Ms Ra Ghule Through Its Sole Proprietor Rajabhau Apparao Ghule vs Sinnar Municipal Council

Court
Bombay High Court

CNR No : HCBM020158542026

2026:BHC-OS:19811
carapl15854-2026-J.doc

AGK
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
IN ITS COMMERCIAL DIVISION
COMM ARBITRATION APPLICATION (L) NO.15854 OF 2026
R.A. Ghule, through it’s sole Proprietor
Rajabhau Apparao Ghule
… Applicant
Vs.
ATUL
GANESH
KULKARNI
1. Sinnar Municipal Council
Digitally signed by
ATUL GANESH
KULKARNI
Date: 2026.09.07
12:00:02 +0530
2. The Chief Officer,
Sinnar Municipal Council
3. State of Maharashtra
4. Town Engineer, Sinnar
Municipal Council
… Respondent
Mr. Manoj Harit with Ms. Saloni Bafna, Ms. Dhrishti
Ostwal, and Mr. Niket Harit i/by Manoj Harit & Co., for
the Applicant.
Mr. Mohit Jadhav, AGP for Respondents-State.
CORAM : AMIT BORKAR, J.
RESERVED ON : SEPTEMBER 2, 2026.
PRONOUNCED ON : SEPTEMBER 7, 2026
JUDGMENT:
1. The present Application has been filed by the Applicant
under Section 11 of the Arbitration and Conciliation Act, 1996,
seeking appointment of an independent Arbitrator and constitution
1
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

of an Arbitral Tribunal in terms of Clause 8 of the Contract
Agreement dated 26 August 2014. The disputes between the
Applicant and the Respondents are stated to arise out of the said
Contract Agreement.
2. The Contract Agreement was executed between the
Applicant and Respondent No.1 on 26 August 2014. Pursuant
thereto, Respondent No.1 issued a Work Order to the Applicant for
execution of the project. The stipulated period for completion of
the work was 24 months, and the work was therefore required to
be completed on or before 25 August 2016. According to the
Applicant, there was delay in handing over the site for carrying out
the work. The Applicant contends that such delay occurred for
various reasons, which, according to the Applicant, were
attributable to the Respondents. It is the case of the Applicant that
the delays were brought to the notice of the Respondents from
time to time. In view of the delays which had occurred, the
Respondents extended the time for completion of the project up to
31 March 2021. On 8 March 2021, a Final Work Completion
Certificate was issued in favour of the Applicant. The said
Certificate recorded that the project work had been completed to
the satisfaction of the Respondents. Thereafter, on 15 March 2021,
the Applicant issued a notice raising a claim of Rs.53,35,71,002/-
towards compensation for delay and other amounts stated to be
payable under the Contract Agreement. On 2 June 2021, the
Applicant issued a further notice to the Respondents and reiterated
its demand for payment of the outstanding amounts. On 23 June
2021, Respondent No.3, by a letter addressed to Respondent No.2,
2
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

directed that the initial deposit amount paid by the Applicant be
refunded. According to the Applicant, however, the said amount
was not released. On 20 September 2021, Respondent No.2 issued
a letter denying the claims made by the Applicant. Respondent
No.2 raised a counter-claim against the Applicant in the sum of
Rs.1,64,30,16,836/-, which, according to the Applicant, was
arbitrary. The Applicant, by its reply dated 4 October 2021, denied
the counter-claim made by the Respondents. The Applicant
reiterated that the work had been completed in accordance with
the Contract Agreement and relied upon the Final Work
Completion Certificate issued in its favour. As the amounts claimed
by the Applicant were not paid and the Respondents had raised the
aforesaid counter-claim, the Applicant filed Writ Petition No.15271
of 2022 before this Court seeking appropriate reliefs against the
Respondents. The said Writ Petition was disposed of on 16
December 2025 after permitting the Applicant to withdraw the
same, as the Applicant intended to invoke the arbitration
agreement contained in Clause 8 of the Contract Agreement.
3. Accordingly, on 18 December 2025, the Applicant issued a
notice invoking arbitration under Clause 8 of the Contract
Agreement and called upon the Respondents to appoint an
Arbitrator. According to the Applicant, after receipt of the
arbitration notice dated 18 December 2025, the Respondents
neither replied to the said notice nor took any steps for
appointment of an Arbitrator. It is in these circumstances that the
present Application has been filed.
3
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

