Sterlite Technologies Ltd vs Bharat Sanchar Nigam Limited

Court
Delhi High Court

IN THE HIGH COURT OF DELHI AT NEW DELHI

% Judgment reserved on: 21.04.2026
Judgment pronounced on: 11.05.2026

+ O.M.P. (COMM) 261/2023
STERLITE TECHNOLOGIES LTD .....Petitioner
Through: Mr. Amit Dhingra, Mr. Rohit
Mahajan & Mr. Siddharth
Agrawal, Advs.
versus
BHARAT SANCHAR NIGAM LIMITED .....Respondent
Through: Mr. Dinesh Agnani, Sr. Adv.
with Ms. Leena Tuteja & Ms.
Ishita Kadyan, Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
J U D G M E N T
1. This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) against the arbitral award
dated 09.05.2023 (for brevity „award‟).
2. The facts shorn of unnecessary detail are that the respondent
invited tender for procurement, supply, trenching, laying, installation,
testing and maintenance of optical fiber cable (OFC), PLB duct and
accessories for construction of Exclusive Optical National Long
Distance (NLD) backbone and optical access routes on turnkey basis
for defence network. The Notice Inviting Tender (NIT) was for seven
packages. The petitioner was successful bidder for package „A‟ for the
State of Jammu and Kashmir of the NTP region and consisted of
laying 9,495 kms of cable. The work was to be executed link-wise
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 1 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

with each link to be installed and commissioned separately.
2.1 The dispute in the present case is only with regard to 547 kms
of cables laid in a common trench having multiple ducts (hereinafter
referred to as „MDC‟).
2.2 On a pre-bid query clarification no.160 was issued by the
respondent stating that twenty-five percent of the quoted rate for
services shall be paid for the cable laid through existing ducts with the
permission of BSNL/PICG.
2.3 On 30.06.2014, an Advance Purchase Order (APO) was issued.
Final Purchase Order (PO) dated 24.07.2014, was issued after
unconditional acceptance by the petitioner on 01.07.2014. The
petitioner by letter dated 10.01.2018, claimed hundred percent service
cost for MDC. Vide communication dated 01.08.2018, the committee
constituted by the respondent recommended that twenty five percent
of the service cost portion is payable for MDC cases initially captured
as per survey planned and approved.
2.4 On 16.06.2020, the petitioner issued notice under Section 21 of
the Act. The arbitrator was appointed by this court. The arbitrator after
considering the clauses of the contract and the clarification no. 160
rejected the claim of the petitioner for hundred percent service cost for
MDC hence, the present petition.
3. Learned counsel for the petitioner argued that the arbitrator read
sub-clause 28(iii) of the PO in isolation and not in conjunction with
the other clauses and the conclusion arrived at is perverse. The
submission is that the arbitrator erred in holding that pre-bid
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 2 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

clarification no.160 was not related to clause 77 of the tender which
was not applicable to the issued involved. The argument is that claim
cannot be rejected by relying on the clarification. The arbitrator has
gone beyond the clauses of the contract and has re-written the clauses,
violating Section 28(3) of the Act.
3.1 It is emphasised that clause 77 of the tender is not applicable to
MDC and pre-bid clarification no.160 was cut, copied and pasted in
clause 27 of the APO and clause 28 of the PO and the award is passed
without appreciating the facts on record. The grievance is that
arbitrator adopted an interpretation contrary to the pleadings and
arguments of the parties. The arbitrator failed to appreciate that the
clarifications in the APO were duly mentioned in a bracket wherever
required and against clause 27 (iii) of APO clarification no.160 was
mentioned in the bracket. The contention is that the conclusion of the
arbitrator that the clarification was not under clause 77 of the tender is
not plausible.
3.2 It is contended that there is no specific pricing for MDC in the
tender and the PO but it is common case of parties that payment for
the cables laid was to be made on per kilometer basis. The argument is
that there is no basis for giving only twenty-five per cent of the service
cost for MDC.
3.3 Reliance is placed upon the decision of the Division Bench of
this court in Engineers India Limited v. Tema India Limited, 2016
SCC OnLine Del 86 to contend that an arbitral tribunal cannot
interpret contractual clauses in a manner contrary to the mutual
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 3 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

