M/S Marino Dredgeco Limited vs The Board Of Trustees Of The Port Of Kolkata
- Court
- Supreme Court
2026 INSC 1238
Non-Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No. 14303 of 2026
(@Special Leave Petition (C) No.15175 of 2025)
M/s Marino Dredgeco Limited
...Appellant
Versus
The Board of Trustees of the Port of Kolkata
...Respondent
With
Civil Appeal No.14304 of 2026
(@Special Leave Petition (C) No.40370 of 2026
@Diary No.50150 of 2025)
J U D G M E N T
K. VINOD CHANDRAN, J.
Leave granted.
2. The two appeals are at the instance of the
awarder and the contractor against the judgment
under Section 37 of the Arbitration and Conciliation
Act, 1996 (for short, ‘the Act’); which appeal was filed
by the awarder. The impugned judgment overturned
Signature Not Verified
the judgment under Section 34 of the Act which
Digitally signed by
VISHAL ANAND
Date: 2026.11.18
16:35:41 IST
Reason:
affirmed the arbitration award and modified the
Page 1 of 13
CA@SLP (C) No.15175 of 2025 etc.
award quantifying the amounts payable by the
awarder to 50% of that quantified by the Arbitrator
and reduced the interest to 6% on the principal sum
from 08.02.2002. The modification was made on the
ground that the amounts claimed for additional works
carried out was more than 70% of the amounts as per
the original contract, which according to the Division
Bench of the High Court of Calcutta shocked the
conscience of the Court. This was despite the Division
Bench having recorded that the award passed by the
Arbitrator cannot be described as one based on ‘no
evidence’ or ‘insufficient evidence’ nor can it be
termed as perverse or patently illegal or against the
fundamental policy of Indian law. According to the
Division Bench, the shock rendered to its conscience
makes it fall within the ambit of conflict with the basic
notions of morality or justice.
3. Mr.R.Anand Padmanabhan and Mr.Amitava
Mukherjee, learned Senior Counsel appeared for the
Contractor; one in the appeal filed by the Contractor
and the other in the appeal of the Port Trust. The
Page 2 of 13
CA@SLP (C) No.15175 of 2025 etc.
learned Senior Counsel argued that the original
contract itself was for dredging of the river bed and
shores at the Sagar Island to make a channel and
basin, which was put in use from 17.04.2001 when it
was inaugurated by the Chairman of the awarder,
Port Trust of Calcutta. As on 19.07.2000, there was a
letter issued by the Port Trust, entrusting additional
work which occurred due to 100% siltation, requiring
dredging of the area repeatedly, more by reason of
the Port Trust having not provided correct data of the
soil constitution and having failed to construct
protective walls. It was argued that the Court under
Section 37 had limited powers of interference as has
been held by the Constitution Bench of this Court in
Gayatri Balasamy v. M/s ISG Novasoft
1
Technologies Limited . The modification made
based on the bills being shockingly high was without
looking at the material relied on by the Arbitrator.
Thus, causing interference on a subjective
presumption that the additional work cannot in its
1 2025 INSC 605
Page 3 of 13
CA@SLP (C) No.15175 of 2025 etc.
value reach a substantial percentage of the value of
the original work. It is on a mere surmise that such a
decision was arrived at without looking at the nature
of the work carried out and the additional work
necessitated.
4. Mr. Siddharth Bhatnagar, learned Senior Counsel
appearing for the respondent awarder Port Trust, in
tune with its decision to file an appeal against the
impugned judgment seeks for setting aside the entire
arbitral award. Alternatively, it is prayed that if at all
the additional work is found to have been carried out
by the contractor, then the impugned judgment has
to be sustained at 50% with reduced interest of 6%.
1
Gayatri Balasamy is relied on to point out that, in
fact, the entire award ought to have been set aside
since the award is against public interest.
5. It is pointed out that no completion certificate
was issued and there was no additional work
entrusted to the contractor. In fact, the work
entrusted was terminated and the appellant failed to
procure the certificate of completion, as is provided
Page 4 of 13
CA@SLP (C) No.15175 of 2025 etc.
under the General Conditions of Contract (GCC).
