br /> <b>29.</b> For the period subsequent to termination, the learned Tribunal <br /> held that the Respondent’s continued possession entitled the Appellant <br /> to compensation in the nature of mesne profits. However, the learned <br /> Tribunal rejected the Appellant’s computation at Rs 2.10 crore per <br /> month, based on valuation report dated 27.05.2020 prepared by CBRE <br /> 10<br /> South Asia Pvt. Ltd. as excessive and unsupported. It was further <br /> recorded that no evidence had been led by either party to establish <br /> precise quantification. Thereafter, the learned Tribunal proceeded to <br /> determine the amount on guesswork. It accordingly awarded mesne <br /> profits at Rs 30,00,000/- per month with effect from 01.07.2019, <br /> aggregating to Rs 15,90,00,000/- up to 30.11.2023, with a direction that <br /> the same would continue at the said rate till the delivery of possession. <br /> <br /> 10<br /> “CBRE report” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>10</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> Claim No. 2, pertaining to the costs of arbitration, was partly allowed, <br /> and 50% of the costs were awarded to the Appellant. <br /> <br /> <br /> <b>30.</b> <b> </b> The Respondent raised five Counter-Claims before the learned <br /> Tribunal. Insofar as Counter-Claim No. 1, seeking specific performance <br /> of the Agreement, is concerned, the learned Tribunal, while relying <br /> upon its findings recorded in respect of Claim No. 1, held that the <br /> Respondent had failed to establish its continuous readiness and <br /> willingness to perform its contractual obligations. The learned Tribunal <br /> also noted that there were repeated defaults on the part of the <br /> Respondent. In view of the finding that the Termination notice dated <br /> 15.06.2019 was valid, the learned Tribunal held that the question of <br /> granting specific performance did not arise. Counter-Claim No. 1 was, <br /> accordingly, rejected. <br /> <br /> <b>31.</b> <b> </b> Counter-Claim No. 2, seeking registration of documents and <br /> allied reliefs, along with claims for loss of profits, was rejected since <br /> delays were attributable to the Respondent and not to the Appellant. <br /> Counter-Claim No.3, relating to the cost of Arbitration was also <br /> rejected. <br /> <br /> <b>32.</b> <b> </b> Counter-Claim No. 4 was partly allowed. The learned Tribunal <br /> permitted adjustment of the consideration amount of Rs. 5.50 crores <br /> which inured to Appellant’s benefit and allowed reimbursement for <br /> certain expenditures, including removal of the overhead transmission <br /> wire, payments made to contractors, and statutory dues such as property <br /> tax and water charges. However, the claims pertaining to expenditures <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>11</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> that were either unsubstantiated or did not result in any benefit to the <br /> Appellant were rejected. <br /> <br /> <b>33.</b> <b> </b> Counter-Claim No. 5, seeking damages towards loss of profits <br /> based on a report of M/s Colliers International (India) Property Services <br /> 11<br /> Pvt. Ltd. , estimating potential revenue, was rejected holding that no <br /> claim for loss of profits could be sustained due to lack of performance <br /> of the agreement and that delay was attributed to the Respondent. <br /> <br /> <b>34.</b> <b> </b> After adjustment, the learned Tribunal awarded Rs. 8,72,16,563/- <br /> in favour of the Appellant and against the Respondent, along with <br /> mesne profits at the rate of Rs. 30,00,000/- per month from 01.07.2019 <br /> to 30.11.2023 and further till the hand-over of possession of the subject <br /> land. <br /> <b> </b><br /> <b>Impugned Order </b><br /> <br /> <b> </b><br /> <b>35.</b> <b> </b> Aggrieved by the Arbitral Award insofar as it allowed Claim No. <br /> 1, particularly the grant of mesne profits, the Respondent filed a petition <br /> under Section 34 of the Act, contending that the quantification suffered <br /> from patent illegality, being based on no cogent evidence and mere <br /> conjecture. <br /> <br /> <b>36.</b> <b> </b> Upon examining the Arbitral Award, it was noted by the learned <br /> Single Judge that the Agreement did not provide for pre-estimated <br /> damages. It was further noted that the learned Tribunal itself <br /> categorically recorded that no evidence was led by either party to <br /> substantiate the quantum of damages, and yet proceeded to award <br /> <br /> 11<br /> “Collier Report” hereinafter <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>12</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> mesne profits at Rs. 30,00,000/- per month by resorting to guesswork, <br /> which was held to be impermissible in law. In this context, reliance was <br /> <i>12</i><br /> placed on <b><i>Airwil JKM Infracon (P) Ltd. v. Cadillac Infotech (P) Ltd.</i></b> , <br /> wherein it was held that where a claimant fails to establish damages, the <br /> Arbitral Tribunal cannot <i>suo motu</i> determine the quantum on a notional <br /> basis, as it is bound to decide in accordance with law under Section 28 <br /> of the Act and cannot resort to equitable considerations unless <br /> authorised. The learned Single Judge also considered the Appellant’s <br /> submission that damages may, in certain circumstances, be assessed on <br /> a reasonable or approximate basis, with reference to decisions such as <br /> <b><i>13</i></b><br /> <b><i>Construction & Design Services v. DDA</i></b> , <b><i>NHAI v. ITD Cementation </i></b><br /> <b><i>14</i></b> 15<br /> <b><i>India Ltd.</i></b> <b><i>, Mohd. Amin v. Mohd. Iqbal</i></b> but distinguished them on <br /> the ground that those cases had some evidentiary or contractual basis <br /> for quantification. <br /> <br /> <b>37.</b> <b> </b> Further reliance was placed on <b><i>Edifice Developers & Project </i></b><br /> <b><i>16</i></b><br /> <b><i>Engineers Ltd. v. Essar Projects (India) Ltd.</i></b> , wherein the arbitral <br /> award towards overhead losses was set aside on the ground that it lacked <br /> any basis. Accordingly, it was concluded that the grant of mesne profits <br /> at Rs. 30,00,000/- per month, aggregating to Rs. 15,90,00,000/-, was <br /> unsupported by evidence and liable to be set aside. The Arbitral Award <br /> was thus interfered with to this limited extent, while leaving it open to <br /> the Appellant to pursue its Claim in accordance with law. <br /> <b> </b> <b> </b><br /> <br /> <b>12</b><br /> <b> 2021 SCC OnLine Del 5126</b> <b> </b><br /> <b>13</b><br /> <b> (2015) 14 SCC 263 </b><br /> <b>14</b><br /> <b> 2010:DHC:404 </b><br /> <b>15</b><br /> <b> 2024 SCC OnLine Del 2395 </b><br /> <b>16</b><br /> <b> 2013 SCC OnLine Bom 5</b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>13</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>Rival Contentions Before This Court </b><br /> <b> </b><br /> <b> </b><br /> <b>38.</b> <b> </b> Mr. Jeevesh Nagrath, learned Senior Counsel appearing for the <br /> Appellant, contended that the learned Single Judge erred in setting aside <br /> the Arbitral Award insofar as it granted mesne profits, as the same did <br /> not suffer from any patent illegality. It was submitted that the learned <br /> Tribunal had, upon appreciation of the material on record, returned a <br /> categorical finding that the Respondent remained in illegal possession <br /> of the subject land from 01.07.2019, thereby depriving the Appellant of <br /> its right to commercially exploit the same and entitling it to <br /> compensation in the nature of mesne profits. In these circumstances, it <br /> was argued that, in the absence of any challenge to the finding of <br /> wrongful possession, interference with the Arbitral Award on the <br /> ground of quantification alone was unwarranted. <b> </b><br /> <b> </b><br /> <b> </b><br /> <b>39.</b> It was contended that the learned Single Judge erred in holding <br /> that the Arbitral Award was based on no evidence, as the learned <br /> Tribunal had considered expert material, including the CBRE report <br /> relied upon by the Appellant, and, upon evaluation, reduced the claim <br /> from Rs. 2.10 crore per month to Rs. 30 lakh per month, thereby <br /> adopting a reasonable approach. It was further submitted that the <br /> learned Single Judge exceeded the limited jurisdiction under Section 34 <br /> of the Act by re-appreciating evidence and substituting his own view <br /> <b><i>17</i></b><br /> on quantification. Reliance was placed on <b><i>Associate Builders v. DDA</i></b> , <b> </b><br /> to contend that interference is not warranted where the Tribunal’s view <br /> is plausible. <b> </b><br /> <br /> <br /> <b>17</b><br /> <b> (2015) 3 SCC 49 </b><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>14</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>40.