4. Mr. Manoj Harit, learned Advocate for the Applicant submits
that Clause 8 is an arbitration agreement within Section 7 of the
Act. It refers the disputes between the parties to a named authority
for a decision that is to be final and binding on both parties, and it
bars recourse to the civil court. Neither the absence of the word
“arbitration”, nor the description of the authority as an “appellate
authority”, nor the circumstance that the named authority is
connected with a party, detracts from its character as an arbitration
agreement. Clause 8 of the Contract:
“That SMC hereby agrees to pay the contractor the agreed
sum. If dispute arises, the same shall be referred to the
Principal Secretary, UD-2, Urban Development Department,
Govt of Maharashtra, Mumbai (hereinafter referred to as the
said authority) and the decision given by the said authority
shall be final and binding on both the parties. In the event of
disagreement by the contractor upon any decision taken by
SMC in respect of the said terms and conditions, the said
authority shall be acting as appellate authority and both the
parties shall be at liberty to prefer an appeal against any
decision of SMC. Decision taken by the said authority on any
appeal shall be final and binding on both the parties. The
contractor shall not be entitled to initiate any dispute in any
court of law and in the event if the contractor initiate any
dispute in court of law it will be treated as the breach of the
said terms and conditions and in that event the contract
awarded to the contractor shall stand automatically
terminated.”
5. He submits that Section 7 of the Act prescribes no particular
form for an arbitration agreement. What has to be seen is whether
the parties intended that a dispute arising between them would be
referred to and decided by a forum of their choice, that intention
4
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

being gathered from the substance of the agreement. In Babanrao
Rajaram Pund v. Samarth Builders & Developers , (2022) 9 SCC
691, the Supreme Court held that a deficiency of words in an
agreement which otherwise fortifies the intention of the parties to
arbitrate cannot invalidate the clause, and that the substance of
the agreement must be given greater weight. The same principle
was laid down in Rukmanibai Gupta v. Collector, Jabalpur , (1980)
4 SCC 556, namely, that an arbitration agreement is not required
to be in any particular form.
6. He submits that a clause by which a dispute is referred to a
named authority whose decision is to be final and binding is an
arbitration agreement, even though the word “arbitration” is not
used, and even though the authority is an officer connected with a
party. In Chief Conservator of Forests, Rewa v. Ratan Singh Hans ,
AIR 1967 SC 166, the contract provided that any dispute as to the
performance or breach of the contract “shall be referred to the
Chief Conservator of Forests whose decision shall be final and
binding on the parties”. The Chief Conservator was a senior officer
of the Government, which was a party to the contract. The
Supreme Court held that the expression “shall be referred to”
meant that the dispute was to be referred to that officer “as an
arbitrator to decide the dispute”, and that the clause conferred
authority upon him "to adjudicate upon disputes". To the same
effect is Rukmanibai Gupta (supra), where the dispute was to be
“decided by the lessor whose decision shall be final”, the lessor
being the State and a party to the lease, and the clause was held to
spell out an arbitration agreement. Clause 8 stands on the same
5
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

footing: the dispute is to be “referred to” the said authority, whose
decision is to be “final and binding on both the parties”.
7. The description of the said authority as an “appellate
authority”, and the liberty of the parties to “prefer an appeal”, do
not take Clause 8 out of arbitration. In Ratan Singh (supra), the
decision of the officer was, under Rule 15(1) of the governing
rules, “final and binding on the parties, except to the extent that it
shall be subject to an appeal to the Conservator of Forests”, and
was nonetheless treated as the decision of an arbitrator. A decision
that is final and binding, and yet subject to an appeal, does not
cease to be arbitral. The Supreme Court has since held, in
Centrotrade Minerals & Metals Inc. v. Hindustan Copper Ltd. ,
(2017) 2 SCC 228, that the expression “final and binding” does not
preclude an appeal, and that parties are free to provide for an
appellate or two-tier arbitral procedure.
8. The settled elements of an arbitration agreement are (i) a
reference of disputes by either party to a forum other than a court
for its decision; (ii) an enquiry by that forum with opportunity to
both sides; and (iii) a decision that is final and binding on the
parties, without recourse to any other remedy. In support, Mr.
Harit relied on the judgments in P. Dasaratharama Reddy Complex
v. Government of Karnataka , (2014) 2 SCC 201; K.K. Modi v. K.N.
Modi , (1998) 3 SCC 573; and Bihar State Mineral Development
Corpn. v. Encon Builders (I) (P) Ltd ., (2003) 7 SCC 418. Clause 8
answers each of these. The dispute is referred to the said authority,
a forum outside the court. The authority sits over an appeal
preferred against the decision of SMC, which imports a hearing of
6
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