understanding of the parties. The decisions of the Supreme Court in
Ssangyong Engineering & Construction Co. Ltd. v. NHAI , (2019)
15 SCC 131 and PSA SICAL Terminals Pvt. Ltd. v. Board of
Trustees of V.O. Chidambaranar Port Trust, AIR 2021 SC 4661
are relied upon to submit that unilateral addition or alteration of
contractual terms cannot be foisted upon an unwilling party, nor can a
party be compelled to perform a bargain not agreed to. The decision in
Rajasthan State Industrial Development & Investment
Corporation v. Diamond & Gem Development Corporation Ltd.,
(2013) 5 SCC 470 is relied upon to argue that the contract is to be
interpreted by giving effect to the actual meaning of the terms and the
court cannot make a new contract, if the parties have not made it for
themselves. Reliance is also placed on the decision of the Supreme
Court in Indian Oil Corporation Ltd. v. Shree Ganesh Petroleum ,
(2022) 4 SCC 463 and of this court in Union of India v. Jindal Rail
Infrastructure Ltd., (2022) SCC online Del 1540 to contend that re-
writing a contract for the parties would be a breach of fundamental
principles of justice and the court should interfere.
4. Per contra , the scope of interference under Section 34 of the
Act is limited. There cannot be interference with a plausible view of
the arbitrator and the evidence cannot be re-appreciated. The
submission is that in a trench dug by the petitioner multiple ducts were
laid and after blowing the cable for the first link the other ducts were
“existing duct”. It is contended that multiple ducting was included in
the contract since inception and all other bidders for the other
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 4 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

packages have accepted twenty-five percent payment for MDC. The
emphasis is that clause 28(iii) of the PO specifically stipulated that for
blowing the cables through the existing ducts twenty five percent of
the quoted rate of service cost shall be paid.
5. Before proceeding further it would be relevant to reproduce the
following clauses of the tender, APO, PO and the clarification no.160:
“Payment Terms
84.1 Payment for 60% of the material cost price shall be
made on receipt of goods by consignee at site and after
successful inspection by the concerned store-in-charges
nominated by PICG. Inspection will be carried out by
PICG after delivery of goods. The consignee receipt will
be Issued after completion of Inspection.
84.2 Payment for 30% amount of the cost of the materials
and 80% amount of the cost of the works executed shall
be released after commissioning of the respective NLD
link and completion of Access Networks at respective
Army sites as described in clause 85 below.
Reimbursement of RoW charges shall be made on
commissioning of the respective NLD link/access
network.
84.3 Payment for 10% amount of the cost of the materials
and 20% amount of the cost of the works shall be
released against PBG of equivalent amount for one year
for which provisions of clause 55.2 above shall also be
applicable. All the payments will be released to the bidder
by BSNL after issue of requisite inspection and
acceptance test certificates after successful completion of
joint testing by BSNL and PICG.
84.4 The payment shall be made for actual completed
route Km on the basis of quoted rate per Km.”
“96.4.4. Measurement of length of cable. The length of
cables laid in trenches, through pipes and through ducts
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 5 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

shall be measured by use of OTDR. The payment for
Services component shall be made as per the RODO
meter readings and not as per the OTDR readings. The
length should be cross-verified with the marking of
lengths on the cables. The lengths shall be recorded in
sheet provided in the measurement book.”
“96.4.7. Measurement of the work of cable far calculation
of services portion will be taken equal of the length of the
pipe/duct (as measured in the RODO meter) through
which the cable has been pulled and not the total length
of the cable pulled through pipe/duct.”
“130.4. Depth and Size of the trench:
130.4.1. The depth of the trench from top of the surface
shall not be less than 165cms unless otherwise relaxation
is granted by competent authority of BSNL and PICG
under genuine circumstances. In rocky terrain, the depth
of the trench may be restricted to a depth of 100 to
140cms. However, Engineer-in-charge in exceptional
cases due to adverse site conditions encountered, may
allow to lay HDPE/PLB pipes at a lesser depth with
additional protection. In all cases, the slope of the trench
shall not be less than 15 degrees with the horizontal
surface. The width of the trench shall normally be 45 cms
at the top & 30 cms at the bottom. In case, additional
pipes (HDPE/GI/RCC Pipes) are to be laid in some
stretches, the same shall be accommodated in this normal
size trench.
130.4.2. If excavation is not possible to the minimum
depth of 165 cms, as detailed above, full facts shall be
brought to the notice of the Engineer in charge PICG and
BSNL in writing giving details of location and reason for
not being able to excavate that particular portion to the
minimum depth. Approval shall be granted by the
competent authority in writing under genuine
circumstances. The decision of the competent authority
shall be final and binding on the contractor.”
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 6 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

