Ajit Patel vs Evita Co-Operative Housing Society Ltd.

Court
Supreme Court

2026 INSC 1269
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO(S). OF 2026
(Arising out of SLP (Civil) No (s). 29513 of 2026)

AJIT PATEL ….APPELLANT(S)


VERSUS


EVITA CO-OPERATIVE HOUSING
SOCIETY LTD. AND ORS. ….RESPONDENT(S)

J U D G M E N T
Mehta, J.

1. Heard.
2. Leave granted.
3. Respondent No. 5, HGP Community Pvt. Ltd.
(formerly known as Lakeview Developers), developed
residential and commercial buildings in the name
and style of “Hiranandani Gardens” on land bearing
C.T.S. Nos. 4/1 to 4/5 and 4/7, Sector IV-A, Village
Signature Not Verified
Digitally signed by
SONIA BHASIN
Powai, near IIT, Powai, Mumbai-400076. The present
Date: 2026.11.25
17:56:59 IST
Reason:
1

litigation relates to the high-rise building named
“Evita” in the Hiranandani precincts. As per the
proposed plan, the high-rise residential building was
to have a basement, ground floor on stilts, first-floor
nd th
podium and upper floors from 2 to 29 floor, with a
total height of 95.35 metres, measured from general
ground level to the terrace slab.
4. The building plans were submitted to the Chief
Fire Officer, Mumbai Fire Brigade, in the year 2002.
th th
Fire NOCs dated 24 October, 2002 and 26 March,
2004, issued by the Mumbai Fire Brigade prescribed
the fire protection and fire-fighting requirements to
be complied with during construction of the building.
th
5. Condition No. 14 of the NOC dated 26 March,
2004, dealt with refuge areas under two separate
clauses. Clause 14(A) specified the refuge area
th th th
admeasuring 112.84 sq. metres at the 8 , 14 , 20
th
and 26 floor levels and prescribed requirements
governing those areas. Clause 14(B) separately
stipulated that “the terrace floor shall also be treated
as Refuge area,” subject to instructions concerning
refuge-area signage, drinking-water facilities and
emergency lighting.
2
C.A.@ SLP (Civil) No (s). 29513 of 2026

6. The appellant herein purchased Flat Nos.
2902/A to 2902/D, having an aggregate area of 4,575
sq. ft., under four separate Articles of Agreement
th
dated 26 March, 2004. Under these agreements, the
developer undertook to provide additional amenities,
including terrace areas corresponding to the
respective flats. The total consideration specified in
these agreements including the additional amenities
was Rs. 3,02,33,125/-. The appellant asserts that the
flats and the corresponding terrace areas were
allotted/sold to him as an integrated arrangement.
7. The appellant relies upon the subsequent Fire
NOC and sanctioned plans to contend that the
disputed terrace portion was not retained as a refuge
area in the final approved configuration; the
respondents seriously dispute this interpretation.
8. The construction was completed in the year
2006, whereafter the architect of respondent No.5
sought an occupation NOC from the Mumbai Fire
Brigade preceded by inspection of the fire safety
compliances. A senior officer of the Department
visited the building to verify compliance with regard
to the fire protection and fire-fighting requirements
th
stipulated in the NOC dated 24 October, 2002.
3
C.A.@ SLP (Civil) No (s). 29513 of 2026

9. After inspection, the Department conveyed its
no objection to the occupation and use of the
building. The Brihanmumbai Mahanagarpalika
1
(Municipal Corporation of Greater Mumbai,
respondent No.3 herein) issued the Occupation
Certificate for the building, approving the amended
th
plan-cum-full development work, on 15 June, 2007.
10. A specific case is set up by the appellant that
this approved plan did not depict the disputed terrace
portion as a refuge area. As per the appellant, in the
said approved plan, there are two separate sections
of the terrace floor, one above Flat No. 2901 and the
other above Flat No. 2902. The appellant claims
exclusive ownership of the terrace floor above Flat No.
2902, which was purportedly conveyed to him under
st
four separate Agreements dated 31 August, 2007.
The remaining part of the terrace, as per the
appellant, is open to the sky, intended for common
use, and accessible via two separate staircases. The
appellant claims to be in possession of the said flats
and terrace since the year 2007.

