The Office In Charge Naval Officers Mess Annex Noma vs Shri Surya Bhan Singh And Anr
- Court
- Delhi High Court
$~J
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment pronounced on: 01.07.2026
W.P.(C) 3377/2025 and CM APPL.15977/2025
+
THE OFFICE IN CHARGE NAVAL OFFICERS MESS ANNEX
NOMA .....Petitioner
Through: Mr. Vishwendra Verma, Ms. Shivali,
Ms. Ekta Tomar, Mr. Abhedya S.
Verma and Mr. Rajat, Advs.
versus
SHRI SURYA BHAN SINGH AND ANR .....Respondents
Through:
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA
JUDGMENT
1. The present petition has been filed by the petitioner assailing an order
dated 04.12.2023 passed by the Authority under Minimum Wages Act, 1948
and Regional Labour Commissioner (Central) New Delhi (hereinafter
referred as “ the Authority ”).
2. The respondent no.1/claimant, employed as security guard [through
respondent no.2 (OP-1 before the Authority), a security agency] with the
petitioner (OP-2 before the Authority) preferred an application dated
10.10.2019 before the Authority alleging that the petitioner has been paying
wages less than the minimum rates of wages fixed for his category of
employment under the Minimum Wages Act, 1948. The Authority
adjudicated the said application and consequently, by way of the impugned
order directed the petitioner to pay a total sum of Rs. 1,62,951/- to the
Signature Not Verified
W.P.(C) 3377/2025 Page 1 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
respondent no.1/claimant towards difference in minimum wage (amounting
to Rs. 54,317/-) and compensation at the rate of, double of the prescribed
Minimum Wage. Against the said directions the petitioner has preferred the
present petition.
3. Learned counsel on behalf of the petitioner submitted that a contract
dated 30.05.2017 came to be executed between the petitioner and respondent
no.2 for hiring of a supervisor and 17 watchmen (unskilled) for the
petitioner’s office at a minimum wage rate prescribed by the Government of
NCT of Delhi. It is stated that the petitioner and respondent no.2, in the
contract executed between them, mutually agreed for payment of minimum
wages to the concerned workers at a rate prescribed by the Government of
NCT of Delhi instead of Central Government, inasmuch as the contracting
agency i.e., respondent no.2 is registered with the Government of NCT of
Delhi, and therefore rules and regulations prescribed thereunder ought to be
applicable. However, the Authority without examining the merits of the case
and particularly the aforementioned aspect erroneously held respondent no.1
eligible for minimum wage rates prescribed by the Central Government for
skilled workers and issued the impugned directions.
4. It is further submitted that even otherwise the entire claim of the
respondent no.1 preferred before the Authority and also the impugned order
has been silent on the aspect as to why the respondent no.1, an unskilled
worker, is entitled to a minimum wage at the rate of Rs. 710/- per day i.e.,
the minimum wage prescribed by the Central Government for skilled
workers. Further, it is also contended that the attendance sheet undisputedly
proves that the respondent no.1 worked with the petitioner only for 100 days
instead of the 180 days claimed of.
Signature Not Verified
W.P.(C) 3377/2025 Page 2 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
5. It is also submitted that even though part V paragraph 1 of the
Contract Agreement contemplates that the paying authority for claim of bills
is DCDA (N), Project Sea Bird, West Block 5, R.K Puram, New Delhi, the
Authority has erroneously without examining the said aspect passed an order
directing the petitioner to pay the awarded amount.
6. It is thus contended that since the Authority failed to take into the
consideration the aforesaid aspects, the impugned order on account of being
arbitrary and erroneous is liable to be set-aside by this Court.
7. At the outset, it is noticed that vide order dated 19.03.2025 passed in
the present proceedings it was inter-alia recorded as under: -
“3. This petition has been filed after fifteen months of the order being
passed. Counsel for petitioner shall make submission as to why notice
should be issued in this matter, considering the laches in question.”