“134 Cable Blowing and Joining/Splicing
134.1. Cable Blowing. Manholes shall be marked during
HDPE/PLB pipe laying of approx. size of 2m x 2m x 2m
shall be excavated for blowing the cables. There may be
situations where additional manholes are required to be
excavated, for some reasons, to facilitate smooth blowing
of cable. Excavation of additional manholes will be
carried out, without any extra cost. De-watering of the
manholes, if required, will be carried out without any
extra costs. De-watering/De-gasification of ducts, if
required, will be carried out without any extra costs.”
“Appendix J
13.4.2 Multi Duct Laying. Foreseen Duct Laying
Whenever it is foreseen that in future more no of cables
will required, a 110 mm PVC Duct can be laid and 4 nos.
of sub duct can be pulled, which can be tighten by
Anchor block at the end of PVC pipe.
13.4.2.1 In long distance network this 110 mm pipe can
be buried directly in the Sand, and in the Built up areas it
can be encased in the 200x200x200 MM Cement
Concrete.”
“Clause 77 of the tender
The Trenching, Ducting, laying, Installation and
Maintenance of OFC routes will be exclusively carried
for Defence Network. Ducts provided by Governmental
agencies for laying of OFC maybe utilized along
highways etc but ducts of private agencies cannot be
utilized. However no third party/service provider will be
allowed to lay OFC/duct through same trench.”


Ser.
No.
Se
cti
on
Cla
use
No.
Pg.
No.
Brief Description
in the
Clause
Query/Comme
nts
of Bidder
Query
Response
160 I
V
A
77 47 The Trenching,
Ducting, laying,
Installation and
Since tender
does not call
for itemwise
25% of the
quoted rate
for services
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 7 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

Maintenance of
OFC routes will
be exclusively
carried for
Defence Network.
Ducts
provided by
Governmental
agencies for
laying of OFC
may be utilized
along highways
etc. but ducts of
private agencies
cannot be
utilized. However,
no third
party/service
provider will be
allowed to lay
OFC/duct through
same trench
rates, please
clarify how
bidder will be
paid for the
activities done
by him for
laying of cable
in existing
ducts.
shall be paid
if cable is
laid through
existing
ducts with
the
permission
of
BSNL/PICG
.

“APO
27. The Trenching. Ducting, laying, Installation and
Maintenance of OFC routes will be exclusively carried
for Defence Network. Ducts provided by Governmental
agencies for laying of OFC may be utilized along
highways etc but ducts of private agencies cannot be
utilized. However no third party/service provider will be
allowed to lay OFC/duct through same trench.
i) Guidelines in the form of Engineering Instructions (E.
Is.) on Construction Practices of Optical Fiber Cables
issued by BSNL are attached at Appendix J and appendix
K‟ of the tender. In case of any conflict with regards to
OFC route construction and laying practices then
requirements/ procedures given in Section IV shall
supersede those given in Appendix „J‟& „K‟.
ii) In case of Bridge Crossings, where there is no space
for accommodating GI pipe, bidder may be allowed to
utilize the pipes laid by private agencies, with prior
approval of BSNL/PIGC on case to case basis, in case
pipes from Govt. Agencies are not available (clarification
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 8 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

