National Highways Authority Of India vs Bscpl Infrastructure Limited
- Court
- Delhi High Court
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 03.09.2026
Judgment pronounced on: 23.11.2026
# CNR No. DLHC011250152016
+ O.M.P. (COMM) 168/2016
NATIONAL HIGHWAYS AUTHORITY OF INDIA
.....Petitioner
Through: Mr. Ankur Mittal, Sr. Adv. with
Mr. Abhay Gupta, Mr. Ankur
Saboo, Mr. Aviraj Pandey, Ms.
Rabaica Jaiswal, Ms. Simran
Goel and Ms. Allaka Melikeril,
Advs.
versus
BSCPL INFRASTRUCTURE LIMITED .....Respondent
Through: Mr. Ajay Kumar Jha, Adv.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
JUDGMENT
% 23.11.2026
1. The present petition under Section 34 of the Arbitration and
1
Conciliation Act, 1996 is being preferred by National Highways
2
Authority of India , challenging the impugned award dated 13.05.2015
passed by the learned Arbitral Tribunal in the arbitration between the
parties. The impugned award was rendered by a majority of 2:1 and
allowed claims No.1, 2, 4 and 5 of the Respondent/Claimant, along with
interest.
1
“Act” hereinafter
2
“NHAI” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 1 of 33
2. The dispute arises of the Contract Agreement dated 12.04.2006
entered into between NHAI and the Contractor for widening to four
lanes and strengthening of existing two-lane carriageway of NH-26 of
Madhya Pradesh of package ADB-II/C-7 from km: 255 to km: 297
(Sagar to Rajmarg Chouraha). The contract price was Rs.189.63 crores.
3. The work commenced on 27.05.2006, with scheduled completion
in 26.11.2008. The work was actually completed on 05.12.2009,
3
resulting in an extension of time of 374 days. The Engineer
recommended the extension, which was approved by NHAI without
imposition of penalty or liquidated damages.
4. The Respondent thereafter referred the matter to the Dispute
4
Adjudication Board under sub-Clause 67.1 of COPA. The DAB held
that the Respondent was entitled to its claim and directed submission of
detailed calculation to the Engineer for assessment. The details were
furnished to the Engineer, but the claim was thereafter denied. The
Respondent again approached the DAB, however no decision could be
obtained as the constitution of the DAB stood terminated after expiry
of the defect liability period. Thereafter, arbitration was invoked.
5. The Respondent raised claims under several heads being Claim
Nos. 1A to 1D concerned additional cost of POL, cement, steel and
bitumen during the extended period. Claim No.2 concerned additional
cost on account of extended stay of plant and equipment at site. Claim
3
“EOT” hereinafter
4
“DAB” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 2 of 33
No.3 concerned financing charges. Claim Nos.4 and 5 concerned
additional expenditure at site and head office overheads. Claim Nos.6
and 7 concerned loss of promised bonus and loss of profit earning
capacity on account of prolongation of the contract.
6. Against the total claim of Rs.40,33,65,879/-, the Arbitral
Tribunal awarded approximately Rs.15.80 crores. Claim Nos. 1A to 1D,
2, 4 and 5 were allowed, whereas Claim Nos.3, 6 and 7 were rejected.
7. The Tribunal further awarded interest @10% p.a. compounded
monthly in accordance with sub-Clause 60.8 of the contract from the
date of invocation of arbitration to the date of award, and future interest
@10% p.a. on the amounts awarded, including pendente lite interest
from the date of the award till the date of realisation.
PROCEEDINGS BEFORE ARBITRAL TRIBUNAL
8. The Claimant invoked arbitration vide its letter dated 05.02.2011.
Mr. A.C. Mittal was nominated as the Arbitrator by the Claimant and
Mr. K.B. Lal Singal was nominated by NHAI. The two nominated
Arbitrators appointed Mr. Surjeet Singh as the Presiding Arbitrator,
who accepted the appointment, whereupon the Arbitral Tribunal stood
duly constituted.
9. Before the learned Arbitral Tribunal, the Claimant raised a
composite claim for Rs.40,33,65,879/- towards additional expenditure
and losses allegedly suffered on account of the prolongation of the
contract. The claim was divided into seven sub-heads, namely: (i)
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 3 of 33
additional cost of POL, cement, steel and bitumen during the extended
period; (ii) additional cost on account of extended stay of plant and
equipment at site; (iii) financing charges towards delayed recovery of
profit; (iv) additional expenditure towards maintenance of site office
and residential accommodation; (v) additional head-office overheads;
(vi) loss of promised bonus; and (vii) loss of profit-earning capacity on
account of prolongation of the contract.
10. The individual claims were quantified as follows: Claims 1A to
1D towards POL, cement, steel and bitumen were quantified at
Rs.36,50,454/-, Rs.64,19,730/-, Rs.60,07,070/- and Rs.2,77,59,388/-,
respectively. Claim No.2 towards extended deployment of plant and
equipment was Rs.4,55,10,280/-; Claim No.3 towards financing
charges was Rs.47,07,166/-; Claim No.4 towards site office and
residential accommodation was Rs.10,18,59,600/-; Claim No.5 towards
head-office overheads was Rs.1,78,15,097/-; Claim No.6 towards loss
of promised bonus was Rs.11,37,82,238/-; and Claim No.7 towards loss
of profit-earning capacity was Rs.7,58,54,826/-.