</b> <b> </b> Learned Senior Counsel also pointed out that the quantification <br /> of mesne profits was, in fact, traceable to the Colliers report relied upon <br /> by the Respondent, which indicated rental values in the range of Rs. <br /> 50–80 per sq. ft. for an approximate project area of 60,000 sq. ft., <br /> yielding a potential monthly income between Rs. 30–48 lakh. Thus, it <br /> was submitted that the learned Tribunal, while adopting a figure of Rs. <br /> 30 lakhs per month, had undertaken a reasonable estimation based on <br /> such material, and it could not be characterised as a guesswork being <br /> based on no evidence so as to warrant interference. <b> </b><br /> <br /> <b>41.</b> <b> </b> Learned Senior Counsel further submitted that the learned Single <br /> Judge failed to appreciate the settled principle that in claims for <br /> damages, particularly loss of profits or mesne profits, exact <br /> mathematical precision is not required. Reliance was placed on <b><i>Cobra </i></b><br /> <b><i>Instalaciones y Servicios S.A. v. Haryana Vidyut Prasaran Nigam </i></b><br /> <b><i>18</i></b> <b><i>19</i></b><br /> <b><i>Ltd.</i></b> <b>, </b> <b><i>Bharat Heavy Electricals Ltd. v. Delkon India Pvt. Ltd.</i></b> <b>, </b><br /> <b><i>20</i></b><br /> <b><i>Construction & Design Services v. DDA</i></b> <b>, </b> <b><i>A.T. Brij Paul Singh v. </i></b><br /> <b><i>21</i></b><br /> <b><i>State of Gujarat</i></b> <b>, </b> <b><i>Hindustan Petroleum Corporation Ltd. v. </i></b><br /> <b><i>22</i></b><br /> <b><i>Mohanjit Singh (Deceased) Through Legal Heirs</i></b> <b><i>, Krishan Kumar </i></b><br /> <b>23</b> <b><i>24</i></b><br /> <b><i>v. UOI</i></b> <b> and </b> <b><i>Mohd. Salamatullah v. State of Andhra Pradesh</i></b> , to <br /> contend that where breach and resultant loss are established, but precise <br /> quantification is difficult, the Tribunal is entitled to adopt a reasonable <br /> or “rough and ready” method, including honest guesswork. It was <br /> argued that in the present case, the Respondent’s continued occupation <br /> <br /> <b>18</b><br /> <b> 2024 SCC OnLine Del 2755 </b><br /> <b>19</b><br /> <b> 2026 SCC OnLine Del 482 </b><br /> <b>20</b><br /> <b> (2015) 14 SCC 263 </b><br /> <b>21</b><br /> <b> (1984) 4 SCC 59 </b><br /> <b>22</b><br /> <b> 2019 SCC OnLine Del 9419 </b><br /> <b>23</b><br /> <b> (2015) 15 SCC 220 </b><br /> <b>24</b><br /> <b> AIR 1977 SC 1481</b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>15</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> and failure to undertake construction for several years clearly <br /> established loss, and in the absence of exact evidence, the learned <br /> Tribunal was justified in awarding reasonable compensation based on <br /> honest guesswork, warranting no interference. <b> </b><br /> <br /> <b>42.</b> <b> </b> In support of methodology for adoption of honest guesswork by <br /> the learned Arbitrator, reliance was also placed on <b><i>Ramesh Kumar Jain </i></b><br /> <b>25</b><br /> <b><i>v Bharat Aluminium Co. Ltd</i></b> <b><i>,</i></b> <b> </b> <b><i>New Okhla Industrial Development </i></b><br /> <b><i>26</i></b><br /> <b><i>Authority v. Harnand Singh</i></b> <b><i>, Gemini Bay Transcription (P) Ltd. v. </i></b><br /> <b>27</b><br /> <b><i>Integrated Sales Service Ltd.</i></b> <b><i>, </i></b> <b><i>Mahendra Singh Jaggi v. Dataram</i></b> <b><i> </i></b><br /> <b><i>28</i></b> <b><i>29</i></b><br /> <b><i>Jagnnath</i></b> <b><i>, Flovel Hydro Technologies (P) Ltd. v. Mecamidi SA</i></b> , <b><i>DDA </i></b><br /> 30<br /> and <b><i>Jaiprakash Associates Ltd. v. Ircon </i></b><br /> <b><i>v. Anand and Associates</i></b><br /> 31<br /> <b><i>International Ltd</i></b> . <br /> <br /> <b>43.</b> <b> </b> It was also contended that the Impugned Order suffers from a <br /> patent error, inasmuch as it sets aside the Arbitral Award only to the <br /> extent of the quantification of mesne profits while sustaining the <br /> remaining findings. It was argued that the Arbitral Award was rendered <br /> on a holistic basis, with mutual adjustments between the Claims and <br /> Counter-Claims. Therefore, interference with one component in <br /> isolation without disturbing the corresponding adjustments is legally <br /> unsustainable. <br /> <br /> <b> </b><br /> <b>44.</b> It was further submitted that the Appellant was denied a fair <br /> <br /> <b>25</b><br /> <b> 2025 SCC OnLine SC 2857 </b><br /> <b>26</b><br /> <b> 2024 SCC OnLine SC 1691 </b><br /> <b>27</b><br /> <b> 2022 1 SCC 753 </b><br /> <b>28</b><br /> <b> (1998) 9 SCC 28 </b><br /> <b>29</b><br /> <b> 2024 SCC OnLine Del 5039 </b><br /> <b>30</b><br /> <b> 2008 SCC OnLine Del 179 </b><br /> <b>31</b><br /> <b> 2024 SCC OnLine Del 3142</b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>16</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> opportunity to address the basis of quantification as no notice was <br /> served in the Section 34 petition, nor was any opportunity granted to <br /> seek recourse under Section 34(4) of the Act, thereby violating the <br /> principles of natural justice. The reliance on <b><i>Airwil JKM Infracon Pvt. </i></b><br /> <b><i>Ltd.</i></b> <i>(supra)</i> was also contended to be misplaced. <br /> <i> </i><br /> <b>45.</b> <b> </b> <i> Per contra, </i> Mr. Nakul Sachdeva, learned Counsel for the <br /> Respondent supported the Impugned Order, contending that the learned <br /> Single Judge rightly set aside the Arbitral Award to the limited extent <br /> of quantification of mesne profits. It was submitted that the learned <br /> Tribunal itself recorded that no evidence had been led to establish the <br /> quantum of damages, and yet proceeded to award mesne profits at Rs. <br /> 30,00,000/- per month by resorting to guesswork, which is <br /> impermissible in law. <b> </b><br /> <br /> <b>46.</b> <b> </b> It was further contended that the Appellant’s reliance on the <br /> principle of reasonable estimation is misconceived, as such estimation <br /> is permissible only where some foundational material exists to enable <br /> approximation. In the present case, the learned Tribunal had discarded <br /> the valuation reports and expert evidence and relied on no benchmark, <br /> thereby rendering the determination based on pure conjecture. It was <br /> emphasised that entitlement to compensation and its quantification are <br /> distinct, and even if wrongful possession is assumed, damages cannot <br /> be awarded in the absence of cogent evidence such as market data or <br /> reliable expert material. Reliance was placed on <b><i>P. Radhakrishna </i></b><br /> <b><i>32</i></b><br /> <b><i>Murthy v. NBCC Ltd.</i></b> <b><i>, Power Grid Corporation of India v. Ranjit </i></b><br /> <br /> <b>32</b><br /> <b> (2013) 3 SCC 747 </b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>17</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b><i>33</i></b><br /> <b><i>Singh and Co. LLP</i></b> <b><i>, Delhi Metro Rail Corporation v. Kone Elevators </i></b><br /> <b><i>34</i></b><br /> <b><i>India Pvt. Ltd.</i></b> <b><i>, Edifice Developers & Project Engineers Ltd. v. Essar </i></b><br /> <b><i>35</i></b> <b><i>36</i></b><br /> <b><i>Projects (India) Ltd.</i></b> <b><i>, BCCI v. Deccan Chronicle Holding Ltd.</i></b> <b><i>, and </i></b><br /> 37<br /> <b><i>M/s SGS India Pvt. Ltd. v. M/s Vedanta Ltd.</i></b> <b> </b><br /> <br /> <b>47.</b> <b> </b> It was also contended that the learned Tribunal acted beyond its <br /> jurisdiction in resorting to “guesswork” in the purported interest of <br /> justice, without any authorisation under Section 28(2) of the Act. In the <br /> absence of such consent, it was submitted that the learned Tribunal was <br /> bound to decide strictly in accordance with law and the evidence on <br /> record and could not invoke equitable considerations to determine the <br /> quantum. <b> </b><br /> <br /> <b>48.</b> <b> </b> Mr. Nakul Sachdeva further contended that the award of mesne <br /> profits cannot be based on conjecture or judicial assumption and must <br /> be supported by cogent evidence demonstrating actual profit that could <br /> have been earned by the Respondent. In the present case, it was <br /> submitted that in the absence of any such evidence having been <br /> accepted by the learned Tribunal, the grant of mesne profits is <br /> unsustainable in law. <b> </b><br /> <br /> <b>49.</b> <b> </b> Lastly, it was contended that the learned Single Judge had not re-<br /> appreciated the evidence but confined scrutiny to the legality of the <br /> Arbitral Award, particularly the absence of reasoning and evidentiary <br /> basis for quantification. It was further submitted that reliance on <b><i>Airwil </i></b><br /> <b><i>JKM Infracon Pvt. Ltd.</i></b> <i> (supra) </i> was not determinative, as the <br /> <br /> <b>33</b><br /> <b> O.M.P (COMM.) NO. 134 of 2023 </b><br /> <b>34</b><br /> <b> 2021 SCC Online Del 5048 </b><br /> <b>35</b><br /> <b> 2013 SCC OnLine Bom 5 </b><br /> <b>36</b><br /> <b> 2021 SCC Online Bom 834 </b><br /> <b>37</b><br /> <b> O.S.A. No. 306 of 2019</b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>18</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> impugned order rests on settled principles, and correctly identifies <br /> patent illegality warranting no interference. <b> </b><br /> <b> </b><br /> <b>Analysis </b><br /> <b> </b><br /> <b>50.