both parties. And the decision is “final and binding on both the
parties", the contractor being barred from initiating "any dispute in
any court of law”.
9. The decisions in which a similar-sounding clause was held
not to be an arbitration agreement are of a different class and are
distinguishable. In State of U.P. v. Tipper Chand , (1980) 2 SCC
341, State of Orissa v. Damodar Das , (1996) 2 SCC 216, and
Bharat Bhushan Bansal v. U.P. Small Industries Corpn. Ltd ., (1999)
2 SCC 166, the clause made the decision of the Engineer final
upon questions of specifications, drawings, quality, and the like.
Those clauses conferred supervision and administrative control
upon the officer, contained no reference of disputes, and were held
to be administrative and not judicial in character. In Tipper Chand
(supra), the Supreme Court recognized that a clause providing
that “in matter of dispute the case shall be referred to the
Superintending Engineer... whose order shall be final” would be an
arbitration agreement. In P. Dasaratharama Reddy (supra), the
clause failed for the further reason that the decision was made
subject to the contractor's right to “approach the law courts”, and
was therefore not final. Clause 8 falls on the other side of the line
drawn in these very decisions, for it refers disputes, its decision is
final and binding, and it excludes recourse to the court.
10. The said authority is the controlling authority of the
Respondent No.1, and is arrayed as a Respondent, goes to his
eligibility to act, and not to whether Clause 8 is an arbitration
agreement. Such ineligibility is met by the appointment of an
independent Arbitrator by this Court, the agreement to arbitrate
7
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

being severable from the mechanism of appointment. In support,
Mr. Harit relied on the judgments in Haryana Space Application
Centre (HARSAC) v. Pan India Consultants (P) Ltd. , (2021) 3 SCC
103; TRF Ltd. v. Energo Engineering Projects Ltd ., (2017) 8 SCC
377; and Perkins Eastman Architects DPC v. HSCC (India) Ltd. ,
(2020) 20 SCC 760. The existence of the arbitration agreement is
not touched by this.
11. He submits that in any event, at the stage of a reference
under Section 11 the enquiry is confined to the prima facie
existence of an arbitration agreement, and where the matter
admits of two views the reference is to be made, the final
determination being left to the Arbitral Tribunal. He relied on the
judgment in Vidya Drolia v. Durga Trading Corpn. , (2021) 2 SCC 1,
and In re Interplay between Arbitration Agreements under the
Arbitration and Conciliation Act, 1996 and the Stamp Act, 1899 ,
(2024) 6 SCC 1.
12. He submits that for the reasons set out above, Clause 8
constitutes an arbitration agreement within the meaning of Section
7 of the Act. It is respectfully prayed that this Hon'ble Court be
pleased to hold accordingly, and to appoint an independent and
impartial sole Arbitrator to decide the disputes between the
parties.
13. He further submitted that South Delhi Municipal Corporation
of Delhi v. SMS Limited , (2026) 1 SCC 545, does not govern
Clause 8 of the Contract dated 26 August 2014 and is
distinguishable. There, the Court held Article 20 of the concession
8
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

agreements not to be an arbitration agreement, for reasons that
are absent here. The operative words of Clause 8 are these:
“...the same shall be referred to the Principal Secretary, UD-
2, Urban Development Department, Government of
Maharashtra and the decision given by the said authority
shall be final and binding on both the parties the said
authority shall be acting as appellate authority and both the
parties shall be at liberty to prefer an appeal Decision taken
by the said authority on any appeal shall be final and binding
on both the parties. The contractor shall not be entitled to
initiate any dispute in any court of law.”
14. Article 20 was a mediation clause, not an adjudication. Its
operative section was titled “Mediation by Commissioner”, and it
provided only for an officer of the Corporation to look into the
written documents, which the Court held to be, at best, “an
elaborate administrative fact-finding exercise, rather than an
arbitral adjudication”. Clause 8 is not of that character. It refers the
dispute to the said authority for a decision that shall be final and
binding on both the parties, the said authority sitting in appeal
against the decision of SMC. It provides for a binding adjudication,
which is the very judicial element the Court found wanting in
Article 20 in the South Delhi.
15. Article 20 preserved recourse to the civil court; Clause 8
excludes it. The Court in South Delhi relied on the circumstance
that the contractors could always approach the civil Court, Article
20 containing no exclusion of the court, whereas the Court's own
test requires an intention to refer disputes to arbitration excluding
the jurisdiction of the civil courts. Clause 8 excludes the court in
9
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

