M/S. ANURAG CONSTRUCTIONS vs M/S. ELEGANT BUILDERS AND DEVELOPERS
- Court
- Karnataka High Court
- 1 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
TH
DATED THIS THE 12 DAY OF OCTOBER, 2026
BEFORE
THE HON'BLE MR. JUSTICE SACHIN SHANKAR MAGADUM
WRIT PETITION NO. 14188 OF 2019 (GM-CPC)
BETWEEN:
1. M/S. ANURAG CONSTRUCTIONS
REGISTERED PARTNERSHIP FIRM,
NO.493, 1ST B MAIN, M.S.M.RAMIAH CITY,
J.P.NAGAR 8TH PHASE, BANGALORE - 560 076.
2. SRI. MADHAVA REDDY
SON OF SRI. B.KOTI REDDY,
AGED ABOUT 50 YEARS,
RESIDENT OF HIG-27
BALAJINAGAR, KUKATPALLI
HYDERABAD - 72.
3.
3(A)
3(B)
3(C)
SRI. K. KESHAVA REDDY
SON OF SRI.NARASIMHA REDDY,
SINCE, DEAD BY LRs
SMT. K. SARASWATHAMMA
W/O LATE SRI. K. KESHAVA REDDY
AGED ABOUT 68 YEARS
SRI. K. NARASIMHA REDDY
S/O LATE SRI. K. KESHAVA REDDY
AGED ABOUT 47 YEARS
BOTH 1 & 2 R/AT NO.BTF-4
TH
ELEGANT PALACE, 7 MAIN ROAD
ND
2 CROSS, NOBONAGAR, BANGALORE-560076
MRS. P. SREELAKSHMI
D/O LATE SRI. K. KESHAVA REDDY
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 2 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
W/O DR. P. SURESH REDDY
AGED ABOUT 44 YEARS
R/AT APARTMENT NO.601
PARK VIEW HEIGHTS, 6-5-961
NEW ADCC BANK COLONY
RAMNAGAR, ANANTHPUR-515001.
4. SRI. G. PARAMESWARA REDDY
SON OF NAGABHUSHANA REDDY,
AGED ABOUT 65 YEARS,
RESIDENT OF 10-7-32/C,
ANJANEYASWAMY TEMPLE,
ARUNDALPET, NARASARAOPET,
GUNTUR DISTRICT, ANDHRA PRADESH.
5. SRI. RAMI REDDY
SON OF SRI.M.PRAKASH REDDY,
AGED ABOUT 49 YEARS,
RESIDENT OF CHALLAGADDA POST,
NAKRIKALLU MANDAL, GUNTUR DISTRICT
ANDHRA PRADESH.
6. SRI. MANOHAR REDDY
SON OF SRI.THIMMA REDDY,
AGED ABOUT 49 YEARS,
2-125/3/1, ENGINEERS ENCLAVE,
GANGARAM, CHANDANAGAR
HYDERABAD - 50
P2 TO P6 ARE ALL PARTNERS OF P1.
P2, P4,P5 AND P6 ARE REP. BY THEIR
POWER OF ATTORNEY HOLDER
SRI K.KESHAVA REDDY, P3.
…PETITIONERS
(BY SRI. M.A. HUMAYUN, ADVOCATE)
AND:
1. M/S. ELEGANT BUILDERS AND DEVELOPERS
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 3 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
NO.1/116, NEW KEMPEGOWDA LAYOUT,
BANASHANKARI 3RD STAGE,
BANGALORE - 560 085.
