BHARAT SANCHAR NIGAM LTD vs JOYSRI SENGUPTA AND ANR

Court
Calcutta High Court

1

IN THE HIGH COURT AT CALCUTTA
CIVIL APPELLATE JURISDICTION
APPELLATE SIDE
Before:

The Hon’ble Justice Debangsu Basak
And
The Hon’ble Justice Aryak Dutt


FMAT No. 219 of 2021
Bharat Sanchar Nigam Ltd.
Vs.
Joysri Sengupta & Anr.


For the Appellants : Mr. Kallol Basu, Adv.
Mr. Suman Banerjee, Adv.

For the Respondents : Mrs. Anupa Banerjee, Adv.
Mr. Rohan Shaw, Adv.

Heard on : 11.09.2026, 21.09.2026
29.09.2026

Hearing Concluded On : 29.09.2026

Judgment Delivered On : 07.10.2026


Aryak Dutt, J.:
1. This appeal under Section 37(1)(c) of the Arbitration
and Conciliation Act, 1996 (hereinafter referred to as "the Act") is

2

th
directed against the judgment and order dated 16 March, 2020,
th
passed by the learned Additional District Judge, 5 Court at
Barasat, North 24-Parganas, in Misc. Case No. 181 of 2016. By
that judgment, the learned Court below rejected the appellant's
application on contest under Section 34 of the Act and declined
th
to set aside the Arbitral Award dated 13 May, 2016, made by the
learned Sole Arbitrator, Justice Chittatosh Mookerjee, former
Chief Justice of this Court and of the Hon’ble Bombay High
Court.

2. The appellant in the present case is Bharat Sanchar
Nigam Limited (hereinafter referred to as the "BSNL") which was
the respondent before the learned Arbitrator. The original
claimant, Anjan Kumar Sengupta, died during the pendency of
the proceedings and is now represented by his legal heirs
(hereinafter referred to as “the respondent”).

th
3. By a registered lease dated 5 September, 1997, the
premises situated at 47 and 47/1/1, Basudebpur Road,
Shyamnagar, P.S. Jagaddal, District North 24-Parganas,
comprising an area of about 2,662 sq. ft. of covered space and
1,150 sq. ft. of open space, were let to the President of India

3

(Calcutta Telephones) for a term of 25 years for installation and
maintenance of a telephone exchange. The lessee's interest came
to vest in BSNL.

st
4. On 21 March, 2006, the Appellate Authority under
the West Bengal Pollution Control Board permitted operation of
st

the exchange only up to 31 August, 2006, after which BSNL
shifted the active exchange to the adjoining premises. A diesel
generator set and other equipment, however, remained in the
demised premises.

th
5. On or about 16 March, 2006, BSNL notified the
lessor that removal of the generator required the demolition of a
wall of the generator room. The respondent objected and
instituted a Title Suit No. 66 of 2006 before the learned Civil
Judge (Junior Division), Barrackpore.

rd
6. By a notice dated 23 February, 2007, under Clause
rd
7.1, BSNL sought to terminate the lease with effect from 23
nd
August, 2007 and offered vacant possession on 22 August,
2007.

4

7. The respondent subsequently filed an application
under Section 9 of the Act being Misc. Case No. 222 of 2007 and
obtained an interim order of status quo , which was vacated and
th
the application was dismissed on 13 February, 2008. The
respondent thereupon preferred an appeal being F.M.A.T. No.
367 of 2008 and in the appeal therefrom, a Division Bench of this
th
Court on 15 May, 2008, permitted BSNL to dismantle the wall to
remove the generator on condition that the wall be reconstructed
and no damage being caused to the upper floor or any other part
of the building. BSNL's attempt to remove the generator did not
succeed.

th
8. By an order dated 4 April, 2013, in A.P. No. 404 of
2012, this Court appointed the learned Sole Arbitrator. The order
noticed the disputes as to whether the respondent was entitled to
claim rent for the months in which BSNL had not been in
effective occupation of the property, and whether he was entitled
to withhold BSNL's generator set, and recorded that these
disputes were "indicative and not exhaustive".

9. The learned Arbitrator framed four issues: (i) whether
rd
the lease was lawfully terminated by the notice dated 23

5

rd
February, 2007, with effect from 23 August, 2007; (ii) whether
BSNL was liable to pay rent as demanded; (iii) whether BSNL was
liable to pay damages for the condition of the premises and, if so,
in what amount; and (iv) whether BSNL's counter-claim was
maintainable and proved.

th
10.
On 13 May, 2016, the learned Arbitrator passed his
award.