terms, providing that the contractor shall not be entitled to initiate
any dispute in any court of law. The very ingredient that Article 20
lacked, Clause 8 supplies.
16. The observation on finality does not assist against Clause 8.
The Court accepted that the words "final and binding", which
appear in the agreements, prima facie satisfy the requirement of
finality, and that Article 20 failed on other grounds. The remark
that "finality alone does not equate it to arbitration" is therefore of
no application to Clause 8, which does not rest on finality alone,
but couples finality with a reference of disputes, an adjudication
on appeal, and an ouster of the court.
17. The designation of the said authority goes to eligibility, not
to existence. The observations on neutrality in South Delhi were
made of a clause that was, in substance, a mediation controlled by
a party, providing for no adjudication at all, so that the want of
neutrality there confirmed a process of internal resolution and not
arbitration. Where, by contrast, a clause does refer disputes for a
binding decision, the circumstance that it names an officer
connected with a party goes to the eligibility of that officer, which
this Court cures by appointing an independent Arbitrator, and not
to the existence of the arbitration agreement: Chief Conservator of
Forests, Rewa v. Ratan Singh Hans , AIR 1967 SC 166, where a
reference to the Chief Conservator of Forests, an officer of the
Government which was a party, was held to be a reference to him
as an arbitrator; and TRF Ltd. v. Energo Engineering Projects Ltd. ,
(2017) 8 SCC 377; Perkins Eastman Architects DPC v. HSCC
(India) Ltd. , (2020) 20 SCC 760; and HARSAC v. Pan India
10
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

Consultants (P) Ltd. , (2021) 3 SCC 103. It is further relevant that
South Delhi was decided by a Bench of two learned Judges and did
not have occasion to consider Ratan Singh Hans, a decision of
three learned Judges directly in point; on this question the
decision of the larger Bench governs.
18. In sum, South Delhi turned on a mediation clause that
preserved recourse to the civil court and provided no adjudication.
Clause 8 refers the disputes for a decision that is final and binding,
provides for an adjudication on appeal, and ousts the civil court. It
answers each ingredient of the test in South Delhi, and the
designation of the named authority is met by the appointment of
an arbitration agreement.
19. On the other hand, Mr. Joshi, learned Advocate appearing
for the Municipal Council, submitted that Clause 8 cannot be
considered as a valid arbitration agreement. He further submitted
that, in any case, Sinnar would be the seat and venue of
arbitration, since the Agreement was executed and signed at
Sinnar.
R EASONS AND FINDINGS:
20. I have considered the submissions made by Mr. Harit,
learned Advocate for the Applicant and Mr. Joshi, learned
Advocate for the Respondent Municipal Council. The first question
which arises is whether Clause 8 can be considered as a valid
arbitration agreement under Section 7 of the Arbitration and
Conciliation Act, 1996. Along with this, the question about naming
of the Principal Secretary, UD-2, Urban Development Department,
11
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

Government of Maharashtra, and the question whether Mumbai
can be taken as the seat or venue, are required to be considered.
21. Mr. Harit submitted that though the word “arbitration” is not
used in Clause 8, the intention of the parties is clear from the way
the clause is written. According to him, when there is a dispute,
the same is required to be referred to the named authority and the
decision is made final and binding on both parties. There is
provision for appeal and the decision in appeal is again made final
and binding. Therefore, if the clause is read as one complete
provision, it amounts in substance to an arbitration clause. Mr.
Joshi submitted that Clause 8 cannot be treated as an arbitration
clause. According to him, the Principal Secretary is described as an
“appellate authority” and the provision is more an administrative
arrangement. Merely because the decision is stated to be final and
binding, it cannot become an arbitration agreement.
22. While considering this issue, the substance of the clause and
the intention of the parties seen from the agreement are required
to be considered. Merely because some technical word is not used,
the clause cannot be rejected if from the agreement it can
otherwise be understood that the parties intended arbitration. The
Supreme Court in Babanrao Rajaram Pund v. Samarth Builders &
Developers , (2022) 9 SCC 691, after considering K.K. Modi v. K.N.
Modi , has explained the features which are required to be seen for
deciding whether there is an arbitration agreement.
23. The relevant part of K.K. Modi , as quoted by the Supreme
Court, reads:
12
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

“ 17 . Among the attributes which must be present for an
agreement to be considered as an arbitration agreement are:
( 1 ) The arbitration agreement must contemplate that the
decision of the tribunal will be binding on the parties to the
agreement,
( 2 ) that the jurisdiction of the tribunal to decide the rights
of parties must derive either from the consent of the parties
or from an order of the court or from a statute, the terms of
which make it clear that the process is to be an arbitration,
( 3 ) the agreement must contemplate that substantive
rights of parties will be determined by the agreed tribunal,
( 4 ) that the tribunal will determine the rights of the parties
in an impartial and judicial manner with the tribunal owing
an equal obligation of fairness towards both sides,
( 5 ) that the agreement of the parties to refer their disputes
to the decision of the tribunal must be intended to be
enforceable in law and lastly,
( 6 ) the agreement must contemplate that the tribunal will
make a decision upon a dispute which is already formulated
at the time when a reference is made to the tribunal.
18 . The other factors which are relevant include, whether
the agreement contemplates that the tribunal will receive
evidence from both sides and hear their contentions or at
least give the parties an opportunity to put them forward;
whether the wording of the agreement is consistent or
inconsistent with the view that the process was intended to
be an arbitration, and whether the agreement requires the
tribunal to decide the dispute according to law.”
(emphasis supplied)
24. From the above principles, it is clear that the Court has to
see whether the parties intended that a dispute between them
13
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

