Hazel Mercantile Ltd vs Indian Oil Corporation Ltd
- Court
- Delhi High Court
$~29
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 22.04.2026
+ O.M.P. (COMM) 36/2023 & I.A. 1770/2023
HAZEL MERCANTILE LTD .....Petitioner
Through: Mr. Bishwajit Dubey, Mr.
Akshit Awasthi & Mr. Vivek
Sharma, Advs.
versus
INDIAN OIL CORPORATION LTD .....Respondent
Through: Ms. Vineeta Meharia, Senior
Adv. with Mr. Amit Meharia,
Ms. Tannishtha Singh & Mr.
Sambhav, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
AVNEESH JHINGAN, J. (ORAL)
1. This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) for setting aside of the
arbitral award dated 01.10.2022.
2. The brief facts are that the respondent/Indian Oil Corporation
Ltd. (hereinafter referred to as „IOCL‟) vide tender dated 15.01.2018
invited bids for supply of 26,000 MT of Acetic Acid (for brevity „the
acid‟). The petitioner was the successful bidder and a purchase order
(for short „PO‟) dated 25.05.2018 was issued for supply of 13,000 MT
at the rate of Rs. 50,500/- per MT. The supply was to be made over a
period of one year from the date of first supply or till completion of
the total ordered quantity, whichever was earlier. The PO stipulated
delivery to be on a staggered basis as per the schedule to be issued by
Signature Not Verified
Page 1 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
IOCL and the required quantity of the material was to be supplied
within four to seven days of the intimation. The petitioner made the
first supply on 04.06.2018 and the contract was to expire on
03.06.2019. Till 02.02.2019, the petitioner supplied 6504.42 MT of
acid in compliance with the schedules issued by IOCL. The plant of
IOCL was shut down in February, 2019 due to technical reasons and
resumed operations on 28.07.2019. IOCL on 03.04.2019 extended the
tenure of the contract up to 31.08.2019. The petitioner was intimated
on 17.06.2019 that the plant was under shut down and acid storage
was full.
2.1 By email dated 05.08.2019 the petitioner sought extension of
the PO by six months or till completion of the supply of balance
quantity whichever was earlier. IOCL vide letter dated 05.08.2019
asked the petitioner to maintain the supply against the PO at the rate
of 70 MT of acid per day for a further period of one week. On
20.08.2019 the petitioner was informed that no further supply of acid
was envisaged. The terms and conditions agreed between the parties
provided for dispute resolution through arbitration and the
proceedings were invoked by the petitioner.
2.2 The petitioner raised the following claims:
(i) declaration that IOCL breached the contract. Damages of
Rs.8,58,27,060/- for breach of contract were sought. Damages were
quantified by taking the difference between the contract price and the
actual price at which the balance quantity of acid was sold;
(ii) a sum of Rs. 3,71,91,726/- was claimed on account of expenses
incurred for storing 5201.64 MT of acid; and
Signature Not Verified
Page 2 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
(iii) a sum of Rs. 4,87,119/- towards compensation for expenses
incurred for furnishing of performance bank guarantee (for short
„PBG‟) and keeping it alive till it was returned.
2.3 The first issue was decided in favour of the petitioner and IOCL
was held to be in breach of the contract. With regard to the claim for
damages for non-supply of the balance quantity of acid the arbitrator
awarded a sum of Rs. 25,000/- as nominal damages along with interest
at the rate of 9% per annum from the date of the award till realisation.
The claims for storage charges and expenses incurred towards
furnishing the PBG were rejected. Litigation costs of Rs.12,00,000/-
were awarded. Hence, the present petition.
3. Learned counsel for the petitioner contends that the impugned
award is perverse and suffers from patent illegality. It is argued that
relevant evidence including the deposition of CW-1 wherein it was
stated that the petitioner was ready and willing to supply the balance
quantity and that sufficient stock was available with the petitioner
from time to time was ignored. Submission is that no reasons have
been recorded by the arbitrator for awarding damages of Rs. 25,000/-
which is grossly inadequate.
3.1 Reliance is placed upon the decision of Supreme Court in
Associate Builders v. Delhi Development Authority , (2015) 3 SCC 49
to contend that non-consideration of relevant evidence vitiates the
award of patent illegality. The decisions of the Supreme Court in Oil
and Natural Gas Corporation Ltd. v. Western Geco International
Ltd., (2014) 9 SCC 263 and Patel Engineering Ltd. v. North Eastern
Electric Power Corporation Ltd., (2020) 7 SCC 167 are relied upon
Signature Not Verified
Page 3 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
to submit that a perverse or irrational conclusion is a ground for
setting aside the award. The decision in H.B. Gandhi, Excise and
Taxation Officer-cum-Assessing Authority, Karnal & Ors. v. M/s
Gopi Nath & Sons, 1992 (Supp) 2 SCC 312 is relied upon to argue
that judicial review is to ensure fair treatment to the individual and
that the authority authorised by law reaches a conclusion correct in the
eye of law.
4. Per contra , the scope of interference under Section 34 is
limited. The view taken by the arbitrator is plausible and calls for no
interference. The submission is that there cannot be re-appreciation of
the evidence. It is emphasised that as per the terms of the PO there
was no condition that the entire quantity of acid was to be supplied in
one go, thereby necessitating the petitioner to continuously maintain
stock.
5. Heard learned counsel for the parties at length. Perused the
relevant record with their able assistance. Albeit , written submissions
have been filed by the parties but no other issue than those noted
above was pressed.
6. There is no challenge to the finding recorded by the arbitrator
that IOCL had breached the contract. The issue that survives is with
regard to the quantum of damages awarded.