11. Being aggrieved by the award, BSNL presented its
th
application under Section 34 of the Act on 7 September, 2016
before the learned District Court, Barasat. The learned Court
held that the points decided by the learned Arbitrator fell within
the reference. The construction of the notice and the rejection of
the plea of waiver disclosed no patent illegality on the face of the
award. The delay in filing had not been sufficiently explained. The
application was rejected without costs. Hence, this appeal.

12. Learned advocate appearing for the appellant has
made the following submissions, which are also set out in the
written notes of argument filed on its behalf.

6

13. The lease was granted for the specific purpose of
installing and maintaining a telephone exchange, as the claimant
admitted in paragraph 1 of his statement of claim. The direction
of the Appellate Authority of the West Bengal Pollution Control
st
Board to stop the exchange and shift it by 31 August, 2006, was
binding on BSNL. This supervening impossibility frustrated the
contract. BSNL could not defy that direction. The learned
Arbitrator did not consider this aspect although it was taken in
Ground XIV of the Section 34 application. In the written notes of
argument the appellant has relied on Ssangyong Engineering
& Construction Co. Ltd. v. National Highways Authority of
India , reported in (2019) 15 SCC 131 , to contend that the
illegality goes to the root of the matter and calls for interference
under Section 37.

14. It was further submitted by the learned advocate
appearing for the appellant that the Clause 7.1 merely required
six months' previous notice. It does not say that a shortfall of a
few days rendered the notice void, nor that the lease would then
continue indefinitely. By holding that the notice was ineffective
th
because six full months had not elapsed between 14 March,
rd
2007 and 23 August, 2007, the learned Arbitrator took a hyper-

7

technical view. Both the learned Arbitrator and the learned Court
at Barasat misconstrued the clause and in effect rewrote the
contract. This is patent illegality.

15. It was then argued that BSNL made sincere efforts to
deliver vacant possession, but the respondent resisted it. The
respondent did not dispute the termination or sue for re-entry.
Instead, the respondent instituted a Title Suit No.66 of 2006 and
a Section 9 proceeding to keep BSNL in the premises and to
prevent removal of its equipment. The claimant’s witness
admitted receiving BSNL's letters offering to vacate, hand over the
keys and possession and remove its materials. He also admitted
objecting because BSNL wished to dismantle the wall. BSNL's
witness deposed that on the day fixed for removal the respondent
prevented removal.

16. Under Section 34(3) of the Arbitration and Conciliation
Act, 1996, time runs from receipt of the signed copy of the award.
In a large public corporation such as BSNL, the relevant receipt
is by the competent officer who knows of the proceedings and can
take decisions. The signed copy reached the competent divisional
th
office on 4 July, 2016, so the application was filed well within

8

th
time. Even if the time is being counted from 13 May, 2016, the
th
three months expired on 13 August, 2016 and the further 30
th th
days on 13 September, 2016. The application, presented on 7
September, 2016, was within the condonable period.

17. The learned section 34 Court relied on Tarapore &
Co. v. Cochin Shipyard Ltd. , reported in AIR 1984 SC 1072 , to
hold that where a specific question of law is referred, the Court
will not interfere even for an error of law apparent on the face of
the award. That decision was rendered under the repealed
Arbitration Act, 1940. After the 2015 amendment, Section 34(2A)
expressly makes patent illegality appearing on the face of the
award a ground for setting it aside.

18. The building was old and had been occupied since
1997. Faded plaster, damp and age-related cracks over sixteen
years are normal wear and tear. No bills, vouchers or receipts
proving actual expenditure were produced. The learned Arbitrator
accepted a rough estimate of a sum of Rs. 8,00,000 and added 10
per cent for speculative future damages. The summary rejection
of the counter-claim and the award for a sum of Rs. 3,00,000 as
costs are arbitrary and perverse.

9


19. The appellant in order to advance its argument had
relied upon a judgment of Delhi Airport Metro Express (P) Ltd.
v. Delhi Metro Rail Corporation Ltd. , reported in (2022) 1 SCC
131 , the appellant submitted that an award which ignores a vital
contractual term, is founded on a perverse construction and
shocks the conscience of the Court cannot be shielded, and that
the Section 37 court must ensure that the Section 34 court acted
within the statutory parameters. The appellant prayed that the
appeal be allowed, the award and the impugned judgment be set
aside, allowing its counter-claim.

20. Learned advocate for the respondent opposed the
appeal and made the following submissions, which are also set
out in their written notes on argument.