1
For Short “MCGM”.
4
C.A.@ SLP (Civil) No (s). 29513 of 2026

11. Respondent No. 1-Evita Co-operative Housing
2
Society Ltd. was registered in November, 2008. As
per the appellant, right from the inception, the
society was aware about the existence of the two
demarcated sections of the terrace as referred to
supra .
th
12. The Society lodged a complaint dated 28
October, 2016, with the Mumbai Fire Brigade alleging
that the appellant had encroached upon the terrace
reserved as a refuge area and had also made
impermissible deviations in the flats purchased by
him. Pursuant thereto, the premises were inspected
th
and a report dated 8 March, 2017, was prepared by
the Deputy Chief Fire Officer, Mumbai Fire Brigade,
recording that the terrace was divided into two parts
and that the office copy of the NOC for occupation of
th
the building was “under search”. On 18 December,
2020, respondent No.1-Society and its Secretary filed
a writ petition bearing W.P. No. 254 of 2021 before
3
the High Court of Judicature at Bombay, raising
objection to the purported conveyance of the terrace
area by the developer to the appellant, claiming that

2
Hereinafter referred to as “Society” or “respondent No.1-Society”.
3
Hereinafter referred to as the “High Court”.
5
C.A.@ SLP (Civil) No (s). 29513 of 2026

the same was earmarked as a common fire refuge
area and could not have been sold at all. Pleadings
were exchanged in the writ petition, which remained
pending for almost five years.
th
13.
On 6 March, 2025, respondent No.3 issued a
notice to the appellant under Section 53(1) read with
Section 52(1)(b) and (d) of the Maharashtra Regional
4
and Town Planning Act, 1966, imputing that
unauthorised works had been carried out contrary to
the sanctioned plans in Flat No. 2902 and on the
terrace, such as unauthorised covering of a duct,
erection of a spiral staircase, construction of wooden
platforms/decks, and installation of wooden and
glass sliding doors, etc. The appellant was notified
that all this was done without permission of the
competent authority, and he was asked to show
cause or face demolition.
14. The appellant claims that these works pre-
existed and predated the Occupation Certificate, and
the appellant, being a purchaser, cannot be
bona fide
held responsible for carrying out the alleged
unauthorised construction/additions.

4
For Short “MRTP Act”.
6
C.A.@ SLP (Civil) No (s). 29513 of 2026

15. Writ Petition No. 254 of 2021 filed by
respondent Nos. 1 and 2, came to be heard and
decided by the Division Bench of the High Court vide
th 5
judgment dated 5 August, 2026, with the following
observations and directions:
“10. In the wake of the entire conspectus of the
matter, we note that in the affidavit the Developer
has adopted a specific stand and the Respondent
No.4 is harping upon the said stand, but we are
conscious of the fact that arbitration proceedings
are ongoing between them and we are not aware as
to what is the impression given to the Respondent
No.4 by the Developer as it is a specific argument
of the learned counsel representing Respondent
No.4 that an internal staircase, which is seen in the
photographs was already constructed by the
Developer himself and he has not taken any steps.
He harps on the impression given to him that even
the terrace is sold to him and according to the
learned counsel he has paid consideration in that
regard to the Developer. In any case, we do not
intend to get into the same but at present, we
must only note that if the terrace is declared as
a refuge area and if the Fire Department has
imposed a condition that it shall act as a refuge
area and comply with the stipulation like the
entrance doors of the refuge areas painted with
“REFUGE AREA IN CASE OF EMERGENCY”,
provision of adequate drinking water facilities
as well as adequate emergency lighting facility
connected to the electric circuits of staircase,
corridor/passage etc., and if this was the
condition for grant of Occupation Certificate by
the fire department then this facility must be in
place. The occupation of the building itself was
permitted subject to the undertaking given by the

5
Hereinafter referred to as the “impugned judgment”.
7
C.A.@ SLP (Civil) No (s). 29513 of 2026

Developer that he has ensured compliance of all the
requirements but we really wonder whether any
inspection was taken out of the building to ensure
that the facilities have been maintained. In any
case, now since the Society has expressed
apprehension and from the photographs, it is
evidently clear that the entry on the terrace is
blocked and the only access available on the
terrace, which is declared as a refuge area is
through an internal staircase, which is constructed
through Flat No 2902 A and for this purpose
finding it to be unauthorized the Corporation has
issued a notice and even had passed a speaking
order. The aggrieved party Respondent No.4 has
already knocked the doors of the competent court,
but has not yet obtained any stay. In such
circumstances, we are of the view that it is high
time that the Corporation proceed ahead with the
action based on the speaking order dated
10/08/2025, which is passed after issuance of
notice to Respondent No.4 and on consideration of
the response of Respondent No.4 and by following
due process of law if the speaking order is passed,
then it must be immediately given effect. As far as
the dispute between the Developer and the
Respondent No.4 is concerned, we have not
touched or pronounced upon the entitlement of
either party in the said proceedings. We direct the
Corporation to immediately proceed with the
implementation of the order dated 10/08/2025, as
we are informed that there is no stay granted.