should be decided by a private forum and whether the decision of
such forum was intended to bind them. It is not necessary that
particular technical words must be used in every case. What is
important is the intention which can be gathered from the
agreement as a whole.
25. The same position is seen from Encon Builders , as noticed in
Babanrao Rajaram Pund :
“ 13. The essential elements of an arbitration agreement are
as follows:
(1) There must be a present or a future difference in
connection with some contemplated affair.
(2) There must be the intention of the parties to settle such
difference by a private tribunal.
(3) The parties must agree in writing to be bound by the
decision of such tribunal.
(4) The parties must be ad idem. ”
(emphasis supplied)
26. If Clause 8 is considered with these principles, it is seen that
the clause operates when there is a dispute between the parties. It
is not merely giving administrative power to the Principal
Secretary for supervision of work or for taking some decision
during execution of the contract. It provides a manner in which a
dispute between the contracting parties is to be decided. The
clause says that the dispute “shall be referred to” the Principal
Secretary, UD-2, Urban Development Department, Government of
Maharashtra, Mumbai. These words have some importance. They
show that once a dispute arises, the matter is required to go to the
14
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

named authority. It is not an option left to either party to approach
the authority. The expression “shall be referred to” finds support
from the decision in Chief Conservator of Forests and Ors. v.
Rattan Singh. In that case, while considering a provision requiring
reference of disputes to a named officer, the Supreme Court
observed:
“It is conceded, and in our judgment counsel is right in so
conceding, that the expression "shall be referred to" means
"shall be referred to the Officer denominated" as an
arbitrator to decide the dispute.”
27. The present Clause 8 contains the words “shall be referred
to”. Therefore, the nature of the reference cannot be ignored
merely because the word “arbitrator” is not used. The dispute is
required to be referred to the named authority for decision. Clause
8 further provides that the decision of the authority shall be “final
and binding on both the parties”. It is true that these words alone
cannot make every clause an arbitration agreement. The Supreme
Court in South Delhi Municipal Corporation v. SMS Ltd. , (2026) 1
SCC 545, has stated:
“A key argument advanced by the private contractors is that
the decision rendered under Article 20 is “final and binding”,
thereby making it akin to an arbitral award. While it is true
that an arbitration clause must result in a conclusive
determination, finality alone does not equate it to
arbitration.”
28. Therefore, the use of “final and binding” by is not enough.
The complete clause is required to be considered. When the other
parts of Clause 8 are seen, it contains more than only finality. It
15
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

first requires that the dispute “shall be referred to” the named
authority. It then provides for decision by that authority. It further
provides an appeal. The decision in appeal is again made final and
binding on both parties. After this, the clause says that the
contractor shall not be entitled to initiate any dispute in any court
of law. Thus, the clause has a connected arrangement. There is
compulsory reference, then decision, then appeal, and thereafter
finality. There is an express restriction against taking the dispute to
a court. These features, when read together, make the clause
different from administrative provision.
29. Mr. Joshi relied upon South Delhi Municipal Corporation v.
SMS Ltd. and submitted that a final and binding decision cannot
by amount to arbitration. This general proposition is correct. But
the provision considered in that case was of a different nature.
Article 20 was titled “Mediation by Commissioner”. The process
was found to be essentially mediation and administrative fact-
finding. The Supreme Court described it as:
“an elaborate administrative fact-finding exercise, rather
than an arbitral adjudication”.
30. The present Clause 8 is not confined to mediation or
settlement. It deals with a dispute, requires compulsory reference
for decision, provides an appeal and makes the decisions final and
binding. It contains the restriction against the contractor initiating
any dispute in any court of law. In South Delhi Municipal
Corporation , the Court found that the necessary intention to create
an arbitral process was not there. In the present case, the intention
has to be seen from the complete Clause 8. The parties agreed that
16
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

when a dispute arises, the same “shall be referred” to the
designated authority and the decision will bind both parties. Thus,
even though the word “arbitration” is not used, the arrangement
made by the parties shows that the dispute is to be decided
through that mechanism.
31. Mr. Joshi submitted that the description of the Principal
Secretary as an “appellate authority” makes the clause non-
arbitral. I am unable to accept this submission in that manner. The
description of the officer cannot alone decide the legal character of
the clause. The actual function which the officer is required to
perform under the Agreement has to be seen. Here, the authority is
required to decide the dispute between the parties and the
decision is made binding. The provision for appeal forms part of
the same mechanism. Therefore, the use of the words “appellate
authority” does not remove the clause from the scope of
arbitration.
32. The decision in Rattan Singh is useful in this regard. There,
the Supreme Court considered a Government officer who was
required under the contract to decide disputes concerning
performance or breach. The Court considered the manner in which
the officer was required to act. Where the contract required the
dispute to be referred to the officer for adjudication, the reference
was capable of being treated as arbitration. However, where the
officer acted only in departmental or revisional jurisdiction, such
decision could not be treated as an arbitral award. Clause 8 is
directed towards disputes between the contracting parties.
Therefore, the function given to the authority under the clause is
17
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