21. Section 34 provides no appeal on facts or on law. Not
merely because of an erroneous application of law or by re-
appreciating evidence the award cannot be interfered with. The
jurisdiction under Section 37 is confined within the same limits.
In this regard in the written notes reliance was placed on Punjab
State Civil Supplies Corporation Ltd. v. Sanman Rice Mills ,
reported in 2024 SCC OnLine SC 2632 ; Somdatt Builders-

10

NCC-NEC (JV) v. National Highways Authority of India ,
(2025) 6 SCC 757 ; and Jan De Nul Dredging India
reported in
(P) Ltd. v. Tuticorin Port Trust , reported in (2026) 3 SCC 186 .
The respondent argues that a still greater restraint is required
while dealing with an appeal under Section 37.

22.
The respondent further argues that it is not whether
the Arbitrator's reading is the only possible one, but whether it is
so irrational that no reasonable person could adopt it. The
th
learned Arbitrator took the admitted date of service to be 14
March, 2007, compared it with the date of termination which was
rd
23 August, 2007, and held that the lessor had not received the
six months' previous notice as required in the clause. That is at
least a plausible construction. BSNL's grounds that the clause
was "erroneously" construed only invite the Court to substitute
its own reading which is impermissible.

23. The learned Arbitrator found that waiver had been
neither pleaded in the counter-statement nor established by
evidence. He refused to allow it to be raised for the first time at
final argument. That is a finding on pleadings and evidence and
is not patent illegality.

11


24. The learned Arbitrator considered the earlier
proceedings, the order of this Court regarding demolition and
reconstruction of the wall, and the evidence on the attempted
removal. He accepted that the respondent had objected to the
removal of the generator because it involved demolishing a wall.
He did not accept that the respondent had obstructed removal of
the other equipment. He also found that BSNL had admittedly
kept the premises under its own lock and key. It did not
determine that the tenancy had ended or that rent had ceased.

25. The learned Arbitrator did not mechanically allow the
whole claim. He applied limitation and confined arrears from
April 2009 onwards. The enhanced rent from May 2012 follows
from the findings on the subsistence of the tenancy and
continued possession. The counter-claim was rejected with
reasons, including that a witness for BSNL had no personal
knowledge and only produced office records.

26. In the memorandum of appeal, BSNL has for the first
time contended that the lease is invalid and relied on Section 106
of the Transfer of Property Act, 1882. This was never its case in
the arbitration and raised for the first time under Section 37. In

12

any event, Section 106 applies only in the absence of a contract
to the contrary.

27. The respondents prayed that the appeal be dismissed,
the impugned judgment affirmed, and BSNL directed to hand
over possession of the leased premises forthwith.

28. We have considered the submissions and perused the
materials on record. Since the Section 34 application was filed on
th
7 September 2016, after the Arbitration and Conciliation
(Amendment) Act, 2015, the challenge is governed by Section 34
of the amended Act.

29. The Section 34 has been authoritatively explained in
Ssangyong (supra) which is extracted and applied in Delhi
Airport Metro Express ( supra) on which the appellant itself
relies.

30. In the same decision, the Supreme Court cautioned
against "a disturbing tendency of Courts setting aside arbitral
awards, after dissecting and reassessing factual aspects of the
cases". The case of Delhi Airport Metro Express (supra)

13

therefore does not widen the jurisdiction as suggested by the
appellant.

31. On the appellate jurisdiction, the Hon’ble Supreme
Court in Somdatt Builders (supra) held that interference under
Section 37 "cannot travel beyond the restrictions laid down under
Section 34. In other words, the Court cannot undertake an
independent assessment of the merits of the award and must
only ascertain that the exercise of power by the Court under
Section 34 has not exceeded the scope of the provision."

32. The decisions in Sanman Rice Mills (supra) and Jan
De Nul Dredging (supra) , relied on by the respondents in their
written notes, are to the same effect as aforesaid. We need not
multiply authorities.

33. The award here has been upheld by the Section 34
court. Our task is therefore limited. We must see whether the
decision is beyond the reference, a construction no fair-minded
person could adopt, a finding based on no evidence or one
ignoring vital evidence, or a conflict with the public policy of
India. If none is shown, the appeal must fail.

14

th
34. The award is dated 13 May, 2016. Three months from
th
that date expired on 13 August, 2016, and the further period of
th
thirty days under the proviso to Section 34(3) expired on 12
th
September, 2016. The application, presented on 7 September,
2016, was therefore within the outer limit even if time is counted
from the date of the award. The learned Court below did not
accept the appellant's claim that it received the signed award on
th
4 July, 2016, because the claim was not supported by any
document, and held the delay unexplained. However, it also
examined every ground on its merits. We have assumed, in the
appellant's favour, that the application was maintainable and
have tested the impugned judgment on merits.


