M S Ircon International Limited & Anr. vs M S Cannon Engineering Construction Cannon Cottage

Court
Delhi High Court
Case type
First Appeal Order Original Side Commercial
Decided on
24-02-2026

$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) (COMM) 16/2022
Judgment reserved on: 02.02.2026
Judgment pronounced on: 24.02.2026

M S IRCON INTERNATIONAL
LIMITED & ANR. .....Appellants
Through: Mr. Puneet Taneja, Sr. Adv.
with Mr. Manmohan Singh Narula, Mr Amit
Yadav and Mr Anil Kumar, Advs.


versus


M S CANNON ENGINEERING CONSTRUCTION
CANNON COTTAGE .....Respondent
Through: Mr. Simil Purohit, Sr. Adv.
with Mr. Faran Khan, Mr. Sandip
Vimadalal, Mr. Manish Doshi, Mr. Rishit
Vimadalal and Mrs. Bharti Gupta, Advs.

CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT
% 24.02.2026

OM PRAKASH SHUKLA, J.


Introduction

1. The present intra-court appeal has been preferred by the
Appellants under Section 37(1)(c) of the Arbitration and Conciliation
1
Act, 1996 , read with Section 13 of the Commercial Courts Act, 2015

1
“The Act”, hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 1 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

and Section 151 of Code of Civil Procedure, 1908. The appeal assails
2
the judgment dated 01.10.2021 passed by the learned Single Judge in
O.M.P. (COMM) No. 181/2021, titled as “ M/s Ircon International
Limited & Anr. v. M/s Cannon Engineering Construction Cannon
Cottage ”. The impugned judgment arose out of a petition filed by the
Appellants under Section 34 of the Act, seeking to set aside the
3
arbitral award dated 30.01.2021 rendered by the learned Sole
Arbitrator.

2. The dispute giving rise to the arbitral proceedings pertains to a
4
contract dated 05.11.2014 , executed between the parties, for the
“ Construction of service buildings, loco shed, RCC Trunk Drain and
Misc. Civil Works in connection with the Construction of Private
Railway Siding for Solapur Super Thermal Power Project of NTPC
Limited near Hotgi Railway Station in Solapur District, Maharashtra-
5
Pkg.4 ”. By the arbitral award, the learned Arbitral Tribunal allowed
the majority of the claims raised by the Respondent herein (Claimant
before the Tribunal), rejecting only Claim No. 3 and the sole counter-
claim made by the Appellants.

3. Vide the Impugned Judgment, the learned Single Judge partly
allowed the petition under Section 34 of the Act. The learned Single
Judge interfered with the arbitral award only to the limited extent of
setting aside the grant of pre-award interest for the period from
06.11.2016 till 30.01.2021, holding that the contract expressly
prohibited the grant of such interest. The remaining claims, i.e. Claim

2
“Impugned Judgment” hereinafter
3
“Arbitral Award” hereinafter
4
“contract” hereinafter
5
“Tribunal” hereinafter

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 2 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Nos. 1, 2, 4, and 5, along with the entitlement to future interest and
costs, were upheld by the learned Single Judge.

4. The present appeal is confined to challenging the impugned
judgment only insofar as it upholds the arbitral award in respect of
Claim No. 1 (hard rock in earth excavation) and Claim No. 2 (tie bolts
for RCC wall), as well as the entitlement to future interest and costs.
The Appellants contended that the findings underlying the said claims
suffer from patent illegality and, therefore, warrant interference by this
Court in the exercise of its jurisdiction under Section 37 of the Act.


Facts


5. The factual matrix, as relevant for the adjudication of the
present appeal, is outlined below.

6 7
6. NTPC Limited appointed M/s Ircon International Limited as
the Project Management Consultant for the Coal Transportation
System of its Solapur Super Thermal Power Project (2×660 MW) in
Solapur, pursuant to a purchase order dated 01.06.2012. In furtherance
of this, a Power of Attorney dated 07.12.2012 was executed in favour
of Appellant No.1, authorising it to act on behalf of Appellant No.2,
with Appellant No.2 being the employer for the project.


7. For execution of the project, Appellant No.1 issued a Notice
Inviting Tender dated 10.07.2014 for Package–4, which pertained to

6
“Appellant No.2” hereinafter
7
“Appellant No.1” hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 3 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

civil works for the private railway siding of the Solapur Super
Thermal Power Project near Hotgi Railway Station, Maharashtra. The
scope of work included the construction of service buildings, a
locomotive shed, and an RCC trunk drain within the plant area of
Appellant No.2. The Respondent emerged as the lowest bidder and
was awarded the contract by Letter of Award dated 30.09.2014, for a
total contract value of Rs. 21,25,74,013. The formal contract was
executed on 05.11.2014.

8. The work under the contract was to be executed in two
schedules, i.e., Schedule ‘A’ for the Service Building and Loco Shed,
valued at Rs. 4,52,26,447, and Schedule ‘B’ for the Corridor Drain,
with a total value of Rs. 16,73,47,566.

9. The Respondent was required to execute the works in
accordance with the Central Public Works Department Specifications,
8
2009 , which were part of contract. The description of quantities and
9
rates was prescribed in the Bill of Quantities attached to each
Schedule, and the rates provided in CPWD DSR-2013 were
applicable, including for extra works executed under the contract.

10. Clause 2.1 of the CPWD Specifications prescribed that
earthwork shall be classified under specified categories, namely all
kinds of soils, ordinary rock, and hard rock, with each category
measured separately for the purpose of determining the applicable
rates. The measurement of such excavation was required to be carried

8
CPWD specifications
9
“BOQ” hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 4 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

out in accordance with Clause 2.11 of the said CPWD Specifications.

11. CPWD-DSR-2013 prescribed rates for centering and shuttering
of RCC walls of any thickness under Item No. 5.9.2, which was
adopted in the BOQ for Schedule-B under Item No.7. However,
CPWD-DSR-2013 also separately prescribed rates for the use of tie
bolts under Item No. 5.10, which were not expressly included within
the scope of BOQ Item No.7.


12. The Respondent commenced execution of the Schedule B
works in November 2014. During execution, disputes arose regarding
payments for certain items, which the Respondent claimed were either
extra works or otherwise payable at higher rates.

13. While executing the corridor drain works under Schedule B,
the Respondent encountered hard rock at several locations during
excavation. The Respondent claimed that excavation of such hard rock
was not covered under the BOQ and thus, warranted payment as an
extra item. On 19.11.2014, the Respondent informed Appellant No. 1
that hard rock had been encountered and requested a site inspection
for proper classification. The Project Head subsequently conducted a
site inspection, recorded reduced levels, and classified the material as
hard rock in the Field Book, verified by Mr Appa Rao, Engineer at the
site. This classification was also reflected in the 2nd to 5th Running
10
Account Bills. However, payment towards the claimed extra item
was not released.