11. NHAI opposed the claims, principally contending that price
escalation had already been paid under Clause 70, that the delay was
not attributable to NHAI, and that Claims 6 and 7 had not been raised
before the Engineer/DAB.
12. The learned Tribunal rejected the preliminary objection to
Claims 6 and 7, holding that the dispute and cause of action, namely the
prolongation of the contract, remained the same, and that Sub-Clause
67.4(ii) of the contract and Section 23(3) of the Act permitted the claim
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 4 of 33
to be updated. On the objection of non-compliance with Sub-Clauses
53.1 to 53.3, the Tribunal held that the Claimant had all along claimed
costs in its applications for extension of time, and that Sub-Clause 53.4
permitted adjudication of claims substantiated by contemporary
records.
13. The Tribunal held that the stipulated completion date of
26.11.2008 was extended by 374 days, with completion ultimately on
05.12.2009, and attributed the relevant delay to NHAI. The Tribunal
consequently held the Claimant entitled to additional costs arising from
the prolongation.
14. In respect of Claims 1A to 1D, concerning POL, cement, steel
and bitumen, the Tribunal rejected NHAI’s reliance on Clause 70.2 and
awarded Rs.4,38,36,642/-, with interest at 10% per annum,
compounded monthly.
15. Claim No.2, towards extended deployment of plant and
equipment, was allowed to the extent of Rs.4,55,10,280/-, with interest
at 10% per annum, compounded monthly.
16. Claim No.3, towards financing charges of Rs.47,07,166/-, was
rejected for want of proof of actual loss.
17. Claims 4 and 5, towards site and head-office overheads, were
allowed to the extent of Rs.6,86,95,108/-, with interest at 10% per
annum, compounded monthly.
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 5 of 33
18. Claims 6 and 7, relating to loss of promised bonus and loss of
profit-earning capacity, were rejected for want of sufficient contractual
and evidentiary basis.
19. By majority, the Tribunal awarded the Claimant a total principal
sum of Rs.15,80,42,030/-, comprising the amounts awarded under
Claims 1A-1D, Claim No.2 and Claims 4 and 5. The award further
directed payment of interest at 10% per annum, compounded monthly,
from 05.02.2011 till the date of the Award and thereafter till realization.
The remaining claims were dismissed.
20. The Arbitral Award is summarised herein:
Claim Particulars Amount Claimed Amount Awarded
1A Additional cost of POL Rs.36,50,454/- Rs.4,38,36,642/- along with
interest of 10% p.a. compounded
monthly from the date of invocation
i.e. 05.02.2011.
1B Additional cost of
cement
Rs.64,19,730/-
1C Additional cost of steel Rs.60,07,070/-
1D Additional cost of
bitumen
Rs.2,77,59,388/-
2 Extended stay of plant
and equipment
Rs.4,55,10,280/- Rs 4,55,10,280/- along with interest
of 10% p.a. compounded monthly
from the date of invocation i.e.
05.02.2011
3 Financing
charges/interest
Rs.47,07,166/- NIL
4 Site office and
residential
accommodation
Rs.10,18,59,600/- Rs 6,86,95,108/- along with interest
of 10% p.a. compounded monthly
from the date of invocation i.e.
5 Head office overheads Rs.1,78,15,097/- 05.02.2011.
6 Loss of promised
bonus
Rs,11,37,82,238/- NIL
7 Loss of profit-earning
capacity
Rs.7,58,54,826/- NIL
Total
Rs,40,33,65,879/- Rs. 15,80,42,030/- excluding
interest
PROCEEDINGS BEFORE THIS COURT
21. The principal contention of the Petitioner is that the impugned
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 6 of 33
award is beyond the terms of the contract and against the public policy
of India. It is submitted that the Arbitral Tribunal proceeded on
assumption and presumptions without looking into or discussing the
contemporary records and without carrying out the verification exercise
contemplated by the contract.
22. Learned Counsel for the Petitioner submits that, under Clause
5
53.4 of the Conditions of Particular Application the Arbitral Tribunal
could award only such amounts as it considered capable of being
verified by contemporary records. It is contended that the Contract
required the Contractor to notify the Engineer and the Employer of the
event giving rise to the claim, maintain the requisite contemporary
records, make such records available for inspection and submit detailed
particulars of the amounts claimed, together with the grounds
supporting the claim.
23. It is the further contended that there was no compliance by the
Contractor with the requirement of giving notice upon the happening of
the event duly obliged to claim for extension of time or additional costs
and that no contemporary records were made available to the Engineer
for appropriate inspection and verification. According to the Petitioner,
the claim for additional cost surfaced only after EOT had been granted.
24. The Petitioner has also relied on the fact that the Engineer had
repeatedly recorded slow progress, lack of planning, deficient
deployment of resources and improper execution of the works. It is
5
“COPA” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 7 of 33
submitted that the progress achieved by the Claimant upto July 2007
was less than 2% per month and that such matters were repeatedly
pointed out by the Engineer.
25. It is also stated that the first application by the Claimant for EOT
did not set out the additional costs subsequently claimed. The Engineer
had recommended an extension of time without any additional payment
to the Contractor, and the Petitioner approved the extension on that
basis. It is further contended that certain periods of extension related to
bridge design and redesign, execution of extra work and land-related
hindrances, which did not, by themselves, establish the Contractor's
entitlement to additional compensation.