Reliance is also placed on Batliboi Environmental
Engineers Ltd. v. Hindustan Petroleum
2
Corporation Ltd. (HPCL) to argue that the
quantification of amounts should not be whimsical
and absurd, resulting in a windfall or bounty. We
should immediately notice that the cited decision has
no application since it dealt with damages and not
with respect to invoices validly raised for additional
work.
6. We also looked at the judgement of the Single
Judge under Section 34 of the Act which application
prayed for setting aside of the award dated
03.11.2003. Admittedly, the award was for
dredging/evacuation of the approach channel and
basin project of shore-based pilot station at Sagar
Island. The work was to be completed within 18
months and admittedly there was delay due to the
adverse force majeure conditions, not attributable to
the contractor. The learned Single Judge found that
2 (2024) 2 SCC 375
Page 5 of 13
CA@SLP (C) No.15175 of 2025 etc.
admittedly the work was completed by 17.04.2001
when the Chairman of the Port Trust inaugurated the
pilot station using the channel dredged by the
appellant. That there was additional work required to
be done is also evident from the letter dated
19.07.2000, addressed by the Port Trust to the
contractor, produced as Annexure A35 along with the
application to file additional documents. The learned
Single Judge affirmed the award.
7. It was also an admitted position that insofar as
the original work is concerned, the total amount
payable was Rs.2,86,56,200/- out of which
Rs.2,79,32,865/- had been paid. The arbitration was
initiated specifically for the additional work carried
out which is evident from the letter dated
19.07.2000. The additional work was necessitated
due to the force majeure weather conditions and due
to non-compliance of the soil character with the data
supplied by the Port Trust itself. As has been rightly
submitted by the contractor, the work itself was
dredging of river bed and shores to make a channel
Page 6 of 13
CA@SLP (C) No.15175 of 2025 etc.
and basin up to a specified depth with dumping and
disposal of dredged materials. The specific contention
is that re-dredging was required due to the mismatch
of the data supplied with respect to the soil
conditions and the failure to construct protective
walls to avoid further siltation. The work of re-
dredging is identical to that of the original contract, is
the contention raised, which by the nature of the
work, is found to be perfectly valid. Hence, the
modification of the award merely for reason of the
Court’s conscience having been shocked also for the
sole ground of the amount claimed for the additional
work having exceeded 70% of the original contract
cannot at all be sustained.
8. In fact, the Division Bench dealing with the
matter under Section 37 clearly recorded a finding
that the completion certificate was not available since
it was not issued by the Port Trust. Merely for reason
of refusal to issue completion certificate, it cannot be
said that the contractor would not be entitled to the
amounts in the bill raised for the work carried out,
Page 7 of 13
CA@SLP (C) No.15175 of 2025 etc.
was the finding. It was also found that the contractor
himself had produced the measurements and the
award was based on the pre and post work levels.
The Division Bench also found that the documents
relied on for the purpose of quantification of the
amounts due cannot be termed to be irrelevant for
the purpose of such determination, by no stretch of
imagination. The reliance placed on the documents
produced by the contractor to substantiate the work
carried out was found to be quite valid even in the
context of the absence of a completion certificate
issued under the GCC. The Division Bench also found
that the additional work was necessitated because of
the force majeure conditions and the mismatch of the
actual soil character from that disclosed in the data
made available by the Port Trust. Having found that
the arbitration award was based on adequate
evidence and by no stretch of imagination it can be
termed as perverse or patently illegal, we find the
modification on the ground of ‘shocking the
conscience’ to be not coming within the contours of
Page 8 of 13
CA@SLP (C) No.15175 of 2025 etc.
the jurisdiction conferred under Section 37 and it
cannot at all the be said to be in conflict with the
basic notions of morality or justice.
9. The Division Bench had relied on Ssangyong
Engineering & Construction Co. Ltd. v. National
3
Highways Authority of India (NHAI) to cull out
the principles for interference of an arbitration award.
