M/s Simbhaoli Power Private Limited vs Uttar Pradesh Electricity Regulatory Commission & Ors
- Court
- Appellate Tribunal For Electricity
- Case type
- APPEAL
- Decided on
- 16-03-2026
<div> <b>IN THE APPELLATE TRIBUNAL FOR ELECTRICITY </b><br /> (Appellate Jurisdiction) <br /> <b>APPEAL No. 128 of 2021 </b><br /> th<br /> Dated: 16 March, 2026 <br /> Present: Hon’ble Ms. Seema Gupta, Officiating Chairperson <br /> Hon’ble Mr. Virender Bhat, Judicial Member <br /> <b> </b><br /> <b>In the matter of: </b><br /> <br /> <b> </b><br /> <br /> <b>M/s Simbhaoli Power Private Limited </b><br /> Through its Managing Director <br /> Unit – Chilwariya, Dist – Bahraich <br /> Email: [email protected] … Appellant <br /> <i> </i><br /> <i>Versus </i><br /> <br /> <b>1. </b> <b>Uttar Pradesh Electricity Regulatory Commission </b><br /> Through its Secretary, <br /> Vidyut Niyamak Bhawan, <br /> Vibhuti Khand-II, Near Mantri Awas, <br /> Gomti Nagar, Lucknow – 226010, U.P. <br /> Email: [email protected] <br /> <br /> <b>2. </b> <b>Uttar Pradesh Power Corporation Limited </b><br /> Through its Managing Director <br /> Shakti Bhawan, 14, Ashok Marg, <br /> Lucknow – 226001 <br /> Email: [email protected] <br /> <br /> <b>3. </b> <b>Madhyanchal Vidyut Vitran Nigam Ltd. </b><br /> Through its Managing Director <br /> 4A, Gokhale Marg, <br /> Lucknow – 226001 <br /> Email: [email protected] <br /> <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 1 of 33 </i></b><br /> <i> </i><br /><br /> <br /> <b>4. </b> <b>The Chief Engineer </b><br /> Power Purchase Directorate <br /> Shakti Bhawan, 14, Ashok Marg, <br /> Lucknow <br /> Email: [email protected] … Respondent (s) <br /> <br /> <br /> <br /> Counsel for the Appellant(s) : D D Chopra, Sr. Adv. <br /> Shailesh Verma <br /> Swati Updhayay <br /> for App. 1 <br /> <br /> <br /> Counsel for the Respondent(s) : Hemant Sahai <br /> Nitish Gupta <br /> Puja Priyadarshini <br /> Allan Massey <br /> Nipun Sharma <br /> Sagnik Maitra <br /> for Res. 2 <br /> <br /> <br /> <b>J U D G M E N T </b><br /> <b>PER HON’BLE MR. VIRENDER BHAT, JUDICIAL MEMBER </b><br /> 1. The Appellant M/s. Simbhaoli Power Pvt. Ltd., a power <br /> producer from renewable sources in the State of UP, is aggrieved by <br /> th st<br /> the order dated 25 January, 2021 passed by 1 Respondent – Uttar <br /> Pradesh Electricity Regulatory Commission (hereinafter referred to <br /> as “the Commission”) in Petition No. 1557 of 2020. <br /> <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 2 of 33 </i></b><br /> <i> </i><br /><br /> Factual Matrix : <br /> 2. The Appellant is engaged in the business of generation of <br /> renewable power as well as other incidental business and has its <br /> place of work at Chilwariya, District- Baharaich, Uttar Pradesh. <br /> nd<br /> 3. The 2 Respondent – Uttar Pradesh Power Corporation Ltd. <br /> (UPPCL) is the holding company of five Distribution Companies <br /> rd<br /> (DISCOMS) operating in the State of UP. The 3 Respondent – <br /> Madhyanchal Vidyut Vitran Nigam Ltd. is one of those Discoms <br /> under whose area of operation fall the generating units of the <br /> Appellant. <br /> 4. The Appellant owns and operates more than one power <br /> generating units which were commissioned in different years. <br /> 5. The Appellant has entered into a Power Purchase Agreement <br /> th<br /> (PPA) dated 26 April, 2007 with Respondent No. 2 for export of <br /> contracted capacity of 19 MW from its two generating units of <br /> capacity 12 MW and 19 MW after meeting its in-house requirement <br /> of 12 MW for its sugar mill. These two generating units were <br /> commissioned in the year 2007. The Appellant has another <br /> generating unit of 18 MW capacity from which it exports 16 MW of <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 3 of 33 </i></b><br /> <i> </i><br /><br /> nd th<br /> surplus power to the 2 Respondent under PPA dated 27 August, <br /> 2013. <br /> 6. The 12 MW generating unit was the first to be commissioned <br /> by the Appellant. Since, according to the Appellant, this generating <br /> unit had outlived its life for the purpose of optimum performance and <br /> had lost its efficacy on account of becoming very old, its technology <br /> also becoming obsolete as a result of which it require frequent <br /> repairing thus leading to shutdown and higher consumption of fuel, <br /> the Appellant isolated and dismantled the same in order to avoid <br /> further breakdowns and requiring heavy cost of repair. <br /> 7. Upon dismantling of the said 12 MW generating unit, the in-<br /> house consumption of 12 MW was met from the other 19 MW unit <br /> which had been commissioned along with the said 12 MW unit, thus <br /> bringing down the surplus capacity from 19 MW to 7MW for export <br /> nd th<br /> of power to the 2 Respondent under PPA dated 26 April, 2007. <br /> 8. Accordingly, the Appellant informed the Chief Manager, Power <br /> Purchase Directorate (Respondent No. 4) about the said reduction <br /> th<br /> in its export capacity from 19 MW to 7 MW vide letter dated 16 <br /> September, 2019 with the request to carry out necessary <br /> amendments in the PPA in this regard. <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 4 of 33 </i></b><br /> <i> </i><br /><br /> 9. When the Appellant did not receive any response in this regard <br /> from Respondent No. 4, it approached the Commission by way of <br /> Petition No. 1557 of 2020 under Section 86(1)(e) and (f) of the <br /> Electricity Act, 2003 with the following prayers :- <br /> <i>(i)</i> <i>the Hon’ble Commission may be pleased to allow </i><br /> <i>the Petitioner to reduce its export capacity from 19MW </i><br /> <i>after isolation of 12MW generating capacity and reduction </i><br /> <i>of export capacity from its 19MW generating Plant to 7MW </i><br /> <i>with effect from 16/09/2019, and </i><br /> <i>(ii) </i> <i>the Hon’ble Commission may be pleased to direct </i><br /> <i>Respondent No. 3 to suitably amend principle PPA dated </i><br /> <i>26/04/2007 and SPPA dated 27/08/2013 by taking export </i><br /> <i>capacity of the Petitioner at 23MW (7MW + 16MW), and </i><br /> <i>(iii) </i> <i>the