26. As regards Claim No. 1A to 1D, relating to the additional costs
of petroleum, oil and lubricants (POL), cement, steel and bitumen, the
Petitioner contends that the Contractor was already entitled to price
adjustment under Clause 70 of COPA and that no additional
compensation was admissible beyond the contractual mechanism. It is
submitted that the Tribunal failed to appreciate the effect of Sub-
Clauses 70.2 and 70.3 of COPA and erroneously awarded additional
compensation beyond the contractual price-adjustment mechanism.
27. With respect to Claim No.2, concerning the extended deployment
of plant and equipment, the Petitioner contends that the Tribunal
adopted an incorrect pro-rata principle for determining the additional
costs. It is submitted that the cost of machinery is to be arrived at with
reference to the total cost of the project and is not directly
proportionately related to the number of days for which machinery is
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 8 of 33
used.
28. The Petitioner further submits that the Contractor had relied upon
machinery more than five years old and included equipment that was
allegedly not relevant to the execution of the works under the Contract.
It is also contended that the claimed hourly use and interest calculation
were incorrect.
29. In respect of Claim Nos.4 and 5, concerning site and head-office
overheads, the Petitioner submits that no timely notice of the
Contractor’s intention to claim such costs was issued, thereby depriving
the Engineer of an opportunity to inspect and verify the alleged
expenditure. It is further contended that the Contractor failed to produce
verifiable contemporary records and that the Arbitral Tribunal did not
undertake the verification contemplated under Clause 53.4.
30. The Petitioner also questions the quantum awarded towards
overheads as excessive and disproportionate, particularly in view of its
submission that the value of the work in the hindered reaches was
approximately Rs.6.40 crores, whereas the claim towards site overheads
alone was Rs.10,18,59,600/-. Reliance is also placed on the profit and
loss account of the Contractor, which, according to the Petitioner,
reflected overhead expenses of approximately 28.5%.
31. Finally, the Petitioner challenges the award of interest at the rate
of 10% per annum, compounded monthly. It is submitted that Sub-
Clause 60.8 of COPA was not applicable to the compensation awarded
by the Arbitral Tribunal and that, in any event, the rate and manner of
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 9 of 33
computation of interest are excessive.
32. On the contrary, learned Counsel for the Respondent submits that
the petition is devoid of merits and that no grounds, factual or legal,
have been made out for interference with the award. It is contended that
the Arbitral Tribunal considered the submissions advanced by both
parties, examined the material placed on record and rendered a reasoned
award.
33. The Respondent relies upon the settled position that proceedings
under Section 34 of the Act, do not constitute an appeal against an
arbitral award. It is submitted that this Court cannot reappreciate the
evidence or substitute its own findings for those of the Arbitral Tribunal
merely because another view may be possible or because the award is
alleged to be erroneous on facts.
34. It is submitted that the work was completed on 05.12.2009, after
a delay of 374 days, and that the EOT was recommended by the
Engineer and granted by NHAI because the delays were caused by
NHAI’s defaults. The Engineer assessed the various causes of delay and
allowed for overlapping delays, recommended a net extension of 374
days. NHAI granted it without imposing any penalty or liquidated
damages.
35. The Respondent relies upon the findings of the Arbitral Tribunal
that the delay arose from delay in handing over the sites, hindrance and
obstructions, realignment at Bijora, shifting of electric poles consequent
upon land-acquisition issues, stoppage of work at Maharajpur, redesign
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 10 of 33
of bridges, revision of the DPR data, lateral shifts for installation of
traffic signs and appurtenances, variations in bridge works and
execution of extra work. The Tribunal was therefore justified, it is
submitted, in holding the Contractor entitled to the additional costs
incurred during the extended period.
36. On the issue of contractual notices and contemporary records, the
Respondent submits that it had communicated its intention to claim
additional costs in its application for extension of time and had issued
other notices in relation to the delays encountered during execution of
the works. Reliance is placed on Clauses 6.4, 12.2, 42.2 and 44.2 of the
Contract.
37. The Respondent further relies upon Clause 53.4 of COPA,
submitting that non-compliance with the notice and record-keeping
requirements under Sub-Clauses 53.1, 53.2 and 53.3 does not, by itself,
preclude consideration of a claim where the amount claimed can be
substantiated by contemporary records. It is contended that the Arbitral
Tribunal specifically considered the contractual objections and
rendered its findings upon examination of the material available on
record.
38. As regards the contemporary records, the Respondent submits
that the claims were passed upon actually incurred costs and were
supported by contemporary records, vouchers and documents duly
verified and certified by the Chartered Accountant. It is contended that
the Arbitral Tribunal considered the supporting material and that the
Petitioner’s objections essentially seek a reappreciation of the evidence,
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 11 of 33
which is impermissible in proceedings under Section 34 of the Act.
39. In respect of Claim No. 1A to 1D, the Respondent submits that
the Arbitral Tribunal correctly interpreted Sub-Clause 70.2 of COPA
harmoniously with Sub-Clauses 6.4, 12.2 and 42.2. According to the
Respondent, the limitation prescribed under Clause 70 governed the
contractual price-adjustment mechanism, whereas additional costs
incurred during the extended period, arising from the defaults
attributable to NHAI, were independently compensable under the other
contractual provisions. It is further submitted that the Contractor
furnished details of the purchase and consumption of the relevant
materials and deducted the price adjustment already received under
Clause 70 while computing its additional-cost claims.