10
“RA” hereinafter

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 5 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

[

14. On 08.12.2014 and 25.12.2014, the Respondent reiterated its
claim that hard rock had been excavated and that the BOQ under
Schedule B did not contemplate rates for the same.

15. Due to the non-finalisation of the classification and the
applicable rates, the corresponding payments were withheld. As a
result, on 03.03.2015, the Respondent expressed its inability to
proceed without approval for higher rates and indicated that it would
either suspend the work or continue subject to payment of interest for
delayed payments.


16. On 09.06.2015, Appellant No.1 informed the Respondent that
payment for extra items would be considered only upon approval from
the competent authority. Further, on 22.06.2015, based on the
11
recommendation of an internal committee dated 04.06.2015 , it was
conveyed that the trench for the corridor drain fell under the category
of “ordinary rock” as per CPWD Specifications.

17. The Respondent disputed the above classification and, in
December 2015, arranged for an independent geological assessment
by an expert from Walchand College, Maharashtra. The expert
inspected the site in the presence of Mr Appa Rao and opined that the
excavated material was basaltic. The report was forwarded to
Appellant No.1 on 24.12.2015.

18. As the project neared completion, on 03.02.2016, the
Respondent sought permission for blasting in addition to mechanical

11
“internal committee report”, hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 6 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

excavation to expedite the completion of the work. The Respondent
also submitted an updated list of extra items. Instead of granting
permission, on 05.03.2016, Appellant No.1 directed the separate
stacking of hard rock for measurement purposes, which the
Respondent objected to as belated and impracticable due to site
constraints.

19. Disputes also arose concerning the payment for tie bolts used
in RCC wall shuttering and surface finishing of RCC/CC works. The
Respondent claimed that the tie bolts, not covered under the BOQ
item for shuttering corresponding to CPWD-DSR Item No. 5.9.2,
were necessary and payable as an extra item under CPWD-DSR Item
No. 5.10.4. The Appellants, however, argued that the shuttering rate
was a composite rate covering standard shuttering accessories and that
no separate approval for the use of tie bolts had been issued by the
Engineer-in-Charge, as required under Clause 10 of the General
12
Conditions of the Contract . Likewise, the Respondent claimed
surface finishing of the RCC as an extra item, asserting that it was not
included in the BOQ, a claim denied by the Appellants on the ground
that the same stood covered within the agreed contractual rates.

20. The abovementioned issues were repeatedly raised in joint
meetings held on 02.11.2015 and 15.01.2016. However, the disputes
remained unresolved.

21. During the pendency of the works, disputes also arose
concerning statutory levies. By a notification dated 11.05.2015, the

12
“GCC” hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 7 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Government of Maharashtra enhanced the royalty rates on building
materials, and the excise duty on steel was revised from 12% to 12.5%
with effect from 01.03.2015. The Respondent paid the royalty and
deposited Rs. 12,80,000/- with the Government Treasury on
23.03.2016, receiving royalty clearance certificates from the
Tahsildar, South Solapur. The Respondent thereafter sought
reimbursement of Rs. 8,31,936.39/- towards the enhanced royalty and
excise duty, which the Appellants declined, asserting that the
contracted rates were inclusive of statutory levies.

22. The works were completed on 30.06.2016, and the Respondent
demobilised its resources, submitted its 21st and final RA Bill on
07.08.2016 for Rs. 49,19,440.53, which included claims for disputed
items and statutory reimbursements. While part payment was made,
the balance amount was withheld by the Appellants, citing the
execution of non-mandatory extra work without permission and
outstanding royalty issues. The Respondent accepted the partial
payment under protest.

23. The principal issues in disputes between the parties were: (i)
the classification of earthwork under Schedule B work as hard rock or
ordinary rock and payment accordingly; (ii) payment for tie bolts used
in RCC wall shuttering; (iii) surface finishing of RCC/CC works; (iv)
reimbursement of enhanced statutory levies; and (v) release of
amounts withheld from the final bill.

24. As the issues remained unresolved despite repeated
communications and representations, the Respondent invoked
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 8 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

arbitration under Clause 56 of the GCC by notice dated 23.01.2019.
The Chairman and Managing Director of Appellant No.2 thereafter,
referred the disputes to arbitration and appointed Justice (Retd.) Sunil
Ambwani as the Sole Arbitrator by letter dated 01.04.2019.

Proceedings before the Arbitral Tribunal and Arbitral Award

25. The Respondent raised five claims before the learned Arbitral
Tribunal. After considering the pleadings, documentary evidence, and
submissions of the parties, the arbitral proceedings culminated in the
arbitral award. The learned Arbitrator allowed the majority of the
claims raised by the Respondent, rejected the counter-claim filed by
Appellants and awarded pre-award interest, future interest, and costs.
The summary of the claims and amounts awarded is provided below:

Sr.
No.
Particulars Claimed
Amount (Rs.)
Awarded
Amount (Rs)
Claim
Hard Rock in
Earth Excavation
2,09,24,546.52
1,17,55,347.74
No.1
(before
adjustment of
already paid)
Claim
Tie bolt for RCC
58,07,364.75 54,08,398.79
No.2
Wall Shuttering
Claim
Providing finish
52,25,983.32 NIL
No.3
two RCC/PCC
Surface
Claim
Additional cost
8,31,936.39 8,31,936.39
No.4
of excise duty
and Increase in
Royalty Charges
Claim
Final Bill 49,19,400.53 49,19,400.53
No.5

26. Claim No.1 : The Respondent claimed that the original BOQ
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 9 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

provided rates only for excavation in ordinary rock. However, during
execution, hard rock was encountered and excavation was carried out
in it. The Respondent, therefore, treated the excavation in hard rock as
extra work and sought payment, after adjusting the amounts already
paid towards excavation in ordinary rock. Appellant No.1 disputed the
claim, arguing that the material did not qualify as hard rock under
Clauses 2.1, 2.6 and 2.11 of the CPWD Specifications and relied on an
internal committee report that classified the material as ordinary rock.

27. After examining the CPWD Specifications, contemporaneous
records, and the evidence presented, the learned Arbitrator held that
the material encountered during excavation was classifiable as hard
rock. The Tribunal noted that the occurrence of hard rock was timely
reported by the Respondent and was recorded in the Field Book
following a site inspection. The report was signed by both the
Respondent and the Appellants’ site representative. Additionally, the
Tribunal observed that the internal committee’s classification of the
material as ordinary rock was inconsistent with the CPWD
Specifications and the contemporaneous records.