</b> <b> </b> We have heard learned Counsel for both parties and have <br /> undertaken a thorough and comprehensive examination of the entire <br /> record placed before us. <b> </b><br /> <b> </b><br /> <b>51.</b> <b> </b> Before commencing, it would be apposite to remind ourselves <br /> of the limited scope and ambit of interference under Sections 34 and 37 <br /> of the Act, as consistently delineated in a line of decisions of the <br /> Supreme Court and this Court. For this purpose, we find it profitable to <br /> refer the decision in <b><i>PSA SICAL Terminals Pvt. Ltd. v. Board of </i></b><br /> <i>38</i><br /> <b><i>Trustees of V.O. Chidambranar Port Trust, Tuticorin</i></b> , wherein the <br /> Supreme Court encapsulated the scope of interference under Sections <br /> <b><i>39</i></b><br /> 34 and 37, reiterating its earlier view in <b><i>MMTC Ltd. v. Vedanta Ltd.</i></b> , <br /> in the following words: <br /> <br /> <i>“</i> <b><i>38</i></b> <i>. Before that, it will be apposite to refer to the judgment of this </i><br /> <i>Court in MMTC Ltd. [MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC </i><br /> <i>163 : (2019) 2 SCC (Civ) 293] , wherein this Court has revisited the </i><br /> <i>position of law with regard to scope of interference with an arbitral </i><br /> <i>award in India. It will be relevant to refer to the following </i><br /> <i>observations of this Court in MMTC Ltd. [MMTC Ltd. v. Vedanta </i><br /> <i>Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ) 293] : (SCC pp. 166-</i><br /> <i>67, paras 11-14) </i><br /> <i>“11. As far as Section 34 is concerned, the position is </i><br /> <i>well-settled by now that the Court does not sit in appeal </i><br /> <i>over the arbitral award and may interfere on merits on the </i><br /> <i>limited ground provided under Section 34(2)(b)(ii) i.e. if the </i><br /> <i>award is against the public policy of India. As per the legal </i><br /> <br /> <b>38</b><br /> <b> 2021 SCC OnLine SC 508 </b><br /> <b>39</b><br /> <b> (2019) 4 SCC 163</b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>19</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <i>position clarified through decisions of this Court prior to </i><br /> <i>the amendments to the 1996 Act in 2015, a violation of </i><br /> <i>Indian public policy, in turn, includes a violation of the </i><br /> <i>fundamental policy of Indian law, a violation of the interest </i><br /> <i>of India, conflict with justice or morality, and the existence </i><br /> <i>of patent illegality in the arbitral award. Additionally, the </i><br /> <i>concept of the “fundamental policy of Indian law” would </i><br /> <i>cover compliance with statutes and judicial precedents, </i><br /> <i>adopting a judicial approach, compliance with the </i><br /> <i>principles of natural justice, and Wednesbury [Associated </i><br /> <i>Provincial Picture Houses Ltd. v. Wednesbury Corpn., </i><br /> <i>(1948) 1 KB 223 (CA)] reasonableness. Furthermore, </i><br /> <i>“patent illegality” itself has been held to mean </i><br /> <i>contravention of the substantive law of India, contravention </i><br /> <i>of the 1996 Act, and contravention of the terms of the </i><br /> <i>contract. </i><br /> <i>12. It is only if one of these conditions is met that the </i><br /> <i>Court may interfere with an arbitral award in terms of </i><br /> <i>Section 34(2)(b)(ii), but such interference does not entail a </i><br /> <i>review of the merits of the dispute, and is limited to </i><br /> <i>situations where the findings of the arbitrator are arbitrary, </i><br /> <i>capricious or perverse, or when the conscience of the Court </i><br /> <i>is shocked, or when the illegality is not trivial but goes to </i><br /> <i>the root of the matter. An arbitral award may not be </i><br /> <i>interfered with if the view taken by the arbitrator is a </i><br /> <i>40</i><br /> <i>possible view based on facts.</i> <i> </i><br /> <i>13. It is relevant to note that after the 2015 Amendment </i><br /> <i>to Section 34, the above position stands somewhat modified. </i><br /> <i>Pursuant to the insertion of Explanation 1 to Section 34(2), </i><br /> <i>the scope of contravention of Indian public policy has been </i><br /> <i>modified to the extent that it now means fraud or corruption </i><br /> <i>in the making of the award, violation of Section 75 or </i><br /> <i>Section 81 of the Act, contravention of the fundamental </i><br /> <i>policy of Indian law, and conflict with the most basic </i><br /> <i>notions of justice or morality. Additionally, sub-section (2-</i><br /> <i>A) has been inserted in Section 34, which provides that in </i><br /> <i>case of domestic arbitrations, violation of Indian public </i><br /> <i>policy also includes patent illegality appearing on the face </i><br /> <i>of the award. The proviso to the same states that an award </i><br /> <i>shall not be set aside merely on the ground of an erroneous </i><br /> <i>application of the law or by reappreciation of evidence. </i><br /> <i>14. As far as interference with an order made under </i><br /> <i>Section 34, as per Section 37, is concerned, it cannot be </i><br /> <br /> <b>40</b><br /> <b> (See </b> <b><i>Associate Builders</i></b> <b> v. </b> <b><i>DDA</i></b> <b> [</b> <b><i>Associate Builders</i></b> <b> v. </b> <b><i>DDA</i></b> <b>, (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] </b><br /> <b>. Also see </b> <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Saw Pipes Ltd.</i></b> <b> [</b> <b><i>ONGC Ltd.</i></b> <b> v. </b> <b><i>Saw Pipes Ltd.</i></b> <b>, (2003) 5 SCC 705] ; </b> <b><i>Hindustan </i></b><br /> <b><i>Zinc Ltd.</i></b> <b> v. </b> <b><i>Friends CoalCarbonisation</i></b> <b> [</b> <b><i>Hindustan Zinc Ltd.</i></b> <b> v. </b> <b><i>Friends Coal Carbonisation</i></b> <b>, (2006) 4 </b><br /> <b>SCC 445] ; and </b> <b><i>McDermott International Inc.</i></b> <b> v. </b> <b><i>Burn Standard Co. Ltd.</i></b> <b> [</b> <b><i>McDermott International </i></b><br /> <b><i>Inc.</i></b> <b> v. </b> <b><i>Burn Standard Co. Ltd.</i></b> <b>, (2006) 11 SCC 181] ) </b><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>20</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /></div><table><thead><tr><th></th><th>disputed that such interference under Section 37 cannot</th><th></th></tr></thead><tbody><tr><td></td><td>travel beyond the restrictions laid down under Section 34.</td><td></td></tr><tr><td></td><td>In other words, the court cannot undertake an independent</td><td></td></tr><tr><td></td><td>assessment of the merits of the award, and must only</td><td></td></tr><tr><td></td><td>ascertain that the exercise of power by the court under</td><td></td></tr><tr><td></td><td>Section 34 has not exceeded the scope of the provision.</td><td></td></tr><tr><td></td><td>Thus, it is evident that in case an arbitral award has been</td><td></td></tr><tr><td></td><td>confirmed by the court under Section 34 and by the court in</td><td></td></tr><tr><td></td><td>an appeal under Section 37, this Court must be extremely</td><td></td></tr><tr><td></td><td>cautious and slow to disturb such concurrent findings.”</td><td></td></tr><tr><td></td><td></td><td></td></tr></tbody></table><div><br /> <b>52.</b> <b> </b> Recently, this Court, speaking through one of us (Om Prakash <br /> Shukla, J.) in <b><i>M/s JSW Ispat Steel Limited (now known as JSW Steel </i></b><br /> <b><i>41</i></b><br /> <b><i>Limited) v. M/s Gas Authority of India Limited</i></b> , while referring to <br /> <b><i>42</i></b><br /> <b><i>Jan De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust</i></b> <b> </b> and <b> </b> <b><i>M/s </i></b><br /> <b><i>Larsen Air Conditioning and Refrigeration Company v. Union of </i></b><br /> <b><i>43</i></b><br /> <b><i>India & Ors.</i></b> , reiterated that the scope of judicial review under <br /> Sections 34 and 37 of the Act is extremely limited, and powers of a <br /> court under Section 37 are circumscribed and extend only to examining <br /> whether the Section 34 Court has acted within its jurisdiction. It was <br /> further reiterated that the appellate court cannot re-appreciate the <br /> evidence or substitute its own view merely because another <br /> interpretation is possible. An interference is permissible only on <br /> grounds, such as patent illegality, or violation of public policy, and only <br /> where such infirmity goes to the root of the matter. <b> </b><br /> <b> </b><br /> <b>53.</b> <b> </b> Keeping the aforesaid principles in mind, we proceed to deal with <br /> the controversy in the present appeal. <b> </b><br /> <br /> <b>54.