The cited decision held that there can be no
interference with an award on the ground that the
Arbitrator has not adopted a judicial approach since
then, the interference would be on the merits of the
award, which cannot be permitted post the
Amendment of 2015. True, the Court also declared
that the conflict with the most basic notions of
morality or justice brought in after the Amendment,
substituting the “interest of India”; which was the
provision pre-amendment, can only be applied where
the arbitral award shocks the conscience of the Court.
However, the words are not to be applied on a mere
lip service and there should be a substantive reason
3 (2019) 15 SCC 131
Page 9 of 13
CA@SLP (C) No.15175 of 2025 etc.
which blatantly and patently brings forth the conflict
with the most basic notions of morality or justice,
resulting in the conscience of the Court being
shocked.
10. Somdatt Builders–NCC–NEC (JV) v. National
4
Highways Authority of India & Ors. held that the
High Court exercising extremely limited jurisdiction
under Section 37 of the Act cannot set aside an
arbitral award by merely using expressions like
‘opposed to the public policy of India’; ‘patent
illegality’ and ‘shocking the conscience of the Court’
( sic paragraph 51 ). As has already been held the
impugned order has merely used the words on the
sole ground of the bills for the additional work having
exceeded 70% of the original contract; without
looking at the nature of the additional work involved.
1
11. Gayatri Balasamy while putting forth the
proposition that awards, definitely can be set aside in
part, which power is encompassed in the power to set
aside the award in its entirety, made a caveat that
4 (2025) 6 SCC 757
Page 10 of 13
CA@SLP (C) No.15175 of 2025 etc.
setting aside an award partially would not be feasible
when the ‘valid’ and ‘invalid’ portions are legally and
practically inseparable. It was emphasised that the
‘valid’ and ‘invalid’ portions should not be inter-
dependent or intrinsically intertwined.
12. In the present case, there is no question of
severance of the award into separate silos since the
quantification was made in accordance with valid
measurements and the invoices raised by the
contractor. The Division Bench considering the
application under Section 37 has not looked into the
measurement or the invoices, which in any event,
would be an exercise of adjudication on merits,
clearly prohibited under the Act of 1996. The
measurements and invoices raised are of one
character, based on the additional work of re-
dredging which cannot be compartmentalised as
‘valid’ and ‘invalid’.
13. The impugned judgment also expressed shock
by reason merely of the enormity of the quantification
for additional works exceeding 70% of the original
Page 11 of 13
CA@SLP (C) No.15175 of 2025 etc.
contract for reason of the awarder being a State
entity. Pam Developments Private Ltd. v. State
5
of West Bengal required the parties to an
arbitration to be treated with equality; without any
special treatment being given to the Government
entity while even considering the application for grant
of stay of a money decree in proceedings under
Section 34 of the Arbitration Act. There can hence be
no interference caused to the quantum of claim
decided by the Arbitrator, based on valid material,
merely for the reason that the award debtor is a
Government entity and that the quantum appears to
be excessive without any substantiation for such a
ground being raised against the award itself.
14. At the cost of repetition, we have to observe
that the original contract was for dredging to build a
channel and the additional work was also for dredging
to keep the channel and basin operational. We find
the reasoning of the Division Bench under Section 37
to be not in consonance with the grounds provided
5 (2019) 8 SCC 112
Page 12 of 13
CA@SLP (C) No.15175 of 2025 etc.
under the Act to set aside an arbitral award,
especially, when the Arbitrator had looked into the
documents produced by the petitioner on joint
measurements carried out of the additional work
entrusted with the contractor.
15. The order impugned is set aside and the appeal
of the contractor is allowed. The arbitral award stands
restored.
16. The appeal of the Port Trust is disposed of since
already the order impugned is set aside in the other
appeal.
17. Pending application (s), if any, shall stand
disposed of.
……...…….……………………. J.
(J. B. PARDIWALA)
...………….……………………. J.
(K. VINOD CHANDRAN)
NEW DELHI
NOVEMBER 18, 2026.
Page 13 of 13
CA@SLP (C) No.15175 of 2025 etc.