7. In the present case the damages were claimed under Section 73
of the Indian Contract Act, 1872 (for short „Contract Act‟). The
undisputed facts are that the petitioner had a PO for supply of 13,000
MT on a staggered basis over a period of one year. The petitioner
supplied 6,504.42 MT of acid till 02.02.2019 and the supply order was
Signature Not Verified
Page 4 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
closed on 20.08.2019 and the time period of the PO was not extended.
The petitioner claimed that the balance quantity of acid i.e., 5,201.64
MT was sold at a rate lower than the rate agreed between the parties
and sought damages.
8. The arbitrator rejected the claim considering that for various
customers there was no segregation of stock imported by the
petitioner. Admittedly there was a common stock of acid. There was
no means to identify the specific stock meant for supply to IOCL. It
was observed that in the eventuality of IOCL issuing schedules for the
balance quantity, the petitioner was not having sufficient stock on
several dates during the operative period of the contract. In other
words, the petitioner had not procured in advance the entire quantity
of acid to be supplied to IOCL. The deposition of CW-1 was relied
upon wherein it was admitted that for the period from 01.02.2019 to
31.03.2019 the names of various customers to whom supplies were
made found mention in the stock register. It was further admitted that
the opening stock maintained by the petitioner was meant for supply
to various customers. On this basis, it was concluded that there was a
common pool of acid stock and that no stock was maintained
exclusively for IOCL. Moreover, there was no clause in PO requiring
the petitioner to maintain stock for supply to IOCL. The contract
provided a period of four to seven days for execution of the schedule
thereby giving sufficient time to the petitioner to arrange the required
quantity.
9. Taking into account that IOCL had breached the contract,
failure of the petitioner to prove actual loss or damages and as there
Signature Not Verified
Page 5 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
was no genuine pre-estimate of loss agreed between the parties,
nominal damages of Rs. 25,000/- were awarded along with interest at
the rate of 9% per annum.
10. For claiming damages under Section 73 of the Contract Act
actual loss has to be proved and in cases where it cannot be
established nominal damages may be awarded. Reliance is on the
decision of Supreme Court in Unibros v. All India Radio , 2023 SCC
OnLine SC 1366 and the relevant paragraph is as under:
“19. The law, as it should stand thus, is that for claims
related to loss of profit, profitability or opportunities to
succeed, one would be required to establish the following
conditions : first, there was a delay in the completion of the
contract; second, such delay is not attributable to the
claimant; third, the claimant's status as an established
contractor, handling substantial projects; and fourth,
credible evidence to substantiate the claim of loss of
profitability. On perusal of the records, we are satisfied that
the fourth condition, namely, the evidence to substantiate
the claim of loss of profitability remains unfulfilled in the
present case.”
(emphasis supplied)
11. Another aspect is that the damages claimed by the petitioner
were based on the price difference between the rate agreed with IOCL
and the price at which the acid was actually sold. The price difference
by itself does not prove the loss suffered. Every trading transaction
has two sides of the same coin namely purchase and sale. While the
petitioner disclosed the sale price and the contract price with IOCL
but the purchase price was withheld. In the absence of the purchase
price the claim for damages cannot be sustained on the basis of price
difference. The variation in market prices is a relevant factor in
Signature Not Verified
Page 6 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
determining profit or loss of a trader. The quantification of the
nominal damages is a discretion exercised by the arbitrator in the facts
and circumstances of the case calling for no interference under Section
34 of the Act.
12. The arbitrator after recording a finding that no exclusive stock
pool was maintained by the petitioner for supplies to IOCL, rejected
the claim for storage expenses which needs no interference. The claim
for expenses incurred for furnishing and keeping alive PBG was not
pressed.
13. Before concluding, in all fairness the authorities relied upon by
learned counsel for the petitioner be dealt with. There is no quarrel
with the proposition that ignoring relevant evidence tantamounts to
perversity which is a ground available under Section 34 of the Act for
interference with the award. The decisions in Associate Builders
(supra), Oil and Natural Gas Corporation Ltd. (supra) and Patel
Engineering Ltd. (supra) were cited in this regard. These authorities
have no application in the facts of the present case.
13.1 The reliance on the decision in H.B. Gandhi, Excise and
Taxation Officer-cum-Assessing Authority, Karnal & Ors . (supra) is
of no avail. The matter before the Supreme Court arose from a
provision under the Haryana General Sales Tax Act, 1973 with regard
to pre-deposit for hearing of an appeal in a fiscal statute. Another
aspect is that the scope of judicial review under Section 34 is not as
wide as that under Articles 226/227 of the Constitution of India.
14. The scope of interference under Section 34 is well defined. The
view taken by the arbitrator is plausible and calls for no interference.
Signature Not Verified
Page 7 of 8
O.M.P. (COMM) 36/2023
Signed By:HONEY
ARORA
Signing Date:24.04.2026
16:10:13
There can be no re-appreciation of evidence. The conclusion arrived at
that the petitioner failed to establish maintenance of an exclusive stock
of acid for supply to IOCL and actual loss or damage suffered on
account of purchase of the acid at a rate higher than the rate at which it
was actually sold, cannot be tinkered with and the Court does not sit in
appeal over the arbitral award. The view of the arbitrator suffers from
no factual or legal error much less perversity.
15. The petition is dismissed.
16. Since the matter has been decided on merits, the pending
application stands disposed of.
AVNEESH JHINGAN, J
APRIL 22, 2026/ ‘JK’
Reportable:- Yes
Signature Not Verified
Page 8 of 8
O.M.P. (COMM) 36/2023