</b> <b> </b> It is not in dispute that the Respondent breached the Agreement <br /> <br /> <b>41</b><br /> <b> DHC:1922-DB </b><br /> <b>42</b><br /> <b> (2026) 3 SCC 186</b> <br /> <b>43</b><br /> <b> (2023) 15 SCC 472 </b><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>21</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> by failing to adhere to the timelines stipulated under Clause 11 and the <br /> extended timelines under the Addendum. In view thereof, the Appellant <br /> issued a Termination Notice dated 15.06.2019, and the validity of the <br /> said notice was upheld by the learned Tribunal. The learned Tribunal <br /> further held that upon termination, the Respondent was required to hand <br /> over possession within a reasonable time, and its continued occupation <br /> of the subject land beyond such period would entitle the Appellant to <br /> mesne profits, which were quantified at Rs. 30,00,000/- per month from <br /> 01.07.2019 till actual hand over of the possession. <b> </b><br /> <br /> <b>55.</b> <b> </b> The learned Counsel for the Respondent contended that the <br /> award of mesne profits was unsustainable in the absence of evidence <br /> establishing the actual profit derived by the Respondent from its <br /> continued possession, which, according to the Respondent, is a <br /> prerequisite for the grant of mesne profits. <b> </b><br /> <br /> <b>56.</b> <b> </b> It is pertinent to note that the learned Single Judge interfered with <br /> the Arbitral Award only to the limited extent of quantification on the <br /> ground of lack of evidentiary support. Accordingly, our consideration <br /> under Section 37 is confined to examining whether the setting aside of <br /> mesne profits quantified at Rs. 30,00,000/- per month for want of any <br /> evidentiary foundation or reasoning was justified or not. The <br /> Appellant's entitlement to mesne profits, including whether the <br /> Respondent derived actual profit from its continued possession, does <br /> not arise for our consideration in this appeal. <b> </b><br /> <br /> <b>57.</b> <b> </b> The primary reason that weighed with the learned Single Judge <br /> in setting aside the Arbitral Award to the extent of Rs. 15,90,00,000/- <br /> was that the said figure had been arrived at without any evidentiary <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>22</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> basis and without even a semblance of reasoning. The relevant portion <br /> of the Impugned Order is reproduced below: <b> </b><br /> <b> </b><br /> “ <b>21.</b> In the present case also, the learned Arbitrator passed the <br /> award on the basis of stating that, “Unfortunately, no evidence is led <br /> in this behalf by either party and therefore, there is no other <br /> alternative for the Arbitral Tribunal but to award some amount by <br /> making some guesswork.” It is a matter of the fact as recorded in the <br /> impugned award also that the claimant had not produced any <br /> evidence in support to his claim. It is also pertinent to mention here <br /> that learned Arbitrator has not passed an award stating that the figure <br /> has been taken on the basis of the evidence of the respondent. The <br /> perusal of the impugned award indicates that the learned tribunal <br /> awarded the mesne profits @ Rs.30lakhs per month. However, not <br /> even a single reasoning has been given for reaching on this amount. <br /> This court is conscious of the fact that in exercise of jurisdiction <br /> under Section 34 of the Arbitration and Conciliation Act, this court <br /> cannot sit in appeal over the findings of the learned tribunal but at <br /> the same time, within the limited power conferred by the legislation, <br /> the court is required to see whether there is even an iota of reasoning <br /> for reaching the award. Hence, in the circumstances and in view of <br /> there being no evidence to the same, the impugned award to the <br /> extent of grant of Rs.15,90,00,000/- is set aside.” <i> </i><br /> (emphasis supplied) <br /> <i> </i><br /> <i> </i><br /> <b>58.</b> <b> </b> The learned Senior Counsel for the Appellant sought to assail <br /> the aforesaid finding by contending that the quantification of mesne <br /> profits by the learned Tribunal was not arbitrary, but based on honest <br /> guesswork after duly considering the facts and circumstances of the <br /> case. It was argued that such an approach is legally sustainable where <br /> loss is established but precise quantification is not possible. In this <br /> context, it becomes apposite to examine the reasoning adopted by the <br /> learned Tribunal: <br /> <br /> “ <b>142.</b> While coming to this conclusion, the Tribunal also finds <br /> force in the submission of the Respondent that the Claimant has not <br /> been able to substantiate this claim. Had the Respondent completed <br /> the Project, it would have got 54% share therein. Now, with the <br /> termination of the is Contract, the Claimant is in a more <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>23</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> advantageous position as it not required io part with the said share. <br /> The Claimant is, therefore, is in a better position than it would have <br /> been in the event the terms of the Contract had been performed. <br /> There is another aspect highlighted by the Respondent which cannot <br /> be ignored. Even as per the Valuation Report relied upon by the <br /> Claimant, the revenue potential of the Subject Land, after all <br /> construction is presumed ta be completed, was to be INR 120.00 <br /> crore. The Claimant has admitted that the Claimant would only be <br /> entitled to INR 55.00 crore of the aforesaid alleged amount of INR <br /> 120.00 crore had the contract been performed and not terminated. <br /> While the Respondent categorically denies the valuation report <br /> relied upon by the Claimant and all of its findings, if the same is <br /> accepted on a demurrer, the market value of the subject land as on <br /> date is stated to be INR 57.00 crore as per the same, and in the event <br /> the Claimant manages to somehow wriggle out of the Agreement, <br /> he can benefit out of 100% of the sale proceeds. This further <br /> establishes that even as per the best case of the Claimant, the <br /> Claimant has incurred an losses whatsoever. The Tribunal, therefore, <br /> rejects the claim for the period up to 15.06.2019. <br /> <br /> <b>143.</b> The Claimant has, however, also raised the claim for the <br /> period from 01.06.2020 as well till the date of actual hand-over of <br /> the Project land by the Respondent to the Claimant. preferred @ INR <br /> 2.10 crore. It may be claimed that in the Termination Notice dated <br /> 15.06.2019, the Claimant had asked for re-possession of the land of <br /> which the Claimant is the owner. The Respondent, refused to do so <br /> forcing the Claimant to initiate the present arbitration proceeding <br /> where the claim for handing over the possession of land is also made. <br /> The same has been allowed. Since this demand was made in the <br /> Termination Notice and is found to be justified, the Respondent was <br /> supposed to handover the possession within a reasonable period. The <br /> Claimant would be entitled to the loss on this account for the <br /> subsequent period. Giving an allowance of 15 (fifteen) days within <br /> which possession should have been handed over by the Respondent, <br /> the Claimant would be entitled to damages w.e.f. 01.07.2019. INR <br /> 2.10 crore per month. The Claimant has calculated losses @ INR <br /> 2.10 crore per month. For this purpose, the Claimant has produced <br /> Mr. Pankaj Tekchandani (CW-2) who has given his report about the <br /> land in question and its commercial prospects. As against that, the <br /> Respondent has produced Mr. Amit Chawla, RW-2 who has also <br /> deposed about the commercial viability of the property including its <br /> location, etc. Going by the considerations of location of the property, <br /> the fact that even the Claimant could not develop this property from <br /> 2006 to 2014 and ultimately, handed over the same to the <br /> Respondent for development, its marketability and other such <br /> considerations, the Tribunal is of the view that calculations of loss <br /> made by the Claimant for loss @ INR 2.10 crore per month is not <br /> justifiable. <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>24</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <br /> <b>144.</b> As already mentioned above, the Respondent has disputed <br /> the validity of the valuation report (CBRE report) relied upon by the <br /> Claimant. The Respondent has made detailed submissions during <br /> arguments and also in the closing written submissions. The <br /> Respondent has also referred to various questions put to CW-2 and <br /> reply given to those questions. It may not be necessary to produce <br /> the entire discussion in this behalf. It is sufficient to mention that <br /> calculation of INR 2.10 crore per month made in the manner in the <br /> said report and relied upon by the Claimant cannot be accepted. At <br /> the same time, the claim for the period in question cannot be rejected <br /> in toto as the Claimant would be entitled to some claim because of <br /> illegal occupation of the Project land by the Respondent even after <br /> the termination of the Agreements. <b>Unfortunately, no evidence is </b><br /> <b>led in this behalf by either party and therefore, there is no other </b><br /> <b>alternative for the Arbitral Tribunal but to award some amount </b><br /> <b>by making some guesswork. </b><br /> <b> </b><br /> <b>145.