State Industries Promotion Corporation of Tamil Na vs HMTD Engineering Private Ltd
- Court
- Madras High Court
WA No.1463 of 2025
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 17.11.2026
CORAM
THE HON'BLE MR.SUSHRUT ARVIND DHARMADHIKARI,
CHIEF JUSTICE
AND
THE HON'BLE MR.JUSTICE G. ARUL MURUGAN
WA No. 1463 of 2025
CNR:{HCMA010390242025}
1. State Industries Promotion Corporation
of Tamil Nadu Limited
Rep by its Chairman and Managing Director,
19-A, Rukmini Lakshmi Pathy Road,
Egmore, Chennai - 8.
2. The Project Officer
SIPCOT, IT Park, Siruseri, Chengalpattu Taluk,
Kancheepuram district. Appellants
Vs
HMTD Engineering Private Ltd
Rep by its Director, Mr. Munish Agarwal,
Having its Registered Office at D-4, MIDC,
Taloja, District Raigad, Maharastra 410 208. Respondent
Prayer: Appeal filed to set aside the order dated 30-10-2023 passed in WP
No. 10921 of 2021.
For Appellants Mr.Arjun Suresh,
Addl Advocate General
asst by Mr.K.S.Karthik Raja,
Standing Counsel
For Respondent Mr.Hari Radhakrishnan
Page 1 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
JUDGMENT
(Judgment of the Court was delivered by G.Arul Murugan, J.)
The State Industries Promotion Corporation (SIPCOT) has
preferred this intra-court appeal, calling in question the order dated
30.10.2023 in W.P. No.10921 of 2021, whereby the order passed by
the appellant dated 11.03.2021, cancelling the allotment made in
favour of the respondent, was set aside and the writ petition came to
be allowed.
2. The learned counsel appearing for the appellants contended
that the appellants have allotted lands in favour of the respondent vide
proceedings dated 10.01.2002, and since the conditions contained in
the allotment order were not complied with by the respondent, which
they are legally bound to do so, the authority, by the powers contained
in the clause mentioned in the allotment and the subsequent lease
deed executed, had issued the impugned order, which is assailed in the
writ petition, cancelling the allotment. He further submitted that when
the appellant had powers to cancel the allotment and resume the plot,
the learned Single Judge had erroneously interfered with the
proceedings only on the ground that in the earlier writ petition filed by
Page 2 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
the respondent, it was recorded that possession was handed over only
on 18.05.2006 and since the writ petition was pending, the respondent
could not have proceeded with the construction. When the learned
Single Judge has also observed in the order that the respondent could
be found fault with for not complying with the conditions for the period
from 05.07.2019 to 11.03.2021, that period itself is sufficient for
non-compliance of the conditions and in such circumstances ought to
have upheld the order of rejection, but had erroneously set aside the
cancellation order, which seeks for interference.
3. Countering the submissions, the learned counsel appearing for
the respondent submitted that even though the allotment order was
passed in favour of the respondent as early as on 10.01.2002 and the
lease deed was also executed on 11.01.2002, admittedly, the
possession in favour of the respondent was handed over only on
18.05.2006. When the possession was handed over only on
18.05.2006, immediately within two months, the first order of
cancellation came to be passed, which was successfully challenged in
the earlier writ petition, and after the writ petition was allowed, in
spite of the permission sought for by the respondent to proceed with
Page 3 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
the construction, nothing came out, but however, it only resulted in
the second order of cancellation, which was challenged in the writ
petition. He further submitted that the learned Single Judge, rightly by
considering the fact that the respondent cannot complete construction
within two months, had interfered with the order and allowed the writ
petition, thereby setting aside the order of cancellation passed by the
appellant, which needs no interference.
4. We heard the rival submissions and perused the materials
available on record.
5. The appellant has promoted an industrial layout at SIPCOT
Information Technology Park, Siruseri. By proceedings dated
10.01.2002, the appellants had allotted plot No.4/D4, measuring an
extent of 2 acres, in favour of the respondent. Based on the allotment
order issued, a lease deed was executed on 11.01.2002, registered in
the office of the Sub-Registrar, Thiruporur. Even though the allotment
order was issued in favour of the respondent and also a lease deed
was subsequently executed, it is not in dispute that the possession of
the property was handed over to the petitioner only on 18.05.2006.
Page 4 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
6. It is contended that the respondent ought to have come
forward and taken possession immediately on issuance of the
allotment order and execution of the lease deed; but, however, had
waited for nearly 4 to 5 years and had come forward only on
18.05.2006 to take over possession. Even then, when the appellants
chose to handover possession of the property to the respondent only
on 18.05.2006, in all fairness, the appellants ought to have allowed
the respondent to proceed with the construction. But however, the
appellants proceeded to pass an order dated 18.07.2006 cancelling the
allotment made in favour of the respondent. When the possession of
the property was handed over to the respondent only on 18.05.2006,
the cancellation came to be issued within two months on 18.07.2006,
on the ground that the respondent has violated clause 3(vii) and
3(viii), as the respondent has not put-up construction, completed it,
and put the property to use.
7. When the respondent assailed the first cancellation order in
W.P. No.33785 of 2007, the learned Single Judge, after finding that
when the possession was handed over only on 18.05.2006, the
appellants ought not to have passed an order of cancellation within
Page 5 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
two months on 18.07.2006, and thereby, by order dated 05.07.2019,
allowed the writ petition, setting aside the order of cancellation, and
remanded the matter back to the file of the appellants for fresh
consideration.