8. The law is well settled that although there is no prescribed limit for
filing of a writ petition, however, the aspect of delay and laches should not
be disregarded. The Court depending upon the facts and circumstances of a
particular matter ought to determine whether the petitioner is guilty of delay
and laches, so as to dismiss the petition on the said ground itself. The
Supreme Court has time and again reiterated the aforesaid view including in
Sudama Devi vs Commissioner and Ors., (1983) 2 SCC 1 as under:-
“We are of the view that so far as writ petition under Article 226 of the
Constitution is concerned, there can be no hard and fast rule of 90 days
by way of period of limitation but the general rule of laches alone can be
applied and this must necessarily depend on the facts and circumstances
of each case. The High Court has said in its order that “the writ petition
was beyond time by 136 days. Neither the explanation of 136 days nor
the explanation for filing it today, was given.” This view does not appear
to be correct because the High Court has proceeded on the assumption
that there is a period of limitation of 90 days and unless sufficient cause
is shown as contemplated under Section 5 of the Limitation Act a writ
petition filed after the expiration of 90 days is liable to be rejected. This
Signature Not Verified
W.P.(C) 3377/2025 Page 3 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
assumption is wholly unjustified. There is no period of limitation
prescribed by any law for filing a writ petition under Article 226 of the
Constitution. It is in fact doubtful whether any such period of limitation
can be prescribed by law. In any event one thing is clear and beyond
doubt that no such period of limitation can be laid down either under
rules made by the High Court or by practice. In every case it would have
to be decided on the facts and circumstances whether the petitioner is
guilty of laches and that would have to be done without taking into
account any specific period as a period of limitation. There may be cases
where even short delay may be fatal while there may be cases where even
a long delay may not be evidence of laches on the part of the petitioner.
We would, therefore, set aside the order of the High Court and remand
the writ petition to the High Court so that the High Court may dispose it
of on merits in accordance with law. We accordingly allow the appeal,
set aside the judgment and order of the High Court and direct that the
writ petition may be disposed of by the High Court on merits in
accordance with law. There will be no order as to costs.”
9. Similarly, in Mrinmoy Maity vs Chhanda Koley and Ors ., (2024) 15
SCC 215 the Supreme Court has held as under :-
“9. Having heard rival contentions raised and on perusal of the facts
obtained in the present case, we are of the considered view that the writ
petitioner ought to have been non-suited or in other words the writ
petition ought to have been dismissed on the ground of delay and laches
itself.
An applicant who approaches the court belatedly or in other words
sleeps over his rights for a considerable period of time, wakes up from
his deep slumber ought not to be granted the extraordinary relief by the
writ courts. This Court time and again has held that delay defeats equity.
Delay or laches is one of the factors which should be borne in mind by
the High Court while exercising discretionary powers under Article 226
of the Constitution of India. In a given case, the High Court may refuse
to invoke its extraordinary powers if laxity on the part of the applicant to
assert his right has allowed the cause of action to drift away and
attempts are made subsequently to rekindle the lapsed cause of action.
10. The discretion to be exercised would be with care and caution. If the
delay which has occasioned in approaching the writ court is explained
which would appeal to the conscience of the court, in such circumstances
it cannot be gainsaid by the contesting party that for all times to come
the delay is not to be condoned. There may be myriad circumstances
which gives rise to the invoking of the extraordinary jurisdiction and it
all depends on facts and circumstances of each case, same cannot be
described in a straitjacket formula with mathematical precision. The
ultimate discretion to be exercised by the writ court depends upon the
Signature Not Verified
W.P.(C) 3377/2025 Page 4 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
facts that it has to travel or the terrain in which the facts have travelled.