2. SMT. V. PRABHA
WIFE OF SRI.M. SUBRAMANI,
AGED ABOURT 41 YEARS,
3. SRI. M. SUBRAMANI
SON OF LATE MUTHULA NAIDU,
AGED ABOURT 49 YEARS,
4. SRI. S.N. MANJUNATH
SON OF SRI. M.SUBRAMANI,
AGED ABOURT 25 YEARS,
5. SRI. S. RAJESH
SON OF M.SUBRAMANI,
AGED ABOURT 24 YEARS,
ALL ARE R/AT NO.1/116,
NEW KEMPEGOWDA LAYOUT,
BANASHANKARI 3RD STAGE,
BANGALORE - 560 085
REPRESENTED BY SRI M SUBRAMANI (R-3 HEREIN)
…RESPONDENTS
(BY SRI. SUDHAKAR .G.V, ADVOCATE FOR R1 TO R5)
THIS WP IS FILED UNDER ARTICLE 227 OF THE
CONSTITUTION OF INDIA, PRAYING TO QUASH / SET ASIDE
THE IMPUGNED ORDER AT ANNEXURE-A DATED 28.02.2019
PASSED ON I.A.NO.1/2019 IN O.S.NO.25933/2013 BY THE
LXXII ADDITIONAL CITY CIVIL AND SESSIONS JUDGE,
BENGALURU (CCH.NO.73) AND CONSEQUENTLY ALLOW
I.A.NO.1/19 FILED BY THE PETITIONERS.
THIS PETITION, COMING ON FOR DICTATING ORDERS,
THIS DAY, ORDER WAS MADE THEREIN AS UNDER:
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 4 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
CORAM: HON'BLE MR. JUSTICE SACHIN SHANKAR MAGADUM
ORAL ORDER
The captioned writ petition is filed by the plaintiffs
calling in question the order dated 28.02.2019 passed by
the learned Trial Court in O.S.No.25933/2013, whereby
I.A.No.1/2019 filed by the plaintiffs under Order VI Rule
17 read with Section 151 of the Code of Civil Procedure,
1908, (for short ‘CPC’) seeking amendment of the plaint to
incorporate an additional prayer for delivery of vacant
possession, came to be rejected.
2. Brief facts leading to the case are as under;
The plaintiffs claim to be the absolute owners of the
suit schedule property. The plaintiffs entered into a Joint
Development Agreement with the defendants and also
executed a General Power of Attorney dated 21.06.2010 in
favour of the defendants. Subsequently, on account of
changes in the measurement and boundaries of the
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 5 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
property, a rectification deed came to be executed
between the parties.
3. Under the Joint Development Agreement, the
defendants were required to complete the construction
within the stipulated period of 18 months, with a grace
period of three months, and were required to hand over
the plaintiffs’ agreed share in the constructed area. The
agreement further contemplated payment of damages at
the rate of Rs.10,000/- per month in the event of delay in
completion of the construction.
4. According to the plaintiffs, the defendants failed
to complete the construction and failed to hand over the
17 residential units falling to the share of the plaintiffs.
Consequently, the plaintiffs issued a notice dated
04.06.2013 demanding payment of Rs.25,20,000/-
towards damages stipulated under the Joint Development
Agreement and a further sum of Rs.5,00,000/- towards
expenses incurred by the plaintiffs for completion of the 17
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 6 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
units. The notice was returned with the endorsement “Not
claimed”.
5. The plaintiffs thereafter instituted
O.S.No.25933/2013 seeking recovery of a sum of
Rs.30,20,000/- together with interest at the rate of 24%
per annum from the date of suit till realization.
6. When the suit had reached the stage of reply
arguments of the plaintiffs, an application came to be filed
under Order VI Rule 17 of CPC., seeking amendment of
the plaint by incorporating an additional prayer directing
the defendants to hand over vacant possession of the
additional constructed area stated to be 862 sq. ft., which,
according to the plaintiffs, formed part of their entitlement
under the Joint Development Agreement.
7. The learned Trial Court, by the impugned order,
rejected the said application principally on the ground that
the suit was instituted for recovery of damages and that
the proposed relief of possession would change the texture
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 7 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
and character of the suit and would amount to introducing
a new case. The learned Trial Court also expressed an
apprehension that the proposed amendment may be hit by
Order II Rule 2 of CPC.