Paragraph 18 and 19 of the order is extracted hereunder:
“18. Though the allotment order was passed in the year 2002,
admittedly, possession was handed over to the petitioner only on
18.05.2006 and the impugned order came to be passed on 18.07.2006
on the ground that the petitioner had violated clauses 3(vii) and
3(viii) of the allotment order, and clause 18 of the lease deed, which
was executed in the year 2002, is legally unsustainable and one
cannot set up an Industry within a period of two months and hence
the cancellation order dated 20.07.2007 is liable to be set aside and
accordingly it is set aside.
19. In view of the above, the order dated 20.07.2007 passed
by the first respondent is set aside, and the matter is remitted back
to the first respondent for fresh consideration and pass appropriate
orders. No costs. Consequently, connected Miscellaneous Petition is
closed.”
8. In view of the order passed by the learned Single Judge,
though the order of cancellation dated 18.07.2006 was set aside, the
matter was remitted back to the file of the appellants to make fresh
consideration and pass appropriate orders. In such circumstances,
unless the appellants pass a fresh order, the respondent cannot be
Page 6 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
expected to proceed with the construction. When the order in the writ
petition was passed on 05.07.2019, the appellant by an order dated
07.03.2021 (second cancellation), has issued the impugned order in
the writ petition after referring to the representation made by the
respondent seeking to put-up construction, again cancelling the
allotment made in favour of the respondent. In fact, even in the
second cancellation order dated 11.03.2021, the appellant had chosen
to only refer to violation of clause 3 (vii)(viii)(ix) of the allotment
order, and clause (18) and (19) of the lease deed, which says that the
commencement of construction should be made within six months,
construction completed in 24 months, and commercial production
commenced within 30 months.
9. The second order of cancellation was also assailed by the
respondent before the writ court in W.P.No.10921 of 2021. The learned
Single Judge, by the impugned order dated 30.10.2023, by referring to
the earlier orders passed in the writ petition, disposed of the writ
petition by setting aside the order of cancellation passed by the
appellants, clarifying that it would not preclude the appellants from
determining fresh dates for reckoning the time lines of conditions
Page 7 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
stipulated in the allotment order. The learned Single Judge in the order
has also referred that at the maximum, the respondent could be
faulted only for non-compliance of the conditions during 05.07.2019 to
11.03.2021. In our considered opinion, the same also cannot be
construed as a fault on the part of the respondent as we have
indicated earlier that when the order was passed in the first writ
petition, the said writ petition was allowed and matter was remitted to
the file of the appellants directing them to pass fresh orders after
taking into consideration all the issues. When such an order was
passed, the period from 05.07.2019 to 11.03.2021 taken by the
appellant to pass orders, cannot be construed as default on the part of
the respondent.
10. Admittedly, even though the allotment in favour of the
respondent was made as early as on 10.01.2002 but possession of the
property has been handed over to the respondent only on 18.05.2006,
the appellants ought to have waited and allowed the respondent to
proceed with the construction and put the property into use for the
purpose for which it was allotted. On the contrary, immediately within
two months from the handing over of possession of the property, the
Page 8 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
appellants have issued an order of cancellation. When the cancellation
was challenged, an order of stay was granted in the writ petition, and
the writ petition ultimately came to be allowed only in the year 2019.
Even when the cancellation was set aside in the year 2019, it was with
a rider that the matter would be considered afresh by the authorities.
Even after the second cancellation order made in the year 2021, in the
writ petition, the said order of cancellation was stayed. When the
allotment itself was cancelled, which was only stayed by the interim
orders passed in the writ petition, the respondent cannot be expected
to proceed with the construction and make the property to put into use
for commercial production as it could not risk the entire investment
going waste if ultimately the writ petition came to be dismissed.
11. In such circumstances, we do not find any error or infirmity
in the orders passed by the learned Single Judge warranting
interference. Therefore, we are inclined to dismiss the writ appeal. It is
made clear that the respondent would be free to proceed with the
construction and put the property for commercial use as per the terms
of the allotment order.
Page 9 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
12. For all practical purposes, the conditions contained in the
allotment order would start having implications only from today, i.e.
the disposal of this writ appeal. It is further made clear that if the
respondent makes any further violations calculated from today, in not
complying with the conditions contained in the allotment order, the
appellants are free to take any further proceedings as per the terms of
allotment and the lease deed.
13. With the aforesaid, the writ appeal stands dismissed. There
will be no order as to costs. Consequently, CMP Nos.11155 of 2025
and 30204 of 2026 are closed.
(SUSHRUT ARVIND DHARMADHIKARI, CJ.) (G. ARUL MURUGAN, J.)
17.11.2026
Index : Yes/No
Neutral Citation : Yes/No
tar
Page 10 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
To
1.The Chairman and Managing Director,
State Industries Promotion Corporation
of Tamil Nadu Limited
19-A, Rukmini Lakshmi Pathy Road,
Egmore, Chennai - 8.
2. The Project Officer
SIPCOT, IT Park, Siruseri,
Chengalpattu Taluk,
Kancheepuram District.
Page 11 of 12
https://www.mhc.tn.gov.in/judis ( Uploaded on: 24/11/2026 03:04:28 pm )
WA No.1463 of 2025
THE HON'BLE CHIEF JUSTICE
AND
G. ARUL MURUGAN , J.
(tar)
WA No.1463 of 2025
17.11.2026
Page 12 of 12