11. For filing of a writ petition, there is no doubt that no fixed period of
limitation is prescribed. However, when the extraordinary jurisdiction of
the writ court is invoked, it has to be seen as to whether within a
reasonable time same has been invoked and even submitting of
memorials would not revive the dead cause of action or resurrect the
cause of action which has had a natural death. In such circumstances on
the ground of delay and laches alone, the appeal ought to be dismissed
or the applicant ought to be non-suited. If it is found that the writ
petitioner is guilty of delay and laches, the High Court ought to dismiss
the petition on that sole ground itself, inasmuch as the writ courts are not
to indulge in permitting such indolent litigant to take advantage of his
own wrong. It is true that there cannot be any waiver of fundamental
right but while exercising discretionary jurisdiction under Article 226,
the High Court will have to necessarily take into consideration the delay
and laches on the part of the applicant in approaching a writ court.
12. This Court in Tridip Kumar Dingal v. State of W.B. [Tridip Kumar
Dingal v. State of W.B., (2009) 1 SCC 768 : (2009) 2 SCC (L&S) 119]
has held to the following effect: (SCC p. 784, paras 56-58)
“56. We are unable to uphold the contention. It is no doubt true that
there can be no waiver of fundamental right. But while exercising
discretionary jurisdiction under Articles 32, 226, 227 or 136 of the
Constitution, this Court takes into account certain factors and one of
such considerations is delay and laches on the part of the applicant in
approaching a writ court. It is well settled that power to issue a writ is
discretionary. One of the grounds for refusing reliefs under Article 32
or 226 of the Constitution is that the petitioner is guilty of delay and
laches.
57. If the petitioner wants to invoke jurisdiction of a writ court, he
should come to the Court at the earliest reasonably possible
opportunity. Inordinate delay in making the motion for a writ will
indeed be a good ground for refusing to exercise such discretionary
jurisdiction. The underlying object of this principle is not to
encourage agitation of stale claims and exhume matters which have
already been disposed of or settled or where the rights of third parties
have accrued in the meantime (vide State of M.P. v. Bhailal
Bhai [State of M.P. v. Bhailal Bhai, (1964) 15 STC 450 : 1964 SCC
OnLine SC 10 : (1964) 6 SCR 261 : AIR 1964 SC 1006] , Moon Mills
Ltd. v. Industrial Court [Moon Mills Ltd. v. Industrial Court, 1967
SCC OnLine SC 117 : AIR 1967 SC 1450] and Bhoop Singh v. Union
of India [Bhoop Singh v. Union of India, (1992) 3 SCC 136] ). This
principle applies even in case of an infringement of fundamental right
(vide Tilokchand Motichand v. H.B. Munshi [Tilokchand
Motichand v. H.B. Munshi, (1969) 1 SCC 110 : (1970) 25 STC 289]
, Durga Prashad v. Controller of Imports and Exports [Durga
Signature Not Verified
W.P.(C) 3377/2025 Page 5 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
Prashad v. Controller of Imports and Exports, (1969) 1 SCC 185]
and Rabindranath Bose v. Union of India [Rabindranath
Bose v. Union of India, (1970) 1 SCC 84] ).
58.
There is no upper limit and there is no lower limit as to when a
person can approach a court. The question is one of discretion and
has to be decided on the basis of facts before the court depending on
and varying from case to case. It will depend upon what the breach of
fundamental right and the remedy claimed are and when and how the
delay arose.”
13. It is apposite to take note of the dicta laid down by this Court
in Karnataka Power Corpn. Ltd. v. K. Thangappan [Karnataka Power
Corpn. Ltd. v. K. Thangappan, (2006) 4 SCC 322 : 2006 SCC (L&S)
791
] whereunder it has been held that the High Court may refuse to
exercise extraordinary jurisdiction if there is negligence or omissions on
the part of the applicant to assert his right
. It has been further held
thereunder: (SCC pp. 325-26, paras 6-9)
“6.
Delay or laches is one of the factors which is to be borne in mind
by the High Court when they exercise their discretionary powers
under Article 226 of the Constitution. In an appropriate case the High
Court may refuse to invoke its extraordinary powers if there is such
negligence or omission on the part of the applicant to assert his right
as taken in conjunction with the lapse of time and other
circumstances, causes prejudice to the opposite party. Even where
fundamental right is involved the matter is still within the discretion of
the Court
as pointed out in Durga Prashad v. Controller of Imports
and Exports [Durga Prashad v. Controller of Imports and Exports,
(1969) 1 SCC 185] . Of course, the discretion has to be exercised
judicially and reasonably.