</b> Taking into consideration all the relevant facts and <br /> circumstances of the case, in the opinion of the Tribunal, interest of <br /> justice would be subserved in granting mesne profit for withholding <br /> the possession beyond 01.07.2019 @ INR 30.00 lakh per month <br /> from 01.07.2019 which would come to four years and five months <br /> i.e., 30.00 lakh X 53 = to 15,90,00,000/- till 30.11.2013. The <br /> Claimant shall also be entitled mesne profits at this rate with effect <br /> from 01.12.2023 till the possession of the land is handed over to it.” <br /> <br /> (emphasis supplied) <br /> <br /> <b>59.</b> <b> </b> Upon a plain reading, it is clear that while the learned Tribunal <br /> acknowledged the absence of evidence on both sides, it nonetheless <br /> proceeded to quantify mesne profits at Rs. 30,00,000/- per month on the <br /> basis of guesswork. <br /> <br /> <b>60.</b> <b> </b> Thus, in order to assess whether the reliance on guesswork by the <br /> Arbitrator finding is permissible and consistent with applicable law, it <br /> is necessary to understand the scope of “guesswork” in the context of <br /> arbitral awards. <br /> <br /> <b>61.</b> <b> </b> This Court is aware that reliance on a “rough and ready” estimate <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>25</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> or guesswork is not alien to arbitral jurisprudence and has received <br /> recognition from the Supreme Court as well as this Court. <br /> <b><i> </i></b><br /> <b>62.</b> <b> </b> <b><i> </i></b> In <b><i>DDA v. Anand and Associates</i></b> <b><i>(supra)</i></b> <b>,</b> the methodology of <br /> adopting some degree of guesswork was affirmed. The relevant <br /> observations are as follows: <br /> <br /> “ <b>6.</b> …It is true that while awarding a sum of Rs. 1,91,659/- <br /> towards increase in the labour charges and Rs. 3,50,000/- on account <br /> of the increase in the price of materials, the arbitrator has observed <br /> that no books of accounts had been produced before him and that he <br /> has determined the amount from whatever is available on record yet <br /> interference with that part of the award would also not be justified <br /> in view of the settled legal positions that the court would not set <br /> aside an award simply because it was to an extent based upon some <br /> guesswork. Reference may in this regard be made to Mohd. <br /> Salamatullah and Ors. v. Government of Andhra Pradesh 1977 SC <br /> 1481 where the court has observed:— <br /> “We are not able to discern any tangible material on the <br /> strength of which the High Court reduced the damages from <br /> 15% of the contract price to 10% of the contract price. If the <br /> first was a guess, it was at least a better guess than the <br /> second one. We see no justification for the appellate court <br /> to interfere with a finding of fact given by the trial Court <br /> unless some reason, based on some fact, is traceable on the <br /> record. There being none we are constrained to set aside the <br /> judgment of the High Court in regard to the assessment of <br /> damages for breach of contract.” <br /> (emphasis supplied) <br /> <i> </i><br /> <i> </i><br /> <b>63.</b> <b> </b> Similarly, a Division Bench of this Court in <b><i>Cobra Instalaciones </i></b><br /> <b><i>Y Servicios, S.A. (supra)</i></b> , while considering <b><i>Construction Design </i></b><br /> <b><i>(supra)</i></b> , observed that such a method is a permissible tool available to <br /> an arbitrator, particularly in a situation where material exists to show <br /> that loss has been suffered, but does not furnish granular details for <br /> precise quantification. <br /> <br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>26</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>64.</b> <b> </b> More recently, another Division bench of this Court in <b><i>Bharat </i></b><br /> <b><i>Heavy Electricals Ltd. (supra)</i></b> taking into account <b><i>Cobra </i></b><br /> <b><i>Instalaciones Y Servicios (supra), </i></b> affirmed the adoption of honest <br /> guesswork in the following terms: <br /> <br /> <b>35.</b> In our opinion, there may be three situations. First, there is <br /> no evidence of any loss to a party raising a claim. In such situation <br /> arbitrator cannot presume any loss and award compensation. <br /> Second, where there is evidence of loss as well as evidence on <br /> quantum of damages. This would be an ideal situation in awarding <br /> damages and compensation. Third is the situation where there is <br /> evidence of loss but either there is meager evidence or absence of <br /> evidence in support of claim of damages. In such situation the <br /> arbitrator can use rough and ready method by using a practical guess <br /> work to determine the damages and compensation. But such <br /> compensation should be reasonable in the sense that in given <br /> situation no man of prudence would call it excessive. The third <br /> situation occurs in the present case and therefore, while exercising <br /> very limited jurisdiction under Section 37, we have only to see as to <br /> whether the damages/compensation awarded to Delkon is <br /> reasonable or not. <br /> <b><i></i></b><i></i> <br /> <b>39.</b> The counter claim no. 3 is towards cost of pre assembly and <br /> part wielding completed. The Arbitrator had relied upon the report <br /> of Local Commissioner and awarded lesser amount of interest at the <br /> rate of 12% (against 15% as per clause 57.3 (1) (A) (i) of the <br /> contract) of the contract rate as appropriate and reasonable and held <br /> that value for 12.908 MT works out to Rs. 4182/-. In appeal the <br /> appellant submits that clause 57.2 (1A)(i) does not deal with the <br /> breakup of the cost but instead pertains to the payment milestone. <br /> Again in our considered view, even if the aforesaid clause is <br /> misapplied, the awarded amount of Rs. 4182/- is so meager that it <br /> has to be accepted as the cost of pre assembly and part wielding <br /> completed. <br /> <b><i></i></b><i></i> <br /> <b>46.</b> The argument of learned Counsel for the appellant is that <br /> there is no evidence on record to show that value of T&P was Rs. 40 <br /> lakhs. Further, no evidence has been led to prove respondent's claim <br /> on damages. Learned counsel for the appellant assailed the method <br /> adopted by the Arbitrator for calculating withholding charges. <br /> <b><i></i></b>* <br /> <b>50.</b> After perusing the material available on record, we are of the <br /> opinion that in respect of the heavy machinery, the Arbitrator has <br /> reached to a plausible conclusion that the value of the withheld <br /> machinery would be about Rs. 40,00,000/- and the depreciation <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>27</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> value to be Rs. 10,00,000/-. We concur with the learned District <br /> Judge on Arbitrator's finding on the computation of 210 days and the <br /> methodology adopted for awarding Rs. 5,75,342/- to the respondent <br /> on account of the appellant's illegal withholding of T&P. In other <br /> words the Arbitrator had some basis for calculating withholding <br /> charges of Rs. 5,75,342/-, which is not at all unreasonable if we <br /> consider the nature of T&P which included heavy <br /> equipments/machinery including two Cranes, one Tractor, two <br /> Trailors and one Metador Pickup Van etc. and the duration of 210 <br /> days for which the same were withheld. Hence, we agree with the <br /> view of Arbitrator and learned District Judge on contract clause no. <br /> 7 being reasonable and uphold the same. <br /> COUNTER CLAIM NO. 13 AND 15 <br /> <br /> <b>51.</b> The respondent-Delkon had raised these counter claims <br /> towards cost of mobilization and demobilization of T&P, equipment <br /> and manpower. The appellant has drawn our attention to the <br /> observation of Arbitrator that Delkon has not submitted any <br /> documents for actual expenses incurred by them in mobilization and <br /> demobilization. Therefore, awarding a sum of Rs. 10,52,800/- is <br /> based upon mere surmises and conjectures. <br /> <br /> <b><i></i></b><i></i> <br /> <b>53.