ASSAM POWER DISTRIBUTION COMPANY LTD. vs ONGC TRIPURA POWER COMPANY LIMITED & Ors

Court
Appellate Tribunal For Electricity
Case type
APPEAL
Decided on
06-04-2026
<div> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <b> IN THE APPELLATE TRIBUNAL FOR ELECTRICITY </b><br /> <b>(Appellate Jurisdiction) </b><br /> <b>APPEAL No. 334 OF 2017 </b><br /> <b>th</b><br /> <b>Dated: </b> <b>06</b> <b> APRIL, 2026 </b><br /> <b>Present: Hon`ble Ms. Seema Gupta, Technical Member (Electricity)</b><br /> <b>Hon`ble Mr. Virender Bhat, Judicial Member</b><br /> <b>In the matter of: </b><br /> 1. ASSAM POWER DISTRIBUTION COMPANY LTD.<br /> “Bijulee Bhawan”, Paltanbazaar, <br /> Guwahati – 781001, Assam … Appellant(s) <br /> <b><i>VERSUS</i></b><br /> 1. ONGC TRIPURA POWER COMPANY LIMITED<br /> <i>Through Managing Director, </i><br /> th<br /> 6 Floor, A Wing, IFCI Towers, <br /> New Delhi – 110019. <br /> 2. CENTRAL ELECTRICITY REGULATORY COMMISSION, <br /> <i>Through Secretary </i><br /> rd th<br /> 3 &amp; 4 Floor, Chanderlok Building, <br /> 36, Janpath, New Delhi – 110001. <br /> 3. DEPARTMENT OF POWER <br /> <i>Through Secretary Power, </i><br /> Govt. of Arunachal Pradesh <br /> Vidyut Bhawan, Itanagar – 791111. <br /> 4. DEPARTMENT OF POWER, <br /> <i>Through Chief Engineer, </i><br /> Government of Nagaland <br /> Kohima – 797001. <br /> 5. MANIPUR STATE POWER DISTRIBUTION COMPANY LTD., <br /> <i>Through Its Managing Director, </i><br /> Page <b>1</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> Government of Manipur, <br /> Keishampat, Imphal - 795001. <br /> 6. POWER AND ELECTRICITY DEPARTMENT, <br /> <i>Through Engineer-in- Chief, </i><br /> Government of Mizoram, <br /> Aizawal, Mizoram – 796001. <br /> 7. MEGHALAYA ENERGY CORPORATION LIMITED, <br /> <i>Through Chairman, </i><br /> Short Round road, “LUMJINGSHAI” <br /> Shillong – 793001, Meghalya. <br /> 8. TRIPURA STATE ELECTRICITY CORPORATION LIMITED, <br /> <i>Through DGM </i><br /> Vidyut Bhawan, North Banamalipur, <br /> Agartala, Tripura – 799001. …. Respondents <br /> Counsel on record for the Appellant(s) : Mr. Avijit Roy <br /> for App. 1 <br /> Counsel on record for the Respondent(s) : Mr. Parinay Deep Shah<br /> Ms. Shikha Ohri <br /> Mr. Kartik Sharma <br /> Ms. Ritika Singh <br /> for Res. 1 <br /> <b>JUDGEMENT </b><br /> <b>PER HON’BLE MRS. SEEMA GUPTA, OFFICIATING CHAIRPERSON </b><br /> 1. The present Appeal No. 334 of 2017 has been filed by Assam Power <br /> Distribution Company Limited under Section 111 of the Electricity Act, 2003 <br /> challenging the Corrigendum order dated 03.05.2017 <b>(Impugned Order)</b> read <br /> with order dated 30.03.2017 passed by the Central Electricity Regulatory <br /> Commission in Petition No. 129/GT/2015. <br /> Page <b>2</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <b><i>Description of Parties </i></b><br /> 2. The Appellant, Assam Power Distribution Company Ltd. is a public limited <br /> company fully owned by the Government of Assam undertaking registered under <br /> Companies Act, 1956, and came into existence after unbundling of Assam <br /> Electricity Board into different corporate Entities, to undertake distribution of <br /> Electricity in the State of Assam. <br /> 3. The Respondent No.1, i.e. ONGC Tripura Power Company Limited <br /> ( <i>hereinafter referred as</i> <b><i> “OTPC”</i></b> ) is a joint venture company primarily owned by <br /> ONGC (50%), GAIL (26%), and the Government of Tripura (0.5%). <br /> 4. The Respondent No.2 is the Central Electricity Regulatory Commission <br /> ( <i>hereinafter referred as</i> <b><i> “ Central commission/ </i></b> <b>CERC”)</b><br /> 5. Respondent Nos. 3 to 8 are the distribution licensees responsible for <br /> supplying electricity in the State of Arunachal Pradesh, Nagaland, Imphal, <br /> Mizoram, Meghalaya &amp; Tripura respectively.<br /> Brief facts of the case, relevant for disposal of the present Appeal are <br /> summarized hereunder : <br /> 6. On 18.09.2008, a Shareholders’ Agreement was executed amongst ONGC <br /> Tripura Power Company Limited (OTPC), Oil and Natural Gas Corporation <br /> (ONGC), Infrastructure Leasing &amp; Financial Services (IL&amp;FS), and the <br /> Government of Tripura for the purpose of setting up a generating station named <br /> “Palatana” with an installed capacity of 726.6 MW, comprising two Gas Turbine <br /> (GT) units of 232.39 MW each and two Steam Turbine (ST) units of 130.91 MW <br /> each. OTPC was incorporated as a joint venture of ONGC, IL&amp;FS (through its <br /> Page <b>3</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> affiliate IEDCL), and the Government of Tripura, with shareholding structured as <br /> follows: ONGC (50%), IEDCL (26%), Government of Tripura (0.5%), and residual <br /> equity (23.5%), for development of the project. Out of the total installed capacity, <br /> 628 MW was allocated to the beneficiary States of the North Eastern Region, and <br /> the balance 98 MW was earmarked for merchant sale. <br /> 7. In 2013, Petition No. 199/GT/2013 was filed by OTPC for determination of <br /> tariff of the Palatana generating station, in which on 31.08.2015, the Central <br /> Commission determined the tariff of Block-I of the generating station for the <br /> period from 04.01.2014 to 31.03.2014. <br /> 8. Subsequently, Block-II of the generating station was declared under <br /> commercial operation on 24.03.2015, whereupon OTPC filed Petition No. <br /> 129/GT/2015 seeking determination of tariff for Blocks I and II of the generating <br /> station for the control period 2014–19 in accordance with the provisions of the <br /> 2014 Tariff Regulations. Further, OTPC requested the Commission to relax <br /> operational norms under Regulation 54 of the 2014 Tariff Regulations considering <br /> the insufficient gas supply and approve NAPAF of 68% from the Commercial <br /> Operation Date (COD) of Unit II till the full gas is made available by the fuel <br /> supplier, i.e. ONGC. Central Commission, passed the Order on 30.03.2017 and <br /> relaxed the NAPAF, for recovery of fixed cost from 85 % ( as envisaged in 2014 <br /> Tariff Regulations ) to 76 %. <br /> 9. On 03.05.2017, Central commission passed the corrigendum order in <br /> connection with the order dated 30.03.2017, due to certain inadvertent error in <br /> the calculation. <br /> 10. Aggrieved by the determination of the Normative Annual Plant Availability <br /> Factor (NAPAF) by the CERC in the Impugned Order dated 30.03.2017 (read <br /> with Corrigendum dated 03.05.2017), Appellant has preferred this Appeal and <br /> Page <b>4</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> submitted that by virtue of such relaxation, OTPC was permitted to recover an <br /> additional sum of Rs. 282.43 Crore for the relevant period. <br /> <b>DISCUSSION AND ANALYSIS</b><br /> 11. Heard Mr Avijit Roy, learned counsel for the Appellant and Mr Parinay Deep <br /> Shah, learned counsel for the Respondent No 1, and perused the Impugned <br /> Order, the written submissions filed by the parties and other documents placed <br /> on record. The main contention raised by the Appellant pertains to relaxation in <br /> NAPF from 85% to 76% for the Palatana Project of OTPC in the Impugned Order <br /> on account of shortage in gas supply, while there is a fuel gas supply agreement <br /> with ONGC, which is also the majority stake holders in the subject project, and <br /> OTPC did not invoke the provisions under the Gas Fuel supply Agreement with <br /> ONGC. The Appellant has also alleged diversion of supply of gas to Monarchak <br /> project by ONGC which accentuated the shortage of gas supply to Palatana <br /> Project. <br /> 12. Per Contra, learned Counsel for the Respondent has made elaborate <br /> submissions contending that the shortage of gas for the Palatana project, is <br /> beyond the control of OTPC and it does not exercise control over the operations <br /> of ONGC for prioritisation of gas supply to Palatana project. The submissions of <br /> the parties, insofar as they are relevant for the disposal of the present Appeal, are <br /> summarised hereinafter: <br /> <b> SUBMISSIONS URGED ON BEHALF OF APPELLANT </b><br /> 13. It is submitted that Central Commission, ought not to have granted <br /> relaxation to OTPC in NAPAF from 85% to 76%, especially when ONGC, the <br /> main shareholder of Respondent No. 1 i.e. OTPC, owns the entire gas and <br /> petroleum fields in the South Zone of the North Eastern Region (NER) as well as <br /> major areas in the remaining parts of the NER, and it is the fuel gas supplier to <br /> Page <b>5</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> the generating station. Responsibility for procurement of basic raw materials i.e. <br /> gas in the present case, cannot, in law or in equity, be passed on by OTPC to <br /> the beneficiaries without first exhausting its legal remedies under the Gas Sale &amp; <br /> Purchase Agreement ( GSPA) dated 18.09.2008 executed with ONGC. A <br /> conjoint reading of Clause 8.1(a)(i), Clause 9.1(c), Clause 5.4(b), Clause 15 <br /> (Seller’s Liquidated Damages) read with Clause 17 (Force Majeure) of the GSPA <br /> clearly establishes that ONGC is obligated to ensure supply of gas to the power <br /> plant, and is restrained from unreasonably exercising its voting rights so as to <br /> impede enforcement of supply obligations, and is liable for any seller’s shortfall <br /> in supply in accordance with the agreed terms. In fact as per Clause 17.3 of the <br /> GSPA, any event of Force Majeure was required to be promptly notified by the <br /> fuel supplier, ONGC to Respondent No. 1, and in no case later than 48 hours <br /> from the occurrence of such event; however, no such notice, as contemplated <br /> was ever placed on record by Respondent No.1; instead, it merely relied upon <br /> certain communications issued by ONGC in response to its queries, which do not <br /> qualify as a valid Force Majeure notice in terms of the contractual stipulations. <br /> Consequently, the reduction in NAPAF on grounds allegedly beyond the scope <br /> of the GSPA has unjustly enriched OTPC and, indirectly, its fuel supplier, the <br /> 50% stakeholder, ONGC. It is further submitted that ONGC in its letter dated <br /> 12.07.2018 addressed to OTPC, stated that the decline in gas production was <br /> common in exploration and production operations and was industry-wide <br /> prevalent, which itself belies the claim of a Force Majeure event. <br /> 14. Though Respondent No.1 has contended that no claim for liquidated <br /> damages was raised on the ground that the reduction in supply was attributable <br /> to force majeure, the Central Electricity Regulatory Commission has overruled <br /> such contention in the absence of documentary evidence. Therefore, in the event <br /> of any shortfall in gas supply, it was incumbent upon Respondent No.1 to enforce <br /> its contractual rights and initiate appropriate recovery proceedings against <br /> Page <b>6</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> ONGC, however, no material has been placed on record either before the Central <br /> Commission or this Tribunal <br /> 15. It is submitted that with effect from 28.11.2015, ONGC reduced fuel supply <br /> to the Palatana Generation Project by 10,00,000 Standard Cubic Meter per Day <br /> (SCMD) in order to cater to the Monarchak Project of North Eastern Electric <br /> Power Corporation Limited (NEEPCO), resulting in a reduction of approximately <br /> 200 MW generation at the Palatana Project. Such diversion of gas not only <br /> curtailed availability of cheaper power to the North Eastern States but also <br /> adversely impacted supply in the region. The issue of reduced gas supply was <br /> raised at various levels, including through letters dated 18.12.2015 and February <br /> 2016 issued by Respondent No.1 and the Office of the North Eastern Council <br /> Secretariat, Shillong, Government of India; however, no effective response was <br /> forthcoming from ONGC, notwithstanding its 50% shareholding in Respondent <br /> No.1. <br /> 16. This Tribunal, in its judgment dated 30.04.2013 passed in Appeal No. 110 <br /> of 2012 in the matter of “ <b><i>NTPC Limited vs. Central Electricity Regulatory </i></b><br /> <b><i>Commission &amp; Ors”</i></b> ., has held that coal, being the primary raw material for <br /> generation of electricity, must be procured by the generating company at its own <br /> responsibility, and that such obligation cannot, under any circumstances, be <br /> shifted onto the beneficiaries. This Tribunal further held that non-availability of <br /> sufficient fuel, unless attributable to events strictly falling within the recognized <br /> parameters of Force Majeure—such as war, rebellion, civil commotion, lockouts, <br /> accidents, or acts of God etc, cannot be brought within the ambit of a Force <br /> Majeure event merely on the ground that the same was beyond the control