Hon’ble Commission may be pleased to direct </i><br /> <i>Respondent No.3 to suitably revise weighted average of </i><br /> <i>contracted capacities of the units commissioned in </i><br /> <i>different years as detailed above, and, or </i><br /> <i>(iv) </i> <i>the Hon’ble Commission may be pleased to issue </i><br /> <i>any other further order or directions in favour of the </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 5 of 33 </i></b><br /> <i> </i><br /><br /> <i>Petitioner as it may be deem fit and proper under the facts </i><br /> <i>and circumstances of the case.” </i><br /> 10. This petition has been dismissed by the Commission vide <br /> th<br /> impugned order dated 25 January, 2021 holding that dismantling <br /> as well as isolation of 12 MW generating unit from the plant was a <br /> purely commercial decision of the Appellant which is not covered <br /> under Force Majeure Clause in the PPA as the same was not <br /> exclusively beyond Appellant’s control. The Commission also held <br /> th<br /> that there is no provision in the PPA dated 26 April, 2007 and <br /> th<br /> Supplementary PPA dated 27 August, 2013 permitting reduction of <br /> contracted capacity. Accordingly, the Commission held the <br /> Appellant not entitled to reduction of contracted capacity under the <br /> said PPA and SPPA. <br /> 11. Hence, the Appellant is in the appeal before us. <br /> Submissions of the Learned Counsels : <br /> 12. We have heard the Learned Senior Counsel for the Appellant <br /> nd<br /> and learned Counsel for the 2 Respondent. We have also perused <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 6 of 33 </i></b><br /> <i> </i><br /><br /> the impugned order as well as the written submissions filed by the <br /> Learned Counsels. <br /> 13. Learned Senior Counsel appearing on behalf of the Appellant <br /> vehemently argued that isolation of 12 MW generating unit followed <br /> by its dismantling is an event of unforeseen circumstances that were <br /> beyond the control of the Appellant and as per Article 26 of the PPA <br /> which is co-terminus with the Section 56 of the Indian Contract Act, <br /> 1872. He would argue that even though there is no express clause <br /> in the PPA with regard to the change in the contacted capacity by <br /> any party, the Appellant was prevented from performing its <br /> obligations under the PPAs on account of the reasons beyond its <br /> control and the circumstances in which it was not possible for the <br /> Appellant to operate the said 12 MW generating unit. He submitted <br /> that the Commission has failed to appreciate that the generator <br /> cannot be compelled to continue to export power irrespective of the <br /> problems it may face resulting in a situation where the very object of <br /> entering into a contract namely supply of electricity to the consumer <br /> and the recovery of cost in a reasonable manner would be defeated. <br /> 14. It was further argued by the Learned Senior Counsel that <br /> increase in cost of operating the 12 MW generating unit and resultant <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 7 of 33 </i></b><br /> <i> </i><br /><br /> inability not been able to recover the cost of supply of electricity in a <br /> reasonable manner by the Appellant, can be easily categorized as <br /> Force Majeure event which made it impracticable for the Appellant <br /> performed its obligations under the PPAs. He would submit that the <br /> provisions of the PPA must be given a holistic interpretation and <br /> need to be read in context of the scheme of Electricity Act to balance <br /> the interest of both the generator as well as the purchaser. He placed <br /> reliance upon the judgement of the Hon’ble Supreme Court in <br /> Satyabrata Ghose vs. Mugneeram Bangur & Co., (1953) 2 SCC 437, <br /> Energy Watchdog vs. CERC, (2017) 14 SCC 80 and the judgement <br /> of Delhi High Court in Halliburton Offshore Services vs. Vedanta <br /> Limited 2020 SCC online DEL 2068. <br /> 15. Referring to the judgement in the case of Satyabrata Ghose, <br /> Learned Senior Counsel argued that Force Majeure clause is not to <br /> be interpreted literally but shall also include within its scope <br /> impracticability which hinders the performance of the contract. He <br /> submitted that the general understanding of Force Majeure envisages <br /> that the performance of the promise has become impossible which is <br /> also the purport of Sections 36 & 56 of Indian Contract Act, 1972. He <br /> submitted that the Commission has failed to consider that by running <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 8 of 33 </i></b><br /> <i> </i><br /><br /> an unviable generating unit just to comply with the terms of the PPA, <br /> the Appellant will not be able to recover the cost of electricity which is <br /> against the intent of Section 61(d) of the Electricity Act, 2003. <br /> 16. Thus, according to the Learned Senior Counsel, the impugned <br /> order of the Commission cannot be sustained and is liable to be <br /> dismissed. <br /> nd<br /> 17. Per Contra, it is argued on behalf of the 2 Respondent that <br /> there is no provision in the PPAs for reduction of the contracted <br /> capacity agreed therein and the Appellant cannot be permitted to <br /> resile from express terms of PPA read with SPPA to unilaterally <br /> reduce the contracted capacity agreed therein. It is submitted that the <br /> sanctity of the contracts must be maintained and the terms of the <br /> PPAs cannot be altered unilaterally at whims and fancies of any of <br /> the parties. <br /> 18. It is submitted that the Appellant had signed the PPAs with the <br /> nd<br /> 2 Respondent with open eyes thereby unequivocally undertaking <br /> to supply 35 MW of power for period of 20 years which was <br /> admittedly without any caveats and not premised on the procurement <br /> of bagasse at a particular rate and therefore, the dismantling of 12 <br /> MW unit is in absolute breach of the provisions of the PPAs more so <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 9 of 33 </i></b><br /> <i> </i><br /><br /> nd<br /> for the reason that prior consent of the 2 