40. With respect to Claim No. 2, the Respondent submits that the
deployment of plant and equipment was supported by monthly progress
reports, invoices, inspection records and other documents. It was further
submitted that the plant and machinery deployed during the extended
period were jointly verified by the Engineer on 14.03.2009.
41. It is also submitted that the Tribunal found that sufficient plant
and equipment had actually been mobilised, that the contract required
the Engineer’s permission before removal from site and that the plant
and equipment mentioned in the monthly reports therefore remained at
site. It is also pointed out that the Arbitral Tribunal further found that
the plant and equipment remained underutilised and to an extent idle.
42. As regards Claim Nos.4 and 5, relating to site and head-office
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 12 of 33
overheads, the Respondent places reliance upon the Arbitral Tribunal’s
findings that the entire EOT was on account of defaults of NHAI and
that compensation for site and head office, overheads to the extended
period was therefore justified. The Arbitral Tribunal adopted the
6
Ministry of Road Transport & Highways data book rates of 8% for the
road work and 25% of the bridge work, arriving at a weighted average
of 11.64%, and further reduced the compensation by 15% towards
mitigation and restricted the award to Rs.6,86,95,108/-.
43. The Respondent further submits that the Arbitral Tribunal did not
allow all the claims. Claim No.3 relating to financing charge, Claim
No.6 relating to loss of promised bonus, and Claim No. 7, relating to
loss of profit-earning capacity, were rejected. It is therefore contended
that the Arbitral Tribunal considered the nature of the claims and the
material on record and awarded only Rs.15,80,42,030/- against the total
claim of Rs.40,33,65,879/-.
44. The Respondent submits that the award, being a reasoned
determination by the Arbitral Tribunal, does not warrant interference
under Section 34 of the Act.
ANALYSIS & CONCLUSION
45. Having considered the pleadings, the award and the submissions
of the parties, the following questions arise for determination:
(i) Whether the impugned award goes beyond the terms of the
6
“MoRTH” hereinafter
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 13 of 33
contract or otherwise falls within a ground for setting aside under
Section 34 of the Act?
(ii) Whether the Arbitral Tribunal was justified in allowing
additional costs for the 374-day extended period?
(iii) Whether Claim Nos. 1A to 1D were barred by the price-
adjustment provisions in Clause 70 of COPA?
(iv) Whether Claim No.2 for towards the extended stay of plant
and equipment, lacks sufficient evidentiary or contractual
support?
(v) Whether Claims Nos.4 and 5, for site and head office
overheads, fail for want of notice, contemporary records and
verifications?
(vi) Whether the award of interest under sub-Clause 60.8
warrants interference?
46. This challenge principally concerns the award of
Rs.4,38,36,642/- towards additional costs of POL, cement, steel and
bitumen under Claims 1A-D; Rs.4,55,10,280/- towards extended
deployment of plant and equipment under Claim No. 2; and
Rs.6,86,95,108/- towards site and head-office overheads under Claims
4 and 5. The learned Arbitral Tribunal rejected the claims for financing
charges, loss of promised bonus and loss of profit-earning capacity. The
total principal amount awarded by the majority was Rs.15,80,42,030/-,
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 14 of 33
excluding interest.
47. At the outset, the Court must keep in view the limited scope of
review under Section 34 of the Act. A petition under Section 34 is not
an appeal, and the Court cannot reassess the evidence merely because
it might prefer a different view of the contract or the facts. Interference
is permissible only if a ground recognised by Section 34, as applicable
to the present proceedings, is established.
48. In Ssangyong Engineering & Construction Co. Ltd. v. National
7
Highways Authority of India , the Supreme Court explained the
restricted scope of review under the amended Section 34, including the
requirement that patent illegality under Section 34(2A) must go to the
root of the matter. An erroneous application of law or a disagreement
with the appreciation of evidence does not, by itself, warrant setting
aside an award.
49. Similarly, in Sumitomo Heavy Industries Ltd. v. Oil and
8
Natural Gas Commission , the Supreme Court recognised that where
the construction placed upon the contract by the arbitral tribunal is a
plausible one, the Court ought not to substitute its own interpretation
merely because it considers another construction preferable. The Court
must, therefore, examine whether the majority tribunal’s conclusions
fall within the range of permissible contractual interpretation and
whether the Petitioner has established a ground for interference under
Section 34.
7
(2019) 15 SCC 131
8
(2010) 11 SCC 296
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 15 of 33
50. The scheduled completion date was 26.11.2008, while the work
was completed on 05.12.2009, resulting in a delay of 374 days. The
Engineer recommended an EOT for that period, and NHAI approved it
without imposing a penalty or liquidated damages. These circumstances
are relevant to the Tribunal’s assessment of responsibility for delay,
although the grant of an EOT, by itself, does not automatically establish
an entitlement to every cost claimed for the extended period.
51. NHAI relies on earlier observations by the Engineer concerning
slow progress and deployment of resources. Those observations must
be read with the later assessment of the causes of delay and the formal
decision to grant the EOT. The absence of liquidated damages is not
conclusive on its own; however, it is a relevant circumstance when
considered with the Engineer’s reasons and the contemporary record as
a whole.