of the <br /> generating company. So, for inability to arrange adequate fuel by NTPC, the <br /> beneficiaries cannot be held responsible for the same. <br /> Page <b>7</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <b>SUBMISSIONS URGED ON BEHALF OF RESPONDENT OTPC </b><br /> 17. It is submitted that subsequent to the commissioning of Unit II on <br /> 24.03.2015, the generating station was severely impacted by acute shortage of <br /> fuel gas, and consequently, OTPC invoked Regulation 54 of the 2014 <br /> Regulations and sought relaxation of the Normative Annual Plant Availability <br /> Factor (NAPAF) from 85% to 68% and CERC, granted partial relief by relaxing <br /> the NAPAF from 85% to 76% for the period from 24.03.2015 to 30.09.2018 as a <br /> one-time dispensation and further directed that any incentive earned by OTPC <br /> would be adjusted against the differential Annual Fixed Charges (AFC) until full <br /> recovery. It is further submitted that despite such relaxation, the actual Plant <br /> Availability remained substantially below 76% due to continued gas shortages, <br /> resulting in under-recovery of Annual Fixed Charges. <br /> 18. The Appellant has never disputed the factum of gas shortage; its case rests <br /> solely on the assertion that OTPC ought to have “pressurised” ONGC to supply <br /> more gas on account of ONGC’s shareholding and ownership of major gas fields <br /> in the North-Eastern Region. This premise is untenable. OTPC and ONGC are <br /> distinct entities. ONGC acts separately as shareholder and as supplier under the <br /> GSPA. Shareholding cannot override contractual rights. Clause 9.1(c) of the <br /> Shareholders’ Agreement and Clause 142 of OTPC’s Memorandum of <br /> Association prevent ONGC from interfering in OTPC’s enforcement of GSPA <br /> rights. These provisions unequivocally demonstrate that ONGC’s shareholding <br /> does not translate into control over OTPC’s contractual actions under the GSPA, <br /> nor does it confer upon OTPC any legal authority to dictate ONGC’s allocation of <br /> gas across consumers or any priority right over production from ONGC’s fields. <br /> The Appellant cannot, under the guise of tariff proceedings, invite this Tribunal to <br /> adjudicate upon ONGC’s internal commercial or management decisions or the <br /> Page <b>8</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> internal affairs of OTPC, particularly when ONGC is not even a party to the <br /> present proceedings. <br /> 19. It is submitted that the Impugned Order, upon examination of the material <br /> placed by OTPC, records a categorical finding that OTPC was not receiving <br /> adequate gas to achieve the normative availability of 85% and that such shortfall <br /> was not attributable to OTPC; the shortage stood established on the basis of <br /> actual supply figures and was independent of any allegation concerning <br /> Monarchak. The subject project is located in a remote region, unconnected to the <br /> national gas grid, with no APM allocation, no access to RLNG/ spot market/ or <br /> alternate fuel. It is wholly dependent on ONGC, like other projects in the <br /> North-East. The Ministry of Petroleum in its communication dated 14.03.2012 and <br /> CERC in its Order dated 09.05.2013 in Petition Nos. 127/2012 and 128/2012, <br /> acknowledged nationwide domestic gas shortages affecting multiple existing and <br /> upcoming plants. <br /> 20. The sectoral position has also been judicially recognised. Judgement in <br /> “ <b><i>North Eastern Electric Power Corporation Limited v. APDCL &amp; Ors.</i></b> <b>” 2022 </b><br /> <b><i>SCC OnLine APTEL 69 (Appeal No. 121 of 2019) dated 04.08.2022</i></b> , this <br /> Tribunal, , while dealing with NEEPCO’s Assam Gas-Based Power Plant, held <br /> that the shortage of gas was beyond the generator’s control and remanded the <br /> matter to the CERC for reconsideration of relaxation under Regulation 54 and <br /> pursuant to the remand, the CERC, by order dated 29.04.2023 in Petition No. <br /> 225/MP/2017, acknowledged that NEEPCO was unable to achieve the normative <br /> availability of 72% during FY 2016–17 solely because adequate gas could not be <br /> supplied by Oil India Limited and that arranging spot gas or any alternate fuel in <br /> the remote North-Eastern Region was not feasible; accordingly invoking <br /> Regulation 54 granted relaxation of NAPAF. <br /> Page <b>9</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> 21. Consistent with this backdrop, Clause 14.3 of the GSPA provides for <br /> pro-rata supply in case of reduced production, recognizing possible shortfall. <br /> Allocation of reduced output is ONGC’s contractual prerogative. OTPC cannot <br /> compel prioritization, of supply in its favour nor can shortage be attributed to a <br /> deliberate act or omission on OTPC’s part. In this context, this Tribunal in “ <b><i>Tata </i></b><br /> <b><i>Power Company Limited v. Jharkhand State Electricity &amp; Tata Steel Ltd.</i></b> <b>,”</b><br /> <b>2012 SCC OnLine APTEL 155,</b> has held that it cannot exercise appellate <br /> jurisdiction to substitute one subjective satisfaction with another in the absence <br /> of valid grounds. <br /> 22. Appellant’s Contention that since the CERC rejected OTPC’s plea of non-<br /> availability of gas as a Force Majeure event for the purpose of time overrun, it <br /> could not thereafter relax NAPAF on the ground of inadequate gas supply, is <br /> wholly misconceived. The Force Majeure claim dealt in paragraph 37 of the <br /> Impugned Order pertained exclusively to time overrun in achieving the COD of <br /> Unit II for the period 04.01.2014 to 10.10.2014 (279 days), wherein CERC held <br /> that notwithstanding the blockades, sufficient gas was available during <br /> substantial portions of the said period to enable declaration of COD of Unit II, and <br /> that no Force Majeure condition prevented conduct of the trial run; it accordingly <br /> declined to condone the time overrun and held the delay attributable to OTPC. <br /> Whereas, the relaxation of NAPAF granted by the CERC for the period <br /> 24.03.2015 to 30.09.2018 was founded on an entirely distinct event, namely <br /> unanticipated adverse gas reservoir behaviour affecting availability of gas in the <br /> relevant fields an operational, post-COD phenomenon differing in time, cause and <br /> character from the earlier construction-phase blockades. <br /> 23. The Appellant’s contention that, by reason of ONGC’s shareholding, the <br /> Project was conceived on the premise of assured gas and that OTPC is therefore <br /> precluded from relying on non-availability of gas is misconceived. Gas allocation <br /> Page <b>10</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> to the Project was made pursuant to directions issued by the Ministry of <br /> Petroleum and Natural Gas, which by Order dated 07.10.2004 directed allocation <br /> of 4 MMSCMD, along with any additional gas up to a total of 5 MMSCMD, from <br /> Tripura fields for the Project through the State utility. In furtherance thereof, a <br /> GSPA dated 29.09.2008 was executed between ONGC and OTPC on an arm’s-<br /> length basis. <br /> 24. The Appellant’s reliance on this Tribunal’s Judgment dated 30.04.2013 in <br /> <b><i>NTPC Limited v. CERC &amp; Ors</i></b> <i>.