Sarvam Culture World Pvt. Ltd. vs Delhi Tourism And Transportation Development Corporation Ltd. (Dttdc)
- Court
- Delhi High Court
$~25
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of decision: 24.04.2026
+ O.M.P.(I) (COMM.) 179/2026 & I.A. 11378/2026 (Stay)
SARVAM CULTURE WORLD PVT. LTD. .....Petitioner
Through: Mr. Chirag Sharma, Advocate.
versus
DELHI TOURISM AND TRANSPORTATION
DEVELOPMENT CORPORATION LTD. (DTTDC)
.....Respondent
Through: Ms. Anisha Upadhyay, Mr.
Vaibhav Kalra, Advocates
along with Mr. Ramniwas Dy.
Manager Law DTTDC.
CORAM:
HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
SHANKAR
% JUDGEMENT (ORAL)
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition has been filed under Section 9 of the
Arbitration and Conciliation Act, 1996 [“ the Act ”], seeking the
following reliefs:
“A) Direct the termination of the 'Operations and Maintenance
Lease Contract' dated 08.07.2013 between the Respondent
and the Petitioner pertaining to the Project Facility - conceived
as 'Neighborhood Cultural Centre' under the Raja Garden
Flyover, New Delhi - 110015 to be kept in abeyance during
the pendency of the process of mechanism of dispute
resolution in terms of Article 12 of the said Contract dated
08.07.2013 in the interest of justice;
B) Direct the Respondent to not proceed for the physical and
actual possession of the Project Facility - conceived as
'Neighborhood Cultural Centre' under the Raja Garden
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 1 of 6
Flyover, New Delhi – 110015 during the pendency of the
process of mechanism of dispute resolution in terms of Article
12 of the 'Operations and Maintenance Lease Contract dated
08.07.2013 between the Respondent and the Petitioner in the
interest of justice;
C) Pass any other order(s) as this Hon'ble Court may deem fit and
proper in the present facts and circumstances.”
2. Material on record indicates that the parties entered into a
Operations and Maintenance Lease Contract dated 08.07.2013, which
envisages an arbitration clause, being Article 12, which reads as
under:
“
ARTICLE 12 — DISPUTE RESOLUTION
12.1 Dispute Resolution
12.1.1 Any dispute, difference or controversy of whatever nature
howsoever arising under or out of or in relation to this Contract
(including its interpretation) between the Parties, and so notified in
writing by either Party to the other Party (the "Dispute" ) shall, in
the first instance, be attempted to be resolved amicably in
accordance with the conciliation procedure set forth in Claue 12.2.
12.1.2 The Parties agree to use their best efforts for resolving all
Disputes arising under or in respect of this Contract promptly,
equitably and in good faith, and further agree to provide each other
with reasonable access during normal business hours to all non-
privileged records, information and data pertaining to any Dispute.
Unless the Contract has already been abandoned, repudiated or
terminated, the Operating Agency shall continue to proceed with
the Works/ perform its obligations in accordance with this Contract
during the resolution of the Dispute.
12.2 Conciliation
In the event of any Dispute between the Parties, either Party may
call upon the (Managing Director, DTTDC) to mediate and assist
the Parties in arriving at an amicable settlement thereof. Failing
mediation by the (Managing Director, DTTDC) or without the
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 2 of 6
intervention of the (Managing Director, DTTDC), either Party may
require such Dispute to be referred to the Chairman of Board of
Directors, DTTDC and the Chairman of the Board of Directors of
the Operating Agency for amicable settlement, and upon such
reference, the said persons shall meet no later than 7 (seven) days
from the date of reference to discuss and attempt to amicably
resolve the Dispute. If such meeting does not take place within the
7 (seven) day period or the Dispute is not amicably settled within
15 (fifteen) days of the meeting or the Dispute is not resolved as
evidenced by the signing of written terms of settlement within 30
(thirty) days of the notice in writing referred to in clause 12.1.1 or
such longer period as may be mutually agreed by the Parties, either
Party may refer the Dispute to arbitration in accordance with the
provisions of sub-article 12.3.
12.3 Arbitration
12.3.1 Any Dispute which is not resolved amicably by conciliation,
as provided in sub-article 12.2, shall be finally decided by
reference to arbitration by a Board of Arbitrators appointed in
accordance with clause 12.3.2. Such arbitration shall be held in
accordance with the Rules of Arbitration of the International
Centre for Alternative Dispute Resolution, New Delhi (the
"Rules" ), or such other rules as may be mutually agreed by the
Parties, and shall be subject to the provisions of the Arbitration
Act. The venue of such arbitration shall be New Delhi, and the
language of arbitration proceedings shall be English
12.3.2 There shall be a Board of three arbitrators, of whom each
Party shall select one, and the third arbitrator shall be appointed by
the two arbitrators so selected and in the event of disagreement
between the two arbitrators, the appointment shall be made in
accordance with clauses 12.3.3, 12.3.4.