8. Learned counsel appearing for the
petitioners/plaintiffs would contend that the learned Trial
Court has adopted an unduly technical approach while
considering the application under Order VI Rule 17 of CPC.
According to him, the proposed amendment does not
introduce a new transaction or a new cause of action. The
entire claim arises out of the very same Joint Development
Agreement, General Power of Attorney and the subsequent
rectification deed, which are already specifically pleaded in
the plaint.
9. It is further contended that the plaintiffs had
already pleaded the defendants’ failure to complete the
construction and hand over the agreed residential units
and that the proposed amendment merely seeks an
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 8 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
appropriate consequential relief arising out of those very
foundational facts.
10. Per-contra , learned counsel appearing for the
respondents/defendants would contend that the plaintiffs,
having instituted the suit in the year 2013 only for
recovery of money/damages, cannot, at the fag end of the
proceedings, introduce a substantive relief of possession.
It is contended that the proposed relief relates to an
uncertain and undefined area of 862 sq. ft. and is
therefore also hit by Order VII Rule 3 of CPC. It is further
contended that the rights of the parties are governed by
the Joint Development Agreement and the rectification
deed and that a brochure relied upon by the plaintiffs
cannot furnish the basis for seeking possession. It is also
submitted that no court fee has been paid on the proposed
additional relief.
11. In the light of the rival submissions, the
following points arise for consideration:
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 9 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
(i) Whether the learned Trial Court was justified
in rejecting I.A.No.1/2019 on the ground
that the proposed amendment would change
the nature and character of the suit?
(ii) Whether the proposed amendment is liable to
be rejected on the ground that the relief of
possession is sought belatedly or may be hit
by Order II Rule 2 CPC?
(iii) Whether the impugned order warrants
interference in exercise of the supervisory
jurisdiction of this Court?
Findings on Point Nos.(i) to (iii)
12. Before examining the correctness of the order
under challenge, it would be appropriate to refer to the
relevant pleadings in the original plaint. The plaintiffs, in
paragraphs 6 to 10 of the plaint, have pleaded as under:
6. In this regard the plaintiff states that he
also executed a power of attorney dated
21.06.2010 in favour of the defendants to
enable him to proceed and also empowering him
to sale the portion that are allotted to his share
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 10 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
as per the joint development agreement referred
to herein above. Copy of the said power of
attorney is at Document No.6 and the copy of
the Rectification of the said power of attorney as
Document No.7.
7. The plaintiff states that due to some
constrains in the measurements of the property
which was measuring 21780 Square feet initially
agreed to be developed was reduced to 18,574
Square feet and accordingly the boundaries of
the entire property since changed and hence
necessitating to execute a rectification of the
power of attorney in favour of the defendant by
consent.
8. Plaintiff submits that the defendant
undertook to complete the construction within
18 months from 28-05-2010 i.e., on or before
November 2011, if the grace period of three
months as mentioned in the Joint development
agreement is included the time to deliver
possession expires in March 2012.
9. The plaintiff states that the defendant
undertook to pay a sum of Rs.10,000/- per
month and per unit to the plaintiff if he fails to
deliver the completed units fell to the share of
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 11 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
the plaintiff. It is undisputed that the plaintiff is
entitled to 17 completed units to his share as per
the sharing agreed in the power of attorney as
well as the Joint development agreement. The
plaintiff is also entitled to 862 Square feet
constructed area apart from the 17
units the plaintiff entitled to as per the brochure
printed and circulated by the defendant himself.
Since the defendant failed to deliver the 17 units
to the plaintiff as undertaken the defendant is
liable to pay in all a sum of Rs.25,20,000/-
(Rupees twenty five lakhs and twenty thousand
only) calculated at Rs.10,000/- per unit per
month from April 2012 up to the end of May
2013 for a period of 14 months amounting to
Rs.25,20,000/- for 17 units.