Respondent for the same <br /> was not obtained. <br /> 19. It is also argued that as per Article 7.2 of the PPA, the fuel <br /> linkage is the responsibility of the Appellant and no pass through of <br /> the cost can be permitted and as per Article 12.2 of the PPA the <br /> DISCOM cannot be held responsible for any damage caused to the <br /> electrical system/generating set of the generating plant on account <br /> of errors or defects in the design, procurement, installation, testing, <br /> maintenance and operation of the system. It is argued that inefficient <br /> running of 12 MW unit and its dismantling much before the expiry of <br /> PPA is indicative of the poor design and improper planning of the <br /> project by the Appellant and, therefore, the Appellant is not entitled to <br /> any protection under the Force Majeure clause in the PPAs. <br /> 20. It is further argued that none of the provisions in the PPAs <br /> provides that rise in fuel prices, operational difficulty due to technical <br /> snags, high repairing costs, technology becoming obsolete, high <br /> consumption of bagasse fuel qualifies as Force Majeure event and <br /> the reliance placed on behalf of the Appellant on the phrase,” “or any <br /> other similar or dissimilar cause reasonably beyond its exclusively <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 10 of 33 </i></b><br /> <i> </i><br /><br /> control” used in Clause 26 of the PPA is also far fetched and <br /> misconceived. <br /> 21. Relying upon the judgements of the Hon’ble Supreme Court in <br /> nd<br /> Energy Watchdog case (cited by the Learned Counsel for 2 <br /> Respondent) and Alopi Parshad and Sons Limited Vs. Union of India <br /> 1960 SCC Online SC 13, it is argued that mere hardship or contract <br /> becoming onerous to one of the parties does not automatically lead <br /> to frustration of the contract and therefore, the case set up by the <br /> Appellant has no merit at all. <br /> <b>Our Analysis </b><br /> 22. At the outset we may note that a PPA is a contract executed <br /> between a power generator and a Distribution Licensee whereby the <br /> former agrees to sell the power generated in its generating stations <br /> and the later agrees to purchase the same on the terms and <br /> conditions as stated in the agreement. The tariff at which such power <br /> is to be sold/purchased is an essential term of a PPA. In our view, <br /> upon execution of the PPA it becomes a binding contract between <br /> the power generator and the Distribution Licensees and both are <br /> bound by its terms and conditions as well as the obligations cast <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 11 of 33 </i></b><br /> <i> </i><br /><br /> upon them under the agreement. A PPA is a creation of both the <br /> parties and, therefore, their rights/obligations flow from the terms <br /> and conditions contained therein. <br /> 23. The sanctity of the power purchase agreement had come up <br /> for consideration before the Hon’ble Supreme Court in Gujarat Urja <br /> Vikas Nigam Ltd. vs. Solar Semi-Conductors Power Company (Pvt.) <br /> Ltd., (2017) 16 SCC 498 in which, Hon’ble Justice Kurian Joseph, <br /> speaking for the Bench, held as under :- <br /> <i>“37. </i> <i>This Court should be specially careful in dealing </i><br /> <i>with matters of exercise of inherent powers when the interest </i><br /> <i>of consumers is at stake. The interest of consumers, as an </i><br /> <i>objective, can be clearly ascertained from the Act. The </i><br /> <i>Preamble of the Act mentions “protecting interest of </i><br /> <i>consumers” and Section 61 (d) requires that the interests of </i><br /> <i>the consumers are to be safeguarded when the appropriate </i><br /> <i>Commission specifies the terms and conditions for </i><br /> <i>determination of tariff. Under Section 64 read with Section </i><br /> <i>62, determination of tariff is to be made only after considering </i><br /> <i>all suggestions and objections received from the public. </i><br /> <i>Hence, the generic tariff once determined under the statute </i><br /> <i>with notice to the public can be amended only by following </i><br /> <i>the same procedure. Therefore, the approach of this Court </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 12 of 33 </i></b><br /> <i> </i><br /><br /> <i>ought to be cautious and guarded when the decision has its </i><br /> <i>bearing on the consumers. </i><br /> <i>38. </i> <i>Regulation 85 provides for extension of time. It may </i><br /> <i>be seen that the same is available only in two specified </i><br /> <i>situations – (i) for extension of time prescribed by the </i><br /> <i>Regulations, and (ii) extension of time prescribed by the </i><br /> <i>Commission in its order for doing any act. The control period </i><br /> <i>is not something prescribed by the Commission under the </i><br /> <i>Conduct of Business Regulations. The control period is also </i><br /> <i>not an order by the Commission for doing any act. </i><br /> <i>Commissioning of a project is the act to be performed in </i><br /> <i>terms of the obligation under the PPA and that is between </i><br /> <i>the producer and the purchaser viz. Respondent 1 and </i><br /> <i>appellant. Hence, the Commission cannot extend the time </i><br /> <i>stipulated under the PPA for doing any act contemplated</i> <br /> <i>under the agreement in exercise of its exercise of its powers </i><br /> <i>under Regulation 85. Therefore, there cannot be an </i><br /> <i>extension of the control period under the inherent powers of </i><br /> <i>the Commission</i> . <br /> <i>39. </i> <i>The Commission being a creature of statute cannot </i><br /> <i>assume to itself any powers which are not otherwise </i><br /> <i>conferred on it. In other words, under the guise of exercising </i><br /> <i>its inherent power, as we have already noticed above, the </i><br /> <i>Commission cannot take recourse to exercise of a power, </i><br /> <i>procedure for which is otherwise specifically provided under </i><br /> <i>the Act. </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 13 of 33 </i></b><br /> <i> </i><br /><br /> <i>40. </i> <i>Extension of control