28. The Tribunal further relied on an independent geological
assessment, conducted in the presence of Appellant No.1’s site
representative, which confirmed the material to be basaltic rock, and
the expertise of the assessor remained undisputed. After considering
the contractual provisions, site records, and expert evidence, the
Tribunal allowed Claim No. 1, after adjusting the amounts already
paid.
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 10 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50


29. Claim No.2: This claim concerned the payment for tie bolts
used in RCC wall shuttering for the trunk drain, which the Respondent
asserted was an extra item necessitated by technical requirements to
achieve the required thickness of the wall. Appellant No. 1 disputed
the claim, contending that the BOQ rates for shuttering were
comprehensive and included the cost of all necessary items required
for shuttering tie bolts. Further, Appellants contended that no prior
approval for the use of tie bolts had been granted by the Engineer-in-
Charge and that they were used at the Respondent’s discretion.


30. The Tribunal observed that while shuttering was covered under
the BOQ, the cost of tie bolts was not included therein. It was noted
that the efficacy and use of tie bolts in the execution of the RCC walls
was not in dispute. Therefore, the Tribunal concluded that the
payment for tie bolts could not be denied solely for the lack of formal
approval.

31. The Tribunal further held that deviation or excess work
executed at the instance of the contractor fell within the scope of
Clause 11 of the GCC. The Tribunal found that timely intimations
were provided by the Respondent on 19.11.2014 regarding hard rock
and on 15.01.2015 regarding tie bolts. In the absence of any approval
or rejection by the Appellants within the stipulated period and given
that the Appellants had accepted the benefit of the executed work, the
Tribunal ruled that the claims could not be rejected merely for lack of
formal written approval under Clause 10.

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 11 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

32. Claim No. 3, 4 and 5: The Tribunal rejected Claim No.
3(Surface Finishing of RCC/PCC Works), holding that the work
executed did not fall within the scope of RCC/CC surface finishing.
The Tribunal further observed that, in any case, no approval had been
obtained from the Engineer-in-charge. The Tribunal allowed Claim
No. 4(Excise Duty and Royalty Charges), holding that Clause 17.5 of
13
the Special Conditions of Contract entitled the contractor to
reimbursement for statutory levies imposed after the bid date subject
to producing the documentary evidence in proof of payment. The
Tribunal noted that the enhanced royalty, notified on 11.05.2015, and
increased excise duty, effecting from 01.03.2015, fell under the
purview of this clause. Documentary evidence of payment was
undisputed, and reimbursement was accordingly directed. Claim No.
5(Final Bill) was also allowed, as the final bill submitted by the
Respondent was deemed justifiable.

33. Counter- Claim : The Tribunal rejected the sole counter-claim
filed by Appellants for the recovery of alleged royalty and penalties on
minor minerals. The Tribunal held that the revenue demand did not
substantiate any unauthorised extraction. The Counter-Claim was
based on demand notices and orders dated 03.07.2015 and 16.01.2016,
which had been set aside and remanded by the Upper Commissioner
on 19.12.2019 and had not attained finality. In the absence of any
crystallised or enforceable liability, the counter-claim was deemed
unsustainable and was rejected.


13
“SCC” hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 12 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

34. On the issue of interest, the Tribunal observed that the contract
prohibited the award of interest, as per Clauses 16.1 and 50.3 of the
SCC. However, the Tribunal awarded compensation at the rate of
12.5% per annum on Claim Nos. 2, 4, and 5 under Section 70 of the
14
Indian Contract Act, 1872 , effective from 06.11.2016 (three months
after the submission of the final bill dated 07.08.2016). Furthermore,
the Tribunal directed that if the Appellants failed to make payment
within six weeks from the date of the award, the Respondent would be
entitled to claim interest from the Executing Court in accordance with
Section 31(7) of the Act.



35. The Tribunal awarded arbitration costs to the Respondent
amounting to Rs. 13,45,850/-.

Impugned Judgment

36. Aggrieved by the arbitral award, the Appellants filed a petition
under Section 34 of the Act. The challenge was made in its entirety,
primarily on the grounds that the award was vitiated by patent
illegality as it was contrary to the terms of the Contract and made in
disregard of the documentary evidence placed on record.

37. In respect of Claim No. 1, relating to hard rock excavation, the
learned Single Judge observed that the issue was a pure question of
fact and fell within the exclusive domain of the Arbitral Tribunal. The
Court noted that the Tribunal’s finding was supported by
contemporaneous correspondence between the parties, entries in the

14
“ICA” hereinafter
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 13 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Field Book signed by the Appellant’s officials, and the geological
report from Walchand College identifying the excavated material as
basaltic rock, as well as, prior payments made for hard rock
excavation at the same site to another contractor who had excavated
the same site up to earth surface. The Court found no patent illegality
or perversity in the Tribunal’s reasoning and, therefore, declined to
interfere with the award on this ground.

38. With respect to the use of tie bolts in the shuttering of the trunk
drain, the learned Single Judge noted the Tribunal’s finding that tie
bolts were used for effective execution of the work and were
necessary in accordance with the CPWD Specifications. The Court
noted that this determination was a factual one, and the Appellants
themselves conceded that the issue was not amenable to interference
under Section 34 of the Act.

39. On the issue of non-approval by the Engineer-in-Charge, the
learned Single Judge noted that the Respondent had sought approval
for the extra item within the prescribed time under Clause 11 of the
GCC. However, no decision was taken by the Engineer-in-Charge.
The Court held that the Appellants could not take advantage of their
own inaction, and therefore, no interference was warranted on this
issue.

40. As regards reimbursement of enhanced royalty and excise duty,
the learned Single Judge observed that the Tribunal had correctly
applied Clause 17.5 of the SCC, which entitles the contractor to
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 14 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

reimbursement of statutory levies imposed after the bid date. The
Court further rejected the Appellants’ challenge to the Tribunal’s
rejection of the counter-claim for the recovery of alleged royalty. The
Court noted that the demand notice underlying the counter-claim had
been set aside and remanded by the Upper Commissioner and thus, no
crystallised liability existed against the Respondent.

41. On the issue of interest, the learned Single Judge concurred
with the Tribunal’s decision to decline interest in light of the express
contractual prohibition under Clauses 16.1 and 50.3 of the SCC.
However, the Court held that the Tribunal had erred in awarding
compensation at the rate of 12.5% per annum under Section 70 of the
ICA on certain claims. The Court observed that this amounted to a
colourable circumvention of the contractual prohibition on the award
of interest and therefore constituted patent illegality. However, the
entitlement of future interest was sustained, as it flows statutorily
under Section 31(7)(b) of the Act.