</i> , <b><i>Appeal No. 110 of 2012</i></b> , is misplaced. In that <br /> case, NTPC operated three generating stations despite having insufficient coal <br /> linkage for all three and chose to commission and operate the third plant by <br /> diverting coal from the first two, resulting in none of the stations achieving <br /> normative availability; In the present case, by contrast, OTPC and ONGC are <br /> distinct legal entities, and ONGC has concurrent and independent contractual <br /> obligations to supply gas to both Palatana and Monarchak under separate <br /> agreements; there is no question of OTPC diverting fuel from one plant to <br /> another. Unlike NTPC, OTPC has no comparable alternative—ONGC is the sole <br /> gas supplier in Tripura, there is no pipeline connectivity from the mainland, and <br /> gas from other regions cannot be transported to the Project. Additionally, in <br /> NTPC the governing contract did not treat fuel unavailability as a Force Majeure <br /> event, whereas here Clause 17.1(c) of the GSPA expressly recognizes <br /> unanticipated reservoir behavior as a Force Majeure event. The factual and <br /> contractual matrix in NTPC is thus materially distinct and affords no assistance <br /> to the Appellant. <br /> 25. The Appellant has also assailed the Corrigendum Order dated 03.05.2017; <br /> however, the said Corrigendum was issued by CERC upon OTPC’s request for <br /> clarification and is confined solely to correction of inadvertent arithmetical and <br /> linkage errors in the computation of Return on Equity and Interest on Loan <br /> Page <b>11</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> contained in the Impugned Order. It neither introduces any new reasoning nor <br /> records any fresh findings germane to the issues raised in the present Appeal, <br /> and merely rectifies computational errors in exercise of powers under Regulation <br /> 111 read with Regulation 103 A of the Conduct of Business Regulations, 1999. <br /> The challenge to the Corrigendum is, therefore, wholly devoid of merit. <br /> <b>CONSIDERATION AND OUR VIEW </b><br /> 26. At the outset, we find merit in the submissions advanced by the <br /> Respondent that ONGC Tripura Power Company Limited (OTPC) and Oil and <br /> Natural Gas Corporation Limited (ONGC) are distinct legal entities. The mere fact <br /> of ONGC’s shareholding in OTPC does not, in law, obliterate the separate <br /> corporate personality of either entity. ONGC, in its capacity as shareholder, <br /> stands on a footing entirely different from its role as supplier under the Gas Sale <br /> and Purchase Agreement (GSPA). The contractual rights and obligations arising <br /> under the GSPA are enforceable independently of ONGC’s equity interest, and <br /> OTPC cannot, by virtue of such shareholding, assert any priority claim over <br /> ONGC’s production or dictate the allocation of gas across ONGC’s consumers. <br /> 27. It is apposite, in this context, to advert to the clause 9.1(c) of Shareholders’ <br /> Agreement, as reproduced hereunder, which clearly delineates the respective <br /> rights and obligations of the parties. The said Agreement stipulates that the rights <br /> conferred upon OTPC as a shareholder are confined to governance and <br /> participation in corporate decision-making, and do not extend to interference with <br /> ONGC’s operational or commercial decisions in its capacity as a supplier. The <br /> contractual framework thus preserves the autonomy of ONGC in matters relating <br /> to production and allocation, while safeguarding OTPC’s rights strictly within the <br /> contours of the GSPA. Thus, the contractual obligations under the GSPA are not <br /> overridden or diluted by reference to ONGC’s shareholding in OTPC. <br /> Page <b>12</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <b><i> 9.1 (c) Decisions of the Board </i></b><br /> <i>Subject to the provisions of Clause 12, all decisions of the Board shall be </i><br /> <i>made by simple majority. The Chairman shall have a casting vote in </i><br /> <i>relation to all decisions of the Board with the exception of all decisions </i><br /> <i>related to Reserved Matters, as detailed in Annexure-3. The Board shall </i><br /> <i>have the power to delegate its powers to any person or a sub-committee, </i><br /> <i>subject to the provisions of the Act. </i><br /> <i>Notwithstanding anything to the contrary contained in this Agreement, </i><br /> <i>both the Parties agree that (i) the Chairman of the Board of the Company </i><br /> <i>shall not have any &quot;Casting Vote&quot; right (referred to herein above under </i><br /> <i>clause 9.1(c)) in respect of any matter related to or arising out of Gas Sale </i><br /> <i>and Purchase Agreement and further (ii) ONGC shall not unreasonably </i><br /> <i>use its voting rights to defer, delay, vary or block any Board resolution </i><br /> <i>proposed in connection with the exercise of the Company rights, power </i><br /> <i>and privileges, reserved under Gas Sale and Purchase Agreement to </i><br /> <i>seek enforcement of any supply or pay obligations or termination </i><br /> <i>proceedings in accordance with the terms and conditions of the Gas Sale </i><br /> <i>and Purchase Agreement. </i><br /> 28. It is to further state that this Tribunal neither exercise jurisdiction over <br /> ONGC’s internal commercial and management decisions nor ONGC is a party in <br /> the present proceedings, we shall therefore limit our deliberations with regard to <br /> provisions of GSPA executed between OTPC, the respondent, and ONGC. <br /> 29. The learned Counsel on behalf of Respondent No.1- OTPC