11. Worth it note that if the Corporation find that
the refuge area is not only on the terrace but on the
other floor, which is earmarked by the fire
department is not compliant with the specifications
set out by the fire department in its communication
dated 26/03/2024 while granting the NOC
stipulating fire protection and fire fighting
requirements in construction of the high rise
building, the Corporation is at liberty to bring to
8
C.A.@ SLP (Civil) No (s). 29513 of 2026

the notice of the fire department which shall be
then competent to take appropriate action, which
may even extend to withdrawal of the Occupation
Certificate.

12. It is a contention of Respondent No.4 that the
flats on various floors also have enclosed the duct
and we expect the Corporation to carry out an
inspection in this regard and if according to the
Corporation it is an illegality or an unauthorized
structure, we direct Corporation to initiate action.

13. As far as the staircase is concerned, the learned
counsel for the Respondent No.4 has vehemently
asserted that it is provided by the Developer, but
Mr. Tamboly specifically deny. From the
photographs placed before us the staircase leads to
the terrace and we have an objection about the
terrace being put to exclusive use by Respondent
No.4, but on an inspection being carried out before
taking action for implementation of the speaking
order, if Respondent No.4 close the access to the
terrace and chose to keep the staircase as an
architectural marvel in his own flat, we direct that
the Corporation shall permit it to be retained, if it
do not cause harm to the remaining structure. We
also clarify that Corporation shall ensure that the
common door which has been closed providing
access to the terrace shall be opened. With the
above direction, the Writ Petition is made
absolute.”
(Emphasis supplied)

16. Being aggrieved by the aforesaid judgment, the
appllent (flat owner) is before us in the instant appeal
by special leave.
17. We have heard and considered the submissions
advanced by the learned counsel representing the
9
C.A.@ SLP (Civil) No (s). 29513 of 2026

appellant and the learned counsel representing the
respondents and have perused the impugned
judgment and the material placed on record.
18. The fact that the appellant purchased four flats
bearing Nos. 2902/A, 2902/B, 2902/C and 2902/D
under four separate registered Agreements for Sale,
all dated 31st August, 2007, is not in dispute. There
are claims and counter-claims of the parties
regarding the status of the terrace floor above the
flats purchased by the appellant.
19. While the appellant asserts that the terrace
areas corresponding to the four flats were agreed to
be provided to him as an integrated conveyance along
with the flats, the respondents contest the said claim,
alleging that the entire terrace area of the subject
building was a part of the refuge area under the
original NOC/sanction plan.
20. The Fire Brigade, pursuant to the Society's
th
complaint dated 28 October, 2016, inspected the
th
premises on 4 February, 2017, and issued a report
th
dated 8 March, 2017, which recorded that the office
copy of the NOC for occupation of the building was
“under search”.
10
C.A.@ SLP (Civil) No (s). 29513 of 2026

th
21. The MCGM issued a notice dated 6 March,
2025 to the appellant, under the MRTP Act, 1966,
and, pursuant to the proceedings initiated
th
thereunder, passed an order dated 10 August,
2025, directing the appellant to remove the alleged
unauthorised works within 15 days of receipt thereof.
The appellant challenged the said notice and order in
L.C. Suit No. 102020 of 2025 before the Bombay City
6
Civil Court at Mumbai, which is pending
consideration.
22. On going through the impugned judgment
passed by the Division Bench of the High Court, we
find that the High Court has delved into issues
involving seriously disputed questions of fact to
decide the competing claims of the parties. Whether
or not the terrace portion claimed by the appellant
forms a part of the refuge area would require
appreciation and sifting of evidence and examination
of contemporaneous documents, which are precisely
the issues under consideration before the Civil Court
seized of L.C. Suit No. 102020 of 2025 filed by the
appellant. The observations made by the High Court