10. Plaintiff submits that since the
defendant failed to deliver the completed 17
residential units as agreed the plaintiff was put
to great deal of hardship and also put to heavy
financial loss in completing the units that have
fallen to his share and left Incomplete by the
defendant and he was not able to sell the said
units as they are all not completed by the
defendant as agreed, resulting in causing
damage to the reputation of the plaintiff in the
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 12 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
market. The defendant very cleverly with an
intention to cheat the plaintiff has deliberately
failed to complete the units fell to the share of
the plaintiff and completed the units fell to his
share and has sold the same to prospective
purchasers, without paying the taxes and other
deposits to the concerned authorities. The
defendant though duty bound to complete the
structure and also pay the deposits to the
KPTCL, BWSSB etc., The defendant is duty
bound to pay the said deposits.”
(Emphasis Supplied)
13. The above pleadings assume considerable
significance while considering the application for
amendment. A plain reading of paragraph Nos.6 to 10 of
the plaint makes it evident that the suit is not founded
upon an independent monetary transaction divorced from
the Joint Development Agreement. The claim for damages
is founded upon the alleged failure of the defendants to
comply with the terms and conditions contained in the
Joint Development Agreement and the consequential
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 13 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
failure to complete the construction and hand over the
plaintiffs’ agreed share.
14. The plaintiffs have specifically pleaded the
existence of the Joint Development Agreement, the
General Power of Attorney dated 21.06.2010, the change
in the measurement of the property, the consequent
change in boundaries, the rectification of the documents
and, most importantly, the failure on the part of the
defendants to complete the construction and hand over
the 17 residential units falling to the share of the plaintiffs.
15. Thus, the foundational facts on which the
proposed relief of possession rests are already part of the
original plaint. The proposed amendment does not seek to
substitute the original claim for damages. It does not
withdraw or abandon the original cause of action. The
plaintiffs continue to maintain their claim for damages.
What is sought to be introduced is an additional relief
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 14 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
flowing from the same transaction and the same alleged
breach.
16. The law relating to amendment of pleadings is
by now well settled. In LIFE INSURANCE
CORPORATION OF INDIA V. SANJEEV BUILDERS
PRIVATE LIMITED reported in (2022)16 SCC 1 , the
Hon’ble Supreme Court has reiterated that the Court
should ordinarily allow amendments which are necessary
for determining the real controversy between the parties,
unless the amendment causes injustice or prejudice to the
opposite party, introduces a wholly new and inconsistent
case, is mala fide , or introduces a claim which is clearly
barred by limitation.
17. Similarly, in GANESH PRASAD V. RAJESHWAR
PRASAD reported in (2023) SCC Online SC 256 , the
Hon’ble Supreme Court has cautioned against adopting a
hyper-technical approach while considering an application
for amendment and has recognised that amendments
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 15 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
which facilitate a complete and satisfactory adjudication of
the dispute ought ordinarily to be permitted, subject to
appropriate safeguards.
18. The principle laid down in SAMPATH KUMAR V.
AYYAKANNU reported in (2002)7 SCC 559 is also
apposite. The endeavour of the Court should be to avoid
multiplicity of proceedings and to ensure that all
substantive reliefs arising from the same foundational
facts are adjudicated in the same proceedings.
19. The test, therefore, is not merely whether the
relief sought by way of amendment is different from the
original prayer. The relevant consideration is whether the
amendment introduces an altogether new and inconsistent
case or whether it arises from the same foundational facts
and transaction already pleaded.
20. Applying the aforesaid principles to the present
case, this Court is of the considered view that the
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 16 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
proposed amendment cannot be regarded as introducing
an altogether new case.
21. The plaintiffs have, from the inception, relied
upon the Joint Development Agreement and the General
Power of Attorney. They have specifically pleaded that the
defendants were required to complete the construction
and hand over the plaintiffs’ agreed share of the
constructed area and that the defendants failed to do so.