42. In light of the above discussions, the learned Single Judge
concluded that the arbitral award did not disclose any infirmity within
the narrow grounds of interference under Section 34 of the Act, except
to the extent that the Tribunal had awarded compensation at the rate of
12.5% per annum till the date of the award on certain claims, despite
the express contractual prohibition. The award, therefore, stood
upheld, with the exception of the issue relating to the award of
compensation at the specified rate.


Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 15 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Rival Contentions Before This Court

43. Mr. Puneet Taneja, learned Senior Counsel appearing for the
Appellants, contended that the award on Claim No. 1 was vitiated by
patent illegality, as the Tribunal classified the excavation under
Schedule B as hard rock, disregarding the mandatory criteria set forth
in Clauses 2.1, 2.6, and 2.11 of the CPWD Specifications. It was
argued that hard rock classification is limited to cases requiring
blasting or, where blasting is prohibited, excavation by mechanical
means such as chiselling or equivalent methods. Since the internal
committee report specifically opined that the material could be
loosened by light blasting, which is expressly excluded from hard rock
classification under Clause 2.1(b), the Tribunal’s treatment of the
excavation as hard rock was contended to be contrary to the terms of
the contract.

44. Learned Senior Counsel further submitted that Clause 2.6
mandates prior written approval of the Engineer-in-Charge for
blasting, and Clause 2.11 prescribes specific procedures for stacking
and measuring hard rock, however, none of these procedures were
followed in the present case. In the absence of compliance with these
requirements, it was contended that the mere unilateral use of
mechanical equipment or a belated request for blasting permission
could not justify classifying the excavation as hard rock.

45. Learned Senior Counsel argued that the Tribunal erred in
relying on Field Book entries and the Walchand College geological
report, despite the internal committee report classifying the material as
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 16 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

ordinary rock. It was submitted that such third-party opinions or site-
level entries, especially those signed by an officer who had no
authority to bind the Appellants to any extra financial obligation,
could not override the clear contractual mandate. The reliance on such
extraneous material, despite the unambiguous nature of the contract,
was contended to constitute patent illegality. The Appellants cited the
judgment in Godhra Electricity Co. Ltd & Anr v. State of Gujarat &
15
Anr . , to assert that subsequent material or conduct should be
considered only when the terms of the contract are unclear.

46. With regard to Claim No. 2, concerning the use of tie bolts, it
was contended that BOQ Item 5.9.2 prescribes a composite rate for
centering and shuttering of walls of any thickness, irrespective of
whether tie bolts or other materials are used. It was pointed out that
the use of tie bolts was neither mandated by the contract nor directed
by the Engineer-in-Charge but was used by the Respondent at its own
discretion a matter of the contractor’s discretion. Therefore, it was
argued that the Tribunal erred in treating the use of tie bolts as an
extra item, as their cost stood subsumed within the shuttering rate, and
since the Respondent used them purely for its own convenience, no
independent claim for payment could be sustained.

47. In arguendo , it was contended that even assuming excavation
in hard rock and the use of tie bolts to be extra items, the award on
Claim Nos. 1 and 2 was unsustainable due to non-compliance with
Clause 10, which requires prior written instructions from the
Engineer-in-Charge as a condition precedent for the execution of extra

15
(1975) 1 SCC 199
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 17 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

work. In the absence of such authorisation, Clause 11, being a sequitur
to Clause 10, could not be invoked. By permitting payment without
satisfying this threshold requirement, the Tribunal was contended to
have departed from the contractual scheme by relying on Clause 11,
rendering the award vitiated by patent illegality.

48. Learned Senior Counsel for the Appellants further relied on the
16
judgment of the Single Judge in K.R. Anand v. DDA , where the
award granted for extra work without complying with the condition of
explicit written permission was set aside.


49. It was further submitted that, despite a clarification dated
09.06.2015 expressly stipulating that the contractor was not bound to
execute any extra item without approval from the competent authority,
the Respondent proceeded to execute extra work unilaterally. The
Learned Senior Counsel argued that the Respondent acted in
contravention of the clarification and the contractual scheme, and,
thereafter, cannot derive any contractual benefit from such unilateral
conduct.

50. Learned Senior Counsel also submitted that the award of future
interest was contrary to the express bar on any interest at any stage
under Clause 50 of the SCC, and therefore, the learned Single Judge
erred in upholding the entitlement to award of future interest by
resorting to Section 31(7) of the Act. Reliance was placed on the
17
judgment in Union of India v. Manraj Enterprises .

16
1997 SCCOnline Del 307
17
(2021) SCC Online SC 1081
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 18 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

51. Lastly, it was argued that the award of the entire arbitration
costs of Rs. 13,45,850/- was arbitrary, as Claim No. 3 was rejected
and the Tribunal itself recorded that such costs were not payable in
respect of Claim Nos. 1 and 4. Therefore, it was contended that only
proportionate costs ought to have been awarded. Reliance was placed
18
on Xerox India Ltd. Vs. Computers Unlimited & Another , in
support of this contention.

52. Per contra, Mr. Sunil Purohit, learned Senior Counsel for the
Respondent submitted that the Tribunal’s finding on hard rock
excavation was a pure finding of fact, based on the CPWD
Specifications, contemporaneous Field Book entries, an expert report
prepared in the presence of the Engineer-in-Charge’s site
representative, and evidence showing that similarly situated
contractors were paid for hard rock at the same site. It was argued that
the Tribunal’s view was plausible, neither perverse nor patently
illegal, and thus, beyond interference under Section 37 of the Act.

53. With respect to Claim No. 2, the learned Senior Counsel
contended that the Tribunal correctly held that, in accordance with the
applicable CPWD Specifications, the use of tie bolts was necessary
due to the depth and thickness of the RCC drain walls. Since the cost
of tie bolts was not included in the relevant BOQ item, the Tribunal
rightly treated the use of tie bolts as an extra item and awarded
payment accordingly.


18
(2014) SCC Online Del 159

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 19 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

54. It was further submitted that the reliance on Clause 10 by the
Appellants was misconceived, as Clause 10 applies only to deviations
directed by the Engineer-in-Charge, whereas contractor-proposed
extra items are governed by Clause 11. The Respondent had duly
complied with Clause 11 by notifying the Engineer-in-Charge about
encountering hard rock on 19.11.2014 and seeking approval for the
use of tie bolts on 15.01.2015. Therefore, the Tribunal’s interpretation
of the contractual scheme, as affirmed by the learned Single Judge,
represented a plausible view and warranted no interference.

55. The learned Senior Counsel further submitted that the
Respondent is entitled to the future interest as it is statutorily
mandated under Section 31 of the Act irrespective of the agreement
between the parties.

56. Lastly, it was submitted that the award of awarding costs lies
within the discretion of the Arbitral Tribunal, and the contention that
only proportionate costs could be awarded was without merit.