6
Hereinafter referred to as the “Civil Court”.
11
C.A.@ SLP (Civil) No (s). 29513 of 2026

( supra ) have the tenor of conjectures and surmises
based on some photographs placed on record during
the course of hearing of the writ petition.
23. In view of the competing claims of the parties
regarding the status of the said terrace area and the
specific plea raised by the appellant that apart from
the portion claimed by him, another portion of the
terrace is open to the sky, intended for common use
and accessible through both staircases, we are of the
firm opinion that the High Court erred in exercising
the extraordinary jurisdiction under Article 226 of
the Constitution of India in the petition preferred by
the respondents to adjudicate a lis which involves
seriously disputed questions of fact. The findings in
the impugned judgment being based on conjectures
and surmises, cannot be affirmed.
24. The High Court, the impugned judgment,
vide
directed the Corporation to proceed with the action
th
pursuant to the order dated 10 August, 2025 and to
give immediate effect thereto. While doing so, the
High Court observed that it was not touching or
pronouncing upon the entitlement of either party to
the proceedings. However, in spite thereof, the
Corporation was specifically mandated to
12
C.A.@ SLP (Civil) No (s). 29513 of 2026

immediately implement the said order. The High
Court further issued directions in paragraph 13
concerning the staircase leading to the terrace and,
in its concluding direction, required the Corporation
to ensure that the common door providing access to
the terrace is opened for easy access of all the
residents. The said direction appears to be justified
insofar as it would ensure clear and unhindered
access to the terrace to all occupants of the building
in case of an emergency situation. Thus, to that
extent, the impugned order is sustained without
prejudice to the judicial discretion of the trial Court
in the pending civil suit filed by the appellant.
25. Law is well settled that a Court examining a
lis
under Article 226 of the Constitution of India is not
obliged to entertain a challenge involving seriously
disputed factual aspects. Such issues may more
appropriately be examined by the competent Civil
Court or the prescribed statutory authority, as the
case may be. Indisputably, the civil suit preferred by
th
the appellant, challenging the notice dated 6 March,
2025, and the consequential speaking order dated
th
10 August, 2025, issued by the MCGM in respect of
the alleged unauthorised works in Flat No. 2902 and
13
C.A.@ SLP (Civil) No (s). 29513 of 2026

the terrace area, is pending consideration before the
Civil Court.
26. Suffice it to say that once the appellant had
availed the jurisdiction of the Civil Court by
th
challenging the order of the Corporation dated 10
August, 2025 before the Civil Court, any direction
issued by the High Court requiring the Corporation
to implement the said order would necessarily have
an adverse bearing on the adjudication of the pending
suit, virtually making the remedy redundant.
27. We may note that the High Court for passing the
above directions placed reliance on the fact that the
appellant had not been granted any injunction in the
civil suit. In that situation, the onus would be upon
the MCGM to take necessary steps for
th
implementation of the order dated 10 August, 2025.
28. By effect of the mandatory directions issued by
the High Court supra for immediate implementation,
the remedy before the Civil Court would be
overshadowed, leaving hardly any scope for the Civil
Court to take an independent view on the legality and
th
validity of the order dated 10 August, 2025. In our
opinion, the directions issued by the High Court have
the effect of pre-empting adjudication of seriously
14
C.A.@ SLP (Civil) No (s). 29513 of 2026

disputed questions of fact which completely overlap
with the issues pending before the Civil Court.
Clearly, thus, the dispensation made by the High
Court in the impugned judgment prejudices the
pending civil suit filed by the appellant.
29. Consequently, the impugned judgment to the
extent indicated above is hereby set aside. The
appellant is permitted to raise all his defences and
contentions in the pending civil suit instituted by
him. The respondent No.1-Society shall also be
entitled to contest the suit, if it so desires.
30. Considering the fact that the issues raised
before the Civil Court involve the interpretation of
rival claims over the refuge area, meant for safety and
security of the residents of the building, we hereby
direct the Civil Court to expedite the proceedings and
to try and conclude the same preferably within six
months from the date of presentation of a copy of this
order. Needless to say that the Civil Court shall
decide the suit uninfluenced by the observations
made in the impugned judgment and all parties shall
cooperate in the expeditious disposal of the suit.
31. The appeal is allowed in these terms.
15
C.A.@ SLP (Civil) No (s). 29513 of 2026

32. Pending application(s), if any, shall stand
disposed of.

……….….……………………J.
(VIKRAM NATH)

………....…………………….J.
(SANDEEP MEHTA)

………....…………………….J.
(APARESH KUMAR SINGH)

NEW DELHI;
NOVEMBER 25, 2026.