period has been specifically </i><br /> <i>held to be outside the purview of the power of the </i><br /> <i>Commission as per EMCO. This appeal is hence, allowed. </i><br /> <i>The impugned orders are set aside. However, we make it </i><br /> <i>clear that this judgment or orders of the Appellate Tribunal or </i><br /> <i>Commission shall not stand in the way of Respondent 1 </i><br /> <i>taking recourse to the liberty available to them for </i><br /> <i>redetermining of tariff if otherwise permissible under law and </i><br /> <i>in which case it will be open to the parties to take all available </i><br /> <i>contentions before the Commission.” </i><br /> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i>(Emphasis Supplied) </i><br /> <i> </i><br /> 24. Hon’ble Justice R. Banumathi, in a separate but concurrent <br /> note has observed of this aspect as under :- <br /> <i>“65. </i> <i>It is contended that Section 86(1)(b) of the Act </i><br /> <i>empowers the State Commission to regulate the price of sale </i><br /> <i>and purchase of electricity between the generating </i><br /> <i>companies and distribution licensees and the terms and </i><br /> <i>conditions of the PPA cannot be set to be inviolable. Merely </i><br /> <i>because in PPA, tariff rate as per Tariff Order (2010) is </i><br /> <i>incorporated that does not empower the Commission to vary </i><br /> <i>the terms of the contract to the disadvantage of the </i><br /> <i>consumers whose interest the Commission is bound to </i><br /> <i>safeguard. Sanctity of PPA entered into between the parties </i><br /> <i>by mutual consent cannot be allowed to be breached by a </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 14 of 33 </i></b><br /> <i> </i><br /><br /> <i>decision of the State Commission to extend the earlier </i><br /> <i>control period beyond its expiry date, to the advantage of the </i><br /> <i>generating company-respondent No. 1 and disadvantage of </i><br /> <i>the appellant. Terms of PPA are binding on both the parties </i><br /> <i>equally. </i><br /> <i>66. </i> <i>In Gujarat Urja Vikas Nigam Limited v. EMCO </i><br /> <i>Limited and Another (2016) 11 SCC 182, facts were similar </i><br /> <i>and the question of law raised was whether by passing the </i><br /> <i>terms and conditions of PPA, the respondent can assail the </i><br /> <i>sanctity of PPA. This Court held that Power Producer cannot </i><br /> <i>go against the terms of the PPA and that as per the terms of </i><br /> <i>the PPA, in case, the first respondent is not able to </i><br /> <i>commence the generation of electricity within the 'control </i><br /> <i>period' the first respondent will be entitled only for lower of </i><br /> <i>the tariffs. </i><br /> <i>67. </i> <i>The first respondent placed reliance upon Gujarat </i><br /> <i>Urja Vikas Nigam Limited v. Tarini Infrastructure Limited and </i><br /> <i>Others (2016) 8 SCC 743. In the said case, this Court was </i><br /> <i>faced with the substantial question of law viz. whether the </i><br /> <i>tariff fixed under a PPA (Power Purchase Agreement) is </i><br /> <i>sacrosanct and inviolable and beyond review and correction </i><br /> <i>by the State Electricity Regulatory Commission. In that case, </i><br /> <i>respondent No.1 thereon-power producer had entered into a </i><br /> <i>PPA with the appellant therein-distribution licensee for sale </i><br /> <i>of electricity from the generating stations to the extent of the </i><br /> <i>contracted quantity for a period of 35 years at Rs. 3.29 per </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 15 of 33 </i></b><br /> <i> </i><br /><br /> <i>KWH subject to escalation of 3% per annum till date of </i><br /> <i>commercial operation. However, later the power producer </i><br /> <i>found that the place from where the power was to be </i><br /> <i>evacuated was at a distance of 23 kms. as opposed to a </i><br /> <i>distance of 4 kms, envisaged in the concession agreement </i><br /> <i>entered into between the Respondent-power producer and </i><br /> <i>Narmada Water Resources Department (Respondent No.2 </i><br /> <i>therein). On this ground the respondent had sought revision </i><br /> <i>of tariff by the State Electricity Commission. This Court held </i><br /> <i>that Section 86(1)(b) of the Act empowers State Commission </i><br /> <i>to regulate price of sale and purchase of electricity</i> <i>between </i><br /> <i>generating companies and distribution licensees through </i><br /> <i>agreements for power, produced for distribution and supply </i><br /> <i>and that the state commission has power to re-determine the </i><br /> <i>tariff rate when the tariff rate mentioned in the PPA between </i><br /> <i>generating company and distribution licensee was fixed by </i><br /> <i>State Regulatory Commission in exercise of its statutory </i><br /> <i>powers. Relevant portion of the paras (17) and (18) of the </i><br /> <i>judgment, read as under: (SCC pp.756 & 758) </i><br /> <i>“17. As already noticed, Section 86(1)(b) of the Act </i><br /> <i>empowers the State Commission to regulate the price of </i><br /> <i>sale and purchase of electricity between the generating </i><br /> <i>companies and distribution licensees through agreements </i><br /> <i>for power produced for distribution and supply. As held by </i><br /> <i>this Court in V.S. Rice & Oil Mills v. State of A.P. AIR 1964 </i><br /> <i>SC 1781, K. Ramanathan v. State of T.N. (1985) 2 SCC </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 16 of 33 </i></b><br /> <i> </i><br /><br /> <i>116 and D.K. Trivedi & Sons v. State of Gujarat 1986 </i><br /> <i>Supp. SCC 20 the power of regulation is indeed of wide </i><br /> <i>import. ... </i><br /> <i>18. </i> <i>All the above would suggest that in view of Section </i><br /> <i>86(1)(b) the Court must lean in favour of flexibility and not </i><br /> <i>read inviolability in terms of PPA insofar as the tariff </i><br /> <i>stipulated therein as approved by the Commission is </i><br /> <i>concerned. It would be a sound principle of interpretation </i><br /> <i>to confer such a power if public interest dictated by the </i><br /> <i>surrounding events and circumstances require a review of </i><br /> <i>the tariff. </i><br /> <i>The facts of the present case, as elaborately noted at the </i><br /> <i>threshold of the present opinion, would suggest that the Court </i><br /> <i>must lean in favour of such a view also having due regard to </i><br /> <i>the provisions of Section 41 and 21 of the General Clauses </i><br /> <i>Act, 1898. ... </i><br /> <i>" In the facts and circumstances of that case and that the tariff </i><br /> <i>rate of Rs.3.29/- per KWH was subject to escalation and </i><br /> <i>subject to periodic review. Evacuation was changed from a </i><br /> <i>distance of 4 kms. to 23 kms. from its switch yard. On account </i><br /> <i>of the same, respondent No.1 therein had incurred an </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 17 of 33 </i></b><br /> <i> </i><br /><br /> <i>additional cost of about Rs.10 crores which was not envisaged </i><br /> <i>in the Concession Agreement. In such facts and changed </i><br /> <i>circumstances, this Court thought it apposite to take a lenient </i><br /> <i>view and allow the State Commission to re-determine the tariff </i><br /> <i>rate. </i><br /> <i>68. </i> <i>In exercise of its statutory power, under Section 62 </i><br /> <i>of the Electricity Act, the Commission has fixed the tariff rate. </i><br /> <i>The word ‘tariff’ has not been defined in the Act. Tariff means </i><br /> <i>a schedule of standard/prices or charges provided to the </i><br /> <i>category or categories for procurement by licensee from </i><br /> <i>generating company, wholesale or bulk or retail/various </i><br /> <i>categories of consumers. After taking into consideration the </i><br /> <i>factors in Section 61(1)(a) to (i), the State Commission </i><br /> <i>determined the tariff rate for various categories including </i><br /> <i>Solar Power PV project and the same is applied uniformly </i><br /> <i>throughout the State. When the said tariff rate as determined </i><br /> <i>by the Tariff Order (2010) is incorporated in the PPA between </i><br /> <i>the parties, it is a matter of contract between the parties. In </i><br /> <i>my view, respondent No.1 is bound by the terms and </i><br /> <i>conditions of PPA entered into between respondent No.1 </i><br /> <i>and the appellant by mutual consent and that the State </i><br /> <i>Commission was not right in exercising its inherent </i><br /> <i>jurisdiction by extending the first control period beyond its </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 18 of 33 </i></b><br /> <i> </i><br /><br /> <i>due date and thereby substituting its view in the PPA, which </i><br /> <i>is essentially a matter of contract between the parties.” </i><br /> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i> </i> <i>(Emphasis supplied) </i><br /> 25. These observations of the Hon’ble Supreme Court in the above <br /> noted judgements fortify the view that the PPA between power <br /> generator and Distribution Licensees is sacrosanct document, the <br /> terms and conditions which were binding upon the parties and its <br /> sanctity cannot be permitted to be breached. <br /> 26. Clause 26 of the PPAs executed between the Appellant and the <br /> nd<br /> 2 Respondent relates to Force Majeure and is extracted <br /> hereinbelow :- <br /> <i>26. </i> <i>FORCE MAJEURE </i><br /> <i>26.1 If any party hereto is wholly or partially prevented </i><br /> <i>from performing any of its obligations under this </i><br /> <i>agreement by reason of or due to lightning, earthquake, </i><br /> <i>riots, fire, floods, invasion, insurrection, rebellion, mutiny, </i><br /> <i>tidal wave, civil unrest, epidemics, explosion, the order of </i><br /> <i>any court, judge or civil authority, change in State or </i><br /> <i>National law, war, any act of God or a public enemy, or </i><br /> <i>any other similar or dissimilar cause reasonably beyond </i><br /> <i>its exclusive control and not attributable to its neglect, </i><br /> <i>then in any such event, such party shall be excused from </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 19 of 33 </i></b><br /> <i> </i><br /><br /> <i>whatever performance is prevented by such event, to the </i><br /> <i>extent so prevented, and such party shall not be liable for </i><br /> <i>any damage, sanction or loss for not performing such </i><br /> <i>obligations. </i><br /> <i>26.2 The party invoking this clause shall satisfy the other </i><br /> <i>party of the occurrence of such an event and give written </i><br /> <i>notice explaining the circumstances, within seven days to </i><br /> <i>the other party and take all possible steps to revert to </i><br /> <i>normal conditions at the earliest. </i><br /> <i>26.3 Any payments that become/have become due </i><br /> <i>under this agreement shall not be withheld, on grounds of </i><br /> <i>force majeure conditions developing. </i><br /> 27. The term “Force Majeure” originates from the Code Napoleon <br /> of France that translates to mean “Superior Force’ or ‘Greater <br /> Force”. This would indicate a drastic or a fundamental change in the <br /> substance of the contract that is brought about by an event which <br /> was neither anticipated by the parties nor under their control, <br /> resulting in non-performance of the contractual obligations. <br /> 28. The term “Force Majeure” has been defined in Blacks Law <br /> Dictionary as “an event or effect that can neither be anticipated nor <br /> controlled”. Force Majeure is a contractual provision to deal with <br /> uncertain situations due to which contractual obligations could not <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 20 of 33 </i></b><br /> <i> </i><br /><br /> be performed and these situations cannot be pre-saged at the time <br /> of entering into the contract. Generally, a Force Majeure clause <br /> provides a temporary reprieve to the parties from performing their <br /> obligations under the contract if the events mentioned in the clause <br /> are satisfied. <br /> 29. Although the term “Force Majeure” does not find mention in <br /> any provisions of the Contract Act, 1872, its doctrine can be found <br /> embodied in Section 32 of the Act which renders a contract void <br /> where an event upon which performance