52. The Tribunal considered the causes of delay, including late
handover of sites, hindrances and obstructions, realignment at Bijora,
shifting of electric poles arising from land-acquisition issues, stoppage
of work at Maharajpur, redesign of bridges at km 264+640 and km
276+628, revision of DPR data for Rajmarg Chouraha, lateral shifts for
traffic signs, and variations and extra work relating to bridges.
53. The Tribunal also noted that the Engineer considered an
extension of 185 days reasonable in relation to bridge works and
recommended a total EOT of 374 days, which NHAI granted. The
Tribunal treated the extension and the absence of liquidated damages as
part of the overall evidence; its finding of entitlement rests on the
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 16 of 33
identified delay events and the contractual provisions, not on the EOT
alone.
54. NHAI asks the Court to examine each hindrance separately and
reassess its individual effect on the additional costs. That submission
would require the Court to reconsider the factual assessment already
made by the Tribunal. Such reconsideration is not permitted under
Section 34 unless the finding is shown to be unsupported by evidence,
perverse, or contrary to an express contractual term.
55. The Court cannot isolate each hindrance and independently
recalculate its effect on the extended period. The majority’s finding that
the delay was attributable to NHAI was based on the contemporary
record, including NHAI Headquarters’ internal communication dated
25.01.2010. NHAI has not shown that the Tribunal ignored a material
document that would make its conclusion untenable .
56. In these circumstances, the finding that the Contractor was
entitled to additional cost for the extended period is one arising from
the contractual provisions and the evidence considered by the Tribunal.
A different view of the delay events is not, by itself, a ground to set
aside the award.
57. The majority did not rely solely on the fact that an EOT had been
granted. It considered the circumstances relating to site handover,
hindrances, realignment, shifting of electric poles, stoppage of work,
bridge redesign, revision of data, and additional or varied work. It also
considered the Engineer’s assessment, including the period of 185 days
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 17 of 33
considered reasonable for bridge-related work.
58. The Tribunal then considered NHAI’s objections and concluded
that the additional costs were recoverable under the relevant provisions
of the contract. NHAI’s challenge asks the Court to reallocate
responsibility for individual events and reassess their effect on the
extended period. Unless the Tribunal’s finding is shown to be perverse,
unsupported by evidence or contrary to the contract, Section 34 does
not permit that exercise.
9
59. In NHAI v. M/s Oriental Structural Engineers Pvt. Ltd. , this
Court considered objections to prolongation costs under a highway
construction contract, including the interpretation of Clauses 6.4, 12.2
and 42.2 and the use of industry-based methodologies for
quantification. The Court reiterated that where the tribunal has
examined the contractual provisions and the evidence concerning the
causes of delay, a challenge seeking a fresh assessment of attribution
and quantification cannot succeed merely because the employer
proposes a different view.
60. For these reasons, Petitioner has not established that the
Tribunal’s finding on the 374-day extended period is so unreasonable,
unsupported or contrary to the contract as to warrant interference under
Section 34.
61. The Petitioner has also challenged the award of additional
amounts towards POL, cement, steel and bitumen, contending that
9
2026 SCC OnLine Del 3540
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 18 of 33
Clause 70 of the COPA prescribes the contractual mechanism for price
adjustment and that the contractor could not claim additional amounts
outside that mechanism.
62. The objection requires consideration of the relationship between
Clause 70 and Clauses 6.4, 12.2 and 42.2. The former provides a
contractual mechanism for price adjustment in respect of specified
components, whereas the latter provisions address, in their respective
circumstances, the consequences of delay, physical conditions or failure
attributable to the employer, including the determination of additional
costs.
63. The interpretation of Clause 70, however, requires careful
consideration in the light of the decision of the Supreme Court in
10
National Highways Authority of India v. Progressive-MVR (JV) .
The Supreme Court considered the operation of Sub-Clauses 70.2 and
70.3 and recognised that the contractual price-adjustment mechanism is
governed by the components and formulae stipulated therein. Sub-
Clause 70.2 cannot be disregarded so as to permit a contractor to claim,
under the guise of additional compensation, a price adjustment on
accounts which the contract has expressly excluded from the agreed
formula.
64. The aforesaid principle, however, does not by itself answer the
distinct question that arose before the majority in the present case.
There is a material distinction between a claim seeking a further
escalation in the price of contractual inputs, over and above the
10
(2018) 14 SCC 688
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 19 of 33
adjustment permitted by Clause 70, and a claim seeking reimbursement
of additional expenditure alleged to have been incurred because the
contractor was required to remain at site beyond the stipulated
completion period on account of employer-attributable delay. The latter
claim must be tested against the provisions of the contract said to confer
such entitlement, including Sub-Clauses 6.4, 12.2 and 42.2.
65. The distinction is not merely one of nomenclature. A contractor
cannot circumvent the agreed price-adjustment formula by simply
describing an otherwise excluded escalation claim as a prolongation
claim. At the same time, where the contract independently provides for
recovery of additional costs arising from specified defaults or events
attributable to the employer, the existence of a price-adjustment
mechanism does not, without examining the relevant contractual
provisions, necessarily extinguish that separate entitlement.
