Anup Chawla vs Kapil Chawla
- Court
- Delhi High Court
$~62
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 10.09.2026
# CNR No. DLHC010329062021
+ CONT.CAS(C) 777/2021
ANUP CHAWLA .....Petitioner
Through: Mr. Milan Deep Singh and
Mr. Kartik Dawar, Advocates.
versus
KAPIL CHAWLA .....Respondent
Through: Ms. Arunima Dwivedi, CGSC
along with Ms. Himanshi
Singh, Ms Monalisha Pradhan
and Mr. Suman Ghosh,
Advocates.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
% JUDGEMENT (Oral)
1. The present Contempt Petition has been filed under Section 12
1
of the Contempt of Courts Act, 1971 alleging willful and deliberate
2
disobedience of the Order dated 17.03.2021 passed by the learned
Co-ordinate Bench of this Court in W.P.(C) 3829/2020, titled “Anup
Chawla v. Delhi Development Authority Through its Chairman &
Ors.” . The Impugned Order reads as under:
“1. The lis has been settled between the petitioner and R-3,
courtesy of the Delhi High Court Mediation and
Conciliation Centre, by way of a Settlement Agreement
dated 11.02.2021.
2. Mr. Kapil Chawla/R-3 is present in the Court through
1
CC Act
2
Impugned Order
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:10.09.2026
19:30:40
CONT.CAS(C) 777/2021 Page 1 of 5
video-conferencing and has been identified by his counsel
named above. The petitioner too is present in the Court
through video-conferencing and has been identified by her
counsel.
3. R-3 states that he undertakes to abide by the terms of the
settlement. His undertaking is accepted. The learned
counsel for R-3 submits that there is a will apropos another
property, for which the parties may pursue their remedies.
It, however, does not affect the settlement in any manner.
4. The petition, along with pending application, stands
disposed-off in terms of the Settlement Agreement.
5. The next date of 11.05.2021 stands cancelled.”
2. It is the case of the Petitioner that certain disputes had arisen
between the parties, which came to be settled by way of the
3
Settlement Agreement dated 11.02.2021 . It is further the case of the
Petitioner that, in terms of the Settlement Agreement, the first
installment of Rs. 3,36,000/-, after deduction of the applicable TDS,
was paid to the Respondent.
3. Learned counsel appearing on behalf of the Petitioner submits
that the respective obligations of the parties under the Settlement
Agreement are set out in Clause 4 thereof, which reads as follows:
“ 4 . The Second Party, who is currently residing in Poland,
undertakes that he shall prepare the below-mentioned
documents and send a scanned copy of the same to its
Advocate (Mentioned in the Recitals) within a period of 20
(twenty) days of signing of this Agreement. Upon receiving
documents as above, the Advocate of the Second Party
shall inform the Advocate of the First Party, who shall have
a right to inspect the said documents. Upon the said
inspection by the Advocate of the First Party, the payment
of the first installment of Rs.3,36,000/- (Rupees Three
Lakhs Thirty Six Thousand Only) shall be made by the
First Party to the Second Party within a period of two days.
Upon receipt of the said payment from the First Party, the
Second Party shall deliver to the First Party the original set
of the below-mentioned documents through Blue Dart/DHL
courier service. The cost of the courier shall be borne by the
Second Party. The Second Party shall share with the First
3
Settlement Agreement
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:10.09.2026
19:30:40
CONT.CAS(C) 777/2021 Page 2 of 5
Party the proof of courier within a period of two days from
the date of receipt of payment of the first instalment. The
documents shall be couriered by the Second Party to the
following address:
Name:- Mrs. Pooja Chawla W/o Anup Chawla
Address: 89, Dharam Kunj Apartments, Sector -9, Rohini,
Delhi-110085
Phone No.: 9311521362
The following documents shall be provided by the Second Party to
the First Party:
a. Special Power of Attorney in favour of Mrs. Gulshan
Kukreja w/o Kulbhushan Kukreja, R/O Flat No- 91, Rishi
Apartment, Sector - 9, Rohini, Delhi - 110085 authorizing
her to provide Relinquishment Deed in favour of the First
Party, a draft whereof has been annexed hereto as
Annexure-1;
b. Article 4 Affidavit, a draft whereof has been annexed
hereto as Annexure-2;
c. Self-Attested copy of Passport of the Second Party;
th
d. Self-Attested copy of class 10 marksheet of the Second
Party/a self-attested copy of passport and a copy of PAN
Card.