</b> We are of the opinion that even if no documents were <br /> furnished by respondent-Delkon before the Arbitrator, the <br /> conclusion of the Arbitrator has been arrived at on “the analysis of <br /> unit rates”, which is Annexure -E to Tender No. BHEL: <br /> NR(SCT):RGTTP:BLR:42. This Annexure - E forms the part of the <br /> contract No. 50/96 between the parties. This finding of Arbitrator, <br /> about 65% of the overheads having been consumed in mobilization <br /> and demobilization, is a finding on fact and therefore we are not <br /> inclined to go deeper into it especially when it is based upon Local <br /> Commissioner's report. The Arbitrator has calculated these charges <br /> on the basis of Annexure - E. Therefore, even if no documents were <br /> filed by Delkon to prove expenditure of this overhead, the <br /> calculation by learned Arbitrator is reasonable and justified. <br /> <br /> <b>54. </b> Learned District Judge observed that the award of amount <br /> of Rs. 10,52,800/- towards mobilization and demobilization costs <br /> cannot be held to be without reasons or material evidence on record <br /> <b>and held that as long as there is sufficient material available on </b><br /> <b>record on the basis of which an estimation of loss/expenses/costs </b><br /> <b>incurred can be drawn, an award of that estimate can be </b><br /> <b>granted. We are of the opinion that view of learned District </b><br /> <b>Judge is correct on this issue especially when the Arbitrator had </b><br /> <b>based his estimation on the basis of Local Commissioner's report </b><br /> <b>and “analysis of unit rates” which is part of the contract</b> . The <br /> Arbitrator adopted a rough and ready method with reasonable and <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>28</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> honest guess work on this issue. Consequently, we find no infirmity <br /> in the impugned award and the impugned judgment on this issue. <br /> <br /> (emphasis supplied) <br /> <br /> <br /> <b>65.</b> <b> </b> An analysis of the above-mentioned precedents indicates that, <br /> although the adoption of a “rough and ready” method or honest <br /> guesswork has been judicially recognised, the same is not unguided. <br /> <br /> <b>66.</b> <b> </b> The decision of the Division Bench in <b><i>Cobra Instalaciones y </i></b><br /> <b><i>Servicios S.A</i></b> <i>. </i> <b><i>(supra)</i></b> clarifies that such latitude is available in a <br /> situation where there is material on record to establish that loss has <br /> indeed been suffered, but the evidence falls short of providing precise <br /> quantification. We note that the above principle stands further <br /> elucidated in <b><i>Bharat Heavy Electricals Ltd. (supra)</i></b> <b> </b> in context of <br /> unliquidated damages, where this Court upheld the award of damages <br /> not merely because guesswork was employed, but because such <br /> determination was founded upon a discernible and rational <br /> methodology traceable to the material on record. <br /> <br /> <b>67.</b> <b> </b> In <b><i>Bharat Heavy Electricals Ltd. (supra)</i></b> , the Court was dealing <br /> with multiple claims where the Arbitrator had awarded compensation <br /> despite absence of strict proof of expenditure under certain heads. <br /> However, in our considered view, what weighed with the Court while <br /> assessing reasonability was that, in each such instance, the Arbitrator <br /> had relied upon some identifiable material such as contractual clauses, <br /> reports of the Local Commissioner, admitted quantities, or standard <br /> rates and had applied a rational method of computation. Most <br /> significantly, while upholding the award relating to claim for <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>29</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> withholding of machinery, the Court expressly noted that <i>“the </i><br /> <i>Arbitrator had some basis for calculating… which is not at all </i><br /> <i>unreasonable”</i> . It shows that the existence of a foundational basis, <br /> however limited, is a <i>sine qua non</i> for sustaining such quantification. <br /> <br /> <b>68.</b> <b> </b> The same principle is echoed in <b><i>DDA v. Anand and Associates </i></b><br /> <b><i>(supra)</i></b> , where the Court declined to interfere with an award partly <br /> based on guesswork, as the arbitrator had determined the amount “ <i>from </i><br /> <i>whatever is available on record</i> ”. It thus emerges to us that while <br /> exactitude in proof of damages is not insisted upon, the adjudicatory <br /> process must nevertheless disclose a rational nexus between the <br /> material available and the figure ultimately awarded or atleast some line <br /> of reasoning in mind of the learned Arbitrator to justify the reasonability <br /> of the figure. <br /> <br /> <b>69.</b> <b> </b> This approach also emerges from <b><i>Gemini Bay Transcription (P) </i></b><br /> <b><i>Ltd.</i></b> <b> </b> <b><i>(supra)</i></b> , wherein, although the guesswork method was allowed, it <br /> was also noted that the Arbitrator had made assessment taking into <br /> account some material on record. The relevant observations are as <br /> follows: <br /> <br /></div><table><thead><tr><th>“77. The arbitrator correctly held that as nothing was forthcoming</th><th></th></tr></thead><tbody><tr><td>from any of the appellants, he would have to make a best judgment</td><td></td></tr><tr><td>assessment for damages. In making that assessment, he took into</td><td></td></tr><tr><td>account the commission that was being earned by GBT from the two</td><td></td></tr><tr><td>clients of DMC and arrived at a figure of 100,000 USD per month</td><td></td></tr><tr><td>and then found, on a reasonable estimate, that they would continue</td><td></td></tr><tr><td>to be clients for a period of four years, as a result of which the figure</td><td></td></tr><tr><td>of 6,948,100 USD was reached.</td><td></td></tr></tbody></table><div><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>30</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /></div><table><thead><tr><th>reported as Frederick Thomas Kingsley v. Secy, of State for India</th><th></th><th></th></tr></thead><tbody><tr><td>AIR 1923 Cal 49</td><td>…”</td><td></td></tr></tbody></table><div><br /> (emphasis supplied) <br /> <br /> <br /> <b>70.</b> <b> </b> Thus, what the law countenances is not guesswork in <i>vacuo</i> , but <br /> a reasoned approximation founded on some material, some method, or <br /> at the very least, a discernible line of reasoning. <br /> <br /> <b>71.</b> <b> </b> In the present case, the learned Tribunal rejected the CBRE <br /> Report, holding it to be unreliable and proceeded on the premise that <br /> since no evidence was led by either party for quantification of damages, <br /> mesne profits could be discerned by way of guesswork. The Arbitral <br /> Award, however, discloses no discussion or reasoning for arriving at <br /> the figure of Rs. 30,00,000/- per month. <br /> <br /> <b>72.</b> <b> </b> On behalf of the Appellant, Mr. Nagrath suggested that the said <br /> figure is traceable to the material on record by relying on the Colliers <br /> Report furnished by the Respondent. However, it does not merit our <br /> acceptance. <br /> <br /> <b>73.</b> <b> </b> As per the Appellant, Colliers Report indicates rental values of <br /> Rs. 50–80 per sq. ft. for an approximate built-up area of 60,000 sq. ft., <br /> yielding a possible range of Rs. 30–48 lakh per month. However, the <br /> Arbitral Award neither records reliance on this Report nor adopts such <br /> a methodology. An Award must stand or fall on the reasons contained <br /> therein, and it is impermissible for a party to supplement or reconstruct <br /> the reasoning by reference to material not relied upon by the learned <br /> Tribunal. Even otherwise, there are multiple outcomes possible based <br /> on Colliers Report, and in the absence of any reasoning by the learned <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>31</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> Arbitrator linking the material to the figure awarded, the quantification <br /> cannot be sustained. Moreover, it is settled law that the Arbitrator is the <br /> master of facts and evidence. Once the learned Arbitrator itself recorded <br /> that no evidence had been led by either party, it necessarily follows that <br /> the quantification was not based on any material such as the Colliers <br /> Report. In such circumstances, this Court cannot attribute a basis to the <br /> Arbitral Award which the learned Tribunal itself has not disclosed, nor <br /> can it hold that the figure is traceable to the record when the learned <br /> Tribunal has expressly found otherwise. <br /> <br /> <b>74.</b> <b> </b> It is no doubt true that in cases of unliquidated damages, <br /> particularly those arising from wrongful retention of property, some <br /> degree of estimation is inevitable. However, such estimation must be <br /> reasoned and based on a discernible foundation. In the present case, the <br /> Arbitral Award proceeds merely on the premise that the Appellant is <br /> entitled to compensation on account of wrongful possession of the <br /> subject land by the Respondent, without any analysis of the extent of <br /> loss or any indication of the basis of computation. The absence of such <br /> reasoning renders the determination unsustainable in law. <br /> <br /> <b>75.