35. Under Section 34(2)(a)(iv) of the Act, the question is
whether the award decides a dispute not contemplated by, or not
falling within, the submission to arbitration.

36. Clause 7.1 of the agreement required "six month's
previous notice to the Lessor in writing". The learned Arbitrator
held that a notice which must be given to the lessor operates only
when it is communicated to him. On that view, the lessor

15

received less than six months' notice. This view is a possible and
plausible view. We will not substitute our view.

37. Waiver is the intentional relinquishment of a known
right. The learned Arbitrator found that BSNL had pleaded no
waiver, or relinquishment of the six-month requirement, in its
counter-statement, and that its witnesses had led no evidence to
establish it. On that basis he refused to entertain the plea when
it was raised for the first time at final argument. That is a
conclusion on the pleadings and evidence before him of which he
is the final judge.

38. The direction of the Appellate Authority of the West
Bengal Pollution Control Board required BSNL to stop operating,
and to shift the exchange. BSNL complied by moving the
exchange to adjoining premises. That was its case before the
learned Arbitrator. The Transfer of Property Act, 1882, deals
separately with a lessee's right to avoid the lease where the
property is rendered substantially and permanently unfit for the
purpose for which it was let out. No such case was made out by
the appellant.

16

39. It is also clear that the Board's order did not prevent
BSNL from surrendering the premises. It is for continued
occupation of premises under a subsisting tenancy. We find no
illegality, much less one going to the root of the matter.

40. The learned Arbitrator considered the earlier
proceedings, the order of this Court and the oral and
documentary evidence. He accepted that the respondent objected
to removal of the generator because it involved demolition of a
wall. He did not accept that the respondent had obstructed
removal of the other equipment. He also found that BSNL had at
all times kept the premises under its own lock and key.

41. Re-appreciation of evidence looked into by the
Arbitrator is impermissible in a challenge under Section 34. It is
equally impermissible in an appeal under Section 37 of the Act.

42. The award therefore does not hold BSNL liable for rent
for the period around the attempted removal in September 2008.
The interim order of this Court in F.M.A.T. No. 367 of 2008
permitted removal of the generator on conditions. That appeal
was dismissed for default in May 2010. Yet BSNL has retained
the premises under its own lock and key ever since.

17


43. Section 73 of the Indian Contract Act, 1872, permits
compensation for loss naturally arising from a breach. Whether
the damage exceeds normal wear and tear within Clause 7.2, and
what the cost of repair will be, are questions of fact and
assessment for the Arbitrator which he has done.

44. The learned Arbitrator accepted an estimate on
evidence. The quantification may not be precise, but it rests on
evidence and a stated reason. It does not shock the conscience of
the Court. Interference with it would require exactly the
reassessment of evidence which is not permissible.

45. The counter-claim depended on BSNL proving
deterioration of its equipment and its loss of revenue. The learned
Arbitrator gave reasons for rejecting it. One of BSNL's witnesses
had no personal knowledge and only produced office records, and
that obstruction in respect of the other equipment was not
established. The finding is not perverse. The award for a sum of
Rs. 3,00,000 as costs to the substantially successful party was
well within the discretion of the Tribunal.

18

46. In the memorandum of appeal, the appellant has
questioned the validity of the lease and relied on Section 106 of
the Transfer of Property Act, 1882. This plea was not raised
before the learned Arbitrator. As far as the impugned judgment
shows, it was not raised before the learned Court below. A new
plea which depends on facts cannot be raised for the first time in
an appeal under Section 37 to impeach an award.

47. The appellant asks this Court to reassess the damages,
and to allow its counter-claim. These are matters within the
domain of the Arbitral Tribunal. The award has been upheld by
the Section 34 Court. The appellant has not shown that the
award decides a matter beyond the reference, adopts a
construction no reasonable person could adopt, rests on no
evidence, ignores vital evidence, or conflicts with the public policy
of India.

48. In view of the above, F.M.A.T. No. 219 of 2021 is
dismissed .

th
49. The judgment and order dated 16 March, 2020,
th
passed by the learned Additional District Judge, 5 Court at

19

Barasat, North 24-Parganas, in Misc. Case No. 181 of 2016 is
th
affirmed, and the arbitral award dated 13 May, 2016, is upheld.

50. All other pending applications, if any, stand disposed
of.
51. There shall be no order as to costs.


(ARYAK DUTT, J.)

52. I Agree
(DEBANGSU BASAK, J.)