12.3.3 Asset Manager's nominated Arbitrator shall be of the rank of
Senior Chief Manager or higher serving in the Government of New
Delhi, or equivalent
12.3.4 Within 15 days of the second Arbitrator being appointed by
the parties, the Arbitrators shall attempt to agree on the
appointment of the third Arbitrator as Chairman, who must be a
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 3 of 6
professional/chartered Civil Engineer of repute, with experience
related to dealing directly with claims, disputes, adjudication or
arbitration.
12.3.5 The arbitrators shall make a reasoned award (the "Award ").
Any Award made in any arbitration held pursuant to this sub-
article 12.1 shall be final and binding on the Parties as from the
date it is made and the Operating Agency and Asset Manager agree
and undertake to carry out such Award without delay.
12.3.6 The Operating Agency and Asset Manager agree that an
Award may be enforced against the Operating Agency and/or Asset
Manager, as the case may be, and their respective assets wherever
situated.
12.3.7 This Contract and the rights and obligations of the Parties
shall remain in full force and effect, pending the Award in any
arbitration proceedings hereunder.
12.4 Adjudication by Regulatory Asset Manager or
Commission
In the event of constitution of a statutory Regulatory Asset
Manager or Commission with powers to adjudicate upon disputes
between the Operating Agency and Asset Manager, all Disputes
arising after such constitution shall, instead of reference to
arbitration under sub-article 12.3, be adjudicated upon by such
Regulatory Asset Manager or Commission in accordance with the
Applicable Law and all references to Dispute Resolution Procedure
shall be construed accordingly. For the avoidance of doubt, the
Parties hereto agree that the adjudication hereunder shall not be
final and binding until an appeal against such adjudication has been
decided by an appellate tribunal or High Court, as the case may be,
or no such appeal has been preferred within the time specified in
the Applicable Law.”
3. At the outset, learned counsel appearing on behalf of the parties
would submit that they are ad idem that instead of adjudication on the
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 4 of 6
merits of the present matter, the same may be referred to arbitration.
Further, in the peculiar facts of the present case, the requirement of
Section 21 notice and initiation of separate proceedings under Section
11 of the A&C Act are dispensed with, with the consent of the parties.
4. Since the parties have mutually consented to the adjudication of
their disputes by way of Arbitration, this Court is of the view that the
commencement of arbitral proceedings to adjudicate the disputes
between the parties should not be unduly delayed.
5. In view thereof, this Court is of the view that the matter may be
referred to arbitration by a Sole Arbitrator for the purpose of the
adjudication of the disputes between the parties.
6. Accordingly, this Court hereby requests Mr. Kavindra Kumar
Gill, Advocate (Mobile No. 9911755161) to enter upon the reference
and adjudicate the disputes inter se the parties.
7. The learned Sole Arbitrator may proceed with the arbitration
proceedings, subject to furnishing to the parties the requisite
disclosures as required under Section 12(2) of the A&C Act within a
week of entering the reference.
8. The Registry is directed to forward a copy of this order to the
learned Arbitrator through all permissible modes, including electronic
means.
9. The learned Arbitrator shall be entitled to a fee in accordance
with the Fourth Schedule of the A&C Act or as may otherwise be
agreed to between the parties and the learned Arbitrator.
10. The parties shall share the learned Arbitrator’s fee and arbitral
costs equally.
11. All rights and contentions of the parties are kept open, to be
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 5 of 6
decided by the learned Sole Arbitrator on their merits, in accordance
with law.
12. Accordingly, the present Petition under Section 9 of the A&C
Act shall be treated as an Application under Section 17 of the A&C
Act, and appropriate directions may be passed by the learned
Arbitrator after entering upon the reference.
13. Needless to state, nothing in this order shall be construed as an
expression of opinion of this Court on the merits of the controversy.
14. Accordingly, the present Petition, along with pending
Application(s), if any, stands disposed of in the aforesaid terms.
HARISH VAIDYANATHAN SHANKAR, J.
APRIL 24, 2026/nd/va
Signature Not Verified
Digitally Signed
By:VARNIKA
Signing Date:28.04.2026
11:45:34
O.M.P.(I) (COMM.) 179/2026 Page 6 of 6