has contended <br /> that Appellant confined its case on one contention that ONGC being shareholder <br /> of OTPC could have ensured adequate supply and relied upon the letter dated <br /> 18.12.2015 issued by OTPC to CEA to allege that gas was diverted to Monarchak <br /> project. Though the said letter was submitted along with the Appeal, however, it <br /> was not placed before the commission when reply was filed by Appellant to them <br /> on 12.02.2016. With regard to admissibility of such document at Appellant stage, <br /> without an application and with no specific order by this Tribunal, it has been <br /> submitted that it cannot form part of the evidentiary record for examining the <br /> Page <b>13</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> correctness of the Impugned Order and there is procedural bar under Order XLI <br /> Rule 27 of CPC 1908. <br /> 30. In this context, it is noted that Respondent No.1-OTPC, in its reply dated <br /> 03.04.2018 before this Tribunal has referred to the same letter dated 18.12.2015 <br /> to submit that OTPC has actively pursued with CEA apprising them about the <br /> shortage of gas supply at its Palatana Project and respondent has not placed any <br /> evidence that it had, at any stage, questioned the admissibility of such document <br /> at Appellate Stage. It is well settled that proceedings before this Tribunal are <br /> governed by the provisions of the Electricity Act, 2003 and the Regulations <br /> framed thereunder. The Code of Civil Procedure, 1908 (CPC), in its strict sense, <br /> does not apply to proceedings before this Tribunal. While principles of natural <br /> justice and certain procedural safeguards embodied in the CPC may be invoked <br /> for guidance, the rigours of the CPC cannot be imported at a belated stage of <br /> appellate adjudication. In the present matter, the Respondent has sought to raise <br /> objections regarding the admissibility of a document on the ground that it was not <br /> filed before the State Commission, particularly at a stage when the Appeal is <br /> being finally heard in later part of year 2025, is untenable. The Tribunal, <br /> exercising appellate jurisdiction under Section 111 of the Electricity Act, is not <br /> bound by the technicalities of the CPC. The Tribunal is empowered to examine <br /> the correctness of the Impugned Order on the basis of the material placed before <br /> it, and once both parties have themselves relied upon the document in question, <br /> the objection to its admissibility loses all force. Accordingly, this Tribunal holds <br /> that the provisions of the CPC cannot be pressed into service at such a belated <br /> stage to defeat substantive justice. The objection raised by the Respondent is, <br /> therefore, rejected. <br /> 31. OTPC, Respondent No. 1, and ONGC has entered into GSPA on <br /> 29.09.2009. The said agreement has a basic Term of 15 years with years, with <br /> Page <b>14</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> FY 2008-09 to be the base year. Relevant clauses of GSPA are reproduced <br /> hereunder for ready reference : <br /> <i>“5.4 Failure to take delivery of, or supply, Gas </i><br /> <i> (a) ……. </i><br /> <i>The Seller shall be liable for Seller’s Shortfall in accordance with Clause 15, with </i><br /> <i>(b) </i><br /> <i>effect from the Commercial Supply Date, in the event of: </i><br /> <i>(i) </i> <i> the Seller’s failure to tender for delivery Gas as is scheduled for delivery </i><br /> <i>in accordance with tis Agreement or </i><br /> <i>(ii) </i> <i>any other breach by the Seller of its obligations in accordance with this </i><br /> <i>Agreement.” </i><br /> The clause 15 of GSPA provides for the Seller’s Liquidated damages in the event <br /> of shortfall in supply, in which clause 15.1 (a) defines the Supply Deficiency <br /> Quantity as A – B- C, where: <br /> “ <i>A is the 90% of the aggregated Nominated DCQs during such Contract Year and </i><br /> <i> B is sum of the aggregated quantities of Gas supplied in accordance with the </i><br /> <i>Agreement for such Contract Year and any quantity of Gas which the Seller is excused </i><br /> <i>from delivering under this Agreement including because of Force Majure under (clause </i><br /> <i>17 and Buyer Quantity Deficiency under Clause 8. </i><br /> <i>C is Seller’s Carry Forward accumulated as specified under clause 8.5.” </i><br /> Clause 15.1 (b), provides for compensation by seller, in the event of shortage of <br /> supply as reproduced below: <br /> <i>“(b) </i> <i>The Seller shall compensate the Buyer for any Supply Deficiency Quantity during </i><br /> <i>any Contract Year in accordance with the following formula: </i><br /> <i>CA = [X%] CP x SDQ </i><br /> <i>Where: </i><br /> <i>X% </i> <i> is the percentage of CP </i><br /> <i>st</i> <i>th</i><br /> <i> X </i> <b><i>= 85</i></b> <i> from 1</i> <i> to 5</i> <i> year from Commercial Supply Date, </i><br /> <i>th</i> <i>th</i><br /> <b><i>55</i></b> <i> from 6</i> <i> to 10</i> <i> year from Commercial Supply Date </i><br /> Page <b>15</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <i>th</i> <i>th</i><br /> <b><i>35</i></b> <i> from 11</i> <i> to 15</i> <i> year from Commercial Supply Date </i><br /> <i>CA </i> <i>is the compensation amount </i><br /> <i>CP </i> <i>is the applicable Contract Price for the year </i><br /> <i>SDQ is the Supply Deficiency Quantity” </i><br /> The compensation amount so worked out has been agreed as reasonable pre <br /> estimate of losses as mentioned in clause 15.3: <br /> <i>“15.3 </i> <b><i>Genuine pre-estimate</i></b><br /> <i>The Seller and the Buyer specifically agree and acknowledge that the </i><br /> <i>compensation to the Buyer under this Clause 15.2 in respect of a Supply </i><br /> <i>Deficiency Quantity shall be by way of liquidated damages and such damages </i><br /> <i>as a result of Seller’s failure to make Gas available for delivery hereunder </i><br /> <i>constitute a genuine and reasonable pre-estimate of losses which Buyer shall </i><br /> <i>incur on account of such Supply Deficiency Quantity.” </i><br /> The clause 17 of the GSPA provides for the <i>force majeure</i> under which several <br /> events have been included as <i>force majeure</i> events like, fire, flood, war, act of <br /> government agency, as well as unanticipated adverse behaviour of Sellers Gas <br /> reservoir. In the event of any such force majeure event, the affected party shall <br /> provide notice promptly but