7. What was stated in this regard by Sir Barnes Peacock in Lindsay
Petroleum Co. v. Prosper Armstrong Hurd [Lindsay Petroleum
Co. v. Prosper Armstrong Hurd, (1874) LR 5 PC 221 : 22 WR 492]
(LR PC at p. 239) was approved by this Court in Moon Mills
Ltd. v. Industrial Court [Moon Mills Ltd. v. Industrial Court, 1967
SCC OnLine SC 117 : AIR 1967 SC 1450] and Maharashtra
SRTC v. Balwant Regular Motor Service [Maharashtra
SRTC v. Balwant Regular Motor Service, 1968 SCC OnLine SC 54 :
(1969) 1 SCR 808 : AIR 1969 SC 329] . Sir Barnes had stated:
(Lindsay Petroleum case [Lindsay Petroleum Co. v. Prosper
Armstrong Hurd, (1874) LR 5 PC 221 : 22 WR 492] , LR pp. 239-40)
‘Now, the doctrine of laches in courts of equity is not an arbitrary
or a technical doctrine. Where it would be practically unjust to give
a remedy either because the party has, by his conduct done that
which might fairly be regarded as equivalent to a waiver of it, or
where by his conduct and neglect he has though perhaps not
Signature Not Verified
W.P.(C) 3377/2025 Page 6 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
waiving that remedy, yet put the other party in a situation in which
it would not be reasonable to place him if the remedy were
afterwards to be asserted, in either of these cases, lapse of time and
delay are most material. But in every case, if an argument against
relief, which otherwise would be just, is founded upon mere delay,
that delay of course not amounting to a bar by any statute of
limitation, the validity of that defence must be tried upon principles
substantially equitable. Two circumstances always important in
such cases are, the length of the delay and the nature of the acts
done during the interval which might affect either party and cause
a balance of justice or injustice in taking the one course or the
other, so far as it relates to the remedy.’
8. It would be appropriate to note certain decisions of this Court in
which this aspect has been dealt with in relation to Article 32 of the
Constitution. It is apparent that what has been stated as regards that
article would apply, a fortiori, to Article 226. It was observed
in Rabindranath Bose v. Union of India [Rabindranath Bose v. Union
of India, (1970) 1 SCC 84] that no relief can be given to the petitioner
who without any reasonable explanation approaches this Court under
Article 32 after inordinate delay. It was stated that though Article 32
is itself a guaranteed right, it does not follow from this that it was the
intention of the Constitution-makers that this Court should disregard
all principles and grant relief in petitions filed after inordinate delay
9
.
. It was stated in State of M.P. v. Nandlal Jaiswal [State of
M.P. v. Nandlal Jaiswal, (1986) 4 SCC 566] that the High Court in
exercise of its discretion does not ordinarily assist the tardy and the
indolent or the acquiescent and the lethargic. If there is inordinate
delay on the part of the petitioner and such delay is not satisfactorily
explained, the High Court may decline to intervene and grant relief in
exercise of its writ jurisdiction.
It was stated that this rule is premised
on a number of factors. The High Court does not ordinarily permit a
belated resort to the extraordinary remedy because it is likely to cause
confusion and public inconvenience and bring, in its train new
injustices, and if writ jurisdiction is exercised after unreasonable
delay, it may have the effect of inflicting not only hardship and
inconvenience but also injustice on third parties. It was pointed out
that when writ jurisdiction is invoked, unexplained delay coupled with
the creation of third-party rights in the meantime is an important
factor which also weighs with the High Court in deciding whether or
not to exercise such jurisdiction.”