no.412)
iii) If the cable is laid through existing duct with the
permission of BSNL/PIGC 25% of the quoted rate for
services shall be paid (clarification no.160).”
“PO
28. Guide lines for trenching/ductings
The Trenching, Ducting, laying, Installation and
Maintenance of OFC routes will be exclusively carried
for Defence Network. Ducts provided by Governmental
agencies for laying of OFC may be utilized along
highways etc but ducts of private agencies cannot be
utilized. However, no third party/service provider will be
allowed to lay OFC/duct through same trench.
i) Guidelines in the form of Engineering Instructions
(E.Is.) on Construction Practices of Optical Fiber Cables
Issued by BSNL are attached at Appendix J and appendix
K of the tender. In case of any conflict with regards to
OFC route construction and laying practices then
requirements/ procedures given in Section IV shall
supersede those given in Appendix „J‟ & „K‟.
ii) In case of Bridge Crossings, where there is no space
for accommodating GI pipe, bidder may be allowed to
utilize the pipes laid by private agencies, with prior
approval of BSNL/PICG on case to case basis, in case
pipes from Govt. Agencies are not available.
iii) If the cable is laid through existing ducts with the
permission of BSNL/PIGC, 25 % of the quoted rate for
services shall be paid.”
6. The procedure to be followed for laying the cables was
extensively gone into by the arbitrator and is not in dispute. Initially a
route survey is conducted. The contractor identifies the trenches where
multiple ducting is required. The proposal by the contractor is
considered and approved by the respondent and thereafter trenches are
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 9 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

dug. As per stipulated dimension set out, a layer of soft soil and sand
is laid on which the required number of permanently lubricated high
density polyethylene pipes (ducts) of requisite width are laid. While
laying the ducts manholes are marked. The ducts are protected by
laying them inside reinforced cement concrete (RCC) / galvanized
iron pipes. At road crossings the ducts are required to be laid in RCC
full round spun pipes / GI pipes. After laying and encasing the ducts
trenches are back filled. Thereafter the cable is blown through the
ducts from the manholes and one link is completed. While carrying
out the aforesaid procedure the route plan may necessitate provision
for laying down more than one OFC and for that purpose more than
one duct is laid in the trench. It is possible that out of the multiple
ducts laid in the trench one or two may carry cables while the others
may remain empty for pulling cables at a later stage.
7. The issue is whether after blowing one cable through one of the
ducts in a trench dug by petitioner having multiple ducts, for
additional cable pulled through already laid ducts the petitioner is
entitled to twenty-five percent or hundred percent of the quoted
service cost.
8. The bone of controversy is the meaning to be assigned to
“existing duct”.
9. It is an admitted fact that the contract included multiple ducting.
There was uncertainty for the rates applicable for multiple ducting and
a pre-bid query was raised by the bidders and the petitioner that
“since tender does not call for item-wise rates, please clarify how
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 10 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

bidder will be paid for the activities done by him for laying of cable in
existing ducts.” In response clarification no. 160 was issued stating
that “25% of the quoted rate for services shall be paid if cable is laid
through existing ducts with the permission of BSNL/PICG”. The
clarification was made refering to clause 77 of the tender wherein it is
provided that the project is for the defence network and the ducts
provided by government agencies along highways may be used for
laying OFC but not those of private agencies. Further that no third
party or service provider would be allowed to lay OFC or duct through
the same trench. The petitioner being the lowest bidder for package
„A‟ was issued APO which was followed by the PO. Clause 27 (iii) of
the APO provided that twenty-five percent of the quoted rate for
service shall be paid for laying cables through existing ducts and at the
end clarification no.160 was mentioned in brackets. In the PO clause
28 is similar to clause 27 of the APO but in clause 28 (iii) clarification
no.160 is not mentioned.
10. The petitioner set up a case that clause 77 of the tender had no
applicability to the facts of the case and the service costs for MDC
cannot be reduced to twenty-five percent by relying on clarification
no.160 issued under clause 77 of the tender. The arbitrator agreed that
no government duct was used for laying the subsequent cables. The
contention of the respondent that the return of the contractor to the
same trench where the earlier cable was laid tantanmounts to using a
government trench was rejected and this finding is not under
challenge. The arbitrator agreed with the contention of the learned
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 11 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