more important than the description given to him as an “authority”
or “appellate authority”.
33. The next question is about the Principal Secretary being
connected with the Government. Mr. Harit submitted that even if
the named authority cannot act as arbitrator under Section 12(5)
read with the Seventh Schedule, this would not destroy the
arbitration agreement. The decision in Haryana Space Application
Centre v. Pan India Consultants (P) Ltd. , (2021) 3 SCC 103, is
relevant. In that case, the arbitration clause contemplated
appointment of a Government officer. The Supreme Court held:
“We are of the view that the appointment of the Principal
Secretary, Government of Haryana as the nominee arbitrator
of Harsac which is a nodal agency of the Government of
Haryana, would be invalid under Section 12(5) of the
Arbitration and Conciliation Act, 1996 read with the Seventh
Schedule.”
34. The named person was therefore found ineligible. However,
the arbitration agreement was not treated as having disappeared.
35. The further course adopted by the Supreme Court in that
case is important. The Court recorded:
“The counsel for both the parties during the course of
hearing have consented to the substitution of the existing
Tribunal, by the appointment of a sole arbitrator to complete
the arbitral proceedings.”
36. Thus, the difficulty concerning the person who was to act as
arbitrator was considered separately. The arbitration mechanism
was not rejected. The same position can apply here. If the Principal
Secretary named in Clause 8 is found ineligible under Section
18
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

12(5) read with the Seventh Schedule, he cannot act as arbitrator.
But that is a question concerning the person who is to perform the
arbitral function. It is not the same as deciding whether the parties
had agreed to arbitration. Therefore, the Respondent cannot
succeed only on the ground that the named officer may not be
legally eligible. An eligible and independent arbitrator can be
appointed in accordance with law. The possible defect in the
person named cannot by remove the agreement to arbitrate.
37. Thus, the submission of Mr. Harit that the appointment
mechanism and the existence of the arbitration agreement are
separate matters has force. The principles in TRF Ltd. v. Energo
Engineering Projects Ltd. , Perkins Eastman Architects DPC v. HSCC
(India) Ltd. and Haryana Space Application Centre support the
position that a person who is disqualified cannot act as arbitrator
merely because the agreement had named him. But this does not
mean that the underlying agreement to arbitrate comes to an end.
38. Mr. Harit submitted that the absence of the word
“arbitration” cannot be made the ground to reject Clause 8. I find
substance in this submission. The Court cannot create an
arbitration agreement where there was no intention to arbitrate.
But equally, a clause cannot be rejected only because it is not
drafted in technical arbitration language, if its substance shows the
necessary intention. The Supreme Court in Babanrao Rajaram
Pund has observed:
“The deficiency of words in agreement which otherwise
fortifies the intention of the parties to arbitrate their
disputes, cannot legitimise the annulment of arbitration
19
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

clause.”
39. The Supreme Court has observed:
“the courts have to adopt a pragmatic approach and not a
pedantic or technical approach while interpreting or
construing an arbitration agreement or arbitration clause.”
40. Therefore, Clause 8 has to be understood from its substance
and as part of the Agreement between the parties. At the same
time, the caution in South Delhi Municipal Corporation cannot be
left out. Every provision under which an officer's decision is made
final and binding cannot become an arbitration clause. Some
indication of an adjudicatory intention must be present. In the
present case, such features are present. There is a dispute between
the parties. There is compulsory reference. There is a decision by
the authority. There is an appeal. The decision is final and binding.
There is an express restriction on initiating a dispute in any court
of law. When these provisions are read together, they show that
the parties intended their disputes to be decided through the
mechanism created in Clause 8 and intended to remain bound by
the result. Therefore, the clause contains the necessary substance
of an arbitration agreement. The Government status of the
authority may raise a question about his eligibility to act. But that
question is separate and does not alter the intention found in the
Agreement.
41. The decisions relied upon by the Respondent, including State
of U.P. v. Tipper Chand , State of Orissa v. Damodar Das and Bharat
Bhushan Bansal v. U.P. Small Industries Corporation Ltd. , do not
lead to a different conclusion. Those cases concerned decisions by
20
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