14. Reiterating the aspect of delay and laches would disentitle the
discretionary relief being granted, this Court in Chennai Metropolitan
Water Supply & Sewerage Board v. T.T. Murali Babu [Chennai
Metropolitan Water Supply & Sewerage Board v. T.T. Murali Babu,
(2014) 4 SCC 108 : (2014) 1 SCC (L&S) 38] has held: (SCC p. 117, para
Signature Not Verified
W.P.(C) 3377/2025 Page 7 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
16)
“16.
Thus, the doctrine of delay and laches should not be lightly
brushed aside. A writ court is required to weigh the explanation
offered and the acceptability of the same. The court should bear in
mind that it is exercising an extraordinary and equitable jurisdiction.
As a constitutional court it has a duty to protect the rights of the
citizens but simultaneously it is to keep itself alive to the primary
principle that when an aggrieved person, without adequate reason,
approaches the court at his own leisure or pleasure, the court would
be under legal obligation to scrutinise whether the lis at a belated
stage should be entertained or not. Be it noted, delay comes in the way
of equity. In certain circumstances delay and laches may not be fatal
but in most circumstances inordinate delay would only invite disaster
for the litigant who knocks at the doors of the court. Delay reflects
inactivity and inaction on the part of a litigant — a litigant who has
forgotten the basic norms, namely, “procrastination is the greatest
thief of time” and second, law does not permit one to sleep and rise
like a phoenix. Delay does bring in hazard and causes injury to the
lis.”
10. The petitioner before this Court vide an additional affidavit dated
17.02.2026 attributed delay in filing of the present petition to administrative
delays/lapses and inadvertent misplacement of documents required to be
annexed thereto. The relevant portion of the said affidavit reads as under: -
“3. That it is humbly submitted that impugned order was passed on
04.12.2023. Since, there is no appeal provided under the Minimum
Wages Act, 1948, and the order of the Adjudicating Authority was
obtained by misleading and suppressing the facts a decision of the
Competent Authority at Naval HQs was required to be obtained for filing
a writ petition before this Hon’ble Court.
4. That, obtaining approval of the Competent Authority by processing
the file through various agencies took considerable time and finally the
approval for filing the present writ petiton was obtained. It is submited
meanwhile the office shifted to African Avenue and thereafter, in stepwise
the documents shifted from old office to new office. Thereafter, in the
absence of proper records and transfer the matter could not be filed at
the earliest.
5. That, subsequent to approval for filing writ petition conferences
were held with the counsel for preparation of writ petition and filing the
same before this Hon’ble Court. It is humbly submitted that on the
Signature Not Verified
W.P.(C) 3377/2025 Page 8 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
documents necessary for preparing the writ petition were submitted to
the counsel in the month of 17.10.2024 and the counsel was requested to
prepare the writ petition exepdtiously.
6. That, the certain documents have been misplaced and the Writ
Petition could not be prepared. The counsel requested for another set of
documents for preparation of the writ petition. Accordingly, the
documents were submitted to the counsel once again for preparation of
the writ petition.
7. That, after the vetting of the draft writ petition by the concerned
officials of the petitioner, the same has been filed before this Hon’ble
Court on 17.10.2024 and thereafter, there was delay in refiling after
curing all defects.”
11. The explanation offered by the petitioner for filing the present petition
after 15 months of passing of the impugned order does not bear any merit so
as to condone the same. Administrative delays/inefficiencies, unavailability
of files due to relocation of government offices, alleged misplacement of
documentation by counsel, in opinion of this Court cannot be a plausible or
reasonable rationale to condone delay in filing of the present petition. The
said view has been reiterated by the Supreme Court time and again including
in Shivamma vs. Karnataka Housing Board and Ors ., 2025 SCC OnLine
SC 1969 as under: –
“212. The law as it presently stands, post the decision of Postmaster
General (supra), is unambiguous and clear. Condonation of delay is to
remain an exception, not the rule. Governmental litigants, no less than
private parties, must demonstrate bona fide, sufficient, and cogent cause
for delay. Absent such justification, delay cannot be condoned merely on
the ground of the identity of the applicant.