counsel for the petitioner that clause 77 of the tender had no
application to the issue in hand but held that the clarification is to be
considered independently on the basis of the query and the response
thereto. The backdrop that there was an omission in the tender
regarding the rate of payment in cases of MDC and the letter of the
Deputy General Manager of the respondent dated 20.03.2018
forwarding the claim of the petitioner to higher authorities were taken
into account. The issue as to what constitutes “existing ducts” was
specifically framed and dealt with. The interpretation advanced by the
petitioner that ducts laid in previously excavated trenches by any
government agency and ducts laid by petitioner already carrying a
cable would qualify as “existing ducts” was rejected.
11. It was held that the contractor after trenching, laying the ducts
and backfilling uses one of the ducts for completing one link and upon
returning to use a second duct from the same trench shall be treated as
using an existing duct. It was taken into account that the petitioner in
letters dated 29.01.2016, 04.07.2016, 26.12.2016 and 04.07.2017,
accepted the position that for MDC twenty five percent payment as
prescribed under the PO shall be made and raised grievance that the
cost of additional material used for laying multiple ducts be paid in
addition to the service cost. The petitioner for MDC raised invoices of
twenty-five percent of the full charges. The petitioner changed the
stand for the first time vide letter dated 10.01.2018 and claimed full
service cost for MDC.
12. It was noted that while changing stand the petitioner
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 12 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

emphasised that retrenching was required for subsequent laying of the
cable but this was factually found wrong by a committee set up by the
respondent. It would be relevant to note that during the course of
hearing, learned counsel for the petitioner on instructions fairly
contended that there was no retrenching involved in the claim made
for 547 kilometres of MDC. Even otherwise arbitrator rightly held that
the very object and purpose of laying multiple ducts in a common
trench to avoid difficulty of digging trenches in public places would
stand defeated. The additional activities involved only for laying
multiple ducts in trench were considered. The breakup of cost given
by the petitioner vide letter dated 19.01.2018, was relied upon to
record a factual finding that even as per the petitioner the charges for
MDC were less than fifty percent of the full charges.
13. The emphasis on the non-applicability of clause 77 of the tender
is not enhancing the case of the petitioner. The clause does not deals
with existing ducts but with already laid government ducts and with
utilization of existing government ducts. At the cost of repetition, it is
held by the arbitrator that the multiple ducts laid by the contractor for
this project are not government ducts. The applicability or non-
applicability of clause 77 to the facts of the case has no impact on the
query raised and clarification no.160 issued in response thereto. The
query was for the usage of existing ducts for laying cables and not for
the ducts of the government agencies and so was the response that
twenty five percent of the quoted rate of services shall be paid for
MCD.
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 13 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

14. It is not the case set up by either of the parties that the work
allocated in package „A‟ involved laying of cables only. From a
reading of the NIT, APO and the PO a clear picture emerges that the
work included procurement, supply, trenching, laying, installation,
testing and maintenance of OFC, PLB duct and accessories for the
construction of exclusive Optical National Long Distance (NLD)
backbone and optical access routes for the defence network.
15. The matter needs to be considered from another angle. Clause
28 (iii) of the PO without reference to the clarification unambiguously
stated that twenty-five percent of the quoted rate of service shall be
paid for laying cable through the existing ducts. The clear language of
Clause 28(iii) of PO render the issue of applicability of clause 77 of
the tender document and reliance on clarification no.160
inconsequential. The petitioner acted in consonance of clause 28(iii)
of the PO and submitted invoices in compliance therewith. The only
grievance raised was that the cost of additional material used in laying
multiple ducts be also paid apart from 25% of service cost. It may be
hastened to add that this does not operate as an estoppel against the
petitioner; however it lends support to the conclusion arrived at by the
arbitrator rendering it to be a plausible view.
16. The law is well settled that interference under Section 34 of the
Act is not be made for a possible alternate view. The interpretation of
the clauses of the contract falls within the domain of the arbitrator,
unless the interpretation is perverse no interference is called for
another possible view is not a ground available under Section 34 of
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 14 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

the Act. Reference is made to the following decisions:
16.1 In Punjab State Civil Supplies Corporation Limited & Anr.
v. M/S Sanman Rice Mills & Ors. 2024 INSC 742 it was held as
under:
“13. In paragraph 11 of Bharat Coking Coal Ltd. v.
L.K.Ahuja, it has been observed as under:
“11. There are limitations upon the scope of
interference in awards passed by an arbitrator. When
the arbitrator has applied his mind to the pleadings, the
evidence adduced before him and the terms of the
contract, there is no scope for the court to reappraise
the matter as if this were an appeal and even if two
views are possible, the view taken by the arbitrator
would prevail. So long as an award made by an
arbitrator can be said to be one by a reasonable person
no interference is called for. However, in cases where
an arbitrator exceeds the terms of the agreement or
passes an award in the absence of any evidence, which
is apparent on the face of the award, the same could be
set aside.””
16.2 In Prakash Atlanta (JV) v. National Highways Authority of
India 2026 INSC 76 it was held as under:-
“59. (vi) If an arbitral tribunal‟s view is found to be a
possible and plausible one, it cannot be substituted
merely because an alternate view is possible.
Construction and interpretation of a contract and its terms
is a matter for the arbitral tribunal to determine. Unless
the same is found to be one that no fair-minded or
reasonable person would arrive at, it cannot be interfered
with. If there are two plausible interpretations of the
terms of a contract, then no fault can be found if the
arbitrator accepts one such interpretation as against the
other. To be in conflict with the public policy of India,
the award must contravene the fundamental policy of
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 15 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