</b> <b> </b> The Supreme Court has consistently emphasised that the latitude <br /> available for ‘honest guesswork’ does not dispense with the <br /> requirement of a reasoned determination. In <b><i>New Okhla Industrial </i></b><br /> <b><i>Development Authority (supra)</i></b> <i>, </i> the Supreme Court clarified that while <br /> some degree of estimation or “guesstimation” is permissible in <br /> determining compensation, the exercise cannot be speculative or purely <br /> subjective. The discretion to adopt guesswork is not unfettered and must <br /> have a nexus with the material on record and other relevant factors. It <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>32</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> was observed as follows: <br /> <br /></div><table><thead><tr><th>34. Accordingly, while the Court can use the principle of<br>guesstimation in reasonably estimating the value of land in the<br>absence of direct evidence, the exercise ought not to be purely<br>hypothetical. Instead, the Court must embrace a holistic view and<br>consider all relevant factors and existing evidence, even if not<br>directly comparable, to arrive at a fair determination of<br>compensation. Trishala Jain v. State of Uttaranchal,9 summarizes<br>these yardsticks as follows:<br>“65. It will be appropriate for us to state certain<br>principles controlling the application of “guesstimate”:<br>(a) Wherever the evidence produced by the parties is not<br>sufficient to determine the compensation with exactitude,<br>this principle can be resorted to.<br>(b) Discretion of the court in applying guesswork to the facts of<br>a given case is not unfettered but has to be reasonable and<br>should have a connection to the data on record produced<br>by the parties by way of evidence. Further, this entire<br>exercise has to be within the limitations specified under<br>Sections 23 and 24 of the Act and cannot be made in<br>detriment thereto.”</th><th>34. Accordingly, while the Court can use the principle of</th><th></th><th></th></tr></thead><tbody><tr><td></td><td>guesstimation in reasonably estimating the value of land in the</td><td></td><td></td></tr><tr><td></td><td>absence of direct evidence, the exercise ought not to be purely</td><td></td><td></td></tr><tr><td></td><td>hypothetical. Instead, the Court must embrace a holistic view and</td><td></td><td></td></tr><tr><td></td><td>consider all relevant factors and existing evidence, even if not</td><td></td><td></td></tr><tr><td></td><td>directly comparable, to arrive at a fair determination of</td><td></td><td></td></tr><tr><td></td><td>compensation. Trishala Jain v. State of Uttaranchal,9 summarizes</td><td></td><td></td></tr><tr><td></td><td>these yardsticks as follows:</td><td></td><td></td></tr><tr><td></td><td></td><td></td><td></td></tr><tr><td></td><td></td><td>“65. It will be appropriate for us to state certain</td><td></td></tr><tr><td></td><td></td><td>principles controlling the application of “guesstimate”:</td><td></td></tr><tr><td></td><td>(a) Wherever the evidence produced by the parties is not</td><td></td><td></td></tr><tr><td></td><td>sufficient to determine the compensation with exactitude,</td><td></td><td></td></tr><tr><td></td><td>this principle can be resorted to.</td><td></td><td></td></tr><tr><td></td><td>(b) Discretion of the court in applying guesswork to the facts of</td><td></td><td></td></tr><tr><td></td><td>a given case is not unfettered but has to be reasonable and</td><td></td><td></td></tr><tr><td></td><td>should have a connection to the data on record produced</td><td></td><td></td></tr><tr><td></td><td>by the parties by way of evidence. Further, this entire</td><td></td><td></td></tr><tr><td></td><td>exercise has to be within the limitations specified under</td><td></td><td></td></tr><tr><td></td><td>Sections 23 and 24 of the Act and cannot be made in</td><td></td><td></td></tr><tr><td></td><td>detriment thereto.”</td><td></td><td></td></tr><tr><td>(emphasis supplied)</td><td></td><td></td><td></td></tr><tr><td></td><td></td><td></td><td></td></tr></tbody></table><div><br /> <b>76.</b> <b> </b> Similarly, in <b><i>Ramesh Kumar Jain (supra)</i></b> , the guesswork by the <br /> arbitrator was upheld since it was based on taking into account some <br /> evidence. In <b><i>Ramesh Kumar Jain</i></b> <b><i>(supra)</i></b> , it was also held that an <br /> Arbitral Award may be interfered with if it is based on “no evidence” <br /> because an arbitrator cannot conjure findings out of thin air. The <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>33</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <br /> relevant excerpt is thus: <br /> <br /> <i>“</i> <b><i>35.</i></b> <i> </i> <i> Considering the aforesaid precedents, in our considered </i><br /> <i>view, the said terminology of ‘patent illegality’ indicates more than </i><br /> <i>one scenario such as the findings of the arbitrator must shock the </i><br /> <i>judicial conscience or the arbitrator took into account matters he </i><br /> <i>shouldn't have, or he must have failed to take into account vital </i><br /> <i>matters, leading to an unjust result; or the decision is so irrational </i><br /> <i>that no fair or sensible person would have arrived at it given the </i><br /> <i>same facts. A classic example for the same is when an award is based </i><br /> <i>on “no evidence” i.e., arbitrators cannot conjure figures or facts out </i><br /> <i>of thin air to arrive at his findings. If a crucial finding is unsupported </i><br /> <i>by any evidence or is a result of ignoring vital evidence that was </i><br /> <i>placed before the arbitrator, it may be a ground the warrants </i><br /> <i>interference. However, the said parameter must be applied with </i><br /> <i>caution by keeping in mind that “no evidence” means truly no </i><br /> <i>relevant evidence, not scant or weak evidence. If there is some </i><br /> <i>evidence, even a single witness's testimony or a set of documents, on </i><br /> <i>which the arbitrator could rely upon or has relied upon to arrive at </i><br /> <i>his conclusions, the court cannot regard the conclusion drawn by </i><br /> <i>the arbitrator as patently illegal merely because that evidence has </i><br /> <i>less probative value. This thin line is stood crossed only when the </i><br /> <i>arbitral tribunal's conclusion cannot be reconciled with any </i><br /> <i>permissible view of the evidence.” </i><br /> (emphasis supplied) <br /> <i> </i><br /> <i> </i><br /> <b>77.</b> <b> </b> The Appellant also contended that the Arbitral Award must be <br /> read in its entirety and not by isolating a particular paragraph, and that <br /> the quantification must be understood in the context of the overall <br /> <br /> findings recorded by the learned Tribunal. <br /> <br /> <b>78.</b> <b> </b> We have, accordingly, perused the Arbitral Award as a whole. <br /> While the learned Tribunal has furnished reasons in respect of the <br /> breach and the validity of termination, it is conspicuously silent on the <br /> aspect of quantification of mesne profits. There is no discussion of <br /> material or any discernible methodology or reasoning for arriving at the <br /> figure awarded. The submission on behalf of the Appellant that such <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>34</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> reasoning can be gathered from the record cannot be accepted, as it is <br /> impermissible for this Court to supply reasons which the Arbitral <br /> <br /> Award itself does not disclose. <br /> <br /> <b>79.</b> <b> </b> The distinction between an arbitral award where reasons are <br /> either lacking or unintelligible and an award where reasons are explicit <br /> but appear inadequate was carved out by the Supreme Court in <b><i>OPG </i></b><br /> <b><i>Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) </i></b><br /> <b><i>44</i></b><br /> <b><i>(P) Ltd.</i></b> . The Court therein held that where reasons are merely <br /> inadequate or insufficient but the underlying basis is understandable on <br /> a holistic reading, the Court may sustain the award by explaining such <br /> reasoning. However, the present case falls in the category of awards <br /> suffering from a complete absence of reasoning for quantification. Any <br /> attempt to justify the reasonableness of the quantification on the basis <br /> of submissions advanced before us by the learned Senior Counsel for <br /> the Appellant would amount to impermissibly supplanting the findings <br /> of the learned Tribunal by this Court, which are based on no evidence <br /> or reasoning, by substituting them with this Court’s own interpretation <br /> of the evidence on record which is impermissible. <br /> <br /> <b>80.