of the contract is <br /> contingent, becomes impossible. In order to invoke the doctrine of <br /> Force Majeure, the party doing so shall have to establish; <br /> (i) There is a valid and subsisting contract between the <br /> parties. <br /> <br /> (ii) Some part of the contract is yet to be performed. <br /> <br /> (iii) The contract has become impossible to perform. <br /> <i> </i><br /> 30. The consequences of the Force Majeure event will have to be <br /> ascertained and determined to find out whether it renders the <br /> contract altogether impossible, unlawful or impracticable to perform <br /> and thereby frustrates its performance. Whether it is established that <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 21 of 33 </i></b><br /> <i> </i><br /><br /> the conditions have materially and substantially affected the parties <br /> as well as their obligations and where there is no way to perform the <br /> contract during the existence of such conditions, the contract is <br /> annulled and both the contracting parties are discharged of their <br /> subsequent obligations. Under these circumstances, neither party <br /> has right to sue the other party for breach of such contracts. <br /> 31. In India, the Courts follow the contracts strictly in terms of the <br /> Force Majeure clauses. In a case where the contract must be <br /> rescinded on account of Force Majeure events, the burden to prove <br /> is on the party claiming it. Unless there is compelling evidence that <br /> a contract cannot be performed under any circumstances, the <br /> Courts do not favour party resorting to frustration of contract and its <br /> termination. <br /> 32. The concept of Force Majeure had come up before the Hon’ble <br /> Supreme court in Satyabrata Ghose vs Mugneeram Bangur & Co., <br /> 1954 SCR 310 in which it was held that the word “impossible” has <br /> not been used in the sense of physical or literal impossibilities. The <br /> determination of whether Force Majeure event has actually occurred <br /> does not centre around its impossibilities alone. A mere <br /> “impracticality of performance” with regards to such matter of the <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 22 of 33 </i></b><br /> <i> </i><br /><br /> contract will also suffice. It was held that when an untoward event or <br /> unprecedented change of circumstances impacts the very <br /> foundation of the contract between the parties, this event will be <br /> considered as Force Majeure and the contract, therefore, would <br /> become impossible to perform. <br /> 33. Generally, Force Majeure Clauses are applicable without any <br /> restrictions, but at the same time, a party cannot hide its own <br /> negligence and malafide intention behind this clause. So where the <br /> non-performance is caused by usual and natural consequences and <br /> not by uncertain consequences which are beyond the control of the <br /> parties, the Force Majeure clause cannot be enforced in those <br /> causes. Further, the Force Majeure clause can also not be invoked <br /> simply because the contract has become financially and <br /> commercially more difficult to perform. The party taking shelter <br /> under the Force Majeure clause needs to convince the Court that <br /> the Force Majeure event was beyond its control and the event could <br /> not be stopped even after ensuring due diligence and taking all <br /> possible steps. Broadly speaking, in order to qualify as a Force <br /> Majeure event, it must pass following triple test :- <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 23 of 33 </i></b><br /> <i> </i><br /><br /> <i>(i) </i> <i>the event projected as Force Majeure should be </i><br /> <i>unpractical and unforceable (i.e. unpracticality); </i><br /> <i>(ii) </i> <i>the event must make the execution of the contractual </i><br /> <i>obligations impossible (i.e. impossibility); and </i><br /> <i>(iii) </i> <i>the event must not be created on account of default or </i><br /> <i>negligence of the party claiming it (i.e. externality). </i><br /> 34. Hon’ble Supreme Court has recently settled the law relating to <br /> Force Majeure in Energy Watchdog Vs. CERC (2017) 14 SCC 80 <br /> and has laid down following principles for its application :- <br /> <i>a. </i> <i>“Force Majeure would operate as part of a contract as a </i><br /> <i>contingency under Section 32 of the Indian Contract Act </i><br /> <i>1872 (‘ICA’) </i><br /> <i>b. </i> <i>Independent of the contract sometimes, the doctrine of </i><br /> <i>frustration could be invoked by a party as per Section 56, </i><br /> <i>ICA. </i><br /> <i>c. </i> <i>The impossibility of performance under Section 56, ICA </i><br /> <i>would include impracticability or uselessness keeping in </i><br /> <i>mind the object of the contract. </i><br /> <i>d. </i> <i>If an untoward event or change of circumstance totally </i><br /> <i>upsets the very foundation upon which the parties </i><br /> <i>entered their agreement it can be said that the promisor </i><br /> <i>finds it impossible to do the act which he had promised </i><br /> <i>to do. </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 24 of 33 </i></b><br /> <i> </i><br /><br /> <i>e. </i> <i>Express terms of a contract cannot be ignored on a </i><br /> <i>vague plea of equity. </i><br /> <i>f. </i> <i>Risks associated with a contract would have to be borne </i><br /> <i>by the parties. </i><br /> <i>g. </i> <i>Performance is not discharged simply if it becomes </i><br /> <i>onerous between the parties. </i><br /> <i>h. </i> <i>Alteration of circumstances does not lead to frustration </i><br /> <i>of a contract. </i><br /> <i>i. </i> <i>Courts cannot generally absolve performance of a </i><br /> <i>contract either because it has become onerous or due to </i><br /> <i>an unforeseen turn of events. Doctrine of frustration has </i><br /> <i>to be applied narrowly. </i><br /> <i>j. </i> <i>A mere rise in cost or expense does not lead to </i><br /> <i>frustration. </i><br /> <i>k. </i> <i>If there is an alternative mode of performance, the Force </i><br /> <i>Majeure clause will not apply. </i><br /> <i>l. </i> <i>The terms of the contract, its matrix or