22. Therefore, the defendants cannot legitimately
contend that the proposed relief of possession takes them
by surprise. The defendants were parties to the Joint
Development Agreement and the General Power of
Attorney. They were fully aware of the respective
entitlements of the parties thereunder. The foundational
pleadings relating to the plaintiffs’ entitlement to the
constructed area and the defendants’ failure to hand over
the same are already available on record.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 17 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
23. The proposed amendment, therefore, merely
seeks to place before the Court an appropriate relief
arising from the very facts already pleaded. The fact that
the plaintiffs initially chose to seek damages does not, by
itself, disentitle them from seeking an additional relief if
such relief is otherwise necessary for complete
adjudication of the dispute.
24. It is true that the suit was instituted in the year
2013 and the application for amendment came to be filed
in the year 2019. It is also true that the matter had
reached an advanced stage. However, delay by itself is
not an absolute bar to an amendment. The proviso to
Order VI Rule 17 of CPC requires the Court to examine the
question of due diligence where the amendment is sought
after commencement of trial. Such consideration cannot
be converted into a mechanical rule that every
amendment sought at a later stage must necessarily be
rejected.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 18 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
25. In BASAVARAJ V. INDIRA reported in
(2024)3 SCC 705 , the Hon’ble Supreme Court has
reiterated the requirement of satisfying the test of due
diligence in a post-trial amendment. That principle,
however, does not mean that an amendment which is
otherwise necessary for complete adjudication must
automatically be rejected merely because it is sought at a
later stage.
26. In the present case, the proposed amendment is
founded on the same agreement and the same alleged
failure of the defendants to discharge their obligations
thereunder. The foundational facts were already pleaded.
Therefore, the delay can appropriately be compensated by
imposing costs and by permitting the defendants to meet
the additional plea in accordance with law.
27. The apprehension expressed by the learned Trial
Court regarding Order II Rule 2 of CPC also cannot, at this
stage, furnish a ground for rejecting the amendment.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 19 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
Order II Rule 2 of CPC is intended to prevent splitting of
claims arising out of the same cause of action. The present
case is not one where the plaintiff seeks to institute a
subsequent suit after deliberately omitting a relief in an
earlier suit. The plaintiff is seeking, within the pending
suit, an additional relief founded upon the very same
transaction and foundational facts.
28. Whether the relief of possession is ultimately
maintainable, whether it is barred by limitation, whether
the plaintiffs were entitled to seek such relief at the
inception, and whether the ingredients of Order II Rule 2
of CPC are attracted are matters which, if raised by the
defendants, can be considered in accordance with law
after completion of pleadings.
29. At the stage of considering an application under
Order VI Rule 17 of CPC, the Court ought not to adjudicate
the ultimate merits of the amended claim unless the
proposed claim is ex facie barred by law.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 20 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
30. The defendants have also contended that the
proposed relief concerns an area of 862 sq. ft. which is
uncertain and undefined and is therefore hit by Order VII
Rule 3 of CPC. This Court is not inclined to reject the
amendment on that ground either. The question as to
whether the property over which possession is sought is
sufficiently identified, whether the extent of 862 sq. ft. is
capable of precise identification, and whether the same
can be correlated with the Joint Development Agreement,
rectification deed, sanctioned plan or other documents are
matters which can be examined after the amended
pleadings are brought on record.
31. The objection regarding identification of the
property cannot be used to prevent the plaintiff from
bringing a substantive relief arising out of the very
transaction already pleaded, particularly when the
defendants themselves rely upon the Joint Development
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 21 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
Agreement and rectification deed to contend that the
rights of the parties are governed by those documents.
32. The Court can always direct the plaintiffs,
if necessary, to furnish the requisite particulars so as to
ensure compliance with Order VII Rule 3 of CPC., The
defendants have also rightly pointed out that no court fee
has been paid on the proposed additional relief of
possession. This objection, however, is not a ground to
reject the amendment itself. The plaintiff shall necessarily
be required to pay the requisite court fee on the additional
relief sought by way of amendment, strictly in accordance
with the provisions of the Karnataka Court Fees and Suits
Valuation Act, 1958. The amendment shall, therefore,
take effect only subject to payment of the requisite court
fee within the time stipulated by the Trial Court.
