The Branch Manager, National Insurance Company Limited, Gangtok Division vs Yoel Subba
- Court
- High Court of Sikkim
THE HIGH COURT OF SIKKIM: GANGTOK
(Civil Revisional Jurisdiction)
--------------------------------------------------------------------------------
SINGLE BENCH: THE HON’BLE MR. JUSTICE BHASKAR RAJ PRADHAN, JUDGE
--------------------------------------------------------------------------------
I.A. No.01 of 2026
IN
CRP No. 05 of 2026
The Branch Manager,
National Insurance Company Limited,
Gangtok Division,
Registered Office at NH-10,
Near Police-Headquarter, Gangtok,
Gangtok District, Sikkim, 707101.
….. Applicant
Versus
Shri Yoel SUbba,
Son of Shri Anil Subba,
Resident of Upper Sadam,
P.S. Melli,
Namchi District, Sikkim, 737128.
….. Respondent
Application under Section 5 of the Limitation Act, 1963 of
condonation of delay in filing the instant Revision.
---------------------------------------------------------------------------
Appearance:
Mr. Madan Kumar Sundas, Ms. Anita Limboo and Ms. Priyanka
Subba, Advocates for the Applicant.
Mr. Tarun Choudhary Advocate for the Respondent (through
V.C.).
---------------------------------------------------------------------------
Date of Hearing : 08.10.2026
Date of Order : 08.10.2026
Date on which uploaded : 08.10.2026
2
I.A. No.01 of 2026 IN C.R.P. No.05 of 2026
The Branch Manager, National Insurance Company Limited vs. Yoel Subba
O R D E R (O R A L)
Bhaskar Raj Pradhan, J.
1. An application for condonation of delay of 223 days in
preferring the present revision petition is placed for consideration
before this court.
2. Heard Mr. Madan Kumar Sundas, learned counsel for the
applicant as well as Mr. Tarun Choudhary, learned counsel for the
respondent.
3. The application for condonation of delay was filed on
10.04.2026. A reply thereto was filed on 20.07.2026 by the
respondent. On 27.08.2026 and 23.09.2026 the applicant filed
further affidavits.
4. In the application for condonation of delay of 223 days the
first part of the application the delay is attributed to the earlier
counsel before the learned Trial Court. In the second part of the
application the delay is explained in this fashion. It is stated that on
14.10.2025 the learned counsel presently arguing this case was
approached by the applicant after the impugned order was passed
on 30.08.2025 and as per the submissions of the learned counsel
176 days were taken to prefer the present revision petition.
According to the application on being approached the learned
counsel for the applicant received certified copies of the learned
Trial Court record and impugned order only on the first week of
December, 2025 from the applicant. He thereafter, went through
the entire records and found that it was a tax matter which needed
3
I.A. No.01 of 2026 IN C.R.P. No.05 of 2026
The Branch Manager, National Insurance Company Limited vs. Yoel Subba
detailed examination and therefore, he could file the revision
petition only on 10.04.2026.
5. Further, it is also submitted that the officers of the applicant
were on deputation for Special Intensive Revision (SIR) duty by the
Government of West Bengal and therefore they were unable to
verify and approve the draft revision on time which took them 50 to
60 days to verify and sign it.
6. Insofar as the reasons for delay attributed in the first part of
the application blaming the earlier counsel the affidavit filed on
23.09.2026 states this:
“2. That this Hon’ble Court, vide orders
dated 13.08.2026 and 02.09.2026, was
pleased to direct the Revisionist to explain
the averment made in paragraph 2(c) of the
application for condonation of delay
regarding the alleged ill-health of the
learned Trial Court Counsel, Shri. Sailesh
Rai.
3. That the said averment regarding the ill-
health of Shri Sailesh Rai was inadvertently
and incorrectly incorporated due to a
communication gap/miscommunication and
was not based on any statement made by
the learned counsel that he was ill.
4. That upon verification, Shri Sailesh Rai,
by his email, clarified that he was not ill and
that the reference to his ill-health in the
application was not communicated by him.
5. That the Revisionist Company, upon
realizing the mistake, has sincerely and
unconditionally apologized to Shri Sailesh
Rai, through email dated 03.09.2026 and he
has acknowledged the said apology through
email dated 04.09.2026. A computer
printout of the aforesaid email is annexed
hereto and marked as Annexure-1(colly).
6. That the Revisionist Company hereby
withdraws the said averment regarding the
4
I.A. No.01 of 2026 IN C.R.P. No.05 of 2026
The Branch Manager, National Insurance Company Limited vs. Yoel Subba
ill-health of Shri Sailesh Rai and respectfully
tenders its unconditional apology before this
Hon’ble court for the said inadvertent error.
The Revisionist has no intention whatsoever
to mislead this Hon’ble Court.
7. That the Revisionist further assures
this Hon’ble Court that due care and caution
shall be exercised in future to avoid any
such communication error. ”
7. The affidavit is self explanatory, the entire allegation against
the previous counsel stands withdrawn. Consequently, the only
explanation available before this Court seeking condonation of delay
of 223 days is the explanation relating to the present counsel. The
explanation reflects lethargy and failure on the part of the applicant
which is wanting. The explanation that the officers were involved in
the SIR process of West Bengal as deputed lacks in material
particulars or records to support this. It could be true. It may not be
true as well. The affidavit dated 23.09.2026 reflects that the
application filed earlier for condonation of delay was made on false
pleas which was thereafter, withdrawn. The question before this
Court is therefore should the delay be condoned? Although this
Court is of the opinion that it is always better to decide the case on
merits than to defeat its purpose by not condoning the delay, the
facts in the present case is wanting.
8. In matters pertaining to condonation of delay a justice
oriented approach is required to be taken avoiding a pedantic
approach.
9. A proper appreciation of the pleadings in the application for
condonation of delay makes me believe that it was more on error of
judgment of the draftsman to draft the application in the manner.
5
I.A. No.01 of 2026 IN C.R.P. No.05 of 2026
The Branch Manager, National Insurance Company Limited vs. Yoel Subba
Blaming a counsel who was previously engaged without a proper
verification on the part of the applicant is a serious matter. This was
incorrect and not appreciated. It should be avoided. It is also clear
that the litigants should be conscious about their rights and
approach the Courts in time.
10. On the overall picture as it emerges after perusing the
application for condonation of delay as well as the other two
affidavits and the reply by the respondent I am inclined to condone
the delay for a justice oriented approach giving an opportunity to
the applicant to argue the case on merits. However I am of the
considered view that the applicant must pay a cost of Rs.50,000/-
within a period of two weeks hence. The amount shall be deposited
with the Sikkim State Legal Services Authority which shall be
utilised for the purpose of rehabilitation of the POCSO victims of
sexual assault. A compliance affidavit shall follow. Accordingly, the
I.A. No.01 of 2026 is allowed and the delay is condoned.
( Bhaskar Raj Pradhan )
Judge
to