213. From a combined reading of Bal Kishan Mathur (supra) and Sheo
Raj Singh (supra) it is equally manifest that the ratio of Postmaster
General (supra) is, in essence, twofold. First , that State or any of its
instrumentalities cannot be accorded preferential treatment in matters
concerning condonation of delay under Section 5 of the Limitation Act.
The State must be judged by the same standards as any private litigant.
To do otherwise would not only compromise the sanctity of limitation.
The earlier view, insofar as it favoured a liberal approach towards the
Signature Not Verified
W.P.(C) 3377/2025 Page 9 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
State or any of its instrumentality is no more the correct position of law.
Secondly, that the habitual reliance of Government departments on
bureaucratic red tape, procedural bottlenecks, or administrative
inefficiencies as grounds for seeking condonation of delay cannot
always, invariably accepted as a “sufficient cause” for the purpose of
Section 5 of the Limitation Act. If such reasons were to be accepted as a
matter of course, the very discipline sought to be introduced by the law of
limitation would be diluted, resulting in endless uncertainty in litigation
214. What has been conveyed in so many words, by the decision of
Postmaster General (supra) is that while excuses premised solely on
bureaucratic lethargy cannot, by themselves, constitute sufficient cause,
there may nonetheless be circumstances where the explanation offered,
though involving bureaucratic procedures, reflects a genuine and bona
fide cause for the delay. In such instances, the true test is whether the
explanation demonstrates that the State acted with reasonable diligence
and whether the delay occurred despite efforts to act within time. Where
such bona fides are established, the Court retains the discretion to
condone the delay.
.
215. In other words, Postmaster General (supra) does not shut the door
on condonation of delay by the State in all cases involving bureaucratic
processes. The real distinction lies between a case where delay is the
result of gross negligence, inaction, or casual indifference on the part of
the State, and a case where delay has occurred despite sincere efforts,
owing to the inherent complexities of governmental decision-making.
While the former category must necessarily be rejected to uphold the
discipline of limitation, the latter can still attract judicial indulgence
where public interest is at stake and the cause is shown to be reasonable.
216. In this regard, the vital test that has to be employed, wherever
“sufficient cause” is sought to be demonstrated on the ground of
bureaucratic inefficiencies is to distinguish between whether the same is
an “explanation” or an “excuse”. Although the two may appear to be
one and the same, yet there exists a fine but pertinent distinction between
an “excuse” and an “explanation”.
217. As illustrated in Sheo Raj Singh (supra) an “excuse” is often offered
by a person to deny responsibility and consequences when under attack.
It is sort of a defensive action. Calling something as just an “excuse”
would imply that the explanation proffered is believed not to be true. An
“explanation” on the other hand would demonstrate genuineness in
actions and reasons assigned, and would other wise be devoid of any
gross negligence, deliberate inaction or lack of bona fides, or
indifference or casualness in conduct. Thus said, there is no formula that
caters to all situations and, therefore, each case for condonation of delay
based on existence or absence of sufficient cause has to be decided on its
own facts.
218. However, equally important to note is that wherever, any
Signature Not Verified
W.P.(C) 3377/2025 Page 10 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
explanation is sought to be given on account of bureaucratic lethargy
and inherent complexities of governmental decision-making, the same
more often than not would invariably always is an “excuse”, as
experience has shown us, depicted from a long line of decisions of this
Court. It is at this stage, where the decision of Postmaster
General,(supra) assumes significance. It seeks to convey the messages,
that court should not be agnostic, to how the State or its
instrumentalities, often tend to take the recourse of condonation of delay
in a casual manner.
219.
Which is why, as per the ratio of Postmaster General (supra) and a
plethora of other subsequent decision, the ordinary approach of the
courts, in cases where delay is sought to be condoned by offering the
explanation of bureaucratic lethargy or red-tapism, must be one of
circumspection and reluctance. The courts ought to loathe in accepting
such explanations as “sufficient cause”. They should apply their minds
carefully, be slow in condoning delays on such reasons, and exceptional
instances, where the explanation is found to be genuine, reflective of
reasonable vigilance and promptitude in conduct, and free from gross
negligence, deliberate inaction, lack of bona fides, or casual indifference,
should such an explanation be accepted.