33. Since the amendment introduces an additional
substantive relief, the defendants must necessarily be
afforded an effective opportunity to meet the same. The
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 22 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
defendants shall be entitled to file their additional written
statement/reply, if so advised, in respect of the amended
pleadings and shall also be entitled to cross-examine the
plaintiffs in relation to the matters introduced by way of
amendment.
34. This Court makes it clear that nothing stated in
this order shall be construed as an expression of opinion
on the merits of the plaintiffs’ claim for possession, the
identity or extent of the property, the applicability of the
Joint Development Agreement or rectification deed,
limitation, Order II Rule 2 of CPC, or any other defence
available to the defendants.
35. The learned Trial Court, in the opinion of this
Court, has proceeded primarily on the premise that since
the original suit was for recovery of damages,
incorporation of a prayer for possession would necessarily
change the nature and character of the suit.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 23 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
36. Such an approach overlooks the foundational
pleadings contained in paragraphs 6 to 10 of the plaint.
The plaintiffs have already pleaded the Joint Development
Agreement, the General Power of Attorney, the change in
measurement and boundaries, the rectification of the
documents, the obligation of the defendants to complete
the construction and, significantly, the failure of the
defendants to hand over the 17 residential units falling to
the share of the plaintiffs.
37. The proposed relief of possession is thus
intrinsically connected with the original cause of action and
arises out of the same transaction. It does not displace the
original claim for damages. Rather, permitting the
amendment would enable the Trial Court to adjudicate the
entire controversy between the parties in one proceeding
and would avoid multiplicity of litigation.
38. The learned Trial Court was, therefore, not
justified in rejecting the application merely on the ground
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 24 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
that the original suit was one for recovery of damages or
that the proposed amendment would change the texture
of the suit. The impugned order is liable to be set aside.
Accordingly, Point Nos.(i) and (ii) are answered in the
‘ Negative’ and Point No.(iii) is answered in the
‘ Affirmative’.
39. For the foregoing reasons, this Court proceeds to
pass the following;
ORDER
(i) The writ petition is allowed .
(ii) The order dated 28.02.2019 passed
by the learned Trial Court on I.A.No.1/2019
in O.S.No.25933/2013 is set aside.
(iii) I.A.No.1/2019 filed under Order VI
Rule 17 read with Section 151 of CPC is
allowed. The plaintiffs are permitted to
amend the plaint by incorporating the
proposed additional relief of delivery of
vacant possession of the additional
constructed area, subject to the following
conditions:
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 25 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
(a) The plaintiffs shall carry
out the amendment within the
time prescribed by the learned
Trial Court;
(b) The plaintiffs shall pay
the requisite court fee on the
additional relief of possession,
strictly in accordance with the
provisions of the Karnataka Court
Fees and Suits Valuation Act,
1958;
(c) The defendants shall be
permitted to file their additional
written statement/reply to the
amended pleadings;
(d) The defendants shall be
entitled to cross-examine the
plaintiffs in respect of the matters
introduced by way of the
proposed amendment;
(e) All objections of the
defendants with regard to
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
- 26 -
HC-KAR
NC: 2026:KHC:57406
WP No. 14188 of 2019
CNR: KAHC010088392019
limitation, Order II Rule 2 of CPC,
Order VII Rule 3 of CPC,
identification and extent of the
property, maintainability of the
relief of possession, and all other
defences available in law are kept
open; and
(iv) Nothing contained in this order
shall be construed as an adjudication on the
merits of the additional relief sought by the
plaintiffs.
(v) The learned Trial Court shall
thereafter proceed with the suit in
accordance with law and uninfluenced by any
observations made in this order.
No order as to costs.
Digitally Signed By:
SACHIN SHANKAR MAGADUM
Verified
(SACHIN SHANKAR MAGADUM)
JUDGE
NBM
List No.: 1 Sl No.: 65