Acromax Industries Private Limited vs Government E Marketplace Gem & Anr.
- Court
- Delhi High Court
$~65
* IN THE HIGH COURT OF DELHI AT NEW DELHI
th
% Date of Decision: November 27 , 2026
# CNR No. DLHC010567202026
+ W.P.(C) 17475/2026 & CM APPL. 81656/2026, CM APPL.
81657/2026
ACROMAX INDUSTRIES PRIVATE LIMITED .....Petitioner
Through: Mr. Gurdeep Singh, Mr. Garv
Singh, Advocates.
versus
GOVERNMENT E MARKETPLACE GEM
& ANR. .....Respondents
Through: Ms. Binsy Susan, Mr. Akshay
Sharma, Mr. Sambhav Sharma
and Ms. Deeksha Pokhriyal,
Advocates.
CORAM:
HON'BLE MR. JUSTICE AMIT MAHAJAN
AMIT MAHAJAN, J. (Oral)
1. By the present petition, the petitioner challenges the termination
of his contract by Respondent No. 2 vide its letter dated 26.09.2026.
The petitioner further seeks quashing of the suspension order dated
17.11.2026 imposed by Respondent No. 1 pursuant to which the
petitioner’s account has been marked on temporary moratorium from
17.11.2026 to 16.01.2027.
2. Succinctly stated, the petitioner is a vendor on Respondent No.
1’s platform and is engaged in the business of manufacturing LED
Signature Not Verified
W.P.(C) 17475/2026 Page 1 of 5
Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24
lights, fittings, lamp, accessories and other electrical products. On
14.02.2026, Respondent No. 2 placed an order with the petitioner for
supply installation and commissioning of High Mast Lighting for
hazardous area of Maharashtra region pipeline network for a total
order value of ₹61,36,000/-. The contract stipulated an overall
completion period of eight months with delivery of material within
five months and installation, testing and commissioning during the
succeeding three months. Respondent No.2 terminated the contract
with the petitioner vide letter dated 26.09.2026 alleging inter alia,
non-submission of engineering drawings, incomplete soil bearing
capacity investigations and failure to achieve the stipulated supply and
execution milestones despite reminders and notices. Following the
termination, Respondent No. 2 raised an incident on the GeM portal
alleging non delivery of good/services post successful bidding
resulting in cancellation of a contract exceeding ₹10 lakh.
Consequently, Respondent No. 1 imposed a temporary
moratorium/suspension on the petitioner’s account from 17.11.2026 to
16.01.2027.
3. The petitioner has sought to impress upon this Court that the
very termination of contract by Respondent No. 2 is premature since,
as per the minutes of meeting itself, the contractual completion date
was 14.10.2026. It has been asserted that when the contract
completion date itself stipulated completion on 14.10.2026,
Respondent No. 2 ought not to have prematurely terminated the
contract alleging failure on the part of the petitioner to meet stipulated
delivery milestones, alleged failure to furnish engineering drawings,
Signature Not Verified
W.P.(C) 17475/2026 Page 2 of 5
Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24
incomplete soil investigations and non-delivery of material. As
discernible from the pleadings, the petitioner claims that more than
75% of the contractual work had already been undertaken, and in such
circumstances, it is argued that Respondent No. 2 ought not to have
prematurely terminated the contract.
4. The principal controversy in the present case concerns the
legality of the termination of the underlying contract by Respondent
No. 2 and the consequential incident recorded by Respondent No. 1
which led to suspension of the petitioner’s account from 17.11.2026 to
16.01.2027.
5. While the petitioner has pleaded that more than 75% of the
work was already undertaken by it under the contract and the
stipulated completion of contract was on 14.10.2026, from a perusal
of the impugned termination letter dated 26.09.2026, it is apparent that
Respondent No.2 has disputed the petitioner’s claim and observed that
the physical progress of the contract remained at 0%, and no
meaningful progress towards supply, installation, testing or
commissioning had been achieved. It has further been observed that as
per the contract, the delivery of materials was supposed to be
undertaken within five months, however, despite reminders, the
petitioner failed to even submit structural drawings or undertake
mandatory soil bearing capacity testing at one of the locations.
6. Having considered the grievance of the petitioner, and minutely
traversed the record, this Court is of the opinion that the present case
involves disputes concerning the interpretation, performance and
enforcement of contractual terms. The controversy between the parties
Signature Not Verified
W.P.(C) 17475/2026 Page 3 of 5
Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24
also involves several disputed questions of fact including the actual
extent of work executed by the petitioner, whether completion of soil
bearing test at three out of four locations constituted substantial
compliance, whether non submission of engineering drawings
amounted to contractual default, whether the delay if any was
attributable to the petitioner or to extraneous factors such as site
access, clearances etcetera. Such disputed questions and rival
assertions would necessarily entail detailed factual examination and
interpretation of contractual terms and the same can only be
determined upon appreciation of contractual documents,
correspondences, technical records and other evidences. The said
contentions cannot be ascertained or decided by this Court while
exercising jurisdiction under Article 226 of the Constitution of India.
7. Pertinently, even the impugned measure undertaken by
Respondent No. 1 in the nature of temporary suspension finds its
genesis in the alleged non delivery and consequent cancellation of the
particular commercial contract. The Incident Management Policy
itself clarifies that administrative actions taken thereunder do not
curtail the legal and contractual remedies available to the buyers and
sellers under the contract. The policy further provides a mechanism of
rectification, and subject to stipulated conditions, an appeal against the
imposition of a temporary moratorium.
8. It is well settled that the jurisdiction under Article 226 of the
Constitution of India is discretionary and is not ordinarily exercised
for adjudication of disputes arising essentially out of contractual
obligations, especially where the determination involves disputed
Signature Not Verified
W.P.(C) 17475/2026 Page 4 of 5
Signed By:HARMINDER
KAUR
Signing Date:28.11.2026
16:49:24
questions of facts and appreciation of evidence.
9. In such circumstances, this Court does not find any cogent
ground to exercise its jurisdiction under Article 226 of the
Constitution of India. The present petition is accordingly dismissed.
10. The petitioner is at liberty to avail appropriate remedies in
accordance with law.
11. It is clarified that nothing stated herein shall be construed as an
adjudication or examination of the merits of the disputes.
12. Pending applications also stand disposed of.
AMIT MAHAJAN, J
NOVEMBER 27, 2026
DU