e. Indemnity bond, a draft whereof has been annexed hereto
as Annexure-3;
f. Undertaking, a draft whereof has been annexed hereto as
Annexure-4;
The documents mentioned above shall be duly apostilled/attested
in Poland through appropriate diplomatic mission/authorities;”
4. Thus, from the terms of the Settlement Agreement, it is
apparent that the Petitioner was required to make payment of
Rs.3,36,000/- upon inspection of the documents furnished by the
Respondent. Learned counsel submits that the requisite inspection was
carried out and the payment was thereafter duly made, after deduction
of TDS.
5. Learned counsel appearing on behalf of the Petitioner further
submits that, despite receipt of the first instalment in terms of the
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:10.09.2026
19:30:40
CONT.CAS(C) 777/2021 Page 3 of 5
Settlement Agreement, the Respondent failed to dispatch the original
documents which he was required to send to the Petitioner. It is,
therefore, submitted that the Respondent, in terms of Section 2(b) of
the CC Act, has committed wilful disobedience of the terms of the
Settlement Agreement, which were incorporated in, and formed the
basis of, the Order dated 17.03.2021 and the undertaking furnished by
the Respondent was expressly accepted and recorded therein.
6. Vide Order dated 11.03.2026, this Court had observed that, in
the event of the Respondent not appearing on the next date of hearing,
the matter would be heard ex-parte . The matter was thereafter listed
on 19.05.2026 as well as on 09.09.2026. However, there was no
appearance on behalf of the Respondent on either of the aforesaid
dates.
7. In view of the above, the Court proceeds to hear the present
matter ex-parte .
8. This Court has heard the learned counsel appearing on behalf of
the Petitioner at length, and, with his able assistance, perused the
material placed on record.
9. The Settlement Agreement dated 11.02.2021 is clear and
unambiguous. The obligations undertaken by the Respondent
thereunder are specific and leave no scope for doubt as to the acts
required to be performed by him. The Respondent was, therefore, duty
bound to abide by the terms of the settlement, particularly once the
said terms formed the basis of the disposal of the writ petition and his
undertaking to abide by the settlement was expressly accepted and
recorded by this Court.
10. The material on record demonstrates that, upon inspection of
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:10.09.2026
19:30:40
CONT.CAS(C) 777/2021 Page 4 of 5
the documents, the first instalment was paid by the Petitioner to the
Respondent. Despite receipt of the said payment, the Respondent
failed to dispatch the original documents as required under Clause 4 of
the Settlement Agreement. There has, thus, been a failure on the part
of the Respondent to perform the obligation expressly undertaken by
him. The acceptance of the amount evidences that the Respondent has
accepted and acted upon the terms of Settlement Agreement.
11. It is also significant that the present proceedings have remained
pending since the year 2021 and the Respondent had entered
appearance on various dates. However, he has chosen not to appear
before this Court for a considerable period of time. More importantly,
there is no material before this Court to suggest that the Respondent
has disputed either the Settlement Agreement or his obligation
thereunder to hand over the documents as agreed between the parties.
12. In these circumstances, the continued failure of the Respondent
to comply with the terms of the Settlement Agreement, coupled with
his failure to participate in the present proceedings, leaves this Court
with no manner of doubt that the Respondent has wilfully and
deliberately disobeyed the Order dated 17.03.2021. The Respondent
is, accordingly, held guilty of contempt of this Court.
13. In view of the foregoing discussion, the present Contempt
Petition is allowed.
14. Accordingly, list on 30.10.2026 for sentencing. Respondent
Kapil Chawla is directed to be physically present in Court on the said
date.
HARISH VAIDYANATHAN SHANKAR, J.
SEPTEMBER 10, 2026/tk/ma
Signature Not Verified
Digitally Signed
By:HARVINDER KAUR
BHATIA
Signing Date:10.09.2026
19:30:40
CONT.CAS(C) 777/2021 Page 5 of 5