</b> <b> </b> A mere observation in the Arbitral Award that the determination <br /> is based on the “all the relevant facts and circumstances of the case” <br /> cannot, in our considered view, suffice in a matter of unliquidated <br /> damages. While it may be that the learned Tribunal considered material <br /> such as the CBRE and Colliers reports, along with the testimony of the <br /> expert witnesses, however, the same were ultimately not accepted for <br /> <br /> <b>44</b><br /> <b> (2025) 2 SCC 417 </b><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>35</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> quantification as the learned Tribunal itself recorded that no evidence <br /> had been led by the either party. Once such evidence stood rejected, the <br /> quantification cannot be sustained on the basis of the very same <br /> evidence. Therefore, no linkage can be found between the figure arrived <br /> at and material on record. We may have accepted the linkage between <br /> the said reports and the quantification, had the learned Tribunal not <br /> expressly recorded that there was no evidence. Once such a finding is <br /> returned and the learned Tribunal nevertheless resorts to guesswork, it <br /> was incumbent to disclose some reasoning or basis for the <br /> quantification. In the absence thereof, the figure arrived at remains one <br /> based on mere conjecture and lacks any foundational basis. <br /> <br /> <b>81.</b> <b> </b> In the absence of reasons employed by the learned Tribunal, the <br /> contours of patent illegality assume significance. The Supreme Court <br /> 45<br /> in <b><i>DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd.</i></b> , explained the <br /> same in the following words: <br /> <br /> <i>“</i> <b><i>39.</i></b> <i> In essence, the ground of patent illegality is available for </i><br /> <i>setting aside a domestic award, if the decision of the arbitrator is </i><br /> <i>found to be perverse, or so irrational that no reasonable person </i><br /> <i>would have arrived at it; or the construction of the contract is such </i><br /> <i>that no fair or reasonable person would take; or, that the view of the </i><br /> <i>arbitrator is not even a possible view. A “finding” based on no </i><br /> <i>evidence at all or an award which ignores vital evidence in arriving </i><br /> <i>at its decision would be perverse and liable to be set aside under the </i><br /> <i>head of “patent illegality”. An Award without reasons would suffer </i><br /> <i>from patent illegality. The arbitrator commits a patent illegality by </i><br /> <i>deciding a matter not within his jurisdiction or violating a </i><br /> <i>fundamental principle of natural justice”. </i><br /> <i> </i><br /> (emphasis supplied) <br /> <i> </i><br /> <br /> <br /> <b>45</b><br /> <b> (2024) 6 SCC 357 </b><br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>36</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>82.</b> <b> </b> This principle has also been reiterated in <b><i>Ssangyong </i></b><br /> <b><i>46</i></b><br /> <b><i>Engineering & Construction Co. Ltd. v. NHAI</i></b> <b><i> </i></b> and <b><i> PSA SICAL </i></b><br /> <b><i>Terminals Pvt. Ltd. </i></b> (supra) wherein it was held that a finding based on <br /> no evidence is perverse and liable to be set aside on account of patent <br /> illegality. <br /> <br /> <b>83.</b> <b> </b> On the touchstone of the aforesaid principles, we find that the <br /> Arbitral Award insofar as it quantifies the mesne profits to the extent of <br /> Rs. 30,00,000 per month cannot be sustained. The learned Tribunal, <br /> having discarded the valuation material and not followed any <br /> benchmark or evidentiary basis, nonetheless proceeded to determine a <br /> fixed figure without disclosing any rationale or methodology. As held <br /> in <b><i>Ramesh Kumar Jain (supra)</i></b> <i>,</i> while sufficiency of evidence is not <br /> for the Court to reappreciate, a finding based on “no evidence” warrants <br /> interference, as an Arbitrator cannot conjure a figure out of thin air <br /> without any supporting basis. <br /> <br /> <br /> <b>84.</b> <b> </b> The above conclusion is further reinforced by the decisions in <br /> <b><i>Bharat Heavy Electricals Ltd (supra)</i></b> <i>,</i> <b><i> Gemini Bay Transcription (P) </i></b><br /> <b><i>Ltd. (supra) </i></b> <i>and</i> <b><i>New Okhla Industrial Development Authority </i></b><br /> <b><i>(supra)</i></b> <i>, </i> which <i> </i> clarify that while a degree of approximation is <br /> permissible in assessing damages, such an exercise must be anchored <br /> in some evidence/material on record, method, or identifiable reasoning. <br /> In our view, the latitude for ‘honest guesswork’ is confined to situations <br /> where the record furnishes a foundation, however limited, for a rational <br /> estimation. In the present case, the Arbitral Award discloses no such <br /> <br /> <b>46</b><br /> <b> (2019) 15 SCC 131 </b><br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>37</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> foundational basis, nor is there any attempt to identify the parameters <br /> which may guide this determination. The quantification, therefore, <br /> ceases to be an exercise in estimation and instead assumes the character <br /> of an fixation without any basis, thereby attracting the vice of patent <br /> illegality. Therefore, the learned Single Judge was justified in <br /> interfering with the Arbitral Award to this limited extent. Also, reliance <br /> on <b><i>Flovel Hydro (supra)</i></b> is misplaced, as the said decision was rendered <br /> in the context of an international commercial arbitration, where the <br /> scope of interference is more circumscribed, and the ground of patent <br /> illegality is not available for interference. <br /> <br /> <b>85.</b> <b> </b> Insofar as the submission regarding adjustment of Claims and <br /> Counter-Claims is concerned, we find no merit in the same. The Claims <br /> and Counter-Claims have been adjudicated independently on their <br /> respective merits. The setting aside of the quantification of mesne <br /> profits does not, by itself, warrant reopening of the Counter-Claims or <br /> disturb the findings rendered thereon, unless specifically challenged on <br /> merits in proceedings under Section 34. The adjustment is merely <br /> consequential to the final determination and does not create such <br /> interdependence as to require that the fate of one must necessarily <br /> <br /> govern and/or follow the other.<br /> <br /> <b>86.</b> <b> </b> The Appellant’s contention that the Impugned Order was <br /> vitiated due to violation of the principles of natural justice is also devoid <br /> of merit. The record shows that the Appellant was duly represented and <br /> participated in the proceedings, and all its submissions were considered <br /> in the Impugned Order. The mere fact that the petition was disposed of <br /> at the initial stage, or that no opportunity was granted to file a written <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>38</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> reply, does not, <i>ipso facto</i> , amount to a violation of principles of natural <br /> <br /> justice.<br /> <b> </b><br /> <b>Conclusion </b><br /> <b><i> </i></b><br /> <b>87.</b> <b> </b> Upon a comprehensive consideration of the material on record, <br /> the reasoning of the learned Tribunal, and the settled principles <br /> governing interference under Sections 34 and 37 of the Act, we find no <br /> infirmity in the Impugned Order. <br /> <br /> <b>88.</b> <b> </b> ‘Honest guesswork’ or a ‘rough and ready’ approach may be <br /> adopted in appropriate cases. However, such estimation must still be <br /> based on some material on record or must show a rational nexus. In the <br /> present case, the learned Tribunal, after rejecting the valuation reports <br /> and recording that there was no evidence, nonetheless proceeded to fix <br /> mesne profits without indicating any method, benchmark, or supporting <br /> material. Such an approach goes beyond the limits of permissible <br /> estimation. <br /> <br /> <b>89.</b> <b> </b> Thus, the Arbitral Award, to the extent it awarded Rs. 30,00,000 <br /> per month towards mesne profits suffers from patent illegality being <br /> both unsupported by evidence and devoid of reasons. The learned <br /> Single Judge has rightly exercised its jurisdiction in setting aside the <br /> quantification of mesne profits. We also find no merit in the Appellant’s <br /> contentions regarding adjustment of Claims and Counter-Claims or <br /> alleged violation of principles of natural justice, as the same do not <br /> disclose any ground warranting interference. <br /> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>39</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24<br /><br /> <br /> <b>90.</b> <b> </b> We make it clear that the liberty granted by the learned Single <br /> Judge shall remain, and the Appellant shall be at liberty to agitate its <br /> Claim in accordance with law. If such liberty is exercised, the <br /> concerned authority shall endeavour to decide the same expeditiously. <br /> <br /> <b>91.</b> <b> </b> In light of the foregoing discussion, we dismiss the present <br /> appeal, along with any pending applications, if any. <br /> <br /> <b>92.</b> <b> </b> There shall be no order as to costs. <br /> <b> </b><br /> <b>OM PRAKASH SHUKLA, J.</b> <br /> <br /> <b>C.HARI SHANKAR, J.</b> <br /> <b>April 13, 2026</b> <i>/ss</i> <b>/pa</b> <br /> Signature Not Verified<br /> FAO(OS) (COMM) 156/2024 Page <b>40</b> of <b>40</b> <br /> <br /> Signed By:ANUBHAV<br /> TRIPATHI<br /> Signing Date:13.04.2026<br /> 19:58:24</div>