66. The Tribunal addressed this exact contention by construing Sub-
Clause 70.2 harmoniously with Sub-Clauses 6.4, 12.2, and 42.2, and
supported its view by relying on this Court’s judgment in NHAI v. HCC
11
Ltd . It was held that while Clause 70 limits price adjustment during
the stipulated base period to the formulaic parameters, additional costs
incurred during an extended period caused by employer defaults fall
squarely within the operation of the other empowering clauses.
67. The decision in Progressive-MVR (JV) (supra) requires the
Court to ensure that the distinction drawn by the majority is a real one
and not a matter of nomenclature. In the present case, it is. The claims
11
(OMP 633/2012, decided on 08.07.2014)
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 20 of 33
are confined to materials consumed during the 374-day extended
period, a period which, on the Tribunal's finding, arose wholly from
defaults attributable to NHAI; and the amounts were quantified on
actual purchase and consumption, after giving full credit for the price
adjustment received under Clause 70. No part of the claim relates to the
stipulated period, for which the Tribunal held the Clause 70 formula to
be exhaustive. The award under these heads is therefore compensation
for additional cost under Sub-Clauses 6.4, 12.2 and 42.2, and not an
enhanced escalation under Clause 70.
68. The Respondent’s case is also that it claimed only the uncovered
part actual additional expenses while giving full credit for price
adjustments already received under the contract. The record relied upon
by the Respondent included monthly consumption, monthly
procurement cost and base cost and price adjustment already paid.
69. The Tribunal further considered the quantification and recorded
that sufficient details of purchase and consumption of POL had been
furnished and that the summary was duly certified by the Chartered
Accountant. It also noted that price adjustment received under Clause
70 during the extended period had been deducted from the claim for
additional costs.
70. Therefore, the interpretation adopted by the Tribunal is not
shown to be an interpretation which disregards the contract. It is an
interpretation based upon a harmonious reading of the relevant
contractual provisions.
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 21 of 33
71. The Petitioner prefers an interpretation under which Clause 70
exhaustively governs all additional costs. The Tribunal gave reasons for
rejecting that interpretation. The Court cannot replace a plausible
contractual interpretation with another merely because it might prefer
the latter; interference would require a finding that the interpretation is
contrary to the contract or otherwise falls within a ground under Section
34.
72. No material has been identified to show that the award under
Claims Nos. 1A to 1D grants the same amount twice or ignores the price
adjustment already paid. The interpretation adopted by the Tribunal is
a permissible reading of the relevant clauses, and the award under these
claims does not warrant interference under Section 34.
73. Claim No. 2 concerns the cost of plant and equipment retained at
the site during the extended period. The Tribunal awarded
Rs.4,55,10,280/-. NHAI challenges both the method of calculation and
the evidence supporting the amount.
74. The award records an alternative calculation based on the
machinery component of 20%, the extended period of 374 days and a
15% deduction for mitigation. That calculation yielded
Rs.11,80,32,831/-. The Tribunal did not award that higher figure; it
restricted the award to Rs.4,55,10,280/-, which it treated as the actual
ownership costs claimed by the Contractor.
75. The relevant question is not whether this Court would have
selected the same calculation method. The question is whether the
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 22 of 33
Tribunal had evidence to find that the Contractor incurred additional
machinery-related costs due to the extended period and whether the
amount awarded has a rational and discernible basis in the record.
76. The material before the Tribunal included monthly machinery
reports, invoices, inspection records, an auditor’s certificate and the
Engineer’s joint verification. The Tribunal also considered evidence
that some equipment remained underused or idle. The existence of
equipment at the site does not, by itself, prove the full amount claimed;
the evidence must reasonably connect the deployment or retention of
the equipment to the additional costs awarded.
12
77. In McDermott International Inc. v. Burn Standard Co. Ltd. ,
the Supreme Court recognised that the quantification of damages and
the choice of an appropriate method of assessment are matters
ordinarily within the domain of the arbitral tribunal. The Court
exercising jurisdiction under Section 34 does not undertake the exercise
afresh merely because another method might also have been available.
78. The qualification to that principle is that the amount awarded
cannot be arbitrary or unsupported by reasons. In Batliboi
Environmental Engineers Ltd. v. Hindustan Petroleum Corporation
13
Ltd. , the Supreme Court disapproved an award of overheads and
profitability where the method of computation lacked adequate
justification and the award involved disproportionate or overlapping
recovery. The decision does not prohibit formula-based quantification
in every case; it requires that the method be rationally supported and
12
(2006) 11 SCC 181
13
(2024) 2 SCC 375
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 23 of 33
that the award not result in an unjustified windfall or double recovery.
79. Here, the majority referred to records relating to the machinery
retained at the site and awarded the amount claimed as actual ownership
costs rather than the substantially higher amount produced by its
alternative calculation. The lower figure is not, by itself, proof of
correctness; however, when considered with the invoices, machinery
reports, auditor’s certificate and joint verification, it provides an
identifiable evidentiary basis. NHAI has not identified a specific
contradiction between those records and the Tribunal’s finding, or
shown that the same cost was recovered twice.
80. The Tribunal also recorded that the contract specified minimum
equipment requirements, that equipment had in fact been mobilised, and
that plant and equipment could not be removed from the site without
the Engineer’s written permission. These findings support the
conclusion that the equipment identified in the relevant monthly reports
remained available at the site during the extended period.
81. NHAI also argues that the value of the work in the hindered
reaches was only about Rs.6.40 crores. That figure, by itself, does not
determine whether costs were incurred to retain plant and equipment
for the project as a whole during the extended period. The relevant
question is whether the costs awarded were connected to the prolonged
retention of equipment and supported by records. The Tribunal found
that connection on the material before it.