Indian law, which makes it narrower in its application.”
16.3 In Ramesh Kumar Jain v. Bharat Aluminium Company
Limited (BALCO) 2025 INSC 1457 held as under:-
“28. The bare perusal of section 34 mandates a narrow
lens of supervisory jurisdiction to set aside the arbitral
award strictly on the grounds and parameters enumerated
in sub-section (2) & (3) thereof. The interference is
permitted where the award is found to be in contravention
to public policy of India; is contrary to the fundamental
policy of Indian Law; or offends the most basic notions of
morality or justice. Hence, a plain and purposive reading
of the section 34 makes it abundantly clear that the scope
of interference by a judicial body is extremely narrow. It
is a settled proposition of law as has been constantly
observed by this court and we reiterate, the courts
exercising jurisdiction under section 34 do not sit in
appeal over the arbitral award hence they are not
expected to examine the legality, reasonableness or
correctness of findings on facts or law unless they come
under any of grounds mandated in the said provision. In
14
ONGC Limited. v. Saw Pipes Limited , this court held
that an award can be set aside under Section 34 on the
following grounds: “(a) contravention of fundamental
policy of Indian law; or (b) the interest of India; or (c)
justice or morality, or (d) in addition, if it is patently
illegal.”
16.4 In Parsa Kente Collieries Limited. v. Rajasthan Rajya
Vidyut Utpadan Nigam Limited (2019) 7 SCC 236 held as under:-
“9.1. In Associate Builders [Associate Builders v. DDA,
(2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , this Court
had an occasion to consider in detail the jurisdiction of
the Court to interfere with the award passed by the
Arbitrator in exercise of powers under Section 34 of the
Arbitration Act. In the aforesaid decision, this Court has
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 16 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

considered the limits of power of the Court to interfere
with the arbitral award. It is observed and held that only
when the award is in conflict with the public policy in
India, the Court would be justified in interfering with the
arbitral award. In the aforesaid decision, this Court
considered different heads of “public policy in India”
which, inter alia, includes patent illegality. After referring
Section 28(3) of the Arbitration Act and after considering
the decisions of this Court in McDermott International
Inc. v. Burn Standard Co. Ltd. [McDermott International
Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181] ,
SCC paras 112-113 and Rashtriya Ispat Nigam Ltd. v.
Dewan Chand Ram Saran [Rashtriya Ispat Nigam Ltd. v.
Dewan Chand Ram Saran, (2012) 5 SCC 306] , SCC
paras 43-45, it is observed and held that an Arbitral
Tribunal must decide in accordance with the terms of the
contract, but if an Arbitrator construes a term of the
contract in a reasonable manner, it will not mean that the
award can be set aside on this ground. It is further
observed and held that construction of the terms of a
contract is primarily for an Arbitrator to decide unless the
Arbitrator construes the contract in such a way that it
could be said to be something that no fair-minded or
reasonable person could do. It is further observed by this
Court in the aforesaid decision in para 33 that when a
court is applying the “public policy” test to an arbitration
award, it does not act as a court of appeal and
consequently errors of fact cannot be corrected. A
possible view by the Arbitrator on facts has necessarily to
pass muster as the Arbitrator is the ultimate master of the
quantity and quality of evidence to be relied upon when
he delivers his arbitral award. It is further observed that
thus an award based on little evidence or on evidence
which does not measure up in quality to a trained legal
mind would not be held to be invalid on this score.”
16.5 In Consolidated Construction Consortium Limited Vs.
Software Technology Parks of India (2025) 7 SCC 757 it was held
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 17 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