not later than 48 hours after the occurrence of the <br /> event of Force Majeure, the relevant clause 17.3 is reproduced below: <br /> <b><i>“17.3Notice and resumption of normal performance </i></b><br /> <i>(a) In the event of Force Majeure, the affected Party shall provide notice promptly </i><br /> <i>and but not later than [48] hours after the occurrence of event of Force </i><br /> <i>Majeure, the other Party will respect to the ongoing Force Majeure event </i><br /> <i>giving full particulars of the Force Majeure the estimate duration thereof, the </i><br /> <i>obligation affected and the reasons of its suspension and the affected Party’s </i><br /> <i>ability in recommence performance of its obligations under the Agreement as </i><br /> <i>soon as possible. </i><br /> <i>(b) The Party asserting the claim of Force Majeure shall have the burden of </i><br /> <i>proving the circumstances constitute valid grounds of Force Majeure under </i><br /> Page <b>16</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> <i>this clause and that such Party has exercised reasonable diligence and efforts </i><br /> <i>to remedy the cause of any alleged Force Majeure.” </i><br /> 32. From the reading of various clauses, as referred above, the GSPA provides <br /> for compensation by the fuel supplier i.e. ONGC, in case there is deficiency in <br /> gas supply except <i>force majeure, </i> however for claiming relief under <i>force majeure</i> , <br /> the party claiming <i>force majeure</i> has to give appropriate notice and shall have the <br /> burden for proving the circumstances forming valid ground of <i>force majeure </i> in <br /> accordance with the terms of the agreement. <br /> 33. Our attention has been brought to the letter dated 18.12.2015, from OTPC <br /> addressed to the Chairman, CEA, with regard to shortage of gas supply to its <br /> Palatana Project, submitting that the said project is quite efficient as compared <br /> to other gas power stations in North Eastern Region and requested for suitable <br /> measures to make it run at full capacity. Further the Secretary, North Eastern <br /> Council Secretariat vide its letter dated February 2016 addressed to Secretary <br /> Power has raised the issue of shortage of gas supply to Palatana Project, which <br /> is the cheapest power available to all the seven North Eastern States and has <br /> also raised the issue of diversion of gas meant for Palatana Project to Monarchak <br /> generation project and requested for Ministry of Power intervention for stopping <br /> diversion of gas from Palatana Project and to provide Palatana Project the <br /> desired quantum of fuel. Perusal of these letters establish that shortage of gas <br /> supply to Palatana Project, and diversion of gas meant for it to Monarchak <br /> generation project has been discussed in the various meetings of North Eastern <br /> region, and OTPC being fully aware of the reasons for shortage, also apprised <br /> to Ministry of Power and CEA seeking their intervention; however, no material <br /> has been placed before this Tribunal to indicate that Respondent No. 1, OTPC, <br /> had taken up the matter with the fuel supplier, namely ONGC, for seeking <br /> Page <b>17</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> compensation on account of short supply of gas in accordance with the relevant <br /> provisions of the GSPA. <br /> 34. We take note that ONGC vide its letter dated 18.03.2016, in response to <br /> the letter of OTPC 09.03.2016 has stated the inherent risk of unexpected <br /> reservoir behaviour as one of the reason for short supply of power to Palatana <br /> Project and referred to clause 17.1(c ) ( the force Majeure clause ) under the <br /> GSPA between ONGC and OTPC. <br /> 35. In the Impugned Order, considering the submissions advanced by OTPC, <br /> that due to unexpected reservoir behaviour of reservoir as submitted by ONGC, <br /> which is covered under Force majeure under article 17.1 (c) of the GSPA, fuel <br /> shortage was held to be beyond control of OTPC and relaxation in NAPAF was <br /> allowed from 85 % to 76 % during the period from 24.03.2015 to 30.09.2018, <br /> albeit same was considered as a onetime relaxation. <br /> 36. The Appellant has placed reliance on the judgment of this Tribunal dated <br /> 30.04.2013 in Appeal No. 110 of 2012, <b><i>NTPC Limited vs. Central Electricity </i></b><br /> <b><i>Regulatory Commission &amp; Ors</i></b> <i>.</i> , wherein it was held that the responsibility for <br /> arranging fuel supply rests with the generating company and the beneficiaries <br /> cannot be held accountable and non-availability of sufficient fuel does not fall <br /> under the purview of the <i>force majeure </i> event and relaxation in the NAPAF was <br /> not granted to the generator. In the referred case, the issue pertained to diversion <br /> of coal supply from mines linked to Farakka and Kahalgaon Stage I projects to <br /> the Kahalgaon Stage II project, subsequent to its commissioning, which resulted <br /> in lower plant availability of Farakka and Kahalgaon -I project seeking relaxation <br /> in NAPAF. This Tribunal, in these circumstances, held that NTPC is responsible <br /> for ensuring adequate supply to its generating stations as diversion was held to <br /> be instituted by NTPC itself, as all three projects were connected to the same <br /> coalfields through the Merry-Go-Round system for transportation of coal. <br /> Page <b>18</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> 37. Per Contra, Respondent -OTPC has contended that the said judgment is <br /> not applicable to the present case. Unlike coal, which can be transported through <br /> multiple modes including rail and road and can be diverted among projects <br /> connected to the same source, natural gas presents a fundamentally different <br /> logistical reality. In the present matter, no diversion of gas has been undertaken <br /> by OTPC. Rather, the supply of gas to the project is entirely dependent on ONGC, <br /> which is the sole supplier of natural gas in the state of Tripura. There is no pipeline <br /> connectivity from the mainland to Tripura, and gas sourced from other regions <br /> cannot be transported to the project site. Unlike coal, natural gas cannot be <br /> transported by road or rail; it requires designated pipeline infrastructure, which in <br /> this case does not exist beyond the local supply arrangements. At first instance, <br /> there appears to be some merit in the submissions advanced on behalf of the <br /> Respondent. However, upon a closer examination of the contractual framework, <br /> it becomes clear that the responsibility of arranging fuel lies squarely with the <br /> generator. In the present case, OTPC has assumed this responsibility and, in <br /> discharge thereof, has entered into a Gas Sale and Purchase Agreement (GSPA) <br /> with ONGC. The existence of such an agreement underscores that the generator <br /> itself is entrusted with securing the requisite fuel supply, and cannot shift this <br /> burden onto any other entity. The implications of the said GSPA are deliberated <br /> upon in the subsequent portions of this judgment. <br /> 38. Respondent- OTPC placing reliance on the judgement dated 04.08.2022 <br /> of this Tribunal in <b><i>North Eastern Electric Power Corporation Limited v. </i></b><br /> <b><i>APDCL &amp; Ors.