82. The alternative calculation based on the 20% machinery
component yielded Rs.11,80,32,831/- after applying the period and
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 24 of 33
mitigation adjustment. The Tribunal instead confined the award to
Rs.4,55,10,280/-, the amount claimed as actual ownership costs. Read
with the documentary material identified above, the award does not rest
solely on a notional percentage of the contract price.
83. Accordingly, the award of Rs.4,55,10,280/- under Claim No. 2 is
upheld.
84. Now moving on to Claim Nos. 4 and 5 which relates to additional
expenditure on site-office and residential accommodation during the
extended period, and additional head-office overheads. The amounts
originally claimed were Rs.10,18,59,600/- and Rs.1,78,15,097/-,
respectively. The Tribunal awarded a combined amount of
Rs.6,86,95,108/-.
85. The Petitioner strongly disputes Claims No.4 and 5 on the ground
that no timely notice was issued and no contemporary records capable
of verification were produced. It was further contended that the amount
claimed was excessive.
86. The Respondent’s on the other hand relies upon its
communication wherein it had communicated its intention to claim
additional cost in the applications for EOT and had placed
contemporary records, vouchers and Chartered Accountant’s certified
material before the Tribunal.
87. The Tribunal considered the contractual notice objection and
held that sub-Clause 53.4 permitted adjudication of claims even in the
absence of compliance with sub-Clauses 53.1, 53.2 and 53.3, provided
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 25 of 33
the claims can be substantiated on the basis of contemporary records.
88. The Tribunal thereafter did not accept the entire amount claimed
under the overhead Heads. It adopted the standards recognised in
MoRTH Data Book, which stipulated overheads at 8% for road work
and 25% for bridges work, arrived at a weighted average of 11.64%,
restricted the compensation to that rate for 374 days delay and further
reduced the compensation by 15% for loss mitigation.
89. The final award under Claims No.4 and 5 was thus limited to
Rs.6,86,95,108/- notwithstanding the much larger amount originally
claimed under the two heads. The Petitioner submits that the weighted
average method was uncalled for and that the data book rates related to
cost of project rather than duration.
90. This according to this Court is again an objection to the
methodology adopted by the Tribunal.
91. The award shows that the Tribunal did not simply accept the
amounts claimed. It considered the different rates for road and bridge
works, calculated a weighted average, applied the assessment to the
extended period, and reduced the resulting amount by 15% for
mitigation. These steps provide a discernible method of quantification.
92. Petitioner’s objection about the relationship between the Data
Book rates and the duration of delay is relevant, but it does not by itself
establish patent illegality. On the material described in the award, the
Tribunal used the rates to assess overheads attributable to the extended
period, took account of the mix of road and bridge works, and made a
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 26 of 33
further deduction for mitigation. NHAI has not demonstrated a specific
arithmetic error, an irrelevant cost base or double recovery that would
make the result irrational.
93. Much of the Petitioner’s challenge proceeds on the allegation that
the claims were not supported by contemporary records and that no
verification exercise was undertaken.
94. The Respondent, relied on contemporary records, vouchers,
monthly progress reports, invoices, inspection records and certificates
from the Chartered Accountant. For plant and machinery, it also relied
on the Engineer’s joint inspection dated 14.03.2009.
95. For the material-costs claims, the Tribunal recorded that the
purchase and consumption figures had been certified by the Chartered
Accountant and that the price adjustment already paid under Clause 70
had been deducted.
96. The award deals with the individual heads of claim in paragraphs
14 to 30. The fact that the Tribunal did not accept the Engineer’s reasons
in the manner urged by NHAI does not establish that it failed to consider
the objection. The Tribunal was required to decide the dispute
independently and recorded its findings on the claims and the
supporting material.
97. The fact that the Tribunal disagreed with the Engineer’s rejection
dated 23.10.2010 does not, by itself, invalidate the award. The
Engineer’s decision formed part of the disputed record; the Tribunal
considered the claim afresh and gave its own reasons. The Court must
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 27 of 33
assess those reasons under Section 34, rather than treat the Engineer’s
rejection as conclusive.
98. In view of the records and reasons identified in the award, the
allegation that the Tribunal considered the claims without any
supporting material is not borne out.
99. The Court therefore finds no basis, on the material placed before
it, to conclude that the Tribunal failed to consider contemporary records
or omitted the verification required by the contract. To the extent NHAI
disputes the weight assigned to the records, its challenge seeks a
reappreciation of evidence and does not establish a ground for
interference under Section 34.
100. The Tribunal rejected Claim No. 3, for financing charges of
Rs.47,07,166/-, Claim No. 6, for loss of promised bonus of
Rs.11,37,82,238/-, and Claim No. 7, for loss of profit-earning capacity
of Rs.7,58,54,826/-, because it found the contractual or evidentiary
basis insufficient/-.
101. These rejections do not, by themselves, prove that the other
claims were correctly quantified. They do, however, show that the
Tribunal examined the heads of claim separately and declined relief
where it found the basis for recovery inadequate. This is inconsistent
with the allegation that the Tribunal mechanically accepted the
Contractor’s case in full.