Analysis

57. We have heard the learned Senior Counsel for both parties at
length and have conducted a comprehensive examination of the entire
appeal record, including the impugned judgment rendered by the
learned Single Judge, as well as the arbitral award rendered by the
learned Arbitrator.

58. This Court is called upon to exercise its appellate jurisdiction
under Section 37 of the Act to examine the correctness of the
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 20 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

judgment passed by the learned Single Judge whereby the objections
to the arbitral award were rejected. Therefore, it is pertinent to
reiterate that the scope of interference under Section 37 is extremely
circumscribed . An appellate court does not exercise plenary appellate
jurisdiction but only examines whether the Court exercising
jurisdiction under Section 34 has acted within the limits prescribed by
law. In Punjab State Civil Supplies Corpn. Ltd. and Anr v. Sanman
19
Rice Mills & Ors , the Hon’ble Supreme Court succinctly
summarised the settled position on this matter, in the following words-

“ 14. It is equally well settled that the appellate power under
Section 37 of the Act is not akin to the normal appellate
jurisdiction vested in the civil courts for the reason that the scope
of interference of the courts with arbitral proceedings or award is
very limited, confined to the ambit of Section 34 of the Act only
and even that power cannot be exercised in a casual and a cavalier
manner.

20. In view of the above position in law on the subject, the
scope of the intervention of the court in arbitral matters is virtually
prohibited, if not absolutely barred and that the interference is
confined only to the extent envisaged under Section 34 of the Act.
The appellate power of Section 37 of the Act is limited within the
domain of Section 34 of the Act. It is exercisable only to find out if
the court, exercising power under Section 34 of the Act, has acted
within its limits as prescribed thereunder or has exceeded or failed
to exercise the power so conferred. The Appellate Court has no
authority of law to consider the matter in dispute before the arbitral
tribunal on merits so as to find out as to whether the decision of the
arbitral tribunal is right or wrong upon reappraisal of evidence as if
it is sitting in an ordinary court of appeal. It is only where the court
exercising power under Section 34 has failed to exercise its
jurisdiction vested in it by Section 34 or has travelled beyond its
jurisdiction that the appellate court can step in and set aside the
order passed under Section 34 of the Act. Its power is more akin to
that superintendence as is vested in civil courts while exercising
revisionary powers. The arbitral award is not liable to be interfered
unless a case for interference as set out in the earlier part of the
decision, is made out. It cannot be disturbed only for the reason

19
2024 SCC OnLine SC 2632
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 21 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

that instead of the view taken by the arbitral tribunal, the other
view which is also a possible view is a better view according to the
appellate court.
21. It must also be remembered that proceedings under Section
34 of the Act are summary in nature and are not like a full-fledged
regular civil suit. Therefore, the scope of Section 37 of the Act is
much more summary in nature and not like an ordinary civil
appeal. The award as such cannot be touched unless it is contrary
to the substantive provision of law; any provision of the Act or the
terms of the agreement.”


59. It thus follows that while exercising jurisdiction under Section
37, this Court neither reappreciates the evidence nor reassesses the
merits of the arbitral findings. Interference is warranted only where
the Section 34 court has either failed to exercise the jurisdiction vested
in it or has exceeded the bounds of such jurisdiction. The appeal must,
therefore, be examined strictly on the touchstone of whether the
impugned judgment or the arbitral award discloses any jurisdictional
error, patent illegality, or perversity warranting appellate intervention.

60. Measured against the aforesaid parameters, we find that the
learned Single Judge has rendered a detailed and well-reasoned
judgment, examining the arbitral award claim-wise and categorically
addressing each contention advanced by the Appellants. The present
appeal, in our view, is a reiteration of the arguments already
considered and rejected by the learned Single Judge, in the hope of
securing a different outcome at the appellate stage. No jurisdictional
error or patent illegality is demonstrated so as to warrant interference
by this Court.


61. Before both this Court and the learned Single Judge, the
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 22 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

foremost challenge raised by the Appellants was to the finding of the
learned Tribunal regarding the classification of excavation forming
part of the Schedule B earthwork as hard rock. The Appellants
vehemently contended that the material encountered was ordinary
rock, and that the Tribunal’s contrary conclusion was in contravention
of the contractual framework, particularly the definitions contained in
Clause 2.1 of the CPWD Specifications governing the classification of
soils, which are reproduced hereunder-

“2.1 CLASSIFICATION OF SOILS
2.1.0 The earthwork shall be classified under the following
categories and measurement separately for each category:
a) All kind of soils: Generally any strata, such as sand, gravel,
loam, clay, mud, black cotton moorum, shingle, river or nallah bed
boulders, siding of roads, paths etc. and hard core, macadam
surface of any description (water bound, grouted tarmac etc.), lime
concrete mud concrete and their mixtures which for excavation
yields to application of picks, showels, jumper, scarifiers, ripper
and other manual digging implements.
b) Ordinary rock: Generally any rock which can be excavated by
splitting with crow bars or picks and does not require blasting,
wedging or similar means for excavation such as lime stone, sand
stone, hard laterite, hard conglomerate and unreinforced cement
concrete below ground level. If required light blasting may be
resorted to for loosening the materials but this will not in any way
entitle the material to be classified as "Hard rock”.
c) Hard rock: Generally any rock or boulder for the excavation of
which blasting is required such as quartzite, granite, basalt,
reinforced cement concrete {reinforcement to be cut through but
not separated from concrete) below ground level and the like.
d) Hard rock {blasting prohibited); Hard rock requiring blasting
as described under (c) but where the blasting is prohibited for any
reason and excavation has to be carried out by chiseling, wedging,
use of rock hammers and cutters or any other agreed method.”

(Emphasis supplied)

62. The Appellants relied on Clause 2.1(b) of the CPWD
Specifications, contending that even where light blasting is resorted to
for loosening the material, such excavation does not qualify as hard
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 23 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

rock. The internal committee report had opined that the rock could be
loosened by light blasting, which the Appellants argued indicated that
the material fell within the contractual definition of ordinary rock.
Therefore, the Appellants submitted that the Tribunal’s finding, which
classified the material as hard rock, suffers from patently illegality. In
this context, reference may be made to the reasoning of the Tribunal-