</i></b> <b>,; 2022 SCC OnLine APTEL 69, </b> submitted that while dealing <br /> with NEEPCO’s Assam Gas-Based Power Plant, this Tribunal held that the <br /> shortage of gas was beyond the generator’s control and remanded the matter to <br /> the CERC for reconsideration of relaxation under Regulation 54. In the said <br /> judgement, this Tribunal took note of the fact that the supply of gas to the <br /> NEEPCO project was reduced in view of the directive of Central Govt conveyed <br /> Page <b>19</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> vide letter dated 17.08.2016 &amp; 31.10.2016, and noting that relief being sought by <br /> Appellant (NEEPCO) could have been claimed under the GSPA and directed <br /> against the gas supplier, however taking cognizance of the direction of central <br /> govt, vis-à-vis obligations of gas supplier to supply as per that, resulted in <br /> reduction of supply for the Appellant Project. Since Central commission has not <br /> examined the issue in this perspective, this Tribunal without expressing any <br /> opinion on the merit of the case, remanded the matter to Central commission for <br /> fresh consideration from that perspective. In our view, this judgement cannot be <br /> construed to be holding that arranging fuel is not the responsibility of generator <br /> and it is entitled to relaxation in NAPAF in case of shortage of supply. The <br /> shortage in supply of gas for the subject project in the referred judgement was <br /> considering the directives of Govt, while no such Govt directive have been <br /> referred in the present case, which mandates ONGC to divert the supply <br /> elsewhere. Thus, the facts in the present case are different than the case referred <br /> and accordingly reliance placed on this judgement by Respondent is of no avail. <br /> We further observe that the Respondent has sought to place reliance upon the <br /> order passed by the Central Electricity Regulatory Commission (CERC) pursuant <br /> to the remand directions issued by this Tribunal in the aforesaid matter. In our <br /> considered view, such reliance is misplaced. This Tribunal, being a statutory <br /> appellate forum, is bound by the pronouncements of superior judicial fora and not <br /> by the orders of the regulatory commission, which is subordinate in the judicial <br /> hierarchy. While the orders of the Commission may provide administrative <br /> context or factual narration, they do not constitute binding precedent upon this <br /> Tribunal. The jurisprudential discipline requires us to follow the ratio laid down by <br /> higher courts, and not to be guided by regulatory directions issued in the course <br /> of remand proceedings. Accordingly, the order passed by the CERC upon <br /> remand cannot be treated as determinative for the present adjudication and does <br /> not need consideration by us. <br /> Page <b>20</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> 39. Having observed as above, it is important and relevant to deliberate the <br /> present case vis- a- vis provisions of GSPA, which OTPC has with the gas <br /> supplier ONGC. As noted above, the Respondent OTPC has acknowledged <br /> shortage of gas for their Palatana Project by their gas supplier and sought <br /> relaxation in NAPAF for the period from 24.03.2015 till September 2018, after <br /> which period gas supplier has assured full supply. Through the communications <br /> referred above, shortage in gas supply to Palatana project has been referred to <br /> the diversion of gas by their supplier i.e ONGC to another project i.e Monarchak <br /> and have sought intervention of Ministry of Power, Govt of India for impressing <br /> upon ONGC to supply requisite gas for the Palatana Project. However, OTPC, in <br /> their submissions before CERC have indicated the shortage in supply of gas on <br /> account of <i>force majeure</i> event of gas supplier. We note that on the basis of such <br /> contentions, it has been held in the Impugned Order that OTPC is not getting <br /> enough gas supply and relaxed the NAPAF, however CERC while according <br /> such a relaxation has not examined the provisions of GSPA and whether the <br /> submissions made by OTPC would constitute a force majeure, to constrain <br /> OTPC to avail liquidated damages from the gas supplier in terms of GSPA. In our <br /> considered view, such an approach is legally unsustainable. <br /> 40. We note that GSPA expressly stipulates a specific procedure and timeline <br /> for issuance of notice upon occurrence of a Force Majeure event, such <br /> contractual requirement is required to be complied with both in letter and in spirit. <br /> While OTPC has claimed shortage of supply from 24.03.2015 and claimed <br /> relaxation in NAPAF since then, the letter of ONGC, to be reckoned as a <i>force </i><br /> <i>majeure</i> notice, as no other letter from gas supplier has been referred to us, is <br /> dated 18.03.2016, almost after a year of such occurrence of gas shortage for <br /> which relaxation in NAPAF is sought. The notice contemplated under the <i>force </i><br /> <i>majeure</i> clause is not an idle formality or a mere procedural ritual; rather, it <br /> constitutes the contractual mechanism that sets the claim in motion and enables <br /> Page <b>21</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> the counter-party to take necessary mitigating and administrative measures. This <br /> Tribunal in its judgement dated 07.11.2017 in “ <b><i>Maruti Clean Coal and Power </i></b><br /> <b><i>Limited v. Power Grid Corporation of India Limited and Anr.” 2017 SCC </i></b><br /> <b><i>OnLine APTEL 70 </i></b> has emphasized that compliance with the notice requirement, <br /> where made a condition precedent, is mandatory for availing relief under the force <br /> majeure clause. Therefore, where the contract makes issuance of notice within a <br /> stipulated period or reasonable time, a condition precedent, strict adherence <br /> thereto is mandatory, and failure to comply would disentitle the affected party <br /> from seeking the contractual relief. Similar position has been held in the <br /> judgement of this Tribunal in <b><i>“Punjab State Power Corporation Limited v. </i></b><br /> <b><i>Punjab State Electricity Regulatory Commission &amp; Ors.”