as under:
“46. Scope of Section 34 of the 1996 Act is now well
crystallized by a plethora of judgments of this Court.
Section 34 is not in the nature of an appellate
provision. It provides for setting aside an arbitral award
that too only on very limited grounds i.e. as those
contained in Sub-sections (2) and (2-A) of Section 34.
It is the only remedy for setting aside an arbitral award.
An arbitral award is not liable to be interfered with
only on the ground that the award is illegal or is
erroneous in law which would require re-appraisal of
the evidence adduced before the arbitral tribunal. If
two views are possible, there is no scope for the court
to re-appraise the evidence and to take the view other
than the one taken by the arbitrator. The view taken by
the arbitral tribunal is ordinarily to be accepted and
allowed to prevail. Thus, the scope of interference in
arbitral matters is only confined to the extent envisaged
Under Section 34 of the Act. The court exercising
powers Under Section 34 has perforce to limit its
jurisdiction within the four corners of Section 34. It
cannot travel beyond Section 34. Thus, proceedings
Under Section 34 are summary in nature and not like a
full-fledged civil suit or a civil appeal. The award as
such cannot be touched unless it is contrary to the
substantive provisions of law or Section 34 of the 1996
Act or the terms of the agreement.”
16.6 In The Supreme Court in Sepco Electric Power Construction
Corporation Vs. GMR Kamalanga Energy Ltd. 2025 INSC 1171
held:
“97……..Therefore, it appears that even if the
arbitrator‟s legal or factual reasoning is faulty, the
courts ought to ideally refrain from interfering with an
award until an error of law is evident from the award
itself or in a document that forms an integral
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 18 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

component thereof.”

(emphasis supplied)
17. The arbitrator considering the document of the tender, APO, PO
and the evidence on record concluded that after blowing first cable,
the subsequent usage of the other empty ducts remaining in the
trenches dug by the petitioner would mean “existing duct”. The
interpretation of the clauses of the contract falls solely within the
domain of the arbitrator and is not be interfered with unless the
relevant clause was not considered or the conclusion is a result of
traversing beyond the terms of the contract, which is not so in the
present case.
18. There cannot be a possible second view than the one taken in
the award that inspite of non-applicability of clause 77 of the tender,
clause 28(iii) of the PO of its own is fatal to the claim of the
petitioner.
19. The contention of learned counsel for the petitioner that
payment for laying cable is to be made on a kilometre basis is not in
dispute but the issue involved is the extent of payment to be made for
MDC not the length of the cable laid.
20. There is no quarrel with the proposition that the interpretation
of the contractual clauses by the arbitral tribunal cannot be
diametrically opposed to mutual understanding of the parties for
which Engineers India Limited (supra) was relied upon. Rather the
arbitrator has placed reliance upon the mutual understanding of the
parties regarding the payment to be made for MDC.
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 19 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026
15:10:22

21. The reliance of the learned counsel for the petitioner on the
decisions of the Supreme Court in Ssangyong Engineering &
Construction Co. Ltd. (supra) and PSA SICAL Terminals Pvt. Ltd.
(supra) to contend that there cannot be a unilateral addition or
alteration of contractual terms has no applicability in the present case.
Clause 28(iii) of the PO was not a unilateral addition but formed part
of the terms and conditions agreed between the parties.
22. The reliance of the learned counsel for the petitioner on
Rajasthan State Industrial Development & Investment
Corporation (supra), Indian Oil Corporation Ltd. (supra) and
Jindal Rail Infrastructure Ltd. (supra) to contend that the court
cannot make a new contract to render it reasonable, actual meaning
must be given to the terms and that there cannot be a re-writing of the
contract does not support the challenge to the award by the petitioner.
The arbitrator has given meaning to the terms of the contract and there
is no re-writing of the contract.
23. The award passed by the arbitrator suffers from no factual or
legal error much less perversity, the view of arbitrator is plausible and
calls for no interference under Section 34 of the Act.
24. The petition is dismissed.


AVNEESH JHINGAN, J
MAY 11, 2026/‘ha’
Reportable:- Yes
Signature Not Verified
O.M.P. (COMM) 261/2023 Page 20 of 20
Signed By:CHANCHAL
Signing Date:11.05.2026