“ g. The excavated rock would either fall in the category of
ordinary rock or hard rock as defined in CPWD specifications. For
ordinary rock the specifications provide it to be any rock which
can be excavated by splitting with crow bars or picks and does not
require blasting, wedging of similar means for excavation. If
required, light blasting may be resorted to for loosening the
materials but this will not be in any way entitling the material to be
classified as hard rock. In category 'D' hard rock (blasting
prohibited) the hard rock is classified as a rock requiring blasting
as described in 'c' but where blasting is prohibited for any reason
and the excavation has to be carried by chiselling, wedging, use of
rock hammers and cutters or any other agreed method. It is not
denied by the Respondent that the observed rock / bounder
encountered in excavation were not feasible to be excavated by
manual means. The Committee opined that it can be loosened by
light blasting or using hydraulic breaker. The tribunal is unable to
appreciate the reasons given in the recommendations of the
Committee and the stand taken by the Respondents that the earth
work excavated falls under the category of ordinary rock, when the
Committee had clearly formed an opinion that the excavation of
the encountered rock could not be carried out by manual means
(crow bar or picks) but could be carried out by light blasting using
hydraulic rock breaker.
h. The observations and recommendations of the committee which
also included of Mr. Appa Rao, the Engineer present at site and
who had verified the entries of hard rock in the field book signed
by him at the time of excavation, are contradictory and thus the
Tribunal is of the considered opinion that the earth work
encountered by the Claimant would fall within the category of hard
rock as per CPWD specification classification of soils.”
(Emphasis supplied)

63. The relevant recommendations of the internal committee report
relied upon by the Appellants are as follows:
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 24 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

“iii. The observed rock/boulder encountered in excavation is not
feasible to excavate by manual means (cow bar or picks) but can
be loosed by light blasting or using hydraulic rock breaker. As per
CPWD specifications, this type of rock falls under category of
Ordinary rock.”

64. The Tribunal, interpreting the definitions of ordinary rock and
hard rock under the CPWD Specifications, proceeded on the premise
that Clause 2.1(b) applies to situations where the rock is otherwise
capable of manual excavation. Upon examining the internal committee
report, the Tribunal found an apparent contradiction. While the
committee opined that the material was ordinary rock, it also recorded
that excavation by manual means was not feasible. This contradiction,
coupled with the fact that the material could not be excavated
manually, led the Tribunal to conclude that the material could not be
treated as ordinary rock and therefore fell within the definition of hard
rock.

65. We find no infirmity in the reasoning adopted by the Tribunal.
The internal committee report did not merely state that light blasting
might be used, but also categorically opined that excavation could not
be carried out manually and would require mechanical means or light
blasting. In this context, the Tribunal’s interpretation that Clause
2.1(b), which relates to ordinary rock is inapplicable constitutes a
plausible interpretation and well-reasoned view, given the undisputed
fact that the material was incapable of manual excavation.

66. The learned Single Judge also noted that the Tribunal’s
conclusion was supported by ample material on record, including
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 25 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

contemporaneous Field Book entries, the geological report of
Walchand College, site inspections conducted in the presence of the
Engineer’s representative, and the overall conduct of the parties
during the execution of the works. The reliance on such material was
not to dilute the contractual criteria but rather to substantiate the
Tribunal’s classification of the material.

67. The Appellants’ contention that the terms of the contract were
unambiguous and therefore, the learned Arbitrator was precluded from
the use of contemporaneous material or conduct of the parties is
misconceived. The material relied upon by the Tribunal was not
intended to vary or override the contractual definitions but to ascertain
whether the stipulated conditions were in fact satisfied. The Tribunal’s
reliance on this material was therefore appropriate and does not
constitute an impermissible resort to extrinsic evidence so as to vitiate
the award.

68. We find no merit in the Appellants’ submission that the
absence of prior approval for blasting or strict compliance with
stacking and measurement formalities relevant in determining the
nature of the material encountered. These provisions govern post-
classification processes and do not dictate the foundational issue of
whether the material should be classified as hard rock or ordinary
rock. In any event, the Tribunal based its conclusion on a cumulative
assessment of contemporaneous records and expert material, not
merely on the unilateral use of mechanical equipment by the
respondent.

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 26 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

69. The submission that Mr Appa Rao, the on-site Engineer, lacked
authority to bind the Appellants on matters involving financial
implications is also without merit. The Tribunal, after appraising the
relevant clauses, correspondences, and site records, found that Mr Rao
acted as the authorised representative of the Engineer-in-Charge. In
our view, this finding is a pure finding of fact and is well supported by
the evidence. The attempt to revisit this issue before this Court is
merely a renewed effort in the hope that the said arguments may find
favour at the appellate stage.

70. In the present case, we concur with the learned Single Judge
that the determination of whether the material encountered during
excavation was ordinary rock or hard rock is essentially a question of
fact, lying within the exclusive domain of the Arbitral Tribunal as the
final arbiter of facts. This is a trite principle of law, consistently
reiterated in decisions such as State of Rajasthan v. Puri
20
Construction Co. Ltd. , MCD v. Jagan Nath Ashok Kumar and
21 22
Another , and Oswal Woollen Mills Ltd. v. Oswal Agro Mills Ltd ,
wherein it has been held that the appreciation of evidence lies squarely
within the domain of the learned Arbitrator, and re-evaluation of
finding of fact is outside the limited jurisdiction vested in the Court
under Section 37 of the Act.

71. It is apt to conclude that the finding of the Tribunal regarding
the classification of the material was not a case of rewriting the
contract between the parties, but rather one of construing and applying

20
(1994) (6) SCC 485
21
(1987) 4 SCC 497
22
(2018) 16 SCC 219

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 27 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

its terms to the facts on record. The Tribunal’s conclusion reflects a
careful interpretation and application of the contract, which cannot be
interfered with merely because an alternative view is possible.

72. Another ground of challenge raised by the Appellants
concerned Claim No. 2, wherein they contended that the use of tie
bolts in RCC wall shuttering for the trunk drain was not mandated
under the contract and was adopted purely as a matter of executional
convenience by the Respondent without permission. The Appellants
argued that, in the absence of any explicit contractual stipulation
requiring the use of tie bolts, the Tribunal erred in treating their use as
necessary and in allowing payment by classifying the same as an extra
item.

73. We note that this identical contention was raised before the
learned Single Judge, who recorded that the learned Senior Counsel
for the Appellants had, albeit reluctantly, conceded that the findings
returned by the Tribunal on the issue of the use of tie bolts were
findings of fact not amenable to re-examination under Section 34 of
the Act. Despite such concession, the contention has been reiterated
before us.

74. Upon our perusal of the arbitral award and the impugned
judgment, we find that the learned Arbitrator returned a clear finding
that the use of tie bolts was in compliance with the CPWD
Specifications. Their efficacy and quantity were also not disputed. The
learned Single Judge also noted that the conclusion arrived at by the
learned Arbitrator was based on due appreciation of documentary
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 28 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

evidence, as well as the oral testimony and cross-examination of the
Engineer-in-Charge. These findings, being factual in nature, are based
on the evidence on record, and the reasons cited by the Tribunal have
been concurred with by the Court exercising jurisdiction under Section
34 of the Act. As such, there is no scope for interference by this Court.