</i></b> <i>,</i> Appeal No. 316 of <br /> 2018. In view of the settled position of law, the letter issued by ONGC dated <br /> 18.03.2016 cannot be construed as a valid force majeure notice for the purposes <br /> of the GSPA. Neither OTPC has claimed liquidated damages from the gas <br /> supplier in terms of provision of GSPA, nor the Central commission has <br /> examined, the provisions relating to liquidated damages in the GSPA, which the <br /> OTPC may be entitled from its gas supplier but by relaxing the NAPAF, the <br /> consequences of not achieving the stipulated NAPAF of 85 %, has been passed <br /> on to the beneficiaries beyond NAPAF of 76%. As already stated above, no <br /> documentary evidence has been placed by OTPC with regard to taking measures <br /> for pursuing with ONGC, the gas supplier, with regard to compliance of provisions <br /> of GSPA and to claim liquidated damages. <br /> 41. It is also relevant to note that OTPC was fully aware that there is statutory <br /> requirement of achieving NAPAF of 85% for the Palatana project and under <br /> clause 15.3 of the GSPA, the calculation of LD as calculated in clause 15.2 has <br /> been estimated to be the reasonable estimate for compensation of loss, which <br /> may accrue on account of less supply. It is not even the case of OTPC that <br /> liquidated damages calculated under clause 15.2 is not sufficient to cover the <br /> Page <b>22</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> losses on account of less recovery of fixed costs and need relaxation in NAPAF <br /> to bridge the gap. Thus, even it is held that shortage of supply in gas to Palatana <br /> project is beyond the control of OTPC, and they are not able to recover its fixed <br /> cost, we find OTPC has failed in exercising its claim under the GSPA upon <br /> ONGC, the fuel supplier for shortage in supply and has rather sought to shift <br /> entire obligation upon the beneficiaries i.e. the consumers. It is also pertinent to <br /> note that on one hand ONGC, the gas supplier has not met its supply <br /> commitments as per the GSPA to OTPC, and no claim has been levied upon <br /> them by OTPC with regard to shortage of gas supply leading to non-achieving of <br /> stipulated NAPAF. The relaxation in NAPAF from 85 % to 76 % has effectively <br /> resulted in conferring an undue benefit upon the gas supplier i.e ONGC as well, <br /> which holds a 50% shareholding in the project, thereby allowing the <br /> consequences of supply failure to be passed on to the beneficiaries instead of <br /> the defaulting fuel supplier. Respondent No.1 - OTPC has placed reliance upon <br /> Clause 14.3 of GSPA to contend that this clause provides for pro-rata allocation <br /> of gas supply in case of reduced production, recognizing possible shortfall and <br /> allocation of reduced output is ONGC’s contractual prerogative. It has been <br /> contended that OTPC cannot compel prioritization, of supply in its favour nor can <br /> the shortage be attributed to a deliberate act or omission on OTPC’s part. The <br /> clause 14.3 of the GSPA, as relied upon by OTPC, is reproduced hereunder:<br /> <b><i> “14.3 Reduction of Gas production </i></b><br /> <i>In the event of any reduction in the production of Gas in the Gas Supply </i><br /> <i>Area’s), the Seller shall take all effective steps to fulfil its supply obligations </i><br /> <i>under this Agreement. In any event. the Seller shall at least make available </i><br /> <i>the quantities of Gas to Buyer from Gas Supply Area(s) pro rata of DCQs.” </i><br /> 42. This clause stipulates that, in the event of a reduction in production, the <br /> seller shall be entitled to supply only the pro rata share of the Daily Contract <br /> Quantity (DCQ). This provision is designed to safeguard the seller against liability <br /> Page <b>23</b> of <b>24</b><br /><br /> <i> Judgement in Appeal Nos. 334 of 2017 </i><br /> where the shortfall arises directly from diminished production capacity on day to <br /> day basis. However, Clause 15 of the GSPA expressly provides for the levy of <br /> liquidated damages in the event of failure by the seller to deliver the agreed <br /> quantity of gas over a Contract year. A plain reading of Clause 15 clearly <br /> demonstrates the intention of the parties to hold the seller accountable for any <br /> shortfall in supply during a year. Therefore, any interpretation of the pro rata <br /> supply clause under clause 14.3 as conferring a blanket exemption from liability <br /> for undersupply would render Clause 15 otiose and defeat the commercial <br /> purpose of the agreement. As such, no exceptions have been carved out in <br /> clause 15 for pro rata supply of DCQ under clause 14.3. In such circumstances, <br /> Clause 14.3 cannot be construed in a manner that absolves the gas supplier, i.e., <br /> ONGC, from its contractual obligations under Clause 15. <br /> <b>CONCLUSION </b><br /> 43. In view of the above deliberations, we set aside the CERC Order dated <br /> 30.03.2017 with regard to relaxation in the NAPAF from 85 % to 76 % for the <br /> period from 24.03.2015 to 30.09.2018 and any consequential effect it has had on <br /> the calculation in corrigendum order dated 03.05.2017, which is also impugned <br /> in the present Appeal, shall stand annulled to that extent. <br /> 44. Accordingly, the Captioned Appeals is allowed in above terms and all <br /> pending IAs, if any, are disposed off in these terms. <br /> <b>th</b><br /> <b>PRONOUNCED IN THE OPEN COURT ON THIS 06</b> <b> OF APRIL, 2026. </b><br /> <b>(Virender Bhat) </b><br /> <b>Judicial Member</b><br /> <b>(Seema Gupta) </b><br /> <b>Officiating Chairperson</b><br /> <b>REPORTABLE / NON-REPORTABLE </b><br /> Page <b>24</b> of <b>24</b></div>