(Emphasis supplied)
12. The aforesaid position is more so in light of the fact that the
petitioner before the Authority in its reply to claim of the respondent
no.1/claimant, particularly in terms of paragraph 6, acceded to entitlement of
the respondent no.1 to minimum wages as per the rates prescribed by the
Central Government and stated that extra budget would be sought to defray
the same. Relevant portion of the said reply reads as under: -
“6. It is submitted that the letter clarifying the rates of payment of
minimum wages to casual labour engaged in Central Government
Offices/ Organisation (Ministry of Defence ID No 2 (i) 2011 dated 29th
Jun 2011 letter, copy enclosed) was received post completion of the
contract for Hiring of Security Services at NOMA Kota House. It is
further submitted that extra budget for the rate revision wrt difference
between the wages of the Central Government and the State Government
will be put up to Competent Financial Authority post concurrence of
PIFA (N) for budget allocation and the difference in wages will be paid
to the security agency with which contract was signed for further
disposal to the complainant, as the contract for providing of security
services at NOMA Kota House has been completed on 31 Mar 21.”
Signature Not Verified
W.P.(C) 3377/2025 Page 11 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
13. However, the Authority noting inaction on part of the petitioner
despite the aforesaid undertaking given before it, directed the petitioner to
pay a total sum of Rs. 1,62,951/- to the respondent no.1/claimant towards
difference in minimum wages and compensation at the rate of, double of the
prescribed minimum wage. The said order reads as under: -
“The applicant was working with opponents as Security Guard. It is
falling under Scheduled Employment for the purpose of Minimum. Wages
Act 1948. There is no dispute regarding Employee Employer relationship
or Jurisdiction. Op2 (PE) has agreed that they have not pad Minimum
wage of central government during the proceedings and submitted in
writing.
They have followed the Minimum wage of NCT of Delhi, though the
central government is the appropriate government. Op l has entered into
a contract to pay Minimum wage of NCT of Delhi with Op2.
Op2 has submitted that difference in wages will be paid after getting
approval from competent financial authority But no action has been
taken till date.”
Under these circumstances, the following order is being issued:
ORDER
1. The application is allowed.
2. Op1 and Op2 are liable to pay the difference in minimum wages
amounting to Rs. 54,317 (Rupees Fifty four thousand three hundred
seventeen only) along with two times compensation. Total amount to be paid
is Rs.1,62,951 (Rupees one lakh sixty two thousand nine hundred fifty one).
3. Above amount is to be paid in the name of employee to the authority in the
form of Demand Draft within fifteen days from the date of receipt of this
order.
4. Any failure to comply with this order may result in initiation of recovery
proceedings without any further notice.
5. No costs are awarded in this matter.
6. The claim application is hereby resolved and dispose of. ”
14. Despite the aforesaid, the petitioner instead of complying with the
unequivocal undertaking given before the Authority preferred the present
proceeding to assail the directions issued by the Authority alleging that
despite respondent no.1 being eligible for minimum wage rates prescribed
Signature Not Verified
W.P.(C) 3377/2025 Page 12 of 13
Digitally Signed
By:ABHISHEK THAKUR
Signing Date:01.07.2026
19:21:44
by the GNCTD, the Authority has passed the impugned directions on an
erroneous finding that respondent no.1 is eligible for minimum wage rates
prescribed by the Central Government. The said conduct of the petitioner is
untenable. The petitioner cannot be permitted to retract/resile its
unequivocal stand/submissions made before the Authority in a subsequent
appeal/challenge.
15. In the aforesaid conspectus, this Court finds no occasion to interfere
with the impugned award and accordingly, the present petition stands
dismissed. Pending applications also stands disposed of.
SACHIN DATTA, J
sl
JULY 1, 2026/