75. Another contention raised by the Appellants related to alleged
non-compliance with Clause 10 of the GCC. The Appellants argued
that the execution of any extra item was permissible only after
receiving written instructions from the Engineer-in-Charge, which was
admittedly absent prior to the excavation of hard rock or the use of tie
bolts. They further contended that Clause 11, being merely a provision
to determine rates, could not be invoked independently of Clause 10,
and the learned Arbitrator, by doing so, impermissibly re-wrote the
contract. Clauses 10 and 11 are reproduced below for our
consideration:

“10. The Engineer-in-Charge shall have power (i) to make
alteration in, omissions, from additions to, or substitutions for the
original specifications, drawings, designs and instructions that
may appear to him to be necessary or advisable during the
progress of the work, and (ii) to omit a part· of the works in case of
non-availability of a portion of the Site or for any other reasons
and the Contractor shall be bound to carry out the Works in
accordance with any Instructions given to him in writing signed by
the Engineer-in-Charge and such alterations, omissions, additions
or substitution shall form part of the Contract as if originally
provided therein and any altered, additional or substituted work
which the Contractor may be directed to do in the manner above
specified as part of the Works, shall be carried out by the
Contractor on the same conditions in all respects including price
on which he agreed to do the main work. Any alterations,
omissions, additions or substitutions which radically change the
original nature of· the contract shall be ordered by the Engineer-
in-Charge as a deviation and in the event of any deviation being
ordered which in the opinion of the Contractor changes the
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 29 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

original ·nature of the Contract, he shall nevertheless carry it out
and the disagreement if any, as to the nature of work and the rate
to be paid therefore shall be resolved in accordance with
Condition 56.
11. In the case of contract items, substituted items, contract-cum-
substituted items, or additional items which exceed the limits laid
down in sub-para (vi) of Condition 10 above, the contractor may,
within fourteen days of receipt of order or ·occurrence of the
excess claim revision of the rates, supported by proper analysis,
for the work in excess of above-mentioned limits, provided that if
the rates so claimed are in excess of the rates specified In the
Schedule of Quantities or of those derived in accordance with the
provisions of sub-para (i) to (iv) of Condition 10 by more than five
per cent, inform the Engineer- In-Charge under advice to the
Accepting Authority and the Engineer-in-Charge shall, within
three months of receipt of the claim supported by analysis, after
giving consideration to the analysis of the rates submitted by the
Contractor, determine the rates on the basis of market rates and if
the rates so determined exceed the rates specified in the Schedule
of Quantities or those derived in accordance with the provisions of
sub-paras (i) to (iv) of condition 10 by more than five percent, the
Contractor shall be paid in accordance with the rates so
determined. In the event-of the Contractor falling to claim revision
of rates within the stipulated period, or if the rates determined by
the Engineer-in-charge within a period three months of receipt of
the claim supported by analysis are within five percent of the rates
specified in the Schedule of Quantities or of those determined in
accordance with the provisions of sub-paras (i) to (iv) of Condition
10, the Engineer-in-Charge shall make payment at the rates as
specified in the Schedule of Quantities or those already determined
under sub-paras (i) to (iv) of Condition 1C for the quantities in
excess of the limits laid down in subpara (vi) of Condition 10.”

(Emphasis supplied)


76. In our view, a plain and harmonious reading of Clauses 10 and
11 of the GCC leaves little room for doubt that the two clauses operate
in distinct fields. Clause 10 clearly vests the Engineer-in-Charge with
the authority to direct alterations, additions, omissions or substitutions
to the original scope of work, and applies where such deviations are
ordered through written instructions. The contractor’s obligation under
Clause 10 is thus predicated upon a direction emanating from the
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 30 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Engineer-in-Charge.

77. Clause 11, on the other hand, addresses a materially different
situation. It entitles the contractor to propose and seek revision of rates
where extra work arises during execution, subject to compliance with
the prescribed notice and procedure. It mandates that the contractor
notify the Engineer-in-Charge within fourteen days of such
occurrence, and that the Engineer-in-Charge determines the rates
within three months thereafter. Read thus, Clause 11 operates in a
separate and distinct sphere from Clause 10.


78. The reliance placed by the Appellants on the decision in K.R.
Anand (supra) is misplaced. The said decision was based on a
contractual framework where payment for extra work was contingent
upon written instructions issued by the Engineer-in-Charge. The
present contract, however, expressly incorporates Clause 11, which
governs the framework for additional or excess work proposed by the
contractor and entitles the contractor to payment subject to compliance
with the prescribed procedure.

79. In Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut
23
Utpadan Nigam Ltd. , the Supreme Court held that the interpretation
of contractual terms is primarily within the domain of the learned
Arbitrator, and interference is warranted only where the interpretation
adopted is one that no fair-minded or reasonable person could possibly
arrive at. More recently, in Prakash Atlanta (JV) v. National

23
(2019) 7 SCC 236
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 31 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

24
Highways Authority of India , the Supreme Court reiterated that
arbitral findings regarding the interpretation of the contract cannot be
supplanted merely because an alternative view is plausible. Based on
this principle, the learned Arbitrator’s reliance on Clause 11 cannot be
construed as re-writing or travelling beyond the contractual terms but
constitutes a reasonable and plausible interpretation of the relevant
contractual clauses.

80. We find no infirmity in the learned Arbitrator’s invocation of
Clause 11 of the GCC instead of Clause 10. The Tribunal carefully
examined compliance with the said clause and recorded that the
Respondent promptly notified the Appellants upon encountering hard
rock on 19.11.2014 and sought approval for the use of tie bolts by
notice dated 15.01.2015.

81. The Appellants’ contention regarding unilateral execution
without approval was rejected by the Tribunal on the ground that the
Appellants failed to respond within the stipulated period. Having
continued to accept the execution of the work without objection, the
Appellants were therefore disentitled to resist payment on the ground
of the absence of formal approval.

82. In our considered view, there was neither express approval nor
rejection or direction to stop the work by the Appellants in clear terms
when the extra work was being executed. Having remained supine ,
while continuing to derive the benefit of the executed work, the
Appellants cannot now be permitted to take advantage of their own

24
2026 SCC OnLine SC 98
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 32 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

inaction. The maxim nullus commodum capere potest de injuria sua
propria squarely applies, as a party cannot be allowed to profit from
its own default. Such conduct strikes at the very foundation of fairness
and equity and admits of no indulgence whether under Section 34 or
Section 37 of the Act.