context, the </i><br /> <i>knowledge, expectation, assumptions and the nature of </i><br /> <i>the supervening events have to be considered. </i><br /> <i>m. </i> <i>If the Contract inherently has risk associated with it, the </i><br /> <i>doctrine of frustration is not to be likely invoked. </i><br /> <i>n. </i> <i>Unless there was a break in identity between the </i><br /> <i>contract as envisioned originally and its performance in </i><br /> <i>the altered circumstances, doctrine of frustration would </i><br /> <i>not apply.” </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 25 of 33 </i></b><br /> <i> </i><br /><br /> <i>35. </i> The settled position, thus, is that the Force Majeure Clause is <br /> to be <i>interpreted</i> strictly and the parties to a contract cannot be <br /> excused from its performance on flimsy and unjustified grounds. We <br /> find it profitable to quote following paragraph from another recent <br /> judgement of Supreme Court in Halliburton Offshore Services Vs. <br /> Vedanta Limited and Anr. 2020 SCC Online Del 2068 :- <i> </i><br /> <i>“It is the settled position in law that a Force Majeure </i><br /> <i>clause is to be interpreted narrowly and not broadly. </i><br /> <i>Parties ought to be compelled to adhere to contractual </i><br /> <i>terms and conditions and excusing non-performance </i><br /> <i>would be only in exceptional situations. As observed in </i><br /> <i>Energy Watchdog (supra) it is not in the domain of Courts </i><br /> <i>to absolve parties from performing their part of the </i><br /> <i>contract. It is also not the duty of Courts to provide a </i><br /> <i>shelter for justifying non-performance. There has to be a </i><br /> <i>‘real reason’ and a ‘real justification’ which the Court </i><br /> <i>would consider in order to invoke a Force Majeure </i><br /> <i>clause.” </i><br /> <i>36. </i> Now, let us proceed to examine whether the isolation and <br /> dismantling of 12 MW generating unit by the Appellant was <br /> occasioned by any Force Majeure event as envisaged under Clause <br /> 26 of the PPA and whether the circumstances were such which made <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 26 of 33 </i></b><br /> <i> </i><br /><br /> it impossible for the Appellant to continue performing its obligation <br /> under the PPA thereby frustrating the contracts. <i> </i><br /> th<br /> <i>37. </i> Concededly, letter dated 16 September, 2019 addressed by <br /> st<br /> the Appellant to Respondent No. 4 is the 1 communication sent in <br /> this regard by the Appellant. Therefore its contents are very material <br /> and are extracted hereinbelow:- <i> </i><br /> <i>“Our company has power purchase agreements with </i><br /> <i>Madhyanchal Vidyut Vitran Nigam Ltd, for 19MW dated </i><br /> <i>26/04/2007 and further PPA of 16MW dated 27/08/2013. </i><br /> <i>Therefore total PPA of 35MW with the generation capacity </i><br /> <i>of (1x15MW + 1x22MW + 1x18MW) total 55MW. </i><br /> <i> </i><br /> <i>Since Availability of fuel is one of the constraints as </i><br /> <i>bagasse generation as % of cane has reduced over the </i><br /> <i>year, and also price of bagasse in the market is very high </i><br /> <i>making it non viable to operate. We are using almost 80% </i><br /> <i>biomass in our 18MW Generating plant, even then we are </i><br /> <i>unable to fulfil the fuel requirement of our 15MW </i><br /> <i>generating plant and compelled to stop its operation. </i><br /> <i>Therefore, SPPL is unable to export 19MW Power from </i><br /> <i>its combined generating plant 15MW & 22MW. We will be </i><br /> <i>able to export only 7MW power from 22MW generating </i><br /> <i>plant. </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 27 of 33 </i></b><br /> <i> </i><br /><br /> <i> </i><br /> <i>Therefore you are requested to reduce the export </i><br /> <i>capacity from 19MW to 7MW, ie reduction by 12MW in our </i><br /> <i>PPA dated 26/04/2007, and allow to tariff on weighted </i><br /> <i>average of 7MW in place of 19MW and PPA of 16MW will </i><br /> <i>continue as it is. </i><br /> <i> </i><br /> <i>We request you to kindly issue the amendment in PPA </i><br /> <i>dated 26/04/2007 and accordingly in supplementary </i><br /> <i>PPA.” </i><br /> <i>(Emphasis supplied) </i><br /> <i>38. </i> It is evident that the reason given for reduction of export quantity <br /> of power from 19 MW to 7 MW in this communication is reduction in <br /> availability of fuel and increase in price of Bagasse in the market <br /> which made it non-viable for the Appellant to operate the generating <br /> unit. <i> </i><br /> rd<br /> <i>39. </i> Vide letter dated 23 December, 2019, the Appellant has <br /> intimated the Respondent No. 4 about discarding the 12 MW TG Set <br /> due to process steam requirement of sugar mill and non economical <br /> performance of the same. It is also informed that the Appellant has <br /> installed a new 18 MW TG Set for the said purpose. <i> </i><br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 28 of 33 </i></b><br /> <i> </i><br /><br /> 40. <i> </i> In the petition filed by the Appellant before the Commission <br /> the reasons for isolating and dismantling of the 12 MW generating <br /> unit have been set out in paragraph 9 which is reproduced <br /> hereinbelow:- <br /> <i>“That on account of increase in the cost of bagasse and </i><br /> <i>its non availability the Petitioner is finding it difficult to run </i><br /> <i>its old 12MW bagasse based generating plant on account </i><br /> <i>of its higher consumption of bagasse as compared to </i><br /> <i>newer plants based on modern technology. The Petitioner </i><br /> <i>therefore decided to isolate the above 12MW plant by </i><br /> <i>dismantling the same.” </i><br /> 41. Manifestly, the case of the Appellant throughout has been that <br /> on account of increase in cost of Bagasse and its non-availability, <br /> Appellant found it difficult to run its old 12MW Bagasse based <br /> generating plant on account of its higher consumption of Bagasse as <br /> compared to new generating units based on modern technology. <br /> 42. Therefore, we feel in agreement with the observations of the <br /> Commission in