102. The Tribunal awarded interest @ 10% per annum compounded
monthly under sub-Clause 60.8 from 05.02.2011, the date of invocation
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 28 of 33
of arbitration, until the date of the award, and future interest at the same
rate after the award until realisation.
103. Sub-Clause 60.8 provides for interest on sums remaining unpaid
beyond the contractual period for payment, at the rate stipulated in the
Appendix to Bid. The Petitioner’s objection that the clause can apply
only to amounts previously certified by the Engineer must be examined
in light of the wording of the clause and the judicial interpretation of
comparable contractual provisions.
104. In National Highways Authority of India v. Hindustan
14
Construction Co. Ltd. , this Court rejected a blanket objection that
Sub-Clause 60.8 could apply only to amounts certified by the Engineer.
The Court held that the expression “sums payable” could encompass
amounts found due and payable by the arbitral tribunal. The mere fact
that the amount had been disputed or had not previously been certified
did not, by itself, exclude the operation of the clause.
105. The aforesaid principle, however, does not automatically
determine the date from which interest becomes payable. The
contractual provision must be applied with reference to the relevant
payment mechanism, including the period of 42 days stipulated for
payment following the monthly statement and the period of 84 days
contemplated in relation to the final certificate, as applicable. The date
on which the claim was referred to arbitration cannot, merely by reason
of being the date of invocation, be treated as the contractual due date
unless the relevant contractual and factual circumstances support that
14
2025:DHC:9222
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 29 of 33
conclusion.
106. Here, the Tribunal commenced interest on 05.02.2011, the date
arbitration was invoked. The record summarised above shows that the
claims had already been submitted and rejected by the Engineer before
arbitration was invoked. The award therefore does not grant interest
from the date the costs were first incurred, but from the date on which
the contractual dispute was referred to arbitration. NHAI has not
identified a term of the contract requiring interest to commence only
after the award or otherwise prohibiting interest from the date selected
by the Tribunal.
107. The 10% rate and monthly compounding must be consistent with
the Appendix to Bid and sub-Clause 60.8. The award expressly relies
on that provision. No specific term of the Appendix to Bid has been
identified in the material placed before the Court to show that the
Tribunal used a rate or compounding method different from the agreed
one. A general submission that the contractual rate is excessive does not
establish a ground for interference where the parties have agreed to the
applicable rate and method of calculation.
108. The Tribunal relied on the contract and selected a
commencement date later than the Engineer’s rejection of the claims.
In the absence of material showing that the rate, monthly compounding
or commencement date contradicts the contract, NHAI has not
established a ground under Section 34 to interfere with the award of
interest.
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 30 of 33
CONCLUSION
109. Petitioner’s objections concern the sufficiency of notice, the
existence and verification of contemporary records, the interpretation
of Clauses 53 and 70, responsibility for the 374-day delay, the methods
used to quantify plant-and-equipment costs and overheads, and the
award of interest.
110. The Tribunal considered these matters by reference to the
contract, the EOT, the evidence concerning the claims, the methods of
quantification and NHAI’s objections. The question under Section 34
is not whether this Court would have reached the same findings, but
whether any finding falls within a statutory ground for setting aside the
award.
111. Re-emphasizing the mandate in McDermott International Inc.
15
v. Burn Standard Co. Ltd. , Section 34 courts cannot convert
themselves into courts of appeal to re-examine factual matrices or
mathematical apportionments.
112. Applying these principles, the objections concerning the EOT,
plant and equipment, overheads, notices and contemporary records do
not justify interference merely because NHAI disputes the Tribunal’s
assessment. The Court has examined whether the award identifies
evidence and reasons supporting the findings and whether NHAI has
demonstrated any specific contradiction with the contract or record. For
the reasons set out above, no such defect has been established.
15
(2006) 11 SCC 181
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 31 of 33
113. For Claims Nos. 1A to 1D, the award treats the amounts as
additional costs recoverable under the relevant clauses and records that
the price adjustment already received under Clause 70 was deducted.
For Claim No. 2, the Tribunal relied on the machinery records and joint
verification and awarded the amount claimed as actual ownership costs
rather than the larger formula-based amount. For Claims Nos. 4 and 5,
it explained the weighted rate and mitigation deduction. The award of
interest is supported by sub-Clause 60.8, and NHAI has not shown that
the contractual rate or commencement date was impermissible.
114. On a reading of the award as a whole, the majority’s conclusions
are supported by the material identified in the award and reflect
plausible interpretations of the contract. NHAI has not shown that the
Tribunal ignored a material contractual bar, granted a double recovery,
relied on a finding contradicted by the record, or awarded interest
contrary to sub-Clause 60.8. The objections therefore do not meet the
threshold for interference under Section 34.
115. For the reasons stated above, the majority award dated
13.05.2015 is upheld.
116. The amounts awarded under Claim Nos.1A to 1D, 2, 4 and 5,
together with interest as awarded by the Arbitral Tribunal, shall remain
payable in accordance with the impugned award.
117. The petition under Section 34 of the Act is accordingly
dismissed.
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 32 of 33
118. Pending application(s), if any, are also disposed of. There shall
be no order as to cost(s).
OM PRAKASH SHUKLA, J.
NOVEMBER 23, 2026/pa /gunn
Signature Not Verified
Signed By:GUNN
Signing Date:23.11.2026
19:11:26
O.M.P. (COMM) 168/2016 Page 33 of 33