83. The objection regarding the grant of future interest, despite a
contractual prohibition on interest “at any stage”, is no longer res
integra. The scope and effect of Section 31(7) of the Act have been
authoritatively settled by the Supreme Court in R.P. Garg v. Telecom
25
Department , in the following terms-

“9. We are of the opinion that the judgment of High Court is
clearly erroneous. Firstly, the interest granted by the First
Appellate Court only related to post award period, and therefore,
for this period, the agreement between the parties has no bearing.
Section 31(7)(b) deals with grant of interest for post award period
i.e., from the date of the award till its realization. The statutory
scheme relating to grant of interest provided in Section 31(7)
creates a distinction between interest payable before and after the
award. So far as the interest before the passing of the award is
concerned, it is regulated by Section 31(7)(a) of the Act which
provides that the grant of interest shall be subject to the agreement
between the parties. This is evident from the specific expression at
the commencement of the sub-section which says “unless
otherwise agreed by the parties”.
*
11. So far as the entitlement of the post-award interest is
concerned, sub-Section (b) of Section 31(7) provides that the sum
directed to be paid by the Arbitral Tribunal shall carry interest. The
rate of interest can be provided by the Arbitrator and in default the
statutory prescription will apply. Clause (b) of Section 31(7) is
therefore in contrast with clause (a) and is not subject to party
autonomy. In other words, clause (b) does not give the parties the
right to “contract out” interest for the post-award period. The
expression ‘unless the award otherwise directs’ in Section 31(7)(b)
relates to rate of interest and not entitlement of interest. The only

25
2024 SCC OnLine SC 2928
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 33 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

distinction made by Section 31(7)(b) is that the rate of interest
granted under the Award is to be given precedence over the
statutorily prescribed rate. The assumption of the High Court that
payment of the interest for the post award period is subject to the
contract is a clear error.
12. The clear position of law that granting post-award interest
is not subject to the contract between the parties was recently
affirmed in the decision of this Court in Morgan Securities &
Credits (P) Ltd. v. Videocon Industries Ltd. (2023) 1 SCC
602, wherein the court observed as follows:
“24. The issue before us is whether the phrase “unless the
award otherwise directs” in Section 31(7)(b) of the Act only
provides the arbitrator the discretion to determine the rate of
interest or both the rate of interest and the “sum” it must be paid
against. At this juncture, it is crucial to note that both clauses (a)
and (b) are qualified. While, clause (a) is qualified by the
arbitration agreement, clause (b) is qualified by the arbitration
award. However, the placement of the phrases is crucial to their
interpretation. The words, “unless otherwise agreed by the
parties” occur at the beginning of clause (a) qualifying the entire
provision. However, in clause (b), the words, “unless the award
otherwise directs” occur after the words “a sum directed to be
paid by an arbitral award shall” and before the words “carry
interest at the rate of eighteen per cent”. Thereby, those words
only qualify the rate of post-award interest.
25. Section 31(7)(a) confers a wide discretion upon the
arbitrator in regard to the grant of pre-award interest. The
arbitrator has the discretion to determine the rate of reasonable
interest, the sum on which the interest is to be paid, that is whether
on the whole or any part of the principal amount, and the period
for which payment of interest is to be made — whether it should be
for the whole or any part of the period between the date on which
the cause of action arose and the date of the award. When a
discretion has been conferred on the arbitrator in regard to the
grant of pre-award interest, it would be against the grain of
statutory interpretation to presuppose that the legislative intent
was to reduce the discretionary power of the arbitrator for the
grant of post-award interest under clause (b). Clause (b) only
contemplates a situation where the arbitration award is silent on
post-award interest, in which event the award-holder is entitled to
a post-award interest of eighteen per cent.”
13. The High Court, therefore, committed an error in relying on
the decision of this Court in Jaiprakash (supra). The judgment
in Jaiprakash deals with the issue of prohibition of pendente-
lite interest and will have no application to the facts of the present
case where the claim relates to post-award interest.”

(Emphasis supplied)
Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 34 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

84. The Supreme Court has clearly drawn a distinction between
pre-award interest under Section 31(7)(a), which is subject to party
autonomy, and post-award interest under Section 31(7)(b), which is
statutory and cannot be contracted out. The expression “unless the
award otherwise directs” in Section 31(7)(b) pertains to the rate of
interest, and where the arbitral award specifies a rate, such rates
prevails over a statutory rate. In light of this settled legal position, we
find that there is no infirmity in the view taken by the learned Single
Judge. While the contractual prohibition may validly operate to bar
pre-award interest, it does not affect the entitlement to future interest
to the Respondent due to the bar in the contract. Therefore, no case for
interference is made out.

85. Lastly, we address the objection regarding the award of costs
by the learned Arbitrator. The Arbitral Tribunal, having allowed
Claim Nos. 1, 2, 4, and 5 in favour of the Respondent and having
found the counter-claim to be lacking in bona fide , exercised its
discretion to award costs of Rs.13,45,850/- to the Respondent, while
declining to award costs to the Appellants. The discretion to award
costs squarely lies within the domain of the learned Arbitrator under
Section 31A of the Act. No perversity, arbitrariness, or manifest
injustice has been demonstrated in the exercise of such discretion.
Given that the majority of claims were allowed in favour of the
Respondent, the award of costs does not shock the conscience of the
Court and thus does not warrant interference by us.

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 35 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

Conclusion

86. In view of the above discussion, we are of the considered view
that the Appellants have failed to establish any valid grounds to justify
interference with the arbitral award.

87. The present appeal, in substance, seeks a re-appreciation of
facts and a substitution of the arbitral view with another possible view.
Such an exercise is plainly impermissible within the narrow confines
of interference under Section 34 and 37 of the Act, particularly when
the view adopted by the Tribunal is a reasonable and legally
sustainable one.

88. The findings returned by the Tribunal on the classification of
soil for Claim No. 1, the use of tie-bolts for Claim No. 2, the
entitlement to post-award interest, and the grant of costs are not only
plausible but also justified on the facts of the case. These findings are
supported by contemporaneous records, technical material, and the
conduct of the parties during execution of the works. They fall
squarely within the exclusive domain of the Arbitral Tribunal as the
final arbiter of facts and the interpretation of the contract.

89. No element of arbitrariness, perversity, or patent illegality is
discernible in the arbitral award. Therefore, the arbitral award cannot
be characterised as a re-writing of the contract, as contended by the
Appellants, but rather constitutes a legitimate exercise of arbitral
discretion within the bounds of the agreement and the governing law.

Signature Not Verified
FAO(OS) (COMM) 16/2022 Page 36 of 37

Signed By:ANUBHAV
TRIPATHI
Signing Date:24.02.2026
18:08:50

90. For the reasons aforesaid, the present appeal is accordingly
dismissed.

91. There shall be no order as to costs.



OM PRAKASH SHUKLA, J.

C.HARI SHANKAR, J.
FEBRUARY 24, 2026 /ss/pa/at/gunn