the impugned order that the Appellant has taken the <br /> decision of dismantling the 12 MW generating unit for its inefficient <br /> operational performance viz. higher consumption of bagasse and had <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 29 of 33 </i></b><br /> <i> </i><br /><br /> become economically viable. In these circumstances, it is limpid that <br /> such decision was taken by the Appellant on the basis of purely <br /> commercial consideration and cannot be said to have occasioned due <br /> to any situation beyond the control of the Appellant. It has already <br /> been noted hereinabove on the basis of the legal principles <br /> enunciated by the Hon’ble Supreme Court and Delhi High Court with <br /> regards to the scope and application of “Force Majeure” and “Doctrine <br /> of Frustration” that these two concepts have to be applied narrowly <br /> and the courts cannot generally absolve performance of the contract <br /> either because it had become onerous or due to an unforeseen turn <br /> of events. The parties ought to be compelled to adhere to the terms <br /> and conditions contained in the contract and it does not lie in the <br /> domain of the Courts to absolve parties from performing their part of <br /> the contract and justify the non-performance. <br /> 43. The increase in the price of bagasse and its non-availability are <br /> not the factors which could not have been anticipated by the Appellant <br /> nd<br /> at the time of execution of the PPA with 2 Respondent. These were <br /> usual and natural events which could have been easily foreseen and <br /> taken into consideration at the time of entering into the PPAs with the <br /> nd<br /> 2 Respondent. Further, there is nothing on record from the side of <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 30 of 33 </i></b><br /> <i> </i><br /><br /> the Appellant to show that actually the price of bagasse in the market <br /> had increased astronomically and it was not easily available in the <br /> market. It also does not appear that the Appellant had taken any <br /> serious steps to mitigate the difficulties on account of purported <br /> increase in prices of bagasse and its unavailability in the market. <br /> 44. It is also evident from the record that the isolation and <br /> dismantling of the 12 MW generating unit was unilateral decision of <br /> the Appellant without seeking any concurrence or approval from the <br /> th<br /> respondents. In the letter dated 16 September, 2019, contents of <br /> which have already been extracted hereinabove, the Appellant has <br /> nowhere stated that the isolation and dismantling 12 MW generating <br /> unit is being contemplated and the same would be done shortly. The <br /> Appellant, all of a sudden informed Respondent No. 4 vide letter <br /> rd<br /> dated 23 December, 2019 that the 12 MW generating unit has had <br /> been discarded due to its non-economic performance. The contents <br /> of this letter also indicate that the decision of discarding 12 MW <br /> generating unit by the Appellant was taken only for the reason that <br /> the Appellant found it onerous to continue performing its obligations <br /> under the PPAs. <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 31 of 33 </i></b><br /> <i> </i><br /><br /> rd<br /> 45. Notably in the said letter dated 23 December, 2019, Appellant <br /> has also informed Respondent No. 4 that a new 18 MW generating <br /> unit has been installed in place of the old discarded 12 MW generating <br /> unit. Therefore, the appellant cannot claim inability or impossibility of <br /> performing its obligations under the PPAs for the reason that the <br /> nd<br /> entire contracted capacity could have been supplied to the 2 <br /> Respondent upon installation of new 18 MW generating unit in place <br /> of the old dismantled 12 MW generating unit. <br /> 46. We are unable to find any “real reason” and “real justification” <br /> for the Appellant to invoke the Force Majeure clause in the PPA and <br /> the doctrine of frustration because, as per the case set up by the <br /> Appellant itself before the Commission and before this Tribunal in this <br /> nd<br /> appeal, the contract executed by it with 2 Respondent has become <br /> financially as well as commercially difficult to perform and the plea of <br /> non-performance is based upon usual as well as natural <br /> consequences which were not beyond the anticipation and the control <br /> of the Appellant. Thus, the Appellant cannot be excused from <br /> performing its obligation under the PPAs on such unjustified grounds. <br /> Moreover, it is also manifest that the Appellant had an alternate mode <br /> of performance of the PPAs on account of the fact that a new 18 MW <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 32 of 33 </i></b><br /> <i> </i><br /><br /> generating unit had been installed in place of old dismantled 12 MW <br /> generating unit. <br /> 47. Hence, we are of the considered opinion that no case has been <br /> made out by the Appellant for seeking reduction in contracted <br /> th<br /> capacity by way of amendments in the PPAs dated 26 April, 2007 <br /> th<br /> and 27 August, 2013. The Appellant continues to remain bound by <br /> the terms and conditions agreed upon by the parties in these PPAs <br /> and shall be liable for the consequences in case of its inability to <br /> nd<br /> supply contracted capacity of power to the 2 Respondent. <br /> <b>Conclusion </b><br /> 48. In the light of the above discussion, we do not find any error or <br /> infirmity in the impugned order of the Commission. The appeal is <br /> devoid of any merit and is hereby dismissed. <br /> th<br /> Pronounced in the open court on this 16 day of March, 2026. <br /> <br /> (Virender Bhat) (Seema Gupta) <br /> Judicial Member Officiating Chairperson <br /> <br /> ✓ <br /> <i>REPORTABLE / NON REPORTABLE </i><br /> <br /> <i>js</i> <br /> <b><i>------------------------------------------------------------------------------------------------------------------ </i></b><br /> <b><i>Appeal No. 128 of 2021 </i></b> <b><i> </i></b> <b><i>Page 33 of 33 </i></b><br /> <i> </i></div>