engineers or officers on matters such as specifications, quality, and
other matters connected with execution of the work. Such
technical decisions are different from a clause which requires
disputes between the parties to be referred for decision. Clause 8
in the present case is directed to disputes between the contracting
parties. It therefore cannot be treated merely as a provision for
administrative supervision.
42. The reliance upon P. Dasaratharama Reddy Complex v.
Government of Karnataka does not assist the Respondent. In that
case, the parties retained a right to “approach the law courts”.
Here, Clause 8 provides that the contractor shall not be entitled to
initiate any dispute in any court of law. This difference is material
and supports the submission that the parties intended the agreed
mechanism to decide their disputes. The provision for appeal
cannot by destroy the arbitration arrangement. Parties may agree
to another stage of decision-making. What is important is the
nature of the complete mechanism. In Clause 8, the original
decision and the appellate decision are both included in the agreed
dispute resolution process and both are made binding.
43. I now come to the question of seat and venue. Mr. Harit
submitted that Mumbai is the seat and venue because Clause 8
requires the dispute to be referred to the Principal Secretary, UD-2,
Urban Development Department, Government of Maharashtra,
Mumbai. Mr. Joshi submitted that Sinnar should be treated as the
seat and venue because the Agreement was executed and signed at
Sinnar. 37. On this question, I find substance in the submission of
Mr. Harit. It is true that Clause 8 does not state that “Mumbai shall
21
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

be the seat of arbitration”. However, the intention has to be
gathered from the clause as a whole. The parties have selected a
particular authority for deciding the dispute and have described
that authority as the Principal Secretary, UD-2, Urban
Development Department, Government of Maharashtra, Mumbai.
Thus, the reference to Mumbai is not appearing somewhere
separately in the Agreement. It is part of the very clause under
which the disputes are required to be decided. The authority
selected by the parties for deciding the dispute is connected with
Mumbai. It is no doubt true that seat and venue are not always
one and the same. A place may be used for holding hearings
without becoming the juridical seat. But in the present case, the
place mentioned in Clause 8 is connected with the authority
selected by the parties for deciding their disputes.
44. The Supreme Court in BGS SGS SOMA JV v. NHPC Ltd. ,
(2020) 4 SCC 234, has explained the importance of the place
selected by the parties for the arbitral process. Where a place is
selected as the seat, the courts at that place exercise supervisory
jurisdiction over the arbitration. In the present case, Clause 8 does
not say merely that the authority may hold a meeting at Mumbai.
It says that the dispute shall be referred to the Principal Secretary,
UD-2, Urban Development Department, Government of
Maharashtra, Mumbai. The decision is to be final and binding on
both parties and the appellate decision is made final and binding.
Therefore, Mumbai is directly connected with the authority which
has been entrusted with deciding the dispute. It is not a convenient
place for conducting some hearing. The dispute resolution
22
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

arrangement made by the parties is connected with Mumbai. On
the other hand, there is no provision in the Agreement which says
that Sinnar shall be the seat of arbitration. The Agreement being
signed at Sinnar cannot, by, make Sinnar the juridical seat. The
place of execution of a contract and the place selected as the seat
of arbitration are different matters. The contract may be signed at
one place and arbitration may have its seat at another place.
Therefore, the mere fact that the Agreement was executed at
Sinnar is not sufficient to hold that Sinnar is the seat. The place
where the contractual work was to be performed does not by
determine the seat. The work may be at Sinnar, but the arbitration
may have its juridical seat elsewhere. The place of performance
and the seat of arbitration need not be the same.
45. Here, while making the dispute resolution clause, the parties
referred the dispute to the Principal Secretary at Mumbai. That
part of the contractual wording has to be given due consideration.
The distinction between seat and venue does not prevent Mumbai
from being treated as the seat. Even if some hearings or other
proceedings are held at Sinnar or at another place for convenience,
that circumstance by will not change the seat. The seat has to be
understood from the contractual arrangement and the intention of
the parties.
46. The submission of the Respondent that Sinnar must be
treated as the seat because the Agreement was executed there
therefore cannot be accepted. Clause 8 contains no selection of
Sinnar as the seat. On the other hand, Mumbai is mentioned
together with the authority to whom the disputes are to be
23
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

referred. The indication in the Agreement in favour of Mumbai is
therefore more direct than the mere fact of execution of the
Agreement at Sinnar. I cannot completely ignore the word
“Mumbai” appearing with the description of the Principal
Secretary. The parties have referred to the Principal Secretary, UD-
2, Urban Development Department, Government of Maharashtra,
Mumbai, as the authority to whom the dispute is required to be
referred. The authority and the place are therefore mentioned
together in the dispute resolution clause. This wording must have
some meaning. It cannot be treated as if Mumbai was mentioned
without any connection to the agreed dispute resolution
mechanism. When Clause 8 is read as one provision, it indicates
that the dispute between the parties is to be referred to the
Principal Secretary of the Urban Development Department at
Mumbai for decision. The decision is made final and binding. The
appellate mechanism forms part of the same arrangement.
Therefore, the dispute resolution mechanism agreed by the parties
is connected with Mumbai. In these circumstances, I find that
Mumbai is not merely a place for holding a meeting. It is the place
with which the agreed adjudicatory mechanism is connected. I
therefore hold that Mumbai is the juridical seat of arbitration
under Clause 8 of the Agreement dated 26.08.2014. The fact that
the Agreement was signed at Sinnar does not change this
conclusion. Similarly, the fact that the work was to be performed at
Sinnar does not amount to selection of Sinnar as the arbitral seat.
Once Mumbai is held to be the seat, the legal consequences
attached to the seat will follow. The courts at Mumbai will have
24
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

supervisory jurisdiction over the arbitral proceedings. The parties,
from the wording of Clause 8, have selected Mumbai as the place
with which the agreed dispute resolution mechanism is connected.
This finding does not mean that each hearing must take place
physically at Mumbai. Seat and venue have to be understood
separately. The arbitral tribunal may, subject to the Act and the
circumstances of the proceedings, hold hearings or other
proceedings at another place. Such arrangement for convenience
will not change Mumbai as the seat.
47. I, therefore, hold that Clause 8 contains an arbitration
agreement and that Mumbai is the seat of arbitration. The
reference to the Principal Secretary, UD-2, Urban Development
Department, Government of Maharashtra, Mumbai, when read
with the compulsory reference of disputes, the final and binding
nature of the decision, the appellate mechanism and the restriction
against approaching a court, shows the intention of the parties to
create a binding adjudicatory mechanism connected with Mumbai.
The objection of the Respondent that Sinnar should be treated as
the seat because the Agreement was signed there is therefore
rejected. The place of execution cannot by override the indication
contained in the dispute resolution clause. The fact that the
underlying work relates to Sinnar does not change the seat.The
question regarding eligibility of the Principal Secretary under
Section 12(5) read with the Seventh Schedule is separate from the
question of seat. If the named officer is ineligible to act as
arbitrator, he cannot act as such. An independent and impartial
arbitrator can be appointed in accordance with law. Such
25
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

substitution will not change the seat of arbitration, which remains
Mumbai.
48. In view of the aforesaid, the present Application filed under
Section 11 of the Act, is disposed of by passing the following
order:
A) Justice Avinash Gharote former judge of this Court,
is hereby appointed as the Sole Arbitrator to adjudicate
upon the disputes and differences between the parties
arising out of and in connection with the Agreement
referred to above;
Office Address:- Plot No.49, Ground Floor, Shreenarayan
Complex, Besides Punjab National Bank, Bajaj Nagar,
Nagpur 440010
Email ID: [email protected]
B) A copy of this Order will be communicated to the
Learned Sole Arbitrator by the Advocates for the
Applicant within a period of one week from today. The
Applicant shall provide the contact and communication
particulars of the parties to the Arbitral Tribunal along
with a copy of this Order;
C) The Learned Sole Arbitrator is requested to forward
the statutory Statement of Disclosure under Section
11(8) read with Section 12(1) of the Act to the
Advocates for the Applicant so as to enable them to file
the same in the Registry of this Court. The Registry of
26
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

this Court shall retain the said Statement on the file of
this Applicant and a copy of the same shall be furnished
by the Advocates for the Applicant to the Advocates for
the Respondent;
D) The Learned Sole Arbitrator is requested to forward
the statutory Statement of Disclosure under Section 11(8)
read with Section 12(1) of the Act to the parties within a
period of two weeks from receipt of a copy of this Order;
E) The parties shall appear before the Learned Sole
Arbitrator on such date and at such place as indicated, to
obtain appropriate directions with regard to conduct of
the arbitration including fixing a schedule for pleadings,
examination of witnesses, if any, schedule of hearings etc.
At such meeting, the parties shall provide a valid and
functional email address along with mobile and landline
numbers of the respective Advocates of the parties to the
Arbitral Tribunal. Communications to such email
addresses shall constitute valid service of correspondence
in connection with the arbitration;
49. All arbitral costs and fees of the Arbitral Tribunal shall be
borne by the parties equally in the first instance, and shall be
subject to any final Award that may be passed by the Tribunal in
relation to costs.
50. All contentions of the parties on the merits of their respective
claims and disputes are kept open for consideration by the learned
Arbitral Tribunal in accordance with law.
27
Uploaded on - 07/09/2026 Downloaded on - 07/10/2026 17:16:05

carapl15854-2026-J.doc

51. All actions required to be taken pursuant to this order shall
be taken upon receipt of a